This is a Statement of Work (SOW) for construction services at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The SOW outlines the repair of sanitary waste piping in Building 1 (Main Hospital) under Project 668-24-108, requiring the contractor to provide labor, materials, and equipment necessary to complete the piping repairs. The work scope encompasses assessment, design, procurement, installation, testing, and commissioning of sanitary waste piping systems to restore proper functionality and compliance with applicable codes and standards. The contractor must coordinate with VA facility personnel, maintain safety protocols, manage construction sequencing to minimize disruption to hospital operations, and provide documentation of all work performed including as-built drawings and system certifications.

The SOW specifies performance standards for piping installation, pressure testing requirements, and quality assurance procedures to ensure the repaired system meets VA Medical Center operational needs. The contractor is responsible for obtaining necessary permits, managing waste disposal, conducting final inspections, and providing a warranty period for completed work. All work must comply with Department of Veterans Affairs standards, applicable building codes, and infection control protocols specific to healthcare facility operations. The solicitation (36C26027R0021) contains additional submission requirements and contractual terms governing proposal evaluation and award.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR CONSTRUCTION SERVICES

Mann-Grandstaff VA Medical Center (VAMC) Spokane, WA August 26, 2026

1. Contract Title. 668-24-108 Repair Sanitary Waste Piping Building 1

2. General.

The Mann-Grandstaff VA Medical Center, Spokane, WA requires labor, materials, and equipment for the replacement of drainage and vent piping serving drinking fountains located in Building 1 (Main Hospital). Scope of work is indicated below.

3. Scope.

This project will repair and replace the vertical piping riser that serves the Building 1 drinking fountain drains. Access to the multi-story drinking fountain piping chase will be through existing access panels, removal of existing drinking fountain and water coolers, and penetration of walls where new fixtures are to be mounted. The project will remove Asbestos Containing Materials (ACM) piping and fitting wrap insulation that interferes with demolishing piping and remediate friable ACM from accessible surfaces. Lead containing paint and glazed block will need to be remediated or removed. Replace soil piping, fittings, and branches to fixtures. Pipe replacement includes new piping, connections, and any other new components/details necessary to provide service to new ADA/ABAAS compliant bottle-fill semi-recessed water cooler fixtures. Provide new electrical circuits needed to power new refrigerated water cooler fixtures. Repair wall finishes as necessary to restore existing wall surfaces. Contractor shall provide all supervision, labor, tools and materials, installation, programming, startup, training, O&M documentation and one-year warranty of materials and installation. Contractor shall do a field verification to ensure all equipment, parts and materials are identified and verify all the existing conditions.

3.1. The contractor shall provide a qualified manufacturer’s representative to check complete installation for conformance to manufacturer’s recommendation, to place the system into service, to make all adjustments required for full conformance to design and specified requirements and to perform all demonstrations and testing.

3.2. An operating test shall be run in the presence of the Contracting Officer’s Representative (COR).

3.3. The contractor shall provide demonstrations and training to VA personnel.

3.4. The contractor shall verify locations for space requirements.

4. Deliverables:

Inspection, testing documents and manuals and warranty documents per Specifications.

5. Performance Monitoring The COR will evaluate all work and testing performed. Items must be in a clean state and in proper working condition.

5.1 Additional Requirements

1. Project number and the contract number in the subject line of all emails.

2. Contractors shall comply with the VAPSHCS Smoking Policy.

3. Normal construction work hours are 7:00AM to 4:00PM Monday through Friday, unless other specified in the SOW.

a. Normal work hours can be modified only by written approval of the COR.

b. No work by the Contractor on Federal Holidays, and no work on the weekend when the Federal Holiday is on the respective Monday or Friday.

6.4 Deliveries, Parking, Elevators:

a. Deliveries only at the M&O Loading Dock Building 1, and coordinated with the COR. At time of delivery: provide vehicle information to the VA Police and remove the vehicle as soon as delivery is complete. Move materials in public corridors during low patient time and performed between 6 pm through midnight concluding by 6 AM on the following day.

b. No on-site parking or parking in the VA garage or VA parking lot. The existing VA parking is at capacity and reserved for patients and staff.

6.5 Contractors shall provide construction dumpsters with a surrounding safety fence. Pavement to be protected from damage of loading and unloading the dumpster and dumpster weight.

6.6 No on-site office or on-site storage / office container shall be allowed. Provide ‘just-in-time delivery and pickup’. Coordinate with COR for staging within the area of work.

6. Government-Furnished Equipment (GFE)/Government-Furnished Information (GFI).

The Contractor will not have access to any Government-Furnished Equipment. All equipment and supplies used under the terms of this contract will be the responsibility of the Contractor.

7. Inspection and Acceptance Criteria.

As part of final system acceptance, a systems demonstration is required. System operation and calibration shall be demonstrated by the installer in the presence of COR.

8. Place of Performance.

Mann-Grandstaff VA Medical Center, located at 4815 North Assembly Street, Spokane Washington 99205.

9. Period of Performance.

The Contractor has 209 calendar days to perform all described work.