S04 - Site Visit Meeting Doc_MRI Trailer.pdf
PDF 96 KB Posted
- Attached to
- Z2DA--MRI Trailer Relocate Federal contract opportunity
- Solicitation number
- 36C25923R0021
About this file
This document contains a pre-bid meeting file and related federal contract opportunity solicitation for relocating a mobile MRI trailer at the Grand Junction, Colorado VA Medical Center. Key details include:
-
The solicitation number is 36C25923R0021 for project 575-19-101 to relocate the MRI trailer to a new location on campus, including modifying pavement and utilities, moving the trailer using truck and crane, and connecting utilities and an enclosure.
-
The pre-bid meeting file outlines pertinent dates such as questions due by February 1, 2023 and bids due by February 14, 2023. It provides guidelines for the site visit and prohibits unapproved visits.
-
The opportunity description specifies tasks such as constructing a concrete pad, demolishing an existing dock roof and enclosure, installing HVAC and electrical infrastructure, and certifying the MRI after relocation. Work must be completed within 180 days of the notice to proceed.
-
Safety, regulatory and reporting requirements are defined including submitting a site safety plan, activity hazard analyses, and weekly certified payrolls with invoices. The one-year warranty period is also stated.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S06 - 077100 ROOF SPECIALTIES.pdf | ||
| 36C25923R0021 0002.docx | DOCX document | |
| S05 - RFIs and Responses_2nd.pdf | ||
| GMRVE-3000-D20-48-06 - GE Voyager-Explorer (004).pdf | ||
| GJ Geotech Report 2019.pdf | ||
| Site Utilities.pdf | ||
| S-101.1 CONSTRUCTION.pdf | ||
| 051200 STRUCTURAL STEEL FRAMING_rev1.pdf | ||
| 36C25923R0021 0001.docx | DOCX document | |
| S05 - RFIs and Responses.pdf | ||
| S04 - Pre-Bid Sign in.pdf | ||
| 852.219-75 LOS Certification.docx | DOCX document | |
| 03 Specifications.pdf | ||
| 36C25923R0021.docx | DOCX document | |
| 03 Additional Information.pdf | ||
| 03 Plans.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
575-19-101 Relocate MRI Trailer
Provide labor, materials, equipment, and other services as necessary to modify existing pavement and utilities, relocate the mobile MRI trailer to the new location, and connect the MRI trailer and the existing building with an enclosure.
All work must be done in compliance with applicable OSHA, EPA and federal/state environmental regulations and policies. Contractor is responsible for proper handling and disposal of debris, waste and excess fuel generated during completion of this work.
Location: Grand Junction, CO VA Medical Center
Introductions: Jason Rankin CS and Daren Jack COR
Site Visit:
• The pre-bid meeting/site walk is not mandatory.
• Questions during site visit must be written down and submitted to the Contracting Specialist to provide answers in an amendment to all interested parties.
Pertinent Dates:
• Questions are due by 10:00 AM MT February 1, 2023. Any questions submitted after this time will not be reviewed or answered. Please submit to Jason.Rankin@va.gov.
• Bids are due on February 14, 2023, no later than 10:00 AM MT. Submit via email to Jason.Rankin@va.gov.
Site Visit Guidelines:
• Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
• Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.
• Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
Solicitation Information:
• Confirmation of construction range: between $250,000 and $500,000.
• Bid Guarantee & Payment/Performance Bonds: are required as outlined in the solicitation.
• Special Standards of Responsibility: Please note solicitation requirements for submittal of OSHA and EMR ratings.
• VAAR clause 852.219-75 Limitation on Subcontracting: please ensure you provide a signed copy of this clause with your bid package.
• Contractor shall begin performance within 10 days after Notice to Proceed (NTP) and complete within 180 days.
Post Award Compliance:
• Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor.
The contractor shall submit their weekly certified payrolls with their monthly invoice.