This is a Department of Veterans Affairs (VA) construction solicitation for rehabilitating domestic water lines at the George E. Wahlen VA Medical Center in Salt Lake City, Utah. The project, designated as NRM Project #660-23-101, is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a total project magnitude between $2,000,000 and $5,000,000. The contract will involve replacing main domestic water distribution lines, structurally reinforcing the main booster pump house, and constructing a security gate, with work primarily located on the exterior of campus buildings in roadways and sidewalks.

Key contract details include a base performance period of 340 calendar days after Notice to Proceed, with a site visit scheduled for December 11th, 2025, and proposal submissions due by January 8th, 2026, at 10:00 AM Mountain Time. Offerors must be verified and visible in the SBA certification database, have an active SAM registration, and comply with specific limitations on subcontracting. The solicitation will use a trade-off source selection process, with past performance evaluated as significantly more important than price, and requires contractors to have an Experience Modification Rate of 1.0 or less and no significant OSHA violations.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25926R0003 X 11-24-2025 660-23-101 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Mark Holland 303-712-5828 The contractor shall furnish all labor, equipment, materials, and supervision for the rehabilitation of water lines at the Salt Lake City VA Medical Center, Salt Lake City, UT, 84148.

Project magnitude: between $2,000,000.00 and $5,000,000.00. The NAICS code is 237110.

Small Business size standard is $45 Million.

In accordance with P.L. 109-461, this acquisition is 100% set aside for Service-Disabled Veteran Owned Small Businesses concerns. See VAAR 852.219-10, Notice of Total Service-Disabled Veteran Owned Small Business Set-Aside of this solicitation for information in regard to requirements in order to be considered. Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verifications Evaluation (CVE) prior to proposal receipt.

Failure to be both VERIFIED by CVE and VISIBLE on SBA VetCert prior to contract award will result in the offerors proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the aforementioned required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.

A site visit will be held on December 11th, 2025, at 9:00 A.M. MT. Please meet in building six (6) engineering conference room. A campus map has been added as an attachment for location purposes.

All questions in relation to this solicitation must be submitted in writing via e-mail to Mark.Holland@VA.gov and received no later than December 16th, 2025, at 10:00 A.M. MT.

Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes January 8th, 2026, at 10:00 A.M. MT. Email proposals to Mark.Holland@VA.gov.

Proposals shall be submitted via e-mail in accordance with Part I/Section B, to be considered for this project.

Proposals received in any other format will result in the offeror's proposal not receiving further consideration.

A wet signed and stamped copy of the bid bond must be included in the proposal package.

Related to the design or construction of this project, it is understood that all items and/or materials required for this contract will be manufactured within the United States IAW the Buy American Act: 41 U.S.C. Chapter 83. If an item is identified as not manufactured within the United States it needs to be brought up to the COR and CO as early in the process as possible.

X X 52.211-10 X 10:00

MST

01-08-2026 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin

TX

78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE6
ITEM INFORMATION6
A.4 STATEMENT OF WORK6
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS11
2.1 52.204-7 System for Award Management (DEVIATION DATE)18
2.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)21
2.3 52.216-1 TYPE OF CONTRACT (APR 1984)23
2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)23
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)23
2.6 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation. (DEVIATION SEP 2025)24
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)26
2.8 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)26
2.9 52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)30
2.10 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)30
2.11 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)31
2.12 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008)31
REPRESENTATIONS AND CERTIFICATIONS32
3.1 52.209-13 Violation of Arms Control Treaties or Agreements-Certification. (DEVIATION NOV 2025)32
GENERAL CONDITIONS35
4.1 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards.35
4.2 52.204-13 System for Award Management—Maintenance.37
4.3 52.204-14 Service Contract Reporting Requirements.39
4.4 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded.40
4.5 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (DEVIATION NOV 2025)41
4.6 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)42
4.7 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018) (DEVIATION FEB 2025)45
4.8 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) (DEVIATION FEB 2025)48
4.9 52.222-12 CONTRACT TERMINATION—DEBARMENT (MAY 2014) (DEVIATION FEB 2025)49
4.10 52.222-50 Combating Trafficking in Persons. (NOV 2021) (DEVIATION OCT 2025)50
4.11 52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (MAY 2024) (DEVIATION FEB 2025)58
4.12 52.223-23 SUSTAINABLE PRODUCTS AND SERVICES (MAY 2024) (DEVIATION FEB 2025)59
4.13 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)60
4.14 52.233-1 ALT 1 Disputes. (DEVIATION NOV 2025)65
4.15 52.233-3 Protest after Award. (DEVIATION NOV 2025)65
4.16 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) (DEVIATION NOV 2025)66
4.17 52.236-2 DIFFERING SITE CONDITIONS (NOV 2025) (DEVIATION)67
4.18 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (NOV 2025) (DEVIATION)67
4.19 52.236-5 MATERIAL AND WORKMANSHIP (NOV 2025) (DEVIATION)68
4.20 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (NOV 2025) (DEVIATION)69
4.21 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 2025) (DEVIATION)69
4.22 52.236-8 OTHER CONTRACTS (NOV 2025) (DEVIATION)69
4.23 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (NOV 2025) (DEVIATION)70
4.24 52.236-10 OPERATIONS AND STORAGE AREAS (NOV 2025) (DEVIATION)70
4.25 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (NOV 2025) (DEVIATION)71
4.26 52.236-12 CLEANING UP (NOV 2025) (DEVIATION)71
4.27 52.236-13 ACCIDENT PREVENTION (NOV 2025) (DEVIATION)71
4.28 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (NOV 2025) (DEVIATION)73
4.29 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (NOV 2025) (DEVIATION)73
4.30 52.236-17 LAYOUT OF WORK (NOV 2025) (DEVIATION)74
4.31 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (NOV 2025) (DEVIATION) ALTERNATE II (APR 1984)75
4.32 52.243-4 Changes (DEVIATION JUL 2025)76
4.33 52.244-6DEV SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION FEB 2025)77
4.34 SUPPLEMENTAL INSURANCE REQUIREMENTS79
4.35 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION)80
4.36 52.240-93 Basic Safeguarding of Covered Contractor Information Systems.89
4.37 52.252-4 ALTERATIONS IN CONTRACT (APR 1984)91
4.38 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)91
4.39 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)91
4.40 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)93
4.41 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)96
4.42 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)98
4.43 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)98
4.44 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)98
4.45 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023)98
4.46 VAAR 852.222-71 COMPLIANCE WITH EXECUTIVE ORDER 13899 (DEVIATION)(APR 2025)107
4.47 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)108
4.48 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)111
4.49 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)112
4.50 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)113
4.51 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)113
4.52 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)113
4.53 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)115
4.54 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)115
4.55 WAGE RATES116
4.56 LIST OF ATTACHMENTS129

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

Rehabilitate Domestic Water Lines

Contract Period: Base POP Begin: 01-22-2026 POP End: 12-28-2026 PRINCIPAL NAICS CODE: 237110 - Water and Sewer Line and Related Structures Construction PRODUCT/SERVICE CODE: Z2NE - Repair or Alteration of Water Supply Facilities Full POP - 340 calendar days after NTP Admin POP - 130 calendar days after NTP On-Site POP - 210 calendar days after completion of admin POP

GRAND TOTAL
__________________

A.4 STATEMENT OF WORK

Page 1 of Page 1 of Statement of work

Scope of work:

The contractor shall furnish all necessary services, equipment, labor, materials, supervision, and tools to perform construction services for the NRM Project #660-23-101, entitled “Rehabilitate Domestic Water Lies”, located at 500 Foothill Drive, Salt Lake City, UT 84148 on the George E. Wahlen Department of Veterans Affairs Medical Center campus.

The project is a renovation located throughout the George E. Wahlen Department of Veterans Affairs Medical Center campus. The project site is on the exterior of the buildings on campus, mainly in roadways and sidewalks. The project will replace main domestic water distribution lines, structurally reenforce the main booster pump house, and construct security gate for the booster pump house, as such extra attentions will be for phasing and coordinating water shutdowns to minimize impacts to normal hospital operations.

Contractor shall review all specifications and drawings and shall identify any issues to the contracting officer before solicitation deadline. Contractor shall perform work as specified and shall adhere to standard practices for the industry.

The Prime Contractor shall designate a minimum of one Site Safety and Health Officer (SSHO) to administer the contractor’s safety program and government-accepted Accident Prevention Plan. Each subcontractor shall designate a minimum of one Competent Person (CP) in compliance with 29 CFR 1926.20 (b)(2) that will be identified as a CP to administer their individual safety programs. Also, The SSHO, or an equally qualified designated representative/alternative will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor. CPs will maintain presence during their construction activities in accordance with the above-mentioned clause. A listing of the designated SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA.

In order to comply with above, please do NOT bid for same SSHO that would or would potentially cover multiple projects on the campus.

The scope of work includes:

· performing construction services including but not limited to architectural, electrical, mechanical, plumbing, site investigation, and testing/special inspection services.

· The contractor shall review all drawings to verify the project area/s and what the project entails.

· NESHAP Asbestos Survey is furnished with the bid documents.

· The contractor shall be required to lead meetings to discuss progress and problems with the VA staff.

· The contractor shall be required to take meeting minutes and distribute to the VA for approval and as documentation of what was covered within the meeting.

· The contractor shall show a detailed containment plan for infection control and hazmat control. This plan shall be detailed showing locations and what infection and hazmat control requirements are to be used for each area. Safety and infection control requirements shall be enforced for the duration of the project, regardless of any disruptions, to protect patients, visitors, VA staff, and contractors/subcontractors.

· The contractor shall be responsible for the site during construction and shall ensure all contractor employees and subcontractors adhere to all safety and infection control requirements at all times.

Period of Performance

All work is to be completed within 340 calendar days of the Construction Full Notice to Proceed (NTP), which will be presented at time of award. Submission of safety plans, quality control plan, phasing, schedules, pre‐construction submittals, etc. shall be required to be submitted within 30 days after the pre-construction meeting and before any on-site work is to begin.

Additionally, all badging requirements shall be completed prior to any on-site work. Please note that the badging process can take anywhere between 3 to 6 weeks to complete. See badging section for further details.

Infections Control Risk Assessment (IRCA)

ICRA is not necessary due to this requirement being performed entirely outside. Protection for external air intakes are already in place.

The Contractor shall be required follow proper infection control measures as outlined in the attached PCRA. Any additional infectious control measures shall be routed through the COR and contracting department.

Contractor to ensure that all adjacent surfaces are protected from damage during the period of construction. Patch and repair any damage due to construction before the end of the contract period.

Phasing standards

Due to adjacent buildings being occupied during the weekdays, Monday through Friday from 0700 to 1630, the Contractor shall phase and coordinate construction accordingly with VA COR to ensure that the individual building domestic water supply and affected roads are shut down for a minimal amount of time.

Work Schedule

Normal working hours are from 0700 to 1630. Work is not expected to be performed after hours. However, if work is necessary “Afterhours” working hours are to be limited to a single work shift and afterhours work needs to be approved by VA Contracting Officers Representative (COR) or Resident Engineer (RE). If portions of the afterhours work need to be extended to be completed during “Normal” working hours, work performed during “Normal” working hours will need to be approved and coordinated by the COR or RE.

In order to maintain the schedule, work performed over the weekend, particularly overhead work will be allowed. Contractor to coordinate these efforts with VA COR with a minimum 48-hour notice.

Mitigation statement

Should asbestos or other hazardous materials be discovered, the situation will be treated as unforeseen site conditions and handled accordingly.

Safety

The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the contractor have a “Competent Person” on the job at all times (must have a 30-hour OSHA card), and that all contractor employees have received a minimum of ten (10) hours of OSHA construction safety training. Documentation of these requirements shall be submitted and approved prior to performing the work.

The contractor must submit a company Site Specific Safety Plan (SSSP) that must be approved by VA Safety prior to work beginning. This plan shall detail fire, construction, and health-related safety measures, in addition to listing Training Records for all employees for the previous year. A company standard or boilerplate safety plan will not be acceptable – plan should contain a detailed hazard analysis for each element of construction to be performed such as an Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA).

This entire project shall conform to 100% of all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes.

The Contractor shall be responsible for the health and safety of their own employees. The VA will inform the Contractor of any hazards such as designated permit confined spaces, electrical hazards, etc. which may affect Contractor employees. The Contractor must take precautions appropriate for the safety of their employees as well as provide equipment necessary for these actions. Contractor employees will notify the VA Representative before entering a designated permit required confined space, so precautions can be taken in advance of the work.

The Contractor shall hold harmless and indemnify the Government against any and all liability, claims, and costs of whatsoever kind and nature for injury to or death of any person or persons and for loss or damage to any property occurring in connection with, in any way incident to, or arising out of the occupancy, use, service, operation or performance of work under the terms of the contract, resulting in whole or in part from the negligence acts or omissions of the Contractor, any subcontractor, or any employee, agent, or representative of the Contractor or subcontractor.

The Contractor is responsible for protection of existing finishes, and VA property, furnishings, fixtures, and equipment (FF&E), located in the areas where demolition, construction, preventative maintenance, and repair work is being performed, as well as along paths of travel to and from these areas. Both exterior and interior finishes and property must be maintained. The contractor is liable for any damage to VA property during the course of the contract. Any damage to existing finishes must be repaired by the Contractor to equal or greater quality than existing finishes. All tasks accomplished by the Contractor personnel will be performed to preclude damage or disfigurement of government-owned FF&E and architectural or building structures. Contractor will report any damage or disfigurement to these items when caused by the Contractor’s personnel and will perform repairs or replace government-owned equipment, fixtures, furnishings, grounds and architectural or building structures to their previously existing condition.

Badging:

All employees of general contractor and subcontractors shall comply with VA security management program and obtain temporary VA badges. This will require fingerprinting and background checks of each individual. The employees of the general contractor will obtain permission from VA Human Resources, be identified by project and employer, and restricted from unauthorized access. Copies of required badging pamphlet documents have been included as attachments and are to be used by the successful offer upon award.

Training:

All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete VA Privacy and Information Security Awareness and Rules of Behavior Training.

Post Construction Quality Validation

The contractor is to provide a one (1) year warranty period, from the date of final acceptance of the work, covering defects related to all work performed and any materials/equipment included in the project.

End of Statement of Work

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4. Certified SDVOSB/VOSB listed in the SBA certification database at https://veterans.certify.sba.gov/ (see 13 CFR 128). A joint venture may be considered eligible if it meets the requirements in 13 CFR part 128, and the managing joint venture partner makes the representations under VAAR 819.7003 paragraph (b). An offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETCERT.

I.2A SELECTION PROCEDURES

This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.

I.3A PRE-PROPOSAL SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. If deemed necessary by the station, masks are required to be worn by all employees and contractors while on VA property.

I.4A SELECTION CRITERIA

This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.

The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:

Factor 1 – Past Performance Factor 2 – Price

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

Past performance will be evaluated on a basis of significantly more important than, cost or price.

Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:

ASSESSMENT
DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

Factor 1-Past Performance

(a) Solicitation Submittal Requirements:

Offerors shall provide a minimum of two (2) and maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Mark Holland, Mark.Holland@va.gov.

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts in a project of renovation or remodeling that include general construction in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the offeror’s past performance will be used as a means of evaluating the offeror’s probability to successfully meet the requirements of the RFP.

Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.

If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.

If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.

Factor 2 – Price:

(a) Solicitation Submittal Requirements:

· Standard Form 1442, Solicitation Offer and Award

· All pages of the SF1442 Continuation Sheet

(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

· Comparison of proposed prices received in response to the RFP

· Comparison of proposed prices with the IGCE.

· Comparison of proposed prices with available historical information.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0. If an offeror’s EMR is above 1.0, the offeror must submit a written explanation of the EMR from its insurance carrier on the insurance carrier’s letterhead, describing the reasons for the EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Offerors who fail to meet any special standard of responsibility may not be eligible to receive contract award.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $2,000,000.00 and $5,000,000.00

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email Mark.Holland@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, one attachment for LOS certification, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. A digital bid bond with wet signature, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be included with the proposal and be received no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.

Proposals shall be received by 10:00 A.M. Mountain Time on December 29th, 2025. There will be no public opening of the proposals. Submit proposals to: Mark.Holland@va.gov.

Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Important Notice: Apparent successful offerors must apply for and receive verification from the Small Business Administration (SBA) through the SBA certification database via 13 CFR Part 128, VAAR 819.7011, and VAAR 819.7003 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the SBA certification database at the time of offer submission. Failure to be both VERIFIED by SBA and VISIBLE on the SBA certification database at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the SBA and submit the required documents to obtain verification of their SDVOSB status if they have not already done so.

Or

Meet Federal Acquisition Regulation (FAR) class deviation regarding certification of Service-Disabled Veteran Owned Small Business concerns as per CAAC Letter 2024-02, effective January 1, 2024, until SAM.gov is updated to reflect the SBA’s certification or otherwise rescinded.

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals – Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications – Commercial Products and Commercial Services. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

I.6B PROPOSAL REVISIONS

If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal additional information and/or changed documents would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.

1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).

2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

4. Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, Proposal, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipient’s “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus, or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.

5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

2.1 52.204-7 System for Award Management (DEVIATION DATE) As prescribed in 4.208(b)(1), use the following provision:

System for Award Management (DEVIATION DATE) The Offeror shall have an active Federal Government contracts registration in the System for Award Management (SAM) when submitting an offer or quotation in response to this solicitation and at the time of award. As part of the SAM registration process, the Government collects information, as described in paragraphs (b) through (d) of this provision, that is necessary to identify the Offeror and for the Offeror to be awarded Federal Government contracts. To register in SAM, go to https://www.sam.gov. Allow for processing time when registering in SAM. If the Offeror is not registered in SAM, it should register immediately after receiving this solicitation.

(a) Definitions. As used in this provision— Commercial and Government Entity (CAGE) code has the meaning provided in the clause at the Federal Acquisition Regulation (FAR) 52.204-13, System for Award Management—Maintenance, of this solicitation.

Electronic Funds Transfer (EFT) indicator means a bank account identifier to establish additional System for Award Management records for identifying alternative EFT accounts (see part 32) for the same entity.

Highest-level owner means the entity that owns or controls an immediate owner of the offeror, or that owns or controls one or more entities that control an immediate owner of the offeror. No entity owns or exercises control of the highest-level owner.

Immediate owner means an entity, other than the offeror, that has direct control of the offeror. Indicators of control include, but are not limited to, one or more of the following: ownership or interlocking management, identity of interests among family members, shared facilities and equipment, and the common use of employees. There may be more than one immediate owner (e.g., joint ventures).

Predecessor means an entity whose assets were acquired by the offeror…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .