36C26118R0065-008.docx
DOCX document 20 KB Posted
- Attached to
- V21 Construction MATOC - Group 1 Westpoint
- Solicitation number
- 36C26118R0065
About this file
This document provides details for a multiple award construction contract opportunity with the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21. The solicitation seeks construction services for various construction projects across several VA medical centers and healthcare systems located in California, Nevada, Hawaii, and Guam. Services include new construction, repair, and renovation projects. The opportunity is set aside for verified service-disabled veteran-owned small businesses. The two-phase procurement will evaluate factors of safety, experience, and past performance, with an intent to award a minimum of ten indefinite delivery indefinite quantity contracts for each of two contract groups ranging from $2,000 to over $10 million for task orders. The base period of performance is 24 months with three 12-month option periods. The estimated maximum value per contract is $50 million. The pre-proposal conference is scheduled for September 12, 2018 and proposals are due October 18, 2018.
36C26118R0065 NCO 21 CONSTRUCTION MACC ADDITIONAL TERMS AND CONDITIONS.docx
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NCO 21 CONSTRUCTION MACC
ADDITIONAL TERMS AND CONDITIONS
DEFINITIONS:
1. Biddability is defined as the clarity of the construction acquisition documents, the soundness of the government's evaluation and selection criteria for negotiated acquisitions, and the ease of bidders or offerors to understand the government's requirements, allowing the submission of a competitive bid or offer/proposal that is responsive to the government's requirements.
2. Constructability is defined as the ease of constructing a specified or designed project according to the government's requirements, including the proposed construction duration, and the ease of understanding and administering the contract documents during their execution.
3. Operability is defined as the ability to efficiently operate and maintain a facility or facilities over their life cycle when the facility or facilities are built according to the project's technical drawings and technical specifications.
4. Sustainability is defined as using methods, systems, and materials that optimize incorporation of a site's natural land, water, and energy resources as integral aspects of the development and minimize or avoid harm to the air, water, land, energy, human ecology and nonrenewable resources on- and off-site of the project.
5. Environmentalism is defined as the ability to best achieve stewardship of air, land, water;
plants, animals, and other natural resources; when constructing and operating the project;
and full compliance with FAR and VAAR environmental policies and regulations, including but not limited to Executive Orders 11912, 13221, 13693, and 13783; VA Green Purchasing Program Directive 0058; and VA Green Purchasing Program Handbook 0058.
Government Rights (Unlimited).
The Government shall have unlimited rights, in all drawings, designs, specifications, notes and other works developed in the performance of this contract, including the right to use same on any other Government design or construction without additional compensation to the Contractor. The Contractor hereby grants to the Government a paid-up license throughout the world to all such works to which he may assert or establish any claim under design patent or copyright laws. The Contractor for a period of three (3) years after completion of the project agrees to furnish the original or copies of all such works on the request of the Contracting Officer.
Drawings and Other Data to Become Property of Government.
All designs, drawings, specifications, notes and other works developed in the performance of this contract shall become the sole property of the Government and may be used on any other design or construction without additional compensation to the Contractor. The Government shall be considered the “person for whom the work was prepared” for the purpose of authorship in any copyrightable work under 17 U.S.C. 201(b). With respect thereto, the Contractor agrees not to assert or authorize others to assert any rights nor establish any claim under the design patent or copyright laws. The Contractor for a period of three (3) years after completion of the VISN 21 Construction MACC Program, or completion of last MACC Task Order issued, whichever is later, agrees to furnish all retained works on the request of the Contracting Officer. Unless otherwise provided in this contract, the Contractor shall have the right to retain copies of all works beyond such period.
Notice and Approval of Restricted Designs.
In the performance of this contract, the Contractor shall, to the extent practicable, make maximum use of structures, machines, products, materials, construction methods, equipment, and computer-based technologies, that are readily available through Government or competitive commercial channels, or through standard or proven production techniques, methods, and processes. Unless approved by the Contracting Officer, the Contractor shall not produce a design or specification that requires in this construction work the use of structures, products, materials, construction equipment, processes, or computer-based technologies, that are known by the Contractor to be available only from a sole source. The Contractor shall promptly report any such design or specification to the Contracting Officer and give the reason why it is considered necessary to so restrict the design or specification.
Technical Data--Withholding of Payment.
(a) If technical data specified to be delivered under this contract, is not delivered within the time specified by this contract or is deficient upon delivery (including having restrictive markings not identified elsewhere in this contract), the Contracting Officer may until such data is accepted by the Government, withhold payment to the Contractor of ten percent (10%) of the total contract price or lesser amount unless a lesser withholding is specified in the contract. Payments shall not be withheld nor any other action taken pursuant to this paragraph when the Contractor's failure to make timely delivery or to deliver such data without deficiencies arises out of causes beyond the control and without the fault or negligence of the Contractor.
(b) The withholding of any amount or subsequent payment to the Contractor shall not be construed as a waiver of any rights accruing to the Government under this contract.
Rights in Shop Drawings.
(a) Shop drawings for construction means drawings, submitted to the Government by the Construction Contractor, subcontractor or any lower-tier subcontractor pursuant to a construction contract, showing in detail (i) the proposed fabrication and assembly of structural elements and (ii) the installation (i.e., form, fit, function, and attachment details) of materials or equipment. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.
(b) This clause, including this paragraph (b), shall be included in all subcontracts hereunder at any tier.
Design-Build Contract Order of Precedence.
(a) The contract includes the standard contract clauses and schedules current at the time of contract award. It entails (1) the solicitation in its entirety, including all drawings, cuts, and illustrations, and any amendments, and (2) the successful offeror's accepted proposal. The contract constitutes and defines the entire agreement between the Contractor and the Government. No documentation shall be omitted which in any way bears upon the terms of that agreement.
(b) In the event of conflict or inconsistency between any of the provisions of this contract, precedence shall be given in the following order:
(1) Betterments: Any portions of the accepted proposal which both conform to and exceed the provisions of the solicitation.
(2) The provisions of the solicitation. (See also FAR 52.236-21, Specifications and Drawings for Construction)
(3) All other provisions of the accepted proposal.
(4) Any design products including, but not limited to, plans, specifications, engineering studies and analyses, shop drawings, equipment installation drawings, etc. These are "deliverables" under the contract and are not part of the contract itself. Design products must conform with all provisions of the contract, in the order of precedence herein.
Personnel, Subcontractors and Outside Associates or Consultants.
In connection with this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.
Government-Furnished Specifications, Drawings, Surveys, and Specifications in the Request for Proposal.
This is to clarify VAAR 852.236-71 Specifications and Drawings for Construction refers to any Government-furnished design or design criteria included in this MACC Request for Proposal or subsequent MACC Task Order Request for Proposal (RFP).
Government-Furnished Specifications and Drawings for Construction.
This is to clarify FAR 52.236-21, Specifications and Drawings for Construction, refers to any specifications and drawings furnished in the Request for Proposal (RFP). The term specifications" refers to the design criteria or scope of work, in addition to any attached specifications.
Responsibility of the Contractor for Design.
(a) The Contractor shall be responsible for the professional quality, technical accuracy, and the integrated coordination of all designs, drawings, specifications, and other non-construction services furnished by the Contractor under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other non-construction services and perform any necessary rework or modifications, including any damage to real or personal property, resulting from the design error or omission.
(b) The standard of care for all design services performed under this agreement shall be the care and skill ordinarily used by members of the architectural or engineering professions practicing under similar conditions at the same time and locality. Notwithstanding the above, in the event that the contract specifies that portions of the Work be performed in accordance with a performance standard, the design services shall be performed so as to achieve such standards.
(c) Neither the Government's review, approval or acceptance of, nor payment for, the services required under this contact, shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract. The Contractor shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by the Contractor's negligent performance of any of these services furnished under this contract.
(d) The rights and remedies of the Government provided for under this contract are in addition to any other rights and remedies provided by law.
(e) If the Contractor is comprised of more than one legal entity, each entity shall be jointly and severally liable hereunder.
Warranty of Design.
(a) The Contractor warrants that the design shall be performed in accordance with the contract requirements. Design and design related construction not conforming to the Contract requirements shall be corrected at no additional cost to the Government. The standard of care for design is defined in paragraph (b) of special contract requirement Responsibility of the Contractor for Design.
(b) The period of this warranty shall commence upon final completion and the Government's acceptance of the work, or in the case of the Government's beneficial occupancy of all or part of the work for its convenience, prior to final completion and acceptance, at the time of such occupancy.
(c) This design warranty shall be effective from the above event through the Statue of Limitations and Statute of Repose, as applicable to the state in which a MACC Seed Project or MACC Task Order project is located.
(d) The rights and remedies of the Government provided for under this clause are in addition to any other rights and remedies provided in this contract or by law.
Deviating from the Accepted Design.
(a) The Contractor must obtain the approval of the Designer of Record and the Government's concurrence for any Contractor proposed revision to the professionally stamped and sealed and Government reviewed design, before proceeding with the revision.
(b) The Government reserves the right to non-concur with any revision to the design, which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed design.
(c) Any revision to the design, which deviates from the contract requirements (i.e., the MACC RFP, including any seed projects, accepted proposal, and any MACC Task Orders RFPs/Projects), will require a modification, pursuant to the Changes clause, in addition to Government concurrence. The Government reserves the right to disapprove such a revision.
(d) Unless the Government initiates a change to the contract requirements, or the Government determines that the Government furnished design criteria are incorrect and must be revised, any Contractor initiated proposed change to the contract requirements, which results in additional cost, shall strictly be at the Contractor's expense.
(e) The Contractor shall track all approved revisions to the reviewed and accepted design and shall incorporate them into the as-built design documentation, in accordance with agreed procedures. The Designer of Record shall document its professional concurrence on the as-builts for any revisions in the stamped and sealed drawings and specifications.
Contractor's Role During Design Process.
The contractor's construction management key personnel shall be actively involved during the design process to effectively integrate the design and construction requirements of this contract. In addition to the typical required construction activities, the Contractor's involvement includes, but is not limited to, actions such as: integrating the design schedule into the Master Schedule to maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the contract), ensuring constructability and economy of the design, integrating the shop drawing and installation drawing process into the design, executing the material and equipment acquisition programs to meet critical schedules, effectively interfacing the construction QC program with the design QC program, and maintaining and providing the design team with accurate, up-to-date redline and as-built documentation. The Contractor shall require and manage the active involvement of key trade subcontractors in the above activities.
Value Engineering after Award.
(a) In reference to FAR 52.248-3, Value Engineering-Construction, the Government may refuse to entertain a "Value Engineering Change Proposal" (VECP) for those "performance oriented" aspects of the Solicitation documents which were addressed in the Contractor's accepted contract proposal and which were evaluated in competition with other offerors for award of this contract.
(b) The Government may consider a VECP for those "prescriptive" aspects of the Solicitation documents, not addressed in the Contractor's accepted contract proposal or addressed but evaluated only for minimum conformance with the Solicitation requirements.
(c) For purposes of this clause, the term "performance oriented" refers to those aspects of the design criteria or other contract requirements which allow the offeror or Contractor certain latitude, choice of and flexibility to propose in its accepted contract offer a choice of design, technical approach, design solution, construction approach or other approach to fulfill the contract requirements. Such requirements generally tend to be expressed in terms of functions to be performed, performance required or essential physical characteristics, without dictating a specific process or specific design solution for achieving the desired result.
(d) In contrast, for purposes of this clause, the term "prescriptive" refers to those aspects of the design criteria or other Solicitation requirements wherein the Government expressed the design solution or other requirements in terms of specific material, approaches, systems, and/or processes to be used. Prescriptive aspects typically allow the offerors little or no freedom in the choice of design approach, materials, fabrication techniques, methods of installation, or any other approach to fulfill the contract requirements.
Partnering.
In order to most effectively accomplish this contract, the Government proposes to form a partnership with the Contractor to develop a cohesive building team. It is anticipated that this partnership would involve the Department of Veterans Affairs Network Contracting Office 21, the Contractor, primary subcontractors and designers and the U.S. Department of Veterans Affairs. This partnership would strive to develop a cooperative management team drawing on the strengths of each team member in an effort to achieve a quality project within budget and on schedule. This partnership would be bilateral in membership and participation will be totally voluntary. Any cost associated with effectuating this partnership, excluding travel and lodging cost of Government personnel, will be borne by each party. The partnering meetings shall be held in TBD.
Government Re-Use of Design.
The Government will not ask for additional originals or copies of the design works after the Contractor provides all required design documentation and as-built documentation under the instant MACC contract, including any seed projects, and any resultant MACC Task Orders projects. Further, if the Government uses the design for other projects without additional compensation to the Contractor for re-use, the Government releases the Contractor from liability in the design on the other projects, due to defects in the design that are not the result of fraud, gross mistake as amounts to fraud, gross negligence or intentional misrepresentation.
Basis for Settlement of Proposals.
Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under FAR 49.206-2(b). In evaluating a terminations settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(4) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of FAR 31.205-11).
(5) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.