This file contains ICRA (Infection Control Risk Assessment) Level III requirements for construction work at a healthcare facility. The requirements establish comprehensive dust control, containment, and air quality protocols that contractors must implement throughout project execution. Key requirements include performing work without creating dust, immediately replacing ceiling tiles and access panels upon completion, ensuring all materials and equipment are free of contaminants, and providing active dust control measures such as mobile dust containment carts or water mist systems. Worker clothing must remain clean and free of visible dust before leaving work areas, and air diffusers must be removed or isolated with the HVAC system rebalanced accordingly. For potable water systems, piping must be flushed twice weekly or isolated from the main system to prevent stagnation.
The containment specifications mandate construction of critical barriers meeting NFPA 241 requirements that extend to the ceiling or deck above, with all penetrations sealed using approved materials. The workspace must maintain continuous 24/7 negative pressurization of 0.01 inches water gauge using HEPA exhaust systems directed outdoors at least 25 feet from entrances and air intakes. A differential pressure sensing device must continuously monitor and document negative pressurization. When exterior exhaust is not feasible, Appendix A provides an alternative interior exhaust procedure requiring HEPA filtration, baseline and post-installation particulate sampling using particle counters measuring down to 0.3 microns, vapor assessment, complete flow and pressure analysis, and direction of exhaust only to low-risk areas. Daily cleaning protocols, sealed trash containers, sticky mats at containment entrances, and hand-cleaning equipment availability are also required throughout the project duration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Answers to RFIs.pdf | ||
| 36C25926Q0539 0002.pdf | ||
| 36C25926Q0539 0001.pdf | ||
| S04- Pre bid site visit attendance..pdf | ||
| S04 - Site Visit Meeting Doc.docx | DOCX document | |
| 36C25926Q0539.pdf | ||
| Prime and Sub Contractor Construction Breakdown.xlsx | XLSX spreadsheet | |
| S22 LOS Certification 852.219-75 JAN 2023 DEVIATION.docx | DOCX document | |
| 36C25926Q0539_1 Presol.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ICRA REQUIREMENTS.
The ICRA Level would be considered Level III. Please see below for requirements.
1. Perform work activity in a manner that does not create dust.
1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
1. Any materials and equipment being brought into the facility must be free of contaminants and loose material.
1. Provide active means to control airborne dust from dispersing into occupied areas and/or water mist surface to control dust (e.g., Mobile Dust Containment Cart or some other system).
1. Ensure worker clothing is clean and free of visible dust before leaving the work area.
1. Remove or isolate air diffusers (supply and return) to protect the HVAC system from dust and reduce air turbulence. Rebalance system to address diffuser isolation.
1. When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system.
1. Seal doors to prevent dust migration.
1. Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.
1. Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area.
1. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
1. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
1. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily.
1. Ensure availability of equipment for cleaning hands.
1. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.
1. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.
1. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).
1. Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors, or comply with the alternative method outlined in Appendix A of this document. These control measures must be maintained continuously 24/7 for the duration of the project. HEPA filtered exhaust if discharged directly to the outdoors must be at a distance of 25 feet or greater from entrances, air intakes and operable windows. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited.
1. Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The “ball in the wall” or similar apparatus are not acceptable Appendix A Interior Construction Space Exhaust:
If the facility is not able to exhaust to the building exterior, the Healthcare Environment and Facilities program office has identified an alternate industry-recognized standard interior exhaust procedure that is accepted as providing an equivalent level of infection prevention and control (IPC), and safety. The alternate interior exhaust procedure is implemented by completing the following:
a. If exhaust is directed indoors, then the system must be HEPA filtered. Maintain .01 inches water gauge negative pressurization of the entire workspace by use of HEPA exhaust. These control measures must be maintained continuously 24/7 for the duration of the project.
b. Prior to start of work, including assembly of the ICRA barriers, initial baseline air sampling measurements for particulate levels must be taken in the planned area of discharge. Once containment is erected and completed, HEPA filtration must then be verified by particulate measurement, using a particle counter with multi-channel capabilities to measure down to 0.3 microns, to confirm that the discharge of the HEPA unit does not exceed the baseline particulate count of the area to which the exhaust is directed. Verification must continue at least once per 8 hour shift when there is construction activity. Any exceedance must trigger a work stoppage and an immediate response and resolution. All particulate measurements, including the baseline measurement, must be documented and retrievable.
c. To accommodate the sampling, the negative air pressure machine must be fitted with a 2 ft section of rigid ductwork at the discharge. The sample port for monitoring must be in the rigid ductwork section.
d. Vapor generating processes must be assessed and appropriate filtration must be installed to mitigate transmission to the facility.
e. Engineering must do a complete flow and pressure analysis and document the area to which the air is being discharged to ensure the flow and pressure relationships in that area are not being adversely impacted by the additional flow. Ideally, this is done as part of the construction package to ensure the design is implementable and no additional HVAC changes are required to accommodate the exhaust from the negative air equipment.
f. Install device on exterior of work containment to continually monitor negative pressurization. To ensure proper pressure is continuously maintained, the device(s) shall have a visual pressure indicator, data collection and alarm.
g. Exhaust must be directed to Low Risk areas as defined in Table 3 in this VHA ICRA template. Ideally this discharge must be located so as not to impinge on high traffic areas or create a nuisance with noise or excessive airflow.
NOTE: Exhaust into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is not acceptable.