Site Visit Meeting Doc.docx
DOCX document 19 KB Posted
- Attached to
- Z2DA--666 - (CON) Building 9 Renovation for Dental | Project# 666-11-111 (VA-21-00001829)
- Solicitation number
- 36C25920R0150
About this file
This document outlines requirements for a federal construction contract opportunity with the Department of Veterans Affairs. The contractor will perform renovations for a new dental clinic at the Sheridan VA Medical Center in Wyoming, with a project budget between $1,000,000 and $5,000,000. The solicitation is set aside entirely for verified Service-Disabled Veteran-Owned Small Businesses. Questions are due by specified dates in November, with proposals due December 1st. The selected contractor must begin work within 10 days of notice to proceed and complete the project within 365 days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25920R0150 0005.docx | DOCX document | |
| 36C25920R0150 0004.docx | DOCX document | |
| S06- 36C25920R0150 0004.docx | DOCX document | |
| SOW_ Bldg. 9 Renovation for Dental_updated.docx | DOCX document | |
| 028213 13 Glovebag Asbestos Abatement.pdf | ||
| RFI Questions with Answers.docx | DOCX document | |
| 105113 Metal Lockers.pdf | ||
| Site Visits Attendance.pdf | ||
| 36C25920R0150 0003.docx | DOCX document | |
| 36C25920R0150 0002.docx | DOCX document | |
| 36C25920R0150 0001.docx | DOCX document | |
| SVA_Building9 - Specifications 200724 - Stamped FINAL.pdf | ||
| SVA_Building 9 - Combined Drawings 200724 - Stamped FINAL.pdf | ||
| 36C25920R0150_1.docx | DOCX document | |
| Attachment A Apollo - Material List include with SOW.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Offer Site Visit Meeting 36C25920R0150 Bldg. 9 Renovation Dental Clinic at Sheridan VAMC
The contractor is to provide all labor, tools, materials, equipment and supervision required to complete the construction of the Building 9 Renovation for Dental Clinic at the Sheridan VA Medical Center. Work to include remodeling administration offices into dental clinic space.
Location: Sheridan VA Medical Center
AGENDA:
· Introduction of Aldo F. Girany CO, Thomas Hatch COR
· The pre-offer meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFP:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due November 5 at 1:00 PM MT prior to closing of RFP, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Proposals due on 12/1/2020 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· Masks are to be worn at all times while on VA property.
· Confirmation of construction range is between $1,000,000 and $2,000,000.
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price or $3,000,000.00 whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 365 days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.
Pre-Offer Site Visit Meeting 36C25920R0150 Bldg. 9 Renovation Dental Clinic at Sheridan VAMC 2nd visit The contractor is to provide all labor, tools, materials, equipment and supervision required to complete the construction of the Building 9 Renovation for Dental Clinic at the Sheridan VA Medical Center. Work to include remodeling administration offices into dental clinic space.
Location: Sheridan VA Medical Center
AGENDA:
· Introduction of Aldo F. Girany CO, Thomas Hatch COR
· The pre-offer meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFP:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due November 13 at 10:30 AM MT prior to closing of RFP, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Proposals due on 12/1/2020 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· Masks are to be worn at all times while on VA property.
· Confirmation of construction range is between $1,000,000 and $2,000,000.
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price or $3,000,000.00 whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 365 days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.
File details come from the government source that posted it. Updated .