This is a Price Schedule for janitorial services at the George E. Wahlen VA Medical Center in Salt Lake City, Utah, covering a base year from March 1, 2026 through February 28, 2027, plus two option years. The contract includes six contract line items (CLINs) for the base year and corresponding CLINs for each option year. Services consist of janitorial operations across multiple buildings (1, 2, 4, 5, 6, 7, 8, 9, 14, 16, 18, 47, and 49) with varying shift schedules: CLIN 0001 covers first and second shift services for buildings 2, 4, 5, 6, 7, 8, 9, 16, 18, 47, and 49 on weekdays (7:00 a.m. to 3:30 p.m. and 5:00 p.m. to 1:30 a.m.); CLIN 0002 covers two-shift main hospital services for buildings 1 and 14 on weekdays (5:00 p.m. to 1:30 a.m. and 1:00 a.m. to 9:30 a.m.); CLIN 0003 addresses three-shift weekend services for the main hospital; CLIN 0004 provides porter services in the main hospital on weekdays (7:00 a.m. to 3:30 p.m.); CLIN 0005 covers annual stripping and waxing for all buildings; and CLIN 0006 includes semi-annual carpet cleaning services. The quote submission deadline is February 13, 2026 at 5:00 PM Mountain Time, with all pricing fields left blank for offeror completion.

View the file

Other files for this federal contract opportunity

Other files attached to S201--EMS Housekeeping Services - new base + 2, newest first.
File Type Posted
36C25926Q0071 0004.docx DOCX document
36C25926Q0071 0003.docx DOCX document
Attachment 2 - revised Price Schedule.docx DOCX document
Building 5-13 Complete set.pdf PDF
Room Audit Summary.pdf PDF
DOL Wage Determination 2015-5489.txt TXT text file
Building 37-47 Complete set.pdf PDF
Building 14 Complete set 1.pdf PDF
Building 2-4 Complete set.pdf PDF
Building 1 Complete set 2.pdf PDF
Questions and Answers.docx DOCX document
revised HOUSEKEEPING PWS 2.10.2026.docx DOCX document
Building 16-20 32 Complete set.pdf PDF
Building 1 2 F zone.pdf PDF
Campus Map 1.pdf PDF
36C25926Q0071 0002.docx DOCX document
36C25926Q0071 0001.docx DOCX document
36C25926Q0071.docx DOCX document
Attachment 3 - VA Notice of Limitations on Subcontracting.docx DOCX document
Attachment 2 - Price Schedule.docx DOCX document
Attachment 1 - PWS.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

POP: Base Year March 1, 2026 – February 28, 2027

CLIN
DESCRIPTION OF SERVICES
QTY
U/I
UNIT PRICE
TOTAL AMOUNT
0001
Janitorial services for buildings 2,4,5,6,7,8,9,16,18,47, and 49; first and second shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (outside bldg.)

(Crew 3) 0700 a.m. to 3:30 p.m., (Crew 3A) 5:00 p.m. to 1:30 a.m.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

12
MO
$_______
$_____________
0002
Janitorial services of main hospital areas (bldg. 1 and 14,) for two (2) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (main)

Crew 1 from 5:00 p.m. to 1:30 a.m.

Crew 1A from 1:00 a.m. to 9:30 a.m.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

12
MO
$_______
$_____________
0003
Janitorial services for main hospital (bldg. 1 and 14,); three (3) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Saturday and Sunday, (crew 4).

(Team A), 0700 a.m. to 3:30 p.m.

(Team B) 3:00 p.m. to 11:30 p.m.

(Team C) 11:00 p.m. to 07:30 a.m.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

12
MO
$_______
$_____________
0004
Janitorial services for main hospital (bldg. 1,4 and 14,); one (1) shift to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (porters)

(Crew 2) 07:00 a.m. to 3:30 p.m.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

12
MO
$_______
$_____________
0005
Annual stripping and waxing services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

1
YR
$_______
$_____________
0006
Semi-annual carpet cleaning services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Base POP Begin: 03-01-2026 POP End: 02-28-2027

2
YR
$_______
$_____________

POP: Option Year 1 - March 1, 2027 – February 29, 2028

CLIN
DESCRIPTION OF SERVICES
QTY
U/I
UNIT PRICE
TOTAL AMOUNT
1001
Janitorial services for buildings 2,4,5,6,7,8,9,16,18,47, and 49; first and second shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (outside bldg.)

(Crew 3) 0700 a.m. to 3:30 p.m., (Crew 3A) 5:00 p.m. to 1:30 a.m.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

12
MO
$________
$_____________
1002
Janitorial services of main hospital areas (bldg. 1 and 14,) for two (2) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (main)

Crew 1 from 5:00 p.m. to 1:30 a.m.

Crew 1A from 1:00 a.m. to 9:30 a.m.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

12
MO
$________
$_____________
1003
Janitorial services for main hospital (bldg. 1 and 14,); three (3) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Saturday and Sunday, (crew 4).

(Team A), 0700 a.m. to 3:30 p.m.

(Team B) 3:00 p.m. to 11:30 p.m.

(Team C) 11:00 p.m. to 07:30 a.m.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

12
MO
$________
$_____________
1004
Janitorial services for main hospital (bldg. 1,4 and 14,); one (1) shift to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (porters)

(Crew 2) 07:00 a.m. to 3:30 p.m.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

12
MO
$________
$_____________
1005
Annual stripping and waxing services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

1
YR
$_______
$_____________
1006
Semi-annual carpet cleaning services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Option 1 POP Begin: 03-01-2027 POP End: 02-29-2028

2
YR
$_______
$_____________

POP: Option Year 2 - March 1, 2028 – February 28, 2029

CLIN
DESCRIPTION OF SERVICES
QTY
U/I
UNIT PRICE
TOTAL AMOUNT
2001
Janitorial services for buildings 2,4,5,6,7,8,9,16,18,47, and 49; first and second shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (outside bldg.)

(Crew 3) 0700 a.m. to 3:30 p.m., (Crew 3A) 5:00 p.m. to 1:30 a.m.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

12
MO
$________
$_____________
2002
Janitorial services of main hospital areas (bldg. 1 and 14,) for two (2) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (main)

Crew 1 from 5:00 p.m. to 1:30 a.m.

Crew 1A from 1:00 a.m. to 9:30 a.m.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

12
MO
$________
$_____________
2003
Janitorial services for main hospital (bldg. 1 and 14,); three (3) different shifts to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Saturday and Sunday, (crew 4).

(Team A), 0700 a.m. to 3:30 p.m.

(Team B) 3:00 p.m. to 11:30 p.m.

(Team C) 11:00 p.m. to 07:30 a.m.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

12
MO
$________
$_____________
2004
Janitorial services for main hospital (bldg. 1,4 and 14,); one (1) shift to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement on Monday, Tuesday, Wednesday, Thursday, and Friday. (porters)

(Crew 2) 07:00 a.m. to 3:30 p.m.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

12
MO
$________
$_____________
2005
Annual stripping and waxing services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

1
YR
$_______
$_____________
2006
Semi-annual carpet cleaning services for buildings 1,2,4,5,6,7,8,9,14,16,18, 47, and 49; to the VA Medical Center in Salt Lake City in accordance with the Performance Work Statement.

Contract Period: Option 2 POP Begin: 03-01-2028 POP End: 02-28-2029

2
YR
$_______
$_____________
BASE YEAR TOTAL
$
OPTION YEAR 1 TOTAL
$
OPTION YEAR 2 TOTAL
$
GRAND TOTAL BASE PLUS 2 OPTION YEARS
$