36C26118R0065-0002000.docx

DOCX document 21 KB Posted

Attached to
V21 Construction MATOC - Group 1 Westpoint
Solicitation number
36C26118R0065
Issued by

About this file

This solicitation is for construction services under an Indefinite Delivery, Indefinite Quantity (IDIQ) multiple award construction contract (MATOC) for the Veterans Health Administration (VHA). Services are required at medical centers and clinics in California, Hawaii, Nevada, and Northern California.

The scope of work includes new construction, repair and renovation projects. The contract has a 24-month base period and three 12-month options, with a maximum duration of 60 months. A minimum of ten contracts will be awarded for each of two groups. Group 1 task orders will range from $2,000 to $250,000, while Group 2 task orders will range from $2,000 to $10 million. The estimated maximum value per contract is $50 million.

This is a two-phase solicitation, with evaluation factors including safety, experience and past performance. The Phase I submission due date is October 18, 2018. The procurement is a 100% SDVOSB set-aside. A pre-proposal conference will be held on September 12, 2018.

36C26118R0065 0002 36C26118R0065 0002.docx

View the file

Other files

File Type Posted
36C26119D0103-000.docx DOCX document
36C26119D0102-000.docx DOCX document
36C26119D0101-000.docx DOCX document
36C26119D0100-000.docx DOCX document
36C26119D0099-000.docx DOCX document
36C26119D0098-000.docx DOCX document
36C26119D0097-000.docx DOCX document
36C26119D0096-000.docx DOCX document
36C26119D0095-000.docx DOCX document
36C26119D0094-000.docx DOCX document
36C26119D0093-004.docx DOCX document
36C26118R0065-0004000.docx DOCX document
36C26118R0065-0004001.docx DOCX document
36C26118R0065-0003000.docx DOCX document
36C26118R0065-0003001.docx DOCX document
36C26118R0065-0002001.docx DOCX document
36C26118R0065-0001001.pdf PDF
36C26118R0065-0001000.docx DOCX document
36C26118R0065-0001002.pdf PDF
36C26118R0065-0001003.pdf PDF
36C26118R0065-014.docx DOCX document
36C26118R0065-003.docx DOCX document
36C26118R0065-013.pdf PDF
36C26118R0065-011.pdf PDF
36C26118R0065-002.docx DOCX document
36C26118R0065-005.docx DOCX document
36C26118R0065-006.pdf PDF
36C26118R0065-009.pdf PDF
36C26118R0065-008.docx DOCX document
36C26118R0065-012.pdf PDF
36C26118R0065-001.docx DOCX document
36C26118R0065-007.docx DOCX document
36C26118R0065-004.docx DOCX document
36C26118R0065-010.pdf PDF
36C26118R0065-000.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 10-03-2018 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System 459 Patterson Rd Honolulu

HI

96819-1522 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System 459 Patterson Rd Honolulu

HI

96819-1522 To all Offerors/Bidders

36C26118R0065 10-03-2018

X X X X The purpose of this Amendment is to answer Offeror questions (see next page) and to amend a section of the solicitation (see attachment).

All other terms and conditions remain the same.

Brett Vegeto Contracting Officer

QUESTIONS AND ANSWERS

October 3, 2018

1. Section 2.3.2.i.1 – Recent, Relevant Experience of the Firm – Construction Experience: This question pertains to Group 1 Proposals only. The “Construction Experience” requires 2 of the 5 Projects that are to be submitted as recent and relevant past performance be “New Construction”. It is unlikely that any project under the maximum ordering limit for this group ($250K) would be “New Construction”. Is it acceptable for Group 2 to submit (5) Projects that are Remodeling/Renovations?

Answer: Please see the attached revised language for Group 1 in section 2.3.2.i.1.

2. This question pertains to both groups: How will Projects that are above the maximum ordering limits for each group be evaluated? Will this have a positive, negative, or neutral effect on the evaluation?

Answer: The instructions state in section 2.3.2.i.1 that experience should be “recent relevant projects that are similar in size, scope, and complexity to the RFP.” The basis of evaluation is stated in section (ii):

The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing recent relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s recent relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP.

3. Please confirm that a previously completed PPQ, from another VA solicitation, can be submitted under Factor 2.

Answer: Factor 2 is Recent and Relevant Experience of the Firm which requires completion of Attachment A. A PPQ on another VA solicitation will probably not answer the same questions as what is on Attachment A.

If you are referring to Factor 3, the Past Performance Questionnaire (PPQ) is not mandatory. If you provide PPQs that are not identical to Attachment B in the solicitation, it may not help your firm. In addition, the solicitation states that PPQs should be submitted to the Government from the reference.

4. Section 00100, Para. C.1 – The Phase 1 Proposal includes both a Technical (Factors 1, 2, and 3) volume and an Administrative Volume, which are to be separately bound and tabbed. Please confirm that they are to be sealed envelope/package/box together and marked in the bottom right corner “PHASE I – TECHNICAL PROPOSAL SUBMITTED UNDER RFP 36C26118R0065 – DO NOT OPEN IN MAILROOM.”

Answer: Yes, confirmed.

5. Section 00100, Para. C.1 – Under Administrative Volume, it states “(4) Joint Venture Agreement (if applicable). See section D, “Joint Ventures (JV)”. Please confirm that such is to instead reference Section E.

Answer: Yes, the Section 00100, Para. C.1 section (4) should reference Section E vice Section D.

6. Section 00100, Para. I (letter i), Pre-Award Survey/Responsibility Determination – As it is not clear, please confirm if such information is only required upon request from the Contracting Officer.

Answer: Yes, confirmed. Nothing is required to be submitted for this section.

7. Section 00100, Para. D.5, Format – As Offerors are provided an MS Word template of Attachments A, B, C, and D, please advise that Offerors are able to utilize the formats within those templates and they do not need to adhere to the format requirements of 1.5 line spacing and text size no less than 11 points.

Answer: Yes, on the Attachments, you may utilize the formats within those templates.

8. Section 00110, Factor 4, Seed Project Technical Solution – While the RFP details the solicitation submittal requirements with regard to this factor, the RFP does not provide a detailed description of the basis of evaluation and how the technical solution narrative will be evaluated, only stating the following: The Government will award to the low-priced offeror. However, the Government reserves the right not to make award. Some or all of the content proposed in the Technical Solution may be incorporated into the resultant order and will become material and binding terms to the order. Therefore, please appreciate if a more detailed basis of evaluation would be provided, particularly as the narrative address not only project issues, but also key personnel experience/qualifications.

Answer: The non-priced information that is required for Factor 4, Seed Project, will not be evaluated but is being used for responsibility determination purposes and to possibly be included in the resultant task order to become a binding part of the task order. Factor 4 is price only.

9. Is additional information beyond the Volume I Technical and Administration Volume submission required to satisfy Item I. Pre-Award Survey/Responsibility Determination criteria on RFP Page 13 of 137? If so, please clarify what information should be provided and where it should be placed in the our response.

Answer: Nothing is required to be submitted for this section.

10. The Administration Volume references inclusion of “Any Small Business Administration (SBA) Certifications”. What certifications or documentation should be included in this section to satisfy this requirement?

Answer: This was included in error. The only SBA documentation that would be submitted is a JV agreement, if applicable.

11. Do I need to be a JV to propose on this solicitation?

Answer: You don’t have to be a JV to participate with this acquisition. The purpose of Group 1 is to give an opportunity to the less experienced SDVOSBs so that you have an opportunity to participate in the MATOC and grow as a result. As mentioned in the pre-proposal conference, to be all-inclusive and to include those SDVOSBs to those firms that do not have a lot of experience on large projects, NCO 21 set up 2 Groups for added participation vice just having no groups and only one pool of awardees. The majority of NCO 21 acquisitions are under the SAT so there is ample opportunity to participate in Group 1.

12. The SF1442 issued with the original solicitation and amendment 0001 states that a bid bond is required. Since a price proposal is not required until Phase 2 can you please confirm no bonding information/bid bond is required in phase 1?

Answer: No bid bond is required in Phase 1.

See attached document: 3Oct18 Revised Solicitation Language - Evaluation.