260526 Ground and Boning.pdf
PDF 82 KB Posted
- Attached to
- Z2DA--(CON) *635 - OKLAHOMA CITY VAMC Replace Lawton Outpatient Clinic Air Cool Chiller (VA-21-00046407)
- Solicitation number
- 36C25921R0064
About this file
This solicitation notice provides details for replacing an air-cooled chiller at the Lawton Outpatient Clinic in Lawton, Oklahoma. The project involves replacing an existing 100-ton Trane air-cooled chiller with a new 100-ton air-cooled chiller. The solicitation will be a Service-Disabled Veteran Owned Small Business set-aside with a magnitude between $250,000 to $500,000. Responses are due on or after March 31, 2021. The contractor will be responsible for disconnecting and removing the existing chiller, installing the new chiller, connecting it to existing chilled water piping and controls, and performing start-up activities. Eligible chillers include the Trane CGAM model or other makes that meet specifications. The contractor must also address isolating an existing chilled water pump, insulating new piping, providing temporary cooling if needed, and enlarging the concrete pad if required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25921R0064 0007.docx | DOCX document | |
| Amended SOW.pdf | ||
| 36C25921R0064 0006.pdf | ||
| RFI 2 Answers.pdf | ||
| 36C25921R0064 0005.pdf | ||
| RFI1 Chiller Lawton.pdf | ||
| Clinic Chiller Pre-Bid Sign in.pdf | ||
| 260511 Requirement for Electrical Installation.pdf | ||
| 260519 Low Voltage Electrical Power Conductors and Cables.pdf | ||
| 36C25921R0064 0003.pdf | ||
| 36C25921R0064 0004.pdf | ||
| A004 WD Comanche Couty OK 4_9_2021.docx | DOCX document | |
| WD OK20210049 April 9 2021.pdf | ||
| 36C25921R0064 0002.pdf | ||
| 36C25921R0064 0001.pdf | ||
| 013323 Shopdrawings.pdf | ||
| H10-Floor Plan Piping LAWTON.pdf | ||
| 236400 Packged Chiller.pdf | ||
| 013526 Safety.pdf | ||
| 36C25921R0064 full solicitation.docx | DOCX document | |
| 230800 COMMISSIONING HVAC.pdf | ||
| 010000 General Requirement.pdf | ||
| H12-Large Scale Mechanicl Floor Plans LAWTON.pdf | ||
| 36C25921R0064_1.docx | DOCX document |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01-01-17
26 05 26 - 1
SECTION 26 05 26
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, connection, and testing of grounding and bonding equipment, indicated as grounding equipment in this section.
B. “Grounding electrode system” refers to grounding electrode conductors and all electrodes required or allowed by NEC, as well as made, supplementary, and lightning protection system grounding electrodes.
C. The terms “connect” and “bond” are used interchangeably in this section and have the same meaning.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS:
Requirements that apply to all sections of Division 26.
B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES:
Low-voltage conductors.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS
(PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with drawings and specifications.
b. Submit plans showing the location of system grounding electrodes and connections, and the routing of aboveground and underground grounding electrode conductors.
2. Test Reports:
a. Two weeks prior to the final inspection, submit ground resistance field test reports to the COTR.
3. Certifications:
a. Certification by the Contractor that the grounding equipment has been properly installed and tested.
26 05 26 - 2
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B. American Society for Testing and Materials (ASTM):
B1-13...................Standard Specification for Hard-Drawn Copper
Wire
B3-13...................Standard Specification for Soft or Annealed
Copper Wire
B8-11...................Standard Specification for Concentric-Lay-
Stranded Copper Conductors, Hard, Medium-Hard, or Soft
C. Institute of Electrical and Electronics Engineers, Inc. (IEEE):
81-12...................IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System Part 1: Normal Measurements
D. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (NEC)
70E-15..................National Electrical Safety Code
99-15...................Health Care Facilities
E. Underwriters Laboratories, Inc. (UL):
44-14 ..................Thermoset-Insulated Wires and Cables
83-14 ..................Thermoplastic-Insulated Wires and Cables
467-13 .................Grounding and Bonding Equipment
PART 2 - PRODUCTS
2.1 GROUNDING AND BONDING CONDUCTORS
A. Equipment grounding conductors shall be insulated stranded copper, except that sizes No. 10 AWG and smaller shall be solid copper.
Insulation color shall be continuous green for all equipment grounding conductors, except that wire sizes No. 4 AWG and larger shall be identified per NEC.
B. Bonding conductors shall be bare stranded copper, except that sizes No.
10 AWG and smaller shall be bare solid copper. Bonding conductors shall be stranded for final connection to motors, transformers, and vibrating equipment.
C. Conductor sizes shall not be less than shown on the drawings, or not less than required by the NEC, whichever is greater.
26 05 26 - 3
D. Insulation: THHN-THWN and XHHW-2. XHHW-2 shall be used for isolated power systems.
2.2 GROUND RODS
A. Steel or copper clad steel, 19 mm (0.75 inch) diameter by 3 M (10 feet) long.
B. Quantity of rods shall be as shown on the drawings, and as required to obtain the specified ground resistance.
2.3 CONCRETE ENCASED ELECTRODE
A. Concrete encased electrode shall be No. 4 AWG bare copper wire, installed per NEC.
2.4 GROUND CONNECTIONS
A. Below Grade and Inaccessible Locations: Exothermic-welded type connectors.
B. Above Grade:
1. Bonding Jumpers: Listed for use with aluminum and copper conductors.
For wire sizes No. 8 AWG and larger, use compression-type connectors. For wire sizes smaller than No. 8 AWG, use mechanical type lugs. Connectors or lugs shall use zinc-plated steel bolts, nuts, and washers. Bolts shall be torqued to the values recommended by the manufacturer.
2. Connection to Building Steel: Exothermic-welded type connectors.
3. Connection to Grounding Bus Bars: Listed for use with aluminum and copper conductors. Use mechanical type lugs, with zinc-plated steel bolts, nuts, and washers. Bolts shall be torqued to the values recommended by the manufacturer.
4. Connection to Equipment Rack and Cabinet Ground Bars: Listed for use with aluminum and copper conductors. Use mechanical type lugs, with zinc-plated steel bolts, nuts, and washers. Bolts shall be torqued to the values recommended by the manufacturer.
2.5 EQUIPMENT RACK AND CABINET GROUND BARS
A. Provide solid copper ground bars designed for mounting on the framework of open or cabinet-enclosed equipment racks. Ground bars shall have minimum dimensions of 6.3 mm (0.25 inch) thick x 19 mm (0.75 inch) wide, with length as required or as shown on the drawings. Provide insulators and mounting brackets.
26 05 26 - 4
2.6 GROUND TERMINAL BLOCKS
A. At any equipment mounting location (e.g., backboards and hinged cover enclosures) where rack-type ground bars cannot be mounted, provide mechanical type lugs, with zinc-plated steel bolts, nuts, and washers.
Bolts shall be torqued to the values recommended by the manufacturer.
2.7 GROUNDING BUS BAR
A. Pre-drilled rectangular copper bar with stand-off insulators, minimum
6.3 mm (0.25 inch) thick x 100 mm (4 inches) high in cross-section, length as shown on the drawings, with hole size, quantity, and spacing per detail shown on the drawings. Provide insulators and mounting brackets.
PART 3 - EXECUTION
3.1 GENERAL
A. Installation shall be in accordance with the NEC, as shown on the drawings, and manufacturer’s instructions.
B. System Grounding:
1. Secondary service neutrals: Ground at the supply side of the secondary disconnecting means and at the related transformer.
2. Separately derived systems (transformers downstream from the service entrance): Ground the secondary neutral.
C. Equipment Grounding: Metallic piping, building structural steel, electrical enclosures, raceways, junction boxes, outlet boxes, cabinets, machine frames, and other conductive items in close proximity with electrical circuits, shall be bonded and grounded.
D. For patient care area electrical power system grounding, conform to the latest NFPA 70 and 99.
3.2 INACCESSIBLE GROUNDING CONNECTIONS
A. Make grounding connections, which are normally buried or otherwise inaccessible, by exothermic weld.
3.3 MEDIUM-VOLTAGE EQUIPMENT AND CIRCUITS (NOT USE)
3.4 SECONDARY VOLTAGE EQUIPMENT AND CIRCUITS
A. Main Bonding Jumper: Bond the secondary service neutral to the ground bus in the service equipment.
B. Metallic Piping, Building Structural Steel, and Supplemental
Electrode(s):
1. Provide a grounding electrode conductor sized per NEC between the service equipment ground bus and all metallic water pipe systems, 26 05 26 - 5 building structural steel, and supplemental or made electrodes.
Provide jumpers across insulating joints in the metallic piping.
2. Provide a supplemental ground electrode as shown on the drawings and bond to the grounding electrode system.
3.5 RACEWAY (NOT USE)
3.6 OUTDOOR METALLIC FENCES AROUND ELECTRICAL EQUIPMENT (NOT USE)
3.7 CORROSION INHIBITORS
A. When making grounding and bonding connections, apply a corrosion inhibitor to all contact surfaces. Use corrosion inhibitor appropriate for protecting a connection between the metals used.
3.8 CONDUCTIVE PIPING
A. Bond all conductive piping systems, interior and exterior, to the grounding electrode system. Bonding connections shall be made as close as practical to the equipment ground bus.
B. In operating rooms and at intensive care and coronary care type beds, bond the medical gas piping and medical vacuum piping at the outlets directly to the patient ground bus.
3.9 LIGHTNING PROTECTION SYSTEM
A. Bond the lightning protection system to the electrical grounding electrode system.
3.10 MAIN ELECTRICAL ROOM GROUNDING (NOT USE)
3.11 EXTERIOR LIGHT POLES (NOT USE)
3.12 GROUND RESISTANCE
A. Grounding system resistance to ground shall not exceed 5 ohms. Make any modifications or additions to the grounding electrode system necessary for compliance without additional cost to the Government. Final tests shall ensure that this requirement is met.
B. Grounding system resistance shall comply with the electric utility company ground resistance requirements.
3.13 GROUND ROD INSTALLATION
A. For outdoor installations, drive each rod vertically in the earth, until top of rod is 610 mm (24 inches) below final grade.
B. For indoor installations, leave 100 mm (4 inches) of each rod exposed.
C. Where buried or permanently concealed ground connections are required, make the connections by the exothermic process, to form solid metal
26 05 26 - 6 joints. Make accessible ground connections with mechanical pressure-type ground connectors.
D. Where rock or impenetrable soil prevents the driving of vertical ground rods, install angled ground rods or grounding electrodes in horizontal trenches to achieve the specified ground resistance.
3.14 ACCEPTANCE CHECKS AND TESTS
A. Resistance of the grounding electrode system shall be measured using a four-terminal fall-of-potential method as defined in IEEE 81. Ground resistance measurements shall be made before the electrical distribution system is energized or connected to the electric utility company ground system, and shall be made in normally dry conditions not fewer than 48 hours after the last rainfall.
B. Resistance measurements of separate grounding electrode systems shall be made before the systems are bonded together. The combined resistance of separate systems may be used to meet the required resistance, but the specified number of electrodes must still be provided.
C. Below-grade connections shall be visually inspected by the COR prior to backfilling. The Contractor shall notify the COR 24 hours before the connections are ready for inspection.
---END---