Prime and Sub Contractor Construction Breakdown.xlsx

XLSX spreadsheet 147 KB Posted

Attached to
Imaging System Removal Floor Restoration and Electrical Work Federal contract opportunity
Solicitation number
36C25926Q0539
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19

About this file

This is a construction cost estimate template organized by CSI Divisions for tracking prime and subcontractor construction costs. The spreadsheet provides a standardized framework for estimating and breaking down project costs across 24 construction divisions, including general requirements, concrete, masonry, metals, thermal and moisture protection, doors and windows, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and transportation. Each division section contains separate line items for labor and materials costs, with columns for quantity, unit, and unit price calculations, along with provisions for local market condition adjustments and small business utilization percentages. The template includes a summation sheet that consolidates all division costs and calculates overhead, profit, bonds, and the final project total. All cost fields are currently blank, indicating this is an empty template for future project estimation.

View the file

Other files for this federal contract opportunity

Other files attached to Imaging System Removal Floor Restoration and Electrical Work, newest first.
File Type Posted
Answers to RFIs.pdf PDF
36C25926Q0539 0002.pdf PDF
S04- Pre bid site visit attendance..pdf PDF
S04 - Site Visit Meeting Doc.docx DOCX document
36C25926Q0539 0001.pdf PDF
S22 LOS Certification 852.219-75 JAN 2023 DEVIATION.docx DOCX document
ICRA Requirements.docx DOCX document
36C25926Q0539.pdf PDF
36C25926Q0539_1 Presol.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMATION

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NEW PROJECTNO DESIGNPRELIMINARY
COMPLETEDDESIGN
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMNOTESTOTAL
ABCD
DIVISION 0-SPECIAL SECTIONS$ - 0
DIVISION 1-GENERAL REQUIREMENTS$ - 0
DIVISION 2-EXISTING CONDITIONS$ - 0
DIVISION 3-CONCRETE$ - 0
DIVISION 4-MASONRY$ - 0
DIVISION 5-METALS$ - 0
DIVISION 6-WOOD AND PLASTIC$ - 0
DIVISION 7-THERMAL AND MOISTURE PROTECTION$ - 0
DIVISION 8-DOORS AND WINDOWS$ - 0
DIVISION 9-FINISHES$ - 0
DIVISION 10-SPECIALTIES$ - 0
DIVISION 11-EQUIPMENT$ - 0
DIVISION 12-FURNISHINGS$ - 0
DIVISION 13-SPECIAL CONSTRUCTION$ - 0
DIVISION 14-CONVEYING EQUIPMENT$ - 0
DIVISION 21-FIRE SUPPRESSION$ - 0
DIVISION 22-PLUMBING$ - 0
DIVISION 23-HEAT, VENTILATING, AND AIR CONDITIONING$ - 0
DIVISION 26-ELECTRICAL$ - 0
DIVISION 27-COMMUNICATIONS$ - 0
DIVISION 28-ELECTRONIC SAFETY AND SECURITY$ - 0
DIVISION 31-EARTHWORK$ - 0
DIVISION 32-EXTERIOR IMPROVEMENTS$ - 0
DIVISION 33-UTILITIES$ - 0
DIVISION 34-TRANSPORTATION$ - 0
SUB-TOTAL$ - 0
OVERHEAD@$ - 0
PROFIT@$ - 0
BONDS@$ - 0
PROJECT TOTAL:$ - 0

&A

&D

Div 0 Special Sections

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 0 Special Sections
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&A

&D

Div 1 General Requirements

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Divison 1 General Requirements
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

Div 2 Existing Conditions

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 2 Existing Conditions
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&A

&D

Div 3 Concrete

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 3 Concrete
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&A

&D

Div 4 Masonry

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 4 Masonry
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&A

&D

Div 5 Metals

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 5 Metals
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization0.00%$0
SECTION TOTAL:$0

&A

&D

Div 6 Wood & Plastic

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 6 Wood & Plastic
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&A

&D

Div 7 Thermal & Moisture Protec

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 7 Thermal & Moisture Protection
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 8 Doors & Windows

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 8 Doors & Windows
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&D

Div 9 Finishes

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 9 Finishes
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions10.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 10 Specialties

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 10 Specialties
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 11 Equipment

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 11 Equipment
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 12 Furnishings

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 12 Furnishings
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 13 Special Construction

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 13 Special Construction
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&D

Division 14 Conveying Equipment

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 14 Conveying Equipment
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 21 Fire Suppression

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 21 Fire Suppression
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 22 Plumbing

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 22 Plumbing
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 23 HVAC

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 23 Heat, Ventilating, and Air Conditioning
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&D

Div 26 Electrical

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 26 Electrical
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market ConditionsSmall Business Utilization$0
SECTION TOTAL:$0

&D

Div 27 Communications

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 27 Communications
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 28 Electronic Safety & Secu

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 28 Electronic Safety & Security
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 31 Earthwork

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 31 Earthwork
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization$0
SECTION TOTAL:$0

&D

Div 32 Exterior Improvements

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 32 Exterior Improvements
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 33 Utilities

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 33 Utilities
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0

&D

Div 34 Transportation

DATE
SHEET NO.OFSHEETS

PROJECT NO. LOCATION PROJECT NAME TYPE OF ESTIMATE

NO DESIGNPRELIMINARY
COMPLETEDDESIGN
ESTIMATORNEWALTINDEX NO.BUILDING NO(S)DRAWING NO.
FINALOTHER
DESIGN(SPECIFY)
CODESYSTEM/SUBSYSTEMLABORMATERIALS
ABCDQUANTITYUNIT$/UNITTOTALQUANTITYUNIT$/UNITTOTALTOTAL
Division 34 Transportation
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
$0.00$0.00$0
Adjustments:Local Market Conditions0.00%Small Business Utilization0.00%$0
SECTION TOTAL:$0

&D

File details come from the government source that posted it. Updated .