About this file

This document outlines the requirements for a federal construction contract opportunity. The project involves relocating an MRI trailer at the Grand Junction, Colorado VA Medical Center to a new on-campus location, including demolishing existing structures, constructing a new concrete pad and enclosure, installing HVAC infrastructure, and reconnecting utilities. The contractor will be responsible for project management, scheduling, safety compliance, obtaining badges for employees, conducting interim life safety measures, and providing a one-year warranty on all work. The period of performance is 180 calendar days from notice to proceed. Work hours are generally Monday through Friday from 7:00 AM to 5:00 PM, excluding federal holidays, though some weekend or after-hours work may be approved in advance.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--MRI Trailer Relocate, newest first.
File Type Posted
S06 - 077100 ROOF SPECIALTIES.pdf PDF
36C25923R0021 0002.docx DOCX document
S05 - RFIs and Responses_2nd.pdf PDF
GMRVE-3000-D20-48-06 - GE Voyager-Explorer (004).pdf PDF
GJ Geotech Report 2019.pdf PDF
Site Utilities.pdf PDF
S05 - RFIs and Responses.pdf PDF
S04 - Pre-Bid Sign in.pdf PDF
S-101.1 CONSTRUCTION.pdf PDF
S04 - Site Visit Meeting Doc_MRI Trailer.pdf PDF
36C25923R0021 0001.docx DOCX document
852.219-75 LOS Certification.docx DOCX document
03 Plans.pdf PDF
03 Specifications.pdf PDF
36C25923R0021.docx DOCX document
03 Additional Information.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-18

05 12 00 - 1

SECTION 05 12 00

STRUCTURAL STEEL FRAMING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Structural steel shapes, plates, and bars.

2. Structural pipe.

3. Bolts, nuts, and washers.

1.2 RELATED REQUIREMENTS

A. Steel Joist: Section 05 21 00, STEEL JOIST FRAMING.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. American Institute of Steel Construction (AISC):

1. AISC Manual - Steel Construction Manual, 14th Ed.

2. 303-10 - Code of Structural Steel Buildings and Bridges.

3. 360-10: Specification for Structural Steel Buildings.

C. The American Society of Mechanical Engineers (ASME):

1. B18.22.1-09 - Washers: Helical Spring-Lock, Tooth Lock, and Plain

Washers.

D. American Welding Society (AWS):

1. D1.1/D1.1M-15 - Structural Welding Code - Steel.

E. ASTM International (ASTM):

1. A6/A6M-14 - General Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling.

2. A36/A36M-14 - Carbon Structural Steel.

3. A53/A53M-12 - Pipe, Steel, Black and Hot-Dip, Zinc-Coated, Welded and Seamless.

4. A123/A123M-15 - Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel

Products.

5. A242/A242M-13 - High-Strength Low-Alloy Structural Steel.

6. A283/A283M-13 - Low and Intermediate Tensile Strength Carbon Steel

Plates.

7. A307-14 - Carbon Steel Bolts, Studs, and Threaded Rod 60,000 PSI

Tensile Strength.

8. A500/A500M-13 - Cold-Formed Welded and Seamless Carbon Steel

Structural Tubing and Rounds and Shapes.

05 12 00 - 2

9. A501/A501M-14 - Hot-Formed Welded and Seamless Carbon Steel

Structural Tubing and Rounds and Shapes.

10. A572/A572M-15 - High-Strength Low-Alloy Columbium-Vanadium Structural Steel.

11. A992/A992M-15 - Structural Shapes.

12. F2329/F2329M-15 - Zinc Coating, Hot-Dip, Requirements for

Application to Carbon and Alloy steel Bolts, Screws, washers, Nuts, and Special Threaded Fasteners.

13. F3125/F3125M-15 - Standard Specification for High Strength Structural Bolts, Steel and Alloy Steel, Heat Treated, 120 ksi (830

MPa) and 150 ksi (1040 MPa) Minimum Tensile Strength, Inch and

Metric Dimensions

F. Master Painters Institute (MPI):

1. No. 18 - Primer, Zinc Rich, Organic.

G. Military Specifications (Mil. Spec.):

1. MIL-P-21035 - Paint, High Zinc Dust Content, Galvanizing, Repair.

H. Occupational Safety and Health Administration (OSHA):

1. 29 CFR 1926.752(e) - Guidelines For Establishing The Components Of A

Site-Specific Erection Plan.

2. 29 CFR 1926-2001 - Safety Standards for Steel Erection.

I. Research Council on Structural Connections (RCSC) of The Engineering

Foundation:

1. Specification for Structural Joints Using ASTM F3125 Bolts.

1.4 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Submittal Drawings:

1. Show size, configuration, and fabrication and installation details.

2. The contractor shall submit structural steel shop drawings for all structural steel, steel connections, bolts and fasteners, stamped and signed by a state licensed structural engineer.

C. Sustainable Construction Submittals:

D. Test Reports: Certify products comply with specifications.

1. Welders' qualifying tests.

E. Certificates: Certify each product complies with specifications.

1. Structural steel.

2. Steel connections.

3. Welding materials.

05 12 00 - 3

4. Shop coat primer paint.

F. Qualifications: Substantiate qualifications comply with specifications.

1. Fabricator.

2. Installer.

3. Welders and welding procedures.

G. Delegated Design Drawings and Calculations: Signed and sealed by responsible Architect/Engineer.

1. Connection calculations.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: AISC Quality Certification Program participant designated as AISC-Certified Erector, Category ACSE.

1. Regularly installs specified products.

2. Installed specified products with satisfactory service on five

B. Welders and Welding Procedures Qualifications: AWS D1.1/D1.1M.

1.6 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of

Construction."

PART 2 - PRODUCTS

2.1 SYSTEM PERFORMANCE

A. Design structural steel framing connections complying with specified performance:

1. Load Capacity: Resist loads indicated on drawings. Account for connection and member loads and eccentricities.

a. Request additional design criteria when necessary to complete connection design.

2. Configuration: The details shown on drawings are conceptual and do not indicate the required weld sizes or number of bolts unless specifically noted. Use rational engineering design and standard practice in detailing, accounting for all loads and eccentricities in both the connection and the members. Promptly notify the

Contracting Officer Representative of any location where the connection design criteria is not clearly indicated. The design of all connections is subject to the review and acceptance of the

Contracting Officer's Representative.

05 12 00 - 4

2.2 MATERIALS

A. Welding Materials: AWS D1.1, type to suit application.

2.3 PRODUCTS - GENERAL

A. Basis of Design: Section 09 06 00, SCHEDULE FOR FINISHES.

2.4 FABRICATION

A. Fabricate structural steel according to Chapter M, AISC 360.

B. Shop and Field Connections:

1. Weld connections according to AWS D1.1/D1.1M. Welds shall be made only by welders and welding operators who have been previously qualified by tests as prescribed in AWS D1.1 to perform type of work required.

2. High-Strength Bolts: High-strength bolts tightened to a bolt tension minimum 70 percent of their minimum tensile strength. Tightening done with properly calibrated wrenches, by turn-of-nut method or by use of direct tension indicators (bolts or washers). Tighten bolts in connections identified as slip-critical using Direct Tension

Indicators. Twist-off torque bolts are not an acceptable alternate fastener for slip critical connections.

2.5 FINISHES

A. Shop Priming:

1. Prime paint structural steel according to AISC 303, Section 6.

B. Do not paint:

1. Surfaces within 50 mm (2 inches) of field welded joints.

2. Surfaces indicated to be encased in concrete.

3. Surfaces receiving sprayed on fireproofing.

4. Beam top flanges receiving shear connector studs applied.

C. Structural Steel Galvanizing: ASTM A123/A123M, hot dipped, after fabrication. Touch-up after erection: Clean and wire brush any abraded and other spots worn through zinc coating, including threaded portions of bolts and welds and touch-up with galvanizing repair paint.

1. Galvanize structural steel framing installed at exterior locations.

D. Bolts, Nuts, and Washers Galvanizing: ASTM F2329, hot-dipped.

2.6 ACCESSORIES

A. General: Shop paint steel according to AISC 303, Section 6.

B. Galvanizing Repair Paint: MPI No. 18.

05 12 00 - 5

PART 3 - EXECUTION

3.1 ERECTION

A. Erect structural steel according to AISC 303 and AISC 360.

B. Set structural steel accurately at locations and elevations indicated on drawings.

C. Maintain erection tolerances of structural steel within AISC 303 requirements.

1. Pour Stop Elevation Tolerance: 6 mm (1/4 inch), maximum, before concrete placement.

D. Weld and bolt connections as specified for shop connections.

3.2 FIELD PAINTING

A. After welding, clean and prime weld areas to match adjacent finish.

B. Touch-up primer damaged by construction operations.

3.3 FIELD QUALITY CONTROL

A. Record Survey:

1. Measure and record structural steel framing plumbness, level, and alignment after completing bolting and welding and before installation of work supported by structural steel.

2. Identify deviations from allowable tolerances specified in

AISC Manual.

- - E N D - -