This solicitation package outlines requirements for a federal contract to re-stripe, seal, and maintain three parking garages at the Rocky Mountain Regional VA Medical Center in Colorado. Key details include:
-
The contractor will clean, seal, and re-stripe concrete surfaces on all levels of three parking structures totaling approximately 883,200 square feet. Additional work includes cleaning stairwells and elevator lobbies.
-
Bids are due by June 8, 2023. The period of performance is 90 calendar days from notice to proceed. The estimated value is between $2-5 million.
-
The contractor must submit safety and quality control plans, hazardous material inventories, and personnel qualifications/certifications. Work must follow OSHA, NFPA, and other standards.
-
Questions are due by May 15, 2023 and answers will be provided timely. A pre-bid site visit was held. The Department of Veterans Affairs is the contracting agency.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Site Visit Meeting Solicitation 36C25923B0005 Project #554-23-102 Re-Stripe, Seal, and Maintenance on Parking Garages at RMR VAMC
The contractor is to provide all labor, tools, materials, equipment, and supervision required to complete the construction of the Re-Stripe, Seal, and Maintenance on Parking Garages at the Rocky Mountain Regional, CO VA Medical Center. Work to include all work and labor for re-striping, sealing, and repair of the parking garages.
Location: RMR VA Medical Center
AGENDA:
· Introduction of Christina Beeler-Blackburn CO, Mark Blehm COR
· The pre-bid meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send IFB:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due May 15, 2023 no later than 1:00 PM MT, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Bids due on 6/8/2023 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· All Federal and local COVID requirements shall be followed for the duration of this project.
· Confirmation of construction range is under $2,000,000 to $5,000,000.
· Bid Guarantee & Payment/Performance Bonds: Bid Guarantee is required at 20% of proposal price or $3 million; whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 90 days.
· Post Award Compliance:
· Compliance with Construction wage rates determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.