This solicitation document requests proposals for replacing and upgrading parking lots 1 and 2 at the Muskogee Oklahoma Veterans Affairs Medical Center. The scope of work involves removing existing asphalt and concrete surfaces in the two lots and replacing with new asphalt, including removal and replacement of curbs, wheel stops, signage, and striping. Bidders must provide pricing on the SF1442 form and submit past performance information and responses to representations and certifications. The period of performance is 270 calendar days from notice to proceed. Proposals are due by March 15, 2022. The solicitation will result in a firm-fixed-price contract award and utilizes the tradeoff source selection process.

View the file

Other files

File Type Posted
090600.pdf PDF
36C25922R0035 0003.docx DOCX document
Solar Parking Lot Lighting - Solar Lighting International.pdf PDF
36C25922R0035 0002.pdf PDF
SOW Parking Lots 1 2 revised.docx DOCX document
623-20-135 SPECIFICATIONS 3 1 2022.pdf PDF
36C25922R0035 0001.docx DOCX document
Site Visit Attendance.pdf PDF
parking12WT handout.pdf PDF
623-20-135 SPECIFICATIONS 010722.pdf PDF
623-20-135 DRAWINGS 010722.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 of 36C25922R0035 X 623-20-135 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Ilze Karklins-Powers 307-433-3727 The contractor shall furnish all labor, equipment, materials, and supervision to complete the following project at the Muskogee VA Medical Center located at 1011 Honor Heights Drive, Muskogee, OK 74401 623-20-135 Replace and Upgrade Parking Lots 1 and 2

The project requirement is described in the Scope of Work -see page 5 and associated attachments.

The NAICS code is 236220 with a business size standard of $39.5M.

A site visit will be held on February 22, 2022 at 9:00 AM Central Time (CT). Interested contractors shall meet at the Parking Lot 1 of the Muskogee VA Medical Center.

All questions in relation to this solicitation are due no later than close of business February 28, 2022. Please address questions to ilze.karklins-powers@va.gov

The closing date for this solicitation is March 15, 2022 at 1:00 PM Mountain Time (MT). Please email proposals to ilze. karklins-powers@va.gov

X X 52.211-10 X

1 PM

MDT

03-15-2022 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village

CO

80111 Department of Veterans Affairs Financial Service Center PO Box 149971 Austin

TX

78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 Statement of Work5
A.4 PRICE/COST SCHEDULE12
ITEM INFORMATION12
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS13
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)20
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)20
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)20
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)21
2.5 52.228-1 BID GUARANTEE (SEP 1996)22
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)23
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)23
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)24
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)25
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)25
REPRESENTATIONS AND CERTIFICATIONS26
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION)26
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)29
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)32
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)34
GENERAL CONDITIONS36
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)36
4.2 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)36
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)37
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)38
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)41
4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS45
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)45
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)48
4.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)49
4.10 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)49
4.11 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)51
4.12 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)52
4.13 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)53
4.14 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)53
4.15 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)54
4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)57
4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)58
4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)59
4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)59
4.20 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)59
4.21 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)61
4.22 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)62
4.23 Wage Determination OK2022006162

A.3 Statement of Work

Page 1 of Page 1 of 623-20-135 Replace & Upgrade Parking Lots 1 and 2 Muskogee Oklahoma VAMC

1.0 - OBJECTIVE

Parking lots one and two are located on at the Jack C Montgomery VA Medical Center (VAMC) in Muskogee, Ok. Parking lots currently need replacement and upgrading. Currently, 112 total parking spaces exist between both lots. Contractor shall match or exceed current number of spaces. All electric systems are to remain. All drainage systems are to remain, and parking lots shall use current systems in accordance with federal standards.

2.0 – STATEMENT OF WORK

The project is to remove all existing asphalt pavement surfaces in parking lot 1 and to also remove existing concrete surface in parking lot 2. Then, replace with new asphalt surface with minimum required base, or more, to both lots. The project shall include removal and replacement of all, curbs, concrete wheel stops, bollards, crosswalks, striping, signage, etc. All parking stalls shall have a standard width in coordination with Americans with Disabilities Act’ standards. The area for parking lot 1 & 2 are approximately 38,000 square feet. The project shall be completed in a phased schedule so operation of the medical center can continue with minimum interruption.

3.0 – GENERAL

The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations (CFR) 29, Part 1910 and 1926. This includes the requirement that the Contractor have a “Competent Person” on the job at all times. The Competent Person must have a 30-hour Occupational Safety and Health Administration (OSHA) card. All Contractor employees, on site, shall have a ten (10) hours OSHA construction safety training certificate, at a minimum. Documentation of these requirements shall be submitted and approved prior to performing the work.

This entire project shall conform to 100% of all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes.

The Contractor shall be responsible for the health and safety of their own employees. The VA will inform the Contractor of any hazards such as designated permit confined spaces, electrical hazards, etc. which may affect Contractor employees. The Contractor must take precautions appropriate for the safety of their employees as well as provide equipment necessary for these actions. Contractor employees will notify the VA Representative before entering a designated permit required confined space, so precautions can be taken in advance of the work.

The Contractor shall hold harmless and indemnify the Government against any and all liability, claims, and costs of whatsoever kind and nature for injury to or death of any person or persons and for loss or damage to any property occurring in connection with, in any way incident to, or arising out of the occupancy, use, service, operation or performance of work under the terms of the contract, resulting in whole or in part from the negligence acts or omissions of the Contractor, any Subcontractor, or any employee, agent, or representative of the Contractor or Subcontractor

The Contractor is responsible for protection of existing finishes, and VA property, furnishings, fixtures, and equipment (FF&E), located in the areas where demolition, construction, preventative maintenance, and repair work is being performed, as well as along paths of travel to and from these areas. Both exterior and interior finishes and property must be maintained. The Contractor is liable for any damage to VA property during the course of the contract. Any damage to existing finishes must be repaired by the Contractor to equal or greater quality than existing finishes. All tasks accomplished by the Contractor personnel will be performed to preclude damage or disfigurement of government-owned FF&E and architectural or building structures. Contractor will report any damage or disfigurement to these items when caused by the Contractor’s personnel and will perform repairs or replace government-owned equipment, fixtures, furnishings, grounds and architectural or building structures to their previously existing condition.

4.0 – PROJECT MANAGEMENT

Based on the above list of work items, the Contractor selected must complete, maintain, and submit the following documentation and managerial requirements:

· Construction schedule including sequencing, phasing, and durations.

· The schedule will be provided to the COR within ten (10) working days after Notice to Proceed (NTP).

· Coordinate and follow a phasing schedule. The phasing schedule must be approved by the Contracting Officer’s Representative (COR). Work by others in the construction site requires the Contractor to perform tasks during specific time periods as directed by the COR.

· Obtain VA identification Personal Identity Verification (PIV) badges for all employees. Contractor to consider lead-time for badge procurement.

· Manage job-site access and security.

· Implement and maintain required ICRA and ILSM measures.

· Follow all required safety protocols.

5.0 – SUPPORTING DOCUMENTS

Contractor shall be required to field verify current conditions and accuracy of most current documentation, construction drawings and specifications.

6.0 – CODE & REGULATION COMPLIANCE

The Contractor shall comply with the public laws and statutes including all changes and amendments of federal, state, and local environmental statutes and regulations in effect of date of issuance of this delivery order, including, the applicable portions of the documents cited in the basic contract and below.

· National Fire Protection Association (NFPA):

· NFPA 99-2015 Healthcare Facilities Code

· NFPA 101 – Life Safety Code

· International Code Council (ICC): IBC: International Building, 2015

· Building Officials and Code Administrators International (BOCA), 1999

· International Conference of Building Officials (ICBO): UBC 1997: Uniform Building Code

· 29 CFR 1910 Occupational Safety and Health Standards

· 29 CFR 1926 Safety and Health Regulations for Construction

· Federal Occupational Safety and Health Act (OSHA)

· Underwriters Laboratories

· 2018 International Plumbing Code

· SBCCI Standard Plumbing Code

7.0 – SUBMITTALS

Contractor shall submit the following prior to beginning scope of work:

· Project schedule with sequencing, durations, phasing, and cost loading within 10 working days of NTP, and monthly with invoices.

· Site Specific Safety Plan (SSSP) with an emphasis on, but not limited to, demolition, installation, and safety.

· Submit to VA Safety staff for review within 10 working days after issuance of NTP.

· Include a detailed description of how the work will be performed and be submitted with sketches, supporting documents, submittals etc.

· Detail fire, construction, and health-related safety measures.

· Listing safety training records for all employees expected on site.

· Include detailed Job-Safety-Analysis (JSA) or Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA) for all tasks associated with Statement of Work (SOW)

· Wait for approved by VA Safety staff prior to start of construction activities. Allow 10 working days for approval. Correct if necessary.

· Construction Demolition Removal / Handover Plan.

· Inspection reports, manufacturer approval certificates, and warranties.

· Penetration, live work, or hot work permits as necessary.

· Manufacturer and construction warranties as noted in specifications or where applicable.

· SOV – Schedule of Value. The schedule will be provided to COR 10 working days prior to start of the work.

· Material Submittals – Submit for COR approval

· Physical and electronic Redline (As-Built) drawings of the completed work.

Technical literature and/or descriptions of all materials, equipment and tools proposed for use by the Contractor shall be submitted to the Contracting Officer (CO) or his/her designee for approval prior to contract start and whenever a change is required. All Contractor-furnished materials, equipment and tools used shall be standard products all manufacturers regularly engaged in the production of such items. The Contractor shall secure all materials. The Government assumes no liability for loss of or damage to Contractor-owned property held upon Government premises.

Contractor shall submit hours worked, full report of completed structural, piping, and electrical which shall include: location, hours worked, the full name of Contractor’s employees on site, and digital photographs before and after work is completed. Reports shall be submitted within one day upon completion of work performed. Contractor will provide a completed redline drawing of the completed work. Reports shall be provided in hard copy as well as in an agreeable and compatible electronic format such as, but not limited to, pdf or Microsoft Word.

8.0 – ELECTRONIC/ DIGITAL DELIVERABLES

· CD set with above documents (Report, Summary Report, Handwritten Notes) in a PDF format.

· An electronic copy of redline drawings of the completed work in the latest AutoCAD version.

9.0 – RESOURCES

The Government will not furnish any resources for the fulfillment of the work required under this contract other than electricity for area where work is being conducted. Under this contract, the Contractor must provide all tools, equipment, materials, transportation, professional expertise, personnel, supervision, and for testing and maintenance required for completion of this contract.

Contractor shall provide all necessary parts and equipment to complete the objective of this contract in accordance with manufacturer specifications. All new equipment including parts and labor shall be preapproved by the COR.

The Contractor shall instruct his/her personnel in utilities conservation practices. The Contractor shall be responsible for operating under conditions which preclude the waste of utilities which shall include but not necessarily be limited to:

1.Lights shall be used only in areas where and at the time when work is actually being performed unless otherwise directed.
2.Contractor’s personnel will not adjust mechanical equipment controls for heating, ventilation, and air conditioning systems.
3.Government telephones shall not be used for personal reasons or for any toll or long-distance calls.

10.0 – TECHNICIAN/INSPECTOR QUALIFICATIONS

The Government reserves the right to accept or reject Contractor’s staff for safety violation, lack or required training, or other cause. Documented prior the work, Contractor shall provide staff throughout the contract qualified to perform work on plumbing systems. The Contractor shall notify the Government within 3 business days if it intends to replace a staff member. At the time of notification, the Contractor shall submit all required certifications for all personnel working on the contract. In the event new, or replacement, personnel become involved in the contract, the Contractor must submit all required certification. Additions or changes in personnel require written approval of the Government. The Contractor shall have a back-up staff available in the event the primary staff is unable to perform his/her duties.

The Contractor will ensure their personnel and Subcontractor personnel meet the privacy standards as set forth by HIPPA (Health Insurance Portability and Accountability Act of 1996) with respect to personal and confidential information that they may come upon, while contract work is being performed.

11.0 – PERSONNEL ASSIGNMENTS

The Contractor shall assign the appropriate quantity and type of personnel to successfully complete all functions specified in this SOW within the designated period of performance and required sequencing/ phasing. The Contractor shall maintain throughout the life of this contract, a current list of laborers, tradesmen, technicians, superintendents, etc. and their credentials available for inspection by the Government at any time.

The Contractor shall specify a Project Manager who will have responsibility for performance of contract services. The Project Manager shall be competent to supervise all aspects of contract and shall be available on-site during performance of contract work. The Contracting Officer shall be notified in writing of the name of the Project Manager and of changes in personnel appointed to fulfill this function.

12.0 – ACCEPTANCE STANDARDS

The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA.

13.0 – SAFETY AND FIRE PREVENTION

Comply with the following safety and fire prevention principles and regulations.

a. Precaution shall be exercised at all times for the protection of all persons on the site and government property. These precautions shall include, but not be limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor shall comply with all applicable laws relating to safety precautions.

b. The Contractor shall immediately correct any fire and safety deficiencies caused by his/her personnel. If the Contractor fails or refused to correct deficiencies promptly, the CO may issue an order stopping all or any part of the work and hold the Contractor in default of the contract.

c. The Contractor shall comply with applicable Federal, State, and local safety and fire regulations and codes which are in effect at the beginning of the contract. The Contractor shall keep abreast of and comply with changes in these requirements and codes applicable to the contract. The requirements include but are not limited to, those found in Federal and State OSHA statutes and regulations, such as applicable provisions of Title 29, CFR Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees

d. The Contractor’s personnel shall follow applicable facility policies concerning fire/disaster programs.

e. All materials and equipment will be removed from the facility or stored properly at the end of the workday and secured during the workday. Under no circumstances will the Contractor allow for any equipment to be left unattended for any length of time.

f. The Contractor shall comply with all applicable Federal, State, and local legal requirements regarding workers health and safety.

g. Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.

h. The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially regarding exits and exit way access. Utility shutdowns shall not compromise security, communication, or fire safety for occupants.

i. No flammable liquids shall be stored or used in the Medical Center.

j. The necessary number and appropriate types of portable fire extinguishers are required per NFPA 10 and NFPA 241. Contractor shall keep certification on site at all times of extinguisher inspections.

k. The Contractor shall request from the COR a permit for all live work, cutting, welding, soldering, and permit required confined space entry. All permits shall be prominently displayed during all construction. Allow 10 working days for approval.

l. All necessary precautions shall be taken by the Contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.

m. The Contractor shall assume responsibility of environmental protection of all material storage.

13.1 - ENVIRONMENTAL PROTECTION

Comply with the following environmental protection principles and regulations.

a. In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety Requirements” as well as the specific requirements stated elsewhere in the Contract Documents.

b. The Contractor is responsible for daily cleanup of all areas affected by its work. Areas in use or affected shall be returned to condition in which they were turned over or initially found. VA Housekeeping shall not be dispatched for cleaning associated with Contractor work.

c. Contractor shall use freight elevators for transmission of materials and personnel. Contractor shall take every precaution in preserving the elevators, including the hoist way and lobby doors, interior finishes, and shall conduct all good practices in observing lifting and motor components tolerances. Any damage incurred to any elevator component due to negligence will be repaired at expense of the Contractor, within the workday of incurred damage.

14.0 – WORK STANDARDS AND ICRA/ILSM

Work site shall be free of debris and returned to original condition upon completion of demolition and construction, preventative maintenance, or repairs.

All work is to be performed in areas used daily by facility clients and staff. Contractor will take suitable measures to control all material and equipment to produce a minimum of interference in facility routine. All work shall be performed in a safe and prudent manner.

Contractor shall so perform all work as to offer the least possible obstruction and inconvenience to staff and the public and shall have under construction no greater amount of work than can be completed promptly and properly with due regard to the rights of staff and the public. Any person the COR may deem incompetent or disorderly shall be promptly removed from the facility and not be allowed to return for the duration of the agreement.

The Contractor shall comply with an Infection Control Risk Assessment (ICRA) which will be developed with the COR and the Infection Control Practitioner. The Contractor shall comply with Interim Life Safety Measures (ISLM) which will be developed with the COR and the Safety Office. Multiple ICRA’s may be necessary to address specific risks at various stages of the project and must be approved prior to proceeding on each phase.

15.0 - HAZARDOUS MATERIAL REPORTING

Comply with the following hazardous material reporting principles and regulations.

a. The Contractor shall maintain hazardous material inventories and safety data sheets (SDS) for all hazardous materials (as defined in CFR 1910.120, 40 CFR’s 355, 370, & 372) to be stored and used on this Medical Center. Hazardous materials must be inventoried when received and at the project’s completion. The amounts used shall be maintained for the project duration, and for the calendar year (ending 31 December).

b. Hazardous Materials Inventories, Safety Data Sheets and material quantities used shall be submitted to the CO for approval.

c. In the event of a hazardous spill, Contractor shall immediately notify the COR. The Contractor shall be solely responsible for the expense of any cleanup of such spill, and the cleanup shall be in accordance with the applicable provisions of 40 CFR Part 761.

d. Asbestos Containing Material (ACM) should not present in the workspace. If the Contractor locates suspected ACM, the Contractor shall contact the COR immediately for further direction. If any suspected ACM is disturbed or becomes friable, the construction site shall be shut down until abatement can be performed, after which the job site shall be reopened for continued work.

16.0 – HOURS OF WORK

With few preapproved exceptions, the hours of work shall take place during the normal business hours of 7:00 AM and 4:00 PM, Monday through Friday, Federal Holidays excluded. Weekend, after-hour, and Federal holiday work is permitted with a request in writing submitted beforehand. Allow 10 working days for approval. Off hours are not to billed as overtime. Federal Holidays and any other day declared a federal holiday by the President of the United States are defined below.

New Year’s DayMartin Luther King Jr’s DayPresidents Day
Memorial DayIndependence DayLabor Day
Columbus DayVeterans DayThanksgiving Day
Christmas DayJuneteenth

If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government.

All work shall be scheduled and performed within the dates and times approved by the COR, in conjunction with the department occupying the space served by this equipment and in conjunction with work performed by others within the construction site.

17.0 - BADGES AND PARKING

Contractor must acquire PIV badge for all staff onsite prior to work beginning. While on VA Facilities official I.D. badges shall be worn continuously. Failure of the background check may result in specific personnel being disallowed to work on VA premises and the Contractor will need to provide replacement personnel.

It is the responsibility of the Contractor’s personnel to park in the appropriate designated parking areas. The designated parking area will be specified by COR upon award of contract. While performing under this contract, all vehicles used by the Contractor shall be locked and the keys removed when not in use. This is intended to protect the Contractor’s property and the safety of the patients at the Medical Center.

18.0 – QUALITY CONTROL

The Contractor shall have a quality control program to assure the requirements of this contract are provided as specified. The Contractor and COR will inspect the work. Deficiencies will be noted and corrected. Any damage done by Contractor will also be noted and corrected by the Contractor within a time period specified by the COR. Damage causing an immediate impact on the environment of the hospital shall be corrected immediately.

19.0 – ACCEPTANCE STANDARDS

Completed work will be to the entire satisfaction of the VA. The COR shall be the sole judge as to its acceptability. Any work not acceptable to the COR, shall be immediately, at Contractor’s own expense, refashioned to an acceptable level.

20.0 – KEYS

a. Keys: The COR shall provide the Contractor access to all buildings and rooms required in the provisions of this contract. The Contractor shall notify the COR when leaving these areas.

b. Clearances/Access Controls: Contractor and all personnel shall comply with the security clearances or access controls of areas within the Medical Center. In the event that the Contractor must obtain access to areas that require special security precautions, obtain permission from the COR prior to access.

21.0 – MEETINGS

Pre-Bid meeting and site walk will be held at a date and time specified by the COR to review the scope of work, site conditions, and work requirements with perspective contractors, and to provide answers to any questions. Contractor and/or Sub-contractors are encouraged to attend the pre-bid meeting before submitting a bid. The date and time of this walkthrough will be determined by the CO and COR. Contractor and/or Subcontractors shall be responsible for directing any clarification requests that arise at the pre-bid walkthrough to the CO prior to the bidding of the work.

22.0 – PERIOD OF PERFORMANCE

Government intends to issue NTP immediately after the pre-construction meeting with Contractor. The period of performance for this contract is 270 calendar days.

End Statement of Work

A.4 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
GRAND TOTAL
__________________

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.

I.2A SELECTION PROCEDURES

This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.

I.3A PRE-PROPOSAL SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.

I.4A SELECTION CRITERIA

This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.

The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:

Factor 1 – Past Performance Factor 2 – Price

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.

Past performance will be evaluated on a basis of significantly more important than, cost or price.

Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:

ASSESSMENT
DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

Factor 1-Past Performance

(a) Solicitation Submittal Requirements:

Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Ilze Karklins-Powers, ilze.karklins-powers@va.gov

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts in a project of replacing and upgrading parking lots in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.

If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.

If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.

Factor 2 – Price:

(a) Solicitation Submittal Requirements:

· Standard Form 1442, Solicitation Offer and Award

· All pages of the SF1442 Continuation Sheet

(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

· Comparison of proposed prices received in response to the RFP

· Comparison of proposed prices with the IGCE.

· Comparison of proposed prices with available historical information.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. (2) Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

3. Limitation on Subcontracting:

IAW VAAR 852.219-77 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal documents. Failure to comply with this requirement will result in removal of proposal for consideration for award.

Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $500,000.00 and $1,000,000.00

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email ilze.karklins-powers@va.gov Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.

Proposals shall be received by 1:00 PM. Mountain Time on March 15, 2022. There will be no public opening of the proposals. Submit proposals to: ilze.karklins-powers@va.gov.

Submit bid bonds to:

Department of Veterans Affairs

NCO 19 (90C)

ATTN: Ilze Karklins-Powers 2360 E. Pershing Blvd.

Cheyenne, WY 82001

Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .