36C25923B0005_1.docx

DOCX document 129 KB Posted

Attached to
Z2DA--554-23-102 Re-Stripe, Seal, and Maintenance on Parking Garages
Solicitation number
36C25923B0005
Issued by

About this file

This document outlines a federal contract solicitation for re-striping, sealing, and maintenance of parking garages at the Rocky Mountain Regional Veterans Affairs Medical Center. The solicitation includes two line items - the base requirement to clean, seal and re-stripe three parking garages totaling approximately 883,000 square feet of concrete surface, and an optional additional requirement to complete the same work for an underground loading dock of approximately 40,000 square feet. Bids are due by 10:30 AM MDT on June 6, 2023. The period of performance is 90 calendar days from notice to proceed. The solicitation is set aside 100% for a Service Disabled Veteran Owned Small Business. The work must meet VA standards and specifications as well as all applicable federal, state and local regulations.

View the file

Other files

File Type Posted
S06- 2nd Questions and Responses_updated.docx DOCX document
36C25923B0005 0004.docx DOCX document
S06- 2nd Questions and Responses_updated.docx DOCX document
00.LS.328 PVN Loading Dock Roof Elevation.pdf PDF
36C25923B0005 0003.docx DOCX document
S06- 2nd Questions and Responses.docx DOCX document
13.AS.301 PVS Elevations.pdf PDF
XX.AS.570-A.pdf PDF
S04- 2nd Site Vist Sign-in sheet.pdf PDF
13.AS.302 PVS Elevations.pdf PDF
2nd Site Visit Meeting Doc.docx DOCX document
36C25923B0005 0002.docx DOCX document
ACI RAP-13.pdf PDF
SOW 554-23-102_revised 1JUN23.docx DOCX document
S05- Questions and Responses.docx DOCX document
S04- Site Visit sign in sheet.docx DOCX document
36C25923B0005 0001.docx DOCX document
S04- Site Visit Meeting Doc.docx DOCX document
S02- 36C25923B0005_Solicitation.docx DOCX document
S22- 852.219-75 LOS Certificaiton.docx DOCX document
S02 SELF-PERFORMED CALCULATIONS.docx DOCX document
Bldg 11 Parking Staff North PSN Drawings.zip ZIP file
Bldg 12 Parking Visitor North PVN Drawings.zip ZIP file
Bldg 13 Parking Visitor South PVS Drawings.zip ZIP file
Attachment A - OSHA form - pdf.pdf PDF
Loading Dock Drawings.zip ZIP file
Combined Spec.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5.

REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL

SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25923B0005 X 04-28-2023 554-23-102 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Christina Beeler-Blackburn Christina.Beeler-Blackburn@va.gov

Christina Beeler-Blackburn 303-712-5744 Acquisition Title: 554-23-102 Re-Stripe, Seal, and Maintenance on Parking Garages

Contractor shall provide all necessary labor, materials, equipment and supervision to complete all required project work in accordance with the provided SOW, Specifications and Drawings. The project is located at the Rocky Mountain Regional VA Medical Center, 1700 N Wheeling St., Aurora, CO 80045.

This is a competitive requirement set aside 100% for a Service Disabled Veteran Owned Small Business (SDVOSB). Magnitude of construction: $2,000,000 to $5,000,000. The NAICS code for this pro ject is 236220 with a size standard of $45M.

A pre-bid site visit shall be held on May 9, 2023 at 2:00 PM MT. All interested Contractors shall meet at the following location: Meet at the Cafe near the North Entrance. Park in the North Visitors Parking Lot.

Cut off for submission of RFIs/Questions shall be COB May 15, 2023. All RFIs/Questions must be emailed to:

Chris tina.Beeler-Blackburn@va.gov. Please include the solicitation number 36C25923B0005 on the subject line.

All bidders must submit a bid guarantee as part of their bid package. Additionally, t he Awardee must be able to obtain the necessary level of Performance and Payment Bonds.

Submission of bids: All bids shall be submitted via email to: Christina.Beeler-Blackburn@va .gov by the date and time as stated in Block 13a below. Please include the solicitation number 36C25923B0005 in the subject line.

X X 52.211-10 X

10:30 AM

MDT

06-06-2023 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any req uired performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23.

ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT

WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-th is contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise s pecified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
A.4 DELIVERY SCHEDULE5
A.5 STATEMENT OF WORK5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 Bid Submission Instructions and Special Standards of Responsibility15
2.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)16
2.3 52.216-1 TYPE OF CONTRACT (APR 1984)17
2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)17
2.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)17
2.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)19
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)20
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)21
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)21
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
REPRESENTATIONS AND CERTIFICATIONS22
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)22
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)26
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)29
GENERAL CONDITIONS31
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)31
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)33
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2023)33
4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)35
4.5 SUPPLEMENTAL INSURANCE REQUIREMENTS40
4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)41
4.7 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)44
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)44
4.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)44
4.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (NOV 2022)44
4.11 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING--CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022)47
4.12 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)49
4.13 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)49
4.14 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)49
4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)52
4.16 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)53
4.17 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)54
4.18 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)54
4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)55
4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)56
4.21 WAGE DETERMINATION58
4.22 LIST OF ATTACHMENTS65

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

0.00

__________________
__________________

Base Line Item: See SOW and Instructions to Bidders for details PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

0.00

__________________
__________________

Line Item 002 ( Additive Bid Option): See SOW and Instructions to Bidders for details PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

GRAND TOTAL
__________________

A.4 DELIVERY SCHEDULE

ITEM NUMBER
QUANTITY
DELIVERY DATE
0.00
90 calendar days after NTP
0.00
90 calendar days after NTP

A.5 STATEMENT OF WORK

Page 1 of Page 1 of Re-Stripe, Seal, and Maintain Parking Garages Project Number 554-23-102 Rocky Mountain Regional Veterans Affairs Medical Center (RMRVAMC)

1.0 – OBJECTIVE:

The Department of Veterans Affairs has a requirement to clean, seal, and re-stripe concrete surfaces on all levels of parking structures at the Rocky Mountain Regional VA Medical Center.

2.0 – STATEMENT OF WORK

LINE ITEM 1:

· Concrete surfaces at the parking garages at the RMRVAMC were never properly treated with sealant during construction of the facility several years ago and application of sealant is necessary to preserve longevity of the concrete surfaces.

· Contractor shall clean, seal, and re-stripe all concrete surfaces of Building 11 Parking Staff North (PSN,) Building 12 Parking Visitor North (PVN,) and Building 13 Parking Visitor South (PVS) to include:

· Shot blasting of surface to remove contaminates

· Removal of dust and debris

· Flood coating all concrete surfaces with methacrylate flood coating

· Spreading an even coat of dry white silica sand while sealer coat is tacky

· Replacing all existing pavement markings in kind

· PSN has 1 underground level and 6 above ground levels and measures approximately 393000 square feet (SF) of concrete surface.

· PVN has 1 underground level and 6 above ground levels and measures approximately 333000 SF of concrete surface.

· PVS has 2 underground levels and measures approximately 157200 SF of concrete surface.

· Stairwells and elevator lobbies are not required to be sealed. Contractor shall power wash stairwells and elevator lobbies in preparation for VA painting. Contractor shall coordinate with Contracting Officer’s Representative (COR) who will coordinate with VA shops for hot work permit to flow water to garages.

· Reference attached plans of each floor of each garage.

· The above garages are occupied and in use. Contractor shall phase work into sections of each floor to keep all floors of garage accessible at all times in both entrance/exit directions. If shutdown of garage is necessary, contractor shall anticipate the following timeframes for access in the following phases:

· 2 weeks to complete one vertical half (all floors) of PVS

· 2 weeks to complete other vertical half (all floors) of PVS

· 2 weeks to complete PVN

· 2 weeks to complete PSN

LINE ITEM 2 (ADDITIVE BID OPTION)

· As an additional bid option to the above work, contractor shall clean, seal, and re-stripe all concrete surfaces as outlined above at the underground loading dock adjacent to PVN.

· The loading dock has 1 underground level of approximately 40000 SF and an access drive leading from street level at 17th Avenue down to the dock floor.

· This loading dock is in operation during normal business hours Monday through Friday and contractor should assume any work that will disrupt normal operation of the dock will need to be accomplished after hours or on weekends. The dock can be turned over at 4 PM Friday afternoon and must be ready for full operation again by 6 AM Monday morning.

3.0 GENERAL:

The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the contractor have a “Competent Person” on the job at all times (must have a 30-hour OSHA card), and that all contractor employees have received a minimum of ten (10) hours of OSHA construction safety training. Documentation of these requirements shall be submitted and approved prior to performing the work.

Contractor must submit a company Site Specific Safety Plan (SSSP) that must be reviewed by VA Safety prior to work beginning. This plan shall detail fire, construction, and health-related safety measures, in addition to listing training records for all employees for the previous year. A company standard or boilerplate safety plan will not be acceptable – plan should contain a detailed hazard analysis for each element of construction to be performed such as an Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA).

This entire project shall conform to 100% of all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes.

The Contractor shall be responsible for the health and safety of their own employees. The VA will inform the Contractor of any hazards such as designated permit confined spaces, electrical hazards, etc. which may affect Contractor employees. The Contractor must take precautions appropriate for the safety of their employees as well as provide equipment necessary for these actions. Contractor employees will notify the VA Representative before entering a designated permit required confined space, so precautions can be taken in advance of the work.

The Contractor is responsible for protection of existing finishes, and VA property (FF&E), located in the areas preventative maintenance and repair work is being performed, as well as along paths of travel to and from these areas. Both exterior and interior finishes and property must be maintained. The contractor is liable for any damage to VA property during the course of the contract. Any damage to existing finishes must be repaired by the Contractor to equal or greater quality than existing finishes. All tasks accomplished by the Contractor personnel will be performed to preclude damage or disfigurement of government-owned furnishing, fixtures, equipment and architectural or building structures. Contractor will report any damage or disfigurement to these items when caused by the Contractor’s personnel and will perform repairs or replace government-owned equipment, fixtures, furnishings, grounds and architectural or building structures to their previously existing condition.

4.0 PROJECT MANAGEMENT:

Based on the above list of work items the, general contractor selected must complete, maintain, and submit the following documentation and managerial requirements:

· Construction schedule including sequencing and durations.

· The schedule will be provided to the COR ten (10) working days prior to the start of work.

· Site-Specific Safety Plan (SSSP) with an emphasis on tasks to be performed during the work. The SSSP must:

· Include a detailed description of how the work will be performed and be submitted with sketches, supporting documents, submittals etc.

· Include a Job-Safety-Analysis (JSA) for all tasks associated with Statement of Work (SOW)

· Be reviewed and commented by VA-Safety and COR prior to commencement of work.

· Maintain site supervision by a competent individual(s) with OSHA-30 certificates. OSHA-30 certified technician shall be onsite anytime work is being performed.

· Obtain VA identification PIV badges for all employees. Contractor to consider lead-time for badge procurement.

· Manage job-site access and security.

· Implement and maintain required ICRA and ILSM measures.

5.0 - SUPPORTING DOCUMENTS:

· Drawings:

· Combined Drawings PDF

· Spec:

· Combined Spec PDF

6.0 - CODE & REGULATION COMPLIANCE:

The Contractor shall comply with public laws and statutes including all changes and amendments to federal, state and local environmental statutes and regulations in effect the date of issuance of this delivery order, including applicable portions of the documents cited in the basic contract and below:

· NFPA 99-2015 Healthcare Facilities Codes.

· ANSI/ASSE Z359

· NFPA 101 – Life Safety Code

· Architectural Barriers Act (2005)

· International Code Council (ICC): IBC: International Building, 2015

· Building Officials and Code Administrators International (BOCA), 1999

· International Conference of Building Officials (ICBO): UBC 1997: Uniform Building Code

· 29 CFR 1910 Occupational Safety and Health Standards

· 29 CFR 1926 Safety and Health Regulations for Construction

· Federal Occupational Safety and Health Act (OSHA)

· Underwriters Laboratories

7.0 – SUBMITTALS:

Contractor shall submit the following prior to beginning scope of work:

· Project schedule with sequencing, durations, phasing, and cost loading within 10 working days of Notice to Proceed (NTP), and monthly with invoices.

· Site Specific Safety Plan (SSSP)

· SSSP to be submitted to VA Safety staff and COR for review 10 working days after issuance of NTP.

· SSSP to be reviewed and commented by VA Safety staff and COR prior to start of construction activities.

· Construction Demolition/Removal Plan

· Inspection reports, manufacturer approval certificates, and warranties as noted in specifications.

· Penetration and or hot work permits as necessary.

· Manufacturer and construction warranties as noted in specifications.

· Project Schedule including sequencing and durations.

· SOV – Schedule of Values

· The schedule will be provided to COR 10 working days prior to start of the work.

· Site superintendent OSHA-30, and tradesmen/laborer OSHA-10 certificates. OSHA-30 certified technician shall be onsite anytime work is being performed.

· Material Submittals – Submit for COR approval

· Manufacturer’s specifications for all materials and equipment planned for installation.

· Inspection reports, manufacturer approval certificates, and warranties as noted in specifications.

Technical literature and/or descriptions of all materials, equipment and tools proposed for use by the Contractor shall be submitted to the Contracting Officer or his/her designee for approval prior to contract start and whenever a change is required. All Contractor-furnished materials, equipment and tools used shall be standard products all manufacturers regularly engaged in the production of such items. The Contractor shall secure all materials. The Government assumes no liability for loss of or damage to Contractor-owned property held upon Government premises.

Contractor shall submit hours worked, full report of completed piping which shall include: location, hours worked, the full name of Contractor’s employees on site, and digital photographs before and after work is completed. Reports shall be submitted within one day upon completion of work performed. Contractor will provide a completed redline drawing of the completed routing of piping. If necessary, a secondary report shall be submitted after any repairs outside of the “Work Required” have been completed. Reports shall be provided in hard copy as well as in an agreeable and compatible electronic format such as, but not limited to, pdf or Microsoft Word.

8.0 – RESOURCES

The Government will not furnish any resources for the fulfillment of the work required under this contract other than electricity for area where work is being conducted. Under this contract, the contractor must provide all tools, equipment, materials, transportation, professional expertise, personnel, supervision, and for testing and maintenance required for completion of this contract.

Contractor shall provide all necessary parts and equipment to complete the objective of this contract in accordance with manufacturer specifications. All new equipment including parts and labor shall be preapproved by the COR. Prices for parts shall be invoiced at no more than 10% above contractor’s costs, including shipping and handling. Verification of contractor’s cost shall be included with all invoices. Contractor shall provide all necessary equipment to perform the work required.

Technical literature and/or descriptions of all materials, equipment and tools proposed for use by the Contractor shall be submitted to the Contracting Officer or his/her designee for approval prior to contract start and whenever a change is required. All Contractor-furnished materials, equipment and tools used shall be standard products all manufacturers regularly engaged in the production of such items. The Contractor shall secure all materials. The Government assumes no liability for loss of or damage to Contractor-owned property held upon Government premises.

The Contractor shall instruct his/her personnel in utilities conservation practices. The Contractor shall be responsible for operating under conditions which preclude the waste of utilities which shall include but not necessarily be limited to:

· Lights shall be used only in areas where and at the time when work is actually being performed unless otherwise directed.

· Contractor’s personnel will not adjust mechanical equipment controls for heating, ventilation and air conditioning systems.

· Government telephones shall not be used for personal reasons or for any toll or long-distance calls

9.0 PERSONNEL ASSIGNMENTS:

The Contractor shall assign the appropriate quantity and type of personnel to successfully complete all functions specified in this SOW. The Contractor shall maintain throughout the life of this contract, a current list of technicians and their credentials available for inspection by the Government at any time.

10.0 ACCEPTANCE STANDARDS:

The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA.

11.0 – SAFETY AND FIRE PREVENTION

· In the performance of this contract, the contractor shall take such safety precautions as necessary to protect the lives and health of occupants of the building.

· The Contractor shall immediately correct any fire and safety deficiencies caused by his/her personnel. If the Contractor fails or refused to correct deficiencies promptly, the Contracting Officer may issue an order stopping all or any part of the work and hold the contractor in default of the contract.

· The Contractor shall comply with applicable Federal, State and local safety and fire regulations and codes which are in effect at the beginning of the contract. The contractor shall keep abreast of and comply with changes in these requirements and codes applicable to the contract. The requirements include but are not limited to, those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees

· The Contractor’s personnel shall follow applicable facility policies concerning fire/disaster programs.

· All materials and equipment will be removed from the facility or stored properly at the end of the workday and secured during the workday. Under no circumstances will the Contractor allow for any equipment to be left unattended for any length of time.

· The Contractor shall comply with all applicable Federal, State and local legal requirementsregarding workers health and safety.

· Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.

· The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. Utility shutdowns shall notcompromise security, communication or fire safety for occupants.

· No flammable liquids shall be stored or used in the medical center.

· The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241. Contractor shall keep certification onsite at all times of extinguisher inspections.

· The Contractor shall receive from the COR a permit for all cutting, welding, and soldering 24 hours in advance. All permits shall be prominently displayed during all construction.

· All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.

· The Contractor shall assume responsibility of environmental protection of all material storage.

12.1 – ACCIDENT PREVENTION

Precaution shall be exercised at all times for the protection of persons (including employees) and property. These shall include, but not be limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor shall comply with all applicable laws relating to safety precautions, including the safety regulations of the Division of Industrial Safety, Department of Industrial Regulations of the state.

12.2 - ENVIRONMENTAL PROTECTION

· In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety Requirements” as well as the specific requirements stated elsewhere in the Contract Documents.

· The Contractor is responsible for daily cleanup of all areas affected by its work. Areas in use or affected shall be returned to condition in which they were turned over or initially found. VA Housekeeping shall not be dispatched for cleaning associated with contractor work.

· The Contractor shall take every precaution in preserving flooring, finishes, equipment, and furniture in areas of work. The Contractor shall repair or replace any damage incurred during its work at their expense.

· Contractor shall use freight elevators for transmission of materials and personnel. Contractor shall take every precaution in preserving the elevators, including the hoist way and lobby doors, interior finishes, and shall conduct all good practices in observing lifting and motor components tolerances. Any damage incurred to any elevator component due to negligence will be repaired at expense of the contractor, within the work day of incurred damage.

13.0 – WORK STANDARDS AND ICRA/ILSM

· Work site shall be free of debris and returned to original condition upon completion of preventative maintenance or repairs.

· All work is to be performed in areas used daily by facility patients and staff. Contractor will take suitable measures to control all material and equipment to produce a minimum of interference in facility routine. All work shall be performed in a safe and prudent manner. Contractor shall coordinate all closures of rooms with COR who will coordinate with VA-Chiefs.

· Contractor shall so perform all work as to offer the least possible obstruction and inconvenience to staff, patients and shall have under construction, no greater amount of work than can be completed promptly and properly with due regard to the rights of staff and patients. Any person the COR may deem incompetent or disorderly shall be promptly removed from the facility and not be allowed to return for the duration of the agreement.

· The Contractor shall comply with an Infection Control Risk Assessment (ICRA) which will be developed with the COR and the Infection Control Practitioner. Multiple ICRA’s may be necessary to address specific risks at various stages of the project and must be approved prior to proceeding on each phase. VA anticipates an overall ICRA level II for this project.

14.0 - HAZARDOUS MATERIAL REPORTING

· The Contractor shall maintain hazardous material inventories and material safety data sheets (MSDS) for all hazardous materials (as defined in CFR 1910.120, 40 CFR’s 355, 370, & 372) to be stored and used on this Medical Center. Hazardous materials must be inventoried when received and at the project’s completion. The amounts used shall be maintained for the project duration, and for the calendar year (ending 31 December).

· Hazardous Materials Inventories, Material Safety Data Sheets and material quantities used shall be submitted to the Contracting Officer for approval.

· In the event of a spill, Contractor shall immediately notify the Contracting Officer’s Representative as well as the Contracting Officer. The Contractor shall be solely responsible for the expense of any cleanup of such spill, and the cleanup shall be in accordance with the applicable provisions of 40 CFR Part 761.

· Asbestos Containing Material (ACM) is not present in the workspace. If contractor locates suspected ACM in addition to material noted in report, they shall contact the COR immediately for further direction. If any ACM is disturbed or becomes friable due to contractor actions, the construction site shall be shut down until and contractor shall provide appropriate containment at their own expense. In addition, contractor shall be responsible for all abatement and disposal of affected material at their own expense, only after which the job site shall be reopened for continued work. In the event of an ACM disturbance event, the COR shall be immediately notified and shall provide specifications on asbestos abatement.

15.0 HOURS OF WORK

All construction activities shall be conducted during normal business hours Monday thru Friday from 0730 hrs. to 1600 hrs. (except where indicated differently herein re: after-hours work) excluding Federal Holidays and any other day declared a federal holiday by the President of the United States listed below. Contractor’s work shall not interfere with the functions of the facility during weekends. Barricades, ICRA containment provisions shall be arranged to allow patients and staff unimpeded acces (including wheelchairs and patient beds where applicable) to services and resources within the facility.

New Year’s DayMartin Luther King Jr’s BirthdayPresidents Day
Memorial DayIndependence DayLabor Day
Columbus DayVeterans DayThanksgiving Day

Christmas Day

If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government.

If work requires after hours work due to ICRA constraints or inclement weather, then Contractor shall inform FMS seven (7) days in advance.

Postponement/Delays: In the event climate or weather conditions become unsuitable for work or may induce an environmental hazard, then the entire work shall be rescheduled to a date and time satisfactory to the Contractor and the COR. Postponement due to inclement weather will not cause assessment of the penalty provision outlined above, nor should there be an additional cost to the Government.

All work shall be scheduled and performed within the date and time approved by the COR, in conjunction with the department occupying the space served by this equipment.

16.0 BADGES AND PARKING

All Contractor personnel are required comply with the RMRVAMC badging process. Contractor must acquire PIV badge for all staff onsite prior to work beginning. Failure of the background check may result in specific personnel not being allowed to work on VA premises and the Contractor will need to provide replacement personnel. Contractor to take into account lead-time on PIV Badging process.

It is the responsibility of the Contractor’s personnel to park in the appropriate designated parking areas. The designated parking area will be specified by COR upon award of contract.

17.0 – PERSONNEL QUALIFICATIONS

· The Government reserves the right to accept or reject Contractor’s staff for cause.

· All inspectors/testers shall hold current OSHA 10/30 certification and membership. Documentation of this to be submitted by the Contractor to the COR prior to beginning project work. A competent person with OSHA 30 certification must be on site at all times.

· The Contractor shall have a back-up technician in the event the primary technician is unable to perform his/her duties.

· The Contractor will ensure that their personnel and subcontractor personnel meet the privacy standards as set forth by HIPAA (Health Insurance Portability and Accountability Act of 1996) with respect to personal and confidential information that they may come upon.

· All personnel required to hold OSHA 10 certification as a minimum.

18.0 – PERSONNEL REQUIREMENTS

Supervision: The Contractor shall specify a Project Manager who will have responsibility for performance of contract services. The Project Manager shall be competent to supervise all aspects of contract and shall be available on-site during performance of contract work. The Contracting Officer shall be notified in writing of the names of the Project Manager and of changes in personnel appointed to fulfill this function or in the absence of the Contractor, act for the Contractor as the Contractor’s Representative.

19.0 – QUALITY CONTROL

The Contractor shall have a quality control program to assure the requirements of this contract are provided as specified. The Contractor and COR will inspect the work. Deficiencies will be noted and corrected before beginning work in another area. Any damage done by Contractor will also be noted and corrected by the Contractor within 2 working days. Damage causing an immediate impact on the environment of the hospital shall be corrected immediately.

20.0 – ACCEPTANCE STANDARDS

Completed work will be to the entire satisfaction of the VA and the COR shall be the sole judge as to its acceptability. Any work not acceptable to the COR, shall be immediately, at Contractor’s own expense, refashioned to an acceptable level.

21.0 – MEETINGS

A Pre-Bid meeting and site walk will be held at a date and time specified by the COR to review scope, of service, site, and requirements with perspective contractors, and provide answers to any questions. Contractor and/or Sub-contractors shall attend a pre-bid walkthrough of the work before submitting a bid. VA reserves the right to reject any bidder not attending the Pre-Bid. The date and time of this walkthrough will be determined by the CO and COR. Contractor and/or subcontractors shall be responsible for making any clarification requests that arise at the pre-bid walkthrough directed to the CO prior to the bidding of the work.

22.0 – PERIOD OF PERFORMANCE:

Period of performance including lead time for materials and submittals: ninety (90) calendar days from NTP.

**End of Statement of Work**

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 Bid Submission Instructions and Special Standards of Responsibility Bid Submission Instructions:

1. All bid packages shall be submitted via email to the following email address: Christina.Beeler-Blackburn@va.gov by the specified Bid Closing date and time. The applicable Solicitation Number for this IFB must be included on the subject line of the email. All pricing will be submitted as a detailed breakdown by Division showing all material, labor, profit, and overhead. This should include quantities, rates, and percentages where applicable.

2. A public Bid Opening will not be held. Bids shall be opened by the Contracting Officer and Contract Specialist, witnessed, and recorded on an official Bid Abstract. Bid Abstracts will be available upon request via email.

Special Standards of Responsibility:

1. Solicitation Submittal Requirements The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

a. OSHA or EPA Violation(s): Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years. Form is provided as “Attachment A” which must be completed and submitted as part of your offer.

b. Experience Modification Rate (EMR): Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0. If an offeror’s EMR is above 1.0, the offeror must submit a written explanation of the EMR from its insurance carrier on the insurance carrier’s letterhead, describing the reasons for the EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Limitation on Subcontracting Offerors shall complete and return in its entirety the 852.219-75 LOS clause and certificate attachment. By signing and submitting the offeror agrees to follow the limitations on subcontracting regulations as outlined in VAAR 852.219-75. Form is provided as “S22- 852.219-75 LOS Certificate” which must be completed and submitted as part of your offer.

2.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

(a) Definitions. As used in this provision— "Administrative proceeding" means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

"Federal contracts and grants with total value greater than $10,000,000" means—

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror [ ] has [ ] does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in—

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).

(End of Provision)

2.3 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
13.8 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Aurora, CO Adams County

(End of Provision)

2.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Christina Beeler-Blackburn

Hand-Carried Address:

Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Mailing Address:

Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

(b) The copy of any protest shall be received in the office designated above within one day of…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .