Answers to Questions - 668-24-108.docx
DOCX document 26 KB Posted
- Solicitation number
- 36C26027R0021
About this file
This file is a Questions and Answers document addressing clarifications and technical inquiries related to solicitation 668-24-108 for repair of sanitary waste piping at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The document clarifies that only prime contractor past performance will be considered for the technical proposal factor (not subcontractor work), and that missing drawings including architectural elevations, details, plumbing plans, and electrical drawings have been provided in an updated drawing set (Attachment 11). The VA declined to extend the question period or bid date to allow for review of the missing drawings.
The Q&A addresses numerous technical and administrative requirements including specifications for suspended slab concrete work (Detail 3, AE400), availability of record drawing libraries for selected contractors rather than as-builts, clarification that the deduct alternative discussed in the design narrative is not part of the contract, confirmation that no exterior wall unit masonry or wood framing work is anticipated, and identification of applicable hazardous materials specification sections (Division 02, 02 41 00, 02 82 11, 02 83 33.13). The document clarifies hospital operational constraints: all floors remain occupied with normal work hours weekdays 0730-1630 (outside hours require COR coordination), key personnel require badging to work without VA escort, a freight elevator may be available as of March 2027, Infection Control and Interim Life Safety Measures are detailed on specific drawing sheets (GC100, GI100-GI190), no utility outages are forecasted, and work sequencing is shown on Drawing Sheet GC101 with all floors required to remain fully operational.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
668-24-108 Repair Sanitary Waste Piping Questions and Answers
1. For the Past Performance Factor of the Technical Proposal, will the Government accept or consider recent and relevant projects completed by a proposed first-tier subcontractor that will perform a major or critical portion of the work? If so, should those projects be included within the five-project maximum in Volume 1, with corresponding PPQs or CPARS in Volume 2?
Answer: No. Any relevant past performance must be as a prime contractor.
2. When reviewing the Solicitation, we noticed the following drawings appear to be missing?
· AE209 Ninth Floor Elevation
· AE400 Details
· AE401 Applied Wall Details
· AE402 Existing Wall Details (Add Alternative Only)
· P-001 Plumbing Legend, General Notes and Abbreviations
· PD200 Plumbing Demo Plan – Drinking Water
· PD201 Plumbing Demo Plan – Sanitary, Vent and Roof Leader
· PP200 Plumbing Plan – Drinking Water
· PP201 Plumbing Plan – Sanitary, Vent and Roof Leader
· PP400 Stack 25 Riser Diagram and Schedule
· PP401 Plumbing Details
· EG001 Electrical Legend and General Notes
· E-100 Floor Plans – Electrical
Answer: The VA has provided an updated drawing set with the above-named sections included (see Attachment 11)
3. Will the VA consider extending the period required for questions and extend the bid date to allow for time to review the missing drawings?
Answer: The VA currently has no plans to extend the bid due date or question period.
4. Section 03 30 53 Cast-In-Place Concrete (Short Form) indicates suspended slab on metal deck. Where precisely does this project require this scope of work? It is not on the current set of plans.
Answer: Apply this specification to work shown on Detail 3, AE400.
5. Are there existing As-Built drawings for each floor plan than can be distributed? Are there As-Built Building Sections that identify the wall and floor assemblies of the proposed work area that can be distributed?
Answer: Selected Contractor will have access to Record Drawing libraries for work planning.
6. Plans Indicate 100% Construction Documents. However Professional Stamp on the Title Block indicates not for construction. Please advise.
Answer: Responses to these questions will be incorporated into the Final Conformed Set and issued for construction.
7. Are there As-Builts indicating all the stairwell wall and floor assemblies?
Wall & floor thickness? Concrete? CMU? The Design Narrative indicates that the exhaust will penetrate the 1st floor wall then penetrate the 2nd floor stairwell floor assembly then out the window of the 2nd Floor stairwell.
Answer: Selected Contractor will have access to Record Drawing libraries for work planning.
8. Page 5 of the Design Narrative indicates new casework for the new bottle fill stations. There are no details in the plans nor specifications indicating casework scope. Refer to Specification Section 12 34 00 Manufactured Plastic Casework.
Answer: “Casework” refers to the architectural details shown to reconstruct the wall mounting of the bottle fill stations, as detailed on the Drawings.
9. Page 8 of the Deduct Alternative includes the removal of electrical work, install mechanical only fill stations and remove markups. The Bid Set Specifications do not include a Deduct optional pricing. Please advise.
Answer: See 01 00 00 1.3 for Statement of Bid Items. Deduct Alternative discussed in the Design Narrative is not part of this Contract or Bid.
10. Are there any outside permit and/or inspection requirements required? If so, by what jurisdiction(s)?
Answer: None outside the VHA jurisdiction.
11. Section 04 20 00 Unit Masonry includes Exterior walls. Where specifically will this project require exterior wall Unit Masonry?
Answer: No work is anticipated on exterior walls. Some existing construction may be encountered that requires application of this work specification.
12. Page 6 of the Design Narrative #2 indicates to install new fire-rated doors and frames. What specific doors are to be replaced and what are the door types and what type of glass inserts: half lite, full lite, vision panel? Since Sheet AE402 has not been issued, please consider all applicable details for this scope.
Answer: See Sheet AE402 in this Amendment.
13. Section 06 10 00: Are there any known areas where light wood framing would be required?
Answer: No work is anticipated using wood framing. Some existing construction may be encountered that requires application of this work specification.
14. Section 06 20 00: Are there any known areas where interior millwork will be required? Plans do not indicate this.
Answer: No work is anticipated using wood millwork. Some existing construction may be encountered that requires application of this work specification.
15. Can you provide all available asbestos, lead-based pain, PCB, mercury and silica surveys applicable to the affected work areas?
Answer: See Design Narrative. See Sheet HA100.
16. Can you please identify known hazardous materials in pipe insulation, joint compound, wall finishes, floor penetrations and existing firestopping?
Answer: See Design Narrative. See Sheet HA100.
17. Can you confirm whether abatement is included in the contract or performed under a separate VA contract?
Answer: See Sheet HA100. See Specifications Division 02.
18. Can you please identify the specification sections governing hazardous-material handling and disposal?
Answer: See Specifications Division 02. 02 41 00, 02 82 11, 02 83 33.13
19. Can you please clarify which floors and areas will remain occupied and areas available for exclusive contractor areas?
Answer: All floors will remain occupied. Stair Tower adjacent to this riser is part of the Work Area, and will be closed to traffic.
20. Clarify restrictions on demolition and noisy work, and allowable work hours including weekends?
Answer: 01 00 00 1.6 G. requires coordination with the COR for activities that may impact the surrounding hospital operations. Normal work hours shall be weekdays, 0730 – 1630. Any work planned to be performed outside these hours shall be coordinated and approved by the COR.
21. Can you please clarify escort, security badging and elevator access requirements?
Answer: Escort, Badging: Key individuals assigned roles such as Superintendent, SSHO, QC shall be processed for badging to allow work without VA escort. Freight elevator may or may not be available for materials transport dependent on start date of on-site work. This elevator is under construction, with expected availability of March, 2027.
22. Can you please clarify patient-care areas adjacent to the sanitary piping replacement locations?
Answer: Each floor has different patient-care functions, but all require Infection Control (ICRA) separation from work areas. ICRA Levels are shown in detail on Drawings.
23. Can you please verify project-specific ICRA classification and required containment level for each floor or work area?
Answer: Each floor has different patient-care functions, but all require Infection Control (ICRA) separation from work areas. ICRA Levels are shown in detail on Drawings.
24. Can you please provide negative air, HEPA filtration and dust monitoring requirements?
Answer: ICRA Levels are shown in detail on Drawings, with dust control requirements.
25. Can you clarify Interim Life Safety Measures (ILSM), daily inspection requirements and provide required forms?
Answer: Drawing Sheets GI100 through GI190 are the basis for Interim Life Safety Measures (ILSM). No daily inspection requirements are anticipated. Required forms and coordination with VA Fire and Life Safety officer, including permits to be posted at work areas will be coordinated by the COR.
26. Can you clarify responsibility for ICRA approval and ongoing monitoring?
Answer: Drawing Sheet GC100 is the basis for Infection Control meassures. Required forms and coordination with VA Infection Control officer, including permits to be posted at work areas will be coordinated by the COR.
27. Can you clarify whether barriers, anterooms, pressure monitoring and HEPA equipment are to be included in the base bid?
Answer: See Sheet GC100 and Specification Section 01 35 26 detail these requirements.
28. Can you clarify a maximum allowable outage duration, notification periods and the required outage request and approval process?
Answer: No utility or local service outages are forecast for this work scope. If any such outages are needed, coordinate with the COR.
29. Can you clarify permissible outage windows and any required after-hours or weekend tie-ins?
Answer: No utility or local service outages are forecast for this work scope. If any such outages are needed, coordinate with the COR.
30. Can you clarify temporary bypass and temporary restroom requirements?
Answer: No temporary bypass or temporary restroom requirements are forecast for this work scope. If any such temporary services are needed, coordinate with the COR.
31. Can you clarify VA personnel required for outage coordination?
Answer: No utility or local service outages are forecast for this work scope. If any such outages are needed, coordinate with the COR.
32. Can you clarify all anticipated system interruptions to be included in the offer.
Answer: No utility or local service outages are forecast for this work scope. If any such outages are needed, coordinate with the COR.
33. Can you provide record drawings and as-built plumbing drawings?
Answer: Selected Contractor will have access to Record Drawing libraries for work planning.
34. Can you provide camera inspection reports and piping material verification reports?
Answer: None available.
35. Can you provide existing wall and floor assembly ratings by floor, and existing chase fire-resistance ratings?
Answer: See Drawing Sheets GI100 through GI190.
36. Can you provide the required UL-tested firestop assemblies and engineering judgment requirements?
Answer: See Drawing Details and Specifications.
37. Can you provide third-party firestop inspection requirements?
Answer: COR will perform these inspections.
38. Can you provide prior maintenance records for the sanitary system?
Answer: None available for sharing.
39. Can you provide any known concealed conditions affecting the sanitary risers, and any known discrepancies between field conditions and the contract documents?
Answer: Any known conditions have been addressed in the contract documents.
40. Can you identify contractor parking, material storage, dumpsters and delivery staging?
Answer: Yet to be determined, but will be coordinated and made available.
41. Can you identify designated areas for temporary containment equipment and construction office trailers?
Answer: Yet to be determined, but will be coordinated and made available.
42. Can you identify designated areas for elevator loading and waste removal routes.
Answer: Yet to be determined, but will be coordinated and made available.
43. Can you identify restrictions on movement through occupied patient-care areas?
Answer: COR will coordinate at pre-construction conference.
44. May multiple floors be worked concurrently, and is a top-down or bottom-up sequence required?
Answer: See Drawing Sheet GC101
45. Are any floors required to remain fully operational, and are partial floor turnovers or interim milestones required?
Answer: All floors required to remain fully operational.
46. Are there restrictions on simultaneous demolition activities?
Answer: No restrictions other than coordination of activities with the COR.
47. Can you provide any owner-required phasing plan to be incorporated into the offer?
Answer: See Drawing Sheet GC101
48. Can you provide existing riser materials at each floor and existing branch connection locations.
Answer: See Drawings.
49. Can you provide existing pipe hanger and structural attachment requirements.
Answer: See Drawings.
50. Can you provide temporary support requirements during replacement?
Answer: See Drawings. Contractor expected to devise means and method for installation work.
51. Can you provide any existing plumbing investigation report?
Answer: None available.
52. Can you confirm whether piping support design is prescriptive or delegated to the contractor?
Answer: Design drawings are reasonably detailed. Contractor expected to devise means and method for installation work.