Amendment 3 Rev 1_Bldg 43_501-17-110_20200810.pdf
PDF 13 MB Posted
- Solicitation number
- 36C25820B0015
About this file
This document provides details for a federal contract opportunity to upgrade IT closet storage areas at the New Mexico VA Healthcare System. The solicitation seeks general construction and alteration services to demolish and replace items and upgrade closet lighting and HVAC systems. Offerors must be registered in SAM.gov and VetBiz.gov. The period of performance is 365 calendar days from notice to proceed. The magnitude of the project is between $2 million and $5 million, and it falls under NAICS code 236220 for commercial and institutional building construction. The small business size standard is $36.5 million. A minimum of 15% self-performance is required in accordance with FAR 52.204-7 and VAAR 804.1103-70. Interested parties are encouraged to register on SAM.gov to receive notifications regarding the solicitation and any amendments.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT REVIEW
DATE: APPROVED: DIRECTOR
DATE: APPROVED: ASSOCIATE DIRECTOR
DATE: APPROVED: ASSISTANT DIRECTOR
DATE: APPROVED: CHIEF OF STAFF
DATE: APPROVED: CHIEF ENGINEER
DATE: APPROVED: ASSOCIATE DIRECTOR, PATIENT CARE SERVICES
DATE: APPROVED:
DATE: APPROVED:
ALBUQUERQUE
INTERNATIONAL
AIRPORT
GIBSON BLVD SE
RAYMOND G.
MURPHY VA MEDICAL
CENTER
I-25
S A
N M
A T
E O
B L
V D
S E
Y A
L E
B L
V D
S E
SUNPORT BLVD
PROJECT
LOCATION
ALBUQUERQUE
INTERNATIONAL
AIRPORT
GIBSON BLVD SE
CENTRAL AVE SE
RAYMOND G.
MURPHY VA
MEDICAL
CENTER
W Y
O M
IN
G
B L
V D
S E
CENTRAL AVE SE
I-25
I-25
I-40
S A
N M
A T
E O
B L
V D
S E
Y A
L E
B L
V D
S E
SUNPORT BLVD
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
B
IM
/5
-1
-1
U p g ra d e I T
C lo s e ts
/5
-1
-1
V
A -A
B Q
B ld g
M
E P
.r v t
/2
/2
:5 :2
P
M
G-001
COVER SHEET
TRIPLE C The A/E Group
2266 S. Dobson Rd, Suite. 200
Mesa, AZ 85202
307-460-2054
Mat Perkins
UPGRADE IT CLOSET AREAS
1501 San Pedro Dr. SE, Albuquerque, NM 87108
501-17-110
07/02/2019 M. PERKINS G. WEAVER
ISSUED FOR
CONSTRUCTION
NEW MEXICO VA HEALTH CARE SYSTEM (NMVAHCS)
ISSUED FOR CONSTRUCTION SUBMISSION
JULY 02, 2019
VA PROJECT NO : 501-17-110
UPGRADE IT CLOSET AREAS
BUILDING 43
CLIENT:
Department of Veterans Affairs
Daniel Thelen Contracting Officer Office: 520.629.4830
Daniel.Thelen@va.gov
COR:
Byron Secatero
Office: 505.265.1711 x3844 Byron.Secatero@va.gov
THERE IS NO LEAD OR ASBESTOS MATERIAL DESIGNED INTO THIS PROJECT.
SIGNATURE________________________________ DATE ________________
AUTHOR: MAT PERKINS, AIA, NCARB, PMP, LEED AP BD+C
TRIPLE C - THE A&E GROUP
THIRD-PARTY INSPECTIONS:
COMPREHENSIVE THIRD-PARTY INSPECTIONS, TESTING
AND WRITTEN REPORTS FOR ALL DIVISIONS (PAID BY THE GENERAL
CONTRACTOR). CONTRACTOR SHALL EMPLOY THIRD-PARTY INSPECTION
CONSULTANTS TO PERFORM ALL INSPECTIONS REQUIRED BY THIS CONTRACT.
THE VA HAS NO INSPECTION CAPABILITY. ANY REFERENCE TO VA INSPECTIONS
SHALL BE BY A THIRD-PARTY INSPECTOR QUALIFIED TO PERFORM THE WORK.
CREDENTIALS SHALL BE SUPPLIED TO THE VA/AE AS REQUIRED BY THIS
CONTRACT. ALL INSPECTIONS, TESTING, CERTIFICATIONS, AND PERMITS ARE
TO BE PAID FOR BY THE GENERAL CONTRACTOR. THE VA WILL NOT PAY FOR
OR PERFORM ANY REQUIRED INSPECTIONS. VA INSPECTIONS ARE FOR VA USE
ONLY, WHEN PERFORMED, AND DO NOT REDUCE THE INSPECTION BURDEN ON
THE CONTRACTOR.
THIS PROJECT MUST BE “STAND ALONE”. THAT IS, THE PROJECT CANNOT DEPEND
ON ANOTHER PROJECT OR OTHER FUNDING SOURCE TO MAKE THE FINAL RESULT
COMPLETE AND USABLE.
Sheet Index
Sheet Number Sheet Name
35% Submittal
65% Submittal
95% Submittal
100% Submittal
IFC
Submittal
IFC
Rev01
GENERAL
G-001 COVER SHEET 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-010 GENERAL PROJECT NOTES 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-011 GENERAL INFECTION CONTROL NOTES AND SYMBOLS 07/02/2019
G-012 GENERAL INDOOR AIR QUALITY NOTES 07/02/2019
GS101 GENERAL SITE PLAN 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-101 GENERAL REFERENCE PLAN - FIRST FLOOR - EXISTING 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-102 GENERAL REFERENCE PLAN - SECOND FLOOR - EXISTING 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-103 GENERAL REFERENCE PLAN - SECOND FLOOR - NEW 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
G-104 GENERAL REFERENCE PLAN - ROOF - NEW 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
ARCHITECTURE
A-001 ARCHITECTURAL ABBREVIATIONS, SYMBOLS, & GENERAL NOTES 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-051 EXISTING SITE CONDITION PHOTOS 02/27/2019 04/24/2019 07/02/2019
A-151 ARCHITECTURAL ROOF - PROPOSED PLAN 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-401 ARCHITECTURAL ENLARGED PLANS 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-511 ARCHITECTURAL PARTITION AND FRAMING DETAILS 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-512 ARCHITECTURAL DETAILS 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-531 ARCHITECTURAL CEILING DETAILS 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
A-901 ARCHITECTURAL FIRE PROTECTION CUTSHEETS & BASIS OF DESIGN 02/27/2019 04/24/2019 07/02/2019
INTERIORS
IN101 INTERIOR FINISH PLAN AND ROOM SCHEDULE 10/02/18 11/14/2018 02/27/2019 04/24/2019 07/02/2019
MECHANICAL
M-001 MECHANICAL LEGEND 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
M-102 MECHANICAL PLANS - SECOND FLOOR AND ROOF 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
M-701 MECHANICAL SCHEDULES 10/02/2018 11/20/2018 02/27/2019 04/24/2019 07/02/2019
M-801 MECHANICAL CONTROL SYMBOL LEGEND AND ABBREVIATIONS 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
M-802 MECHANICAL CONTROL DIAGRAMS 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
M-901 MECHANICAL CUTSHEETS & BASIS OF DESIGN 02/27/2019 04/24/2019 07/02/2019
ELECTRICAL
E-001 ELECTRICAL SYMBOL LEGEND AND ABBREVIATIONS 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-002 OIT STATION STANDARD CLOSET 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-401 ENLARGED ELECTRICAL PLANS - SECOND FLOOR - DEFICIENCIES 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-402 ENLARGED ELECTRICAL PLANS - RECOMMENDED CORRECTIONS 07/20/18 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-501 ELECTRICAL DETAILS 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-601 ELECTRICAL DIAGRAMS 10/02/18 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-602 ONE LINE DIAGRAM 11/20/2018 02/27/2019 04/24/2019 07/02/2019
E-901 ELECTRICAL CUTSHEETS & BASIS OF DESIGN 02/27/2019 04/24/2019 07/02/2019
E-902 ELECTRICAL CUTSHEETS & BASIS OF DESIGN 02/27/2019 04/24/2019 07/02/2019
A. PROJECT SCOPE OF WORK
The purpose of this project is to provide a designed solution to address deficiencies associated with IT Closet Areas located within multiple buildings at the NMVAHCS. Multiple buildings on campus include Buildings 1, 2, 3, 4, 5, 6, 8, 10, 11, 18, 39, 41, 43, 45, and 46. Buildings 52 and 53 are in conformance with OIT requirements per OIT leadership and removed from the project at this time.
The Air Force ownes building 47 and was removed from the project per OIT leadership.
The OIT priority building order provided is: Buildings 11, 10, 5/6, 8, 3, 2, 43, 46, 45, 1, 4 ,41 Quadrants (BA, BD, BC, 1A,1B,1C,1D, 2A,2B,2C,2D, 3A,3B,3C,3D, 4B,4C,4D, 5A,5B,5C,5D, 6A,6D).
The construction shall include provisions for expanding the size of IT Closet Areas, addressing UPS deficiencies, grounding and bonding conditions within each closet, alarm monitoring, configuration of equipment within the closets such as cable trays/housings, rack configuration, sizing of sleeves for cabling, removing abandoned cable and addressing physical security needs. The construction shall provide new equipment rack(s) furnished with both horizontal and vertical cable managers, vertical bonding bars, UPS, patch panel and an optical fiber termination shelf. Scope will include re-pulling data drops associated with relocated equipment racks and the termination of optical fiber and all wire management is included in the scope of work.
Additionally, dedicated air conditioning units with monitoring shall be provided. The contractor shall ensure closets are enclosed smoke tight, provide access controls and video surveillance (per Physical security requirements), correct emergency power receptacles for UPS systems and monitoring and ensure cable management trays and removal of old CAT 3 cable infrastructure is documented.
Contractor shall develop and provide a complete set of ICRA drawings in coordination with the scope of each building for COR approval prior to construction. Provide limited construction period services as described in this and other sections of the contract and provide “as-builts” based on observation and contractors’ marked drawings.
LOCATION MAP NORTH
NORTHVICINITY MAP
BUILDING 43 SCOPE OF WORK:
Relocate existing mechanical and electrical infrastructure for new IT Closet on mezzanine, see 501-10-105 Optimize B43 Energy Plant Construct new IT Closet with new secure door (Qty. 1) and repair adjacent finishes, install new dry-agent fire sprinkler system Remove all flooring throughout, all Closets shall receive new wall base (Qty. 170 LF) and new paint (Qty. 815 SF) Remove and relocate existing signage as identified, or specified if no signage exists Provide a dedicated TIA-607-B telecom bonding (grounding) system including primary and secondary bonding bars, bond equipment racks and cable trays where applicable (Qty. 1 rooms) Provide new equipment rack with vertical wire management, bonding bar, 2U UPS unit (Qty. 2).
Provide 12”W x 4” H cable tray system (Qty. 50’-0”) Provide 6 port data jack and drop (Qty. 4) Install 42 data drops to existing data outlets, 100'-0" average length.
Provide L5-30R outlet (Qty. 2) Provide 3-Size 44 EZ-Path (Qty. 1) Provide 4’ linear LED strip light (Qty. 2) Provide occupancy sensor lighting control (Qty. 1) Install new mechanical split system cooling as secondary cooling (Qty. 1) Install access control and security hardware VA – CR needs to have a pin pad (C-CURE 9000, HSPD-12-Compliant, needs to be PIV ready (Qty. 1) VA – CCTV needs to be IC Realtime compliant, run to police operations B41, all digital Go from DVR’s to NVR’s (Qty. 1) No fiber optic expansions are required Slack needed in the cable to slide optical cable shelf
Revisions: Date:
TRIPLE C A& E GROUP, THE A-E OF RECORD FOR THE NEW MEXICO VA HEALTHCARE SYSTEM ON PROJECT 501-17-110, LOCATED IN ALBUQUERQUE, NEW MEXICO CAN CERTIFY THAT NO ASBESTOS CONTAINING BUILDING MATERIAL (ACBM)
OR LEAD BASED PRODUCTS WERE DESIGNED/ SPECIFIED IN THE DESIGN.
AT TIME OF AS-BUILT DRAWINGS APPROVAL, THE A-E OF RECORD FOR THE NEW MEXICO VA HEALTHCARE SYSTEM ON PROJECT 501-17-110, LOCATED ALBUQUERQUE, NEW MEXICO CAN CERTIFY THAT NO ASBESTOS CONTAINING BUILDING MATERIAL (ACBM) OR LEAD BASED PRODUCTS WERE APPROVED VIA ANY CONTRACT SUBMITTALS FROM THE CONSTRUCTION CONTRACTOR. TO THE BEST OF OUR KNOWLEDGE, AND BASED ON THE PRODUCT SUBMITTAL REVIEWS, ALL PRODUCTS USED FOR THE CONSTRUCTION ARE FREE OF ASBESTOS AND
LEAD.
A. CONTRACTOR SHALL FIELD VERIFY ALL NEW AND EXISTING CONDUIT, PIPE AND DUCT ROUTING IN THE AREA OR WORK, BETWEEN PROPOSED AND EXISTING IT CLOSETS AND FROM THE POINT OF BUILDING SERVICE TO NEW AND EXISTING IT CLOSET LOCATIONS. CONTRACTOR SHALL PROVIDE COORDINATION DRAWINGS IN COMPLIANCE WITH THE DIVISION 1, 21, 22, 23, 26, 27 AND 28 SPECIFICATIONS FOR VA/AE APPROVAL PRIOR TO COMMENCING ANY WORK. THESE COORDINATION DRAWINGS SHALL SHOW EXISTING AND PROPOSED CONDUIT, PIPE AND DUCT
ROUTING AND SHALL PROVIDE PROPER CLEARANCES AND ACCESS TO ALL SYSTEMS.
B. CONTRACTOR IS RESPONSIBLE FOR MAINTAINING UNINTERRUPTED UTILITY SERVICE DURING THIS PROJECT. THIS WILL INCLUDE PROVIDING TEMPORARY UTILITIES AND APPROPRIATE PHASING TO ENSURE CHANGING OVER TO THE NEW OR RENOVATED IT CLOSETS DOES NOT RESULT IN DISRUPTIONS OF SERVICE. CONTRACTOR SHALL SUBMIT TEMPORARY UTILITY, PHASING AND SHUTDOWN/CHANGEOVER PLANS TO
THE VA/AE A MINIMUM (21) DAYS PRIOR TO COMMENCING ANY WORK.
C. CONTRACTOR IS RESPONSIBLE FOR ALL CABLING, TERMINATIONS AND OTHER ELECTRICAL AND COMMUNICATIONS CONNECTIONS ON THIS
PROJECT. VA PERSONNEL SHALL NOT BE RESPONSIBLE FOR ANY WORK IN THIS REGARD.
D. CONTRACTOR SHALL PROVIDE A THIRD-PARTY COMMISSIONING AGENT TO PERFORM THE COMMISSIONING SCOPE IDENTIFIED IN SPECIFICATION SECTIONS 01 91 00, 21 08 00, 22 08 00, 23 08 00, 26 08 00, 27 08 00 AND 28 08 00. PROJECT ACCEPTANCE BY THE GOVERNMENT IS CONTINGENT ON THE CONTRACTOR PROVIDING FULLY-COMMISSIONED IT CLOSETS FOR EACH BUILDING.
E. CONTRACTOR SHALL PERFORM ELECTRICAL LOAD TESTING ON THE PANELS IDENTIFIED IN SPECIFICATION 01 00 00, PRIOR TO COMMENCING WORK. THESE LOAD TESTS WILL VALIDATE CURRENT LOADS AND PANEL CAPACITY AT THE TIME OF CONSTRUCTION.
CONTRACTOR RESPONSIBILITIES:
Expires 6.30.16Expires: 6/30/1821
7/2 /19
ISSUED FOR CONSTRUCTION SUBMISSION
JANUARY, 21, 2020
Expires 6.30.16Expires: 6/30/1821
1/2 1/2
01/21/2019
Issue Date
01/21/202006/24/2020 Revision 1 06/24/2020
06/24/2020
BUILDING PRIORITY:
BASE BID: B1, B3, B11, B41 AND B45
ALTERNATE PRIORITY RANKING: B10, B4, B2, B8, B46, B43,B5/6, B39, B18
Expires 6.30.16Expires: 6/30/1821
6/2 4/2
06/24/2020
/2
4/
1/2 1/2
Expires 6.30.16Expires: 6/30/1821
6/2 4/2
Expires 6.30.16Expires: 6/30/1821
7/0 8/2
07/08/2020
F. ALL EXISTING CABLING SERVING EXISTING BUILDING DATA DROPS SHALL BE RETAINED AND REUSED. IT CLOSET SHALL BE RENOVATED WITH EXISTING
CABLING TO REMAIN.
1. THESE GENERAL NOTES APPLY TO ALL DRAWINGS.
2. COMPLY WITH ALL APPLICABLE CODES, RULES, AND REGULATIONS. WHEN REQUIRED BY CODE, ALL
WORK MUST BE INSPECTED AND APPROVED BY LOCAL AUTHORITIES.
3. ALL EXISTING CONDITIONS AND DIMENSIONS SHALL BE VERIFIED BY THE CONTRACTOR(S) PRIOR TO
FABRICATION AND CONSTRUCTION. ANY DISCREPANCIES BETWEEN EXISTING CONDITIONS AND
THESE DRAWINGS, WHICH AFFECT THE SCOPE AND INTENT OF THE WORK DESCRIBED IN
CONSTRUCTION DOCUMENTS, SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT AND COR
IMMEDIATELY.
4. GENERAL CONTRACTOR SHALL COORDINATE ALL MECHANICAL AND ELECTRICAL DUCT SIZES AND
LOCATIONS.
5. ALL EXITS TO BE OPERABLE FROM THE INSIDE WITHOUT THE USE OF A KEY OR SPECIAL
KNOWLEDGE.
6. WALL OUTLETS, SWITCHES,THERMOSTATS, ETC. TO BE INSTALLED LEVEL WITH EACH OTHER AND
PLUMB.
7. THE WORK INDICATED IN THE NOTES DESCRIBES THE GENERAL SCOPE OF WORK ONLY AND IS NOT
INTENDED TO BE INCLUSIVE OF ALL WORK REQUIRED TO COMPLETE FULL SCOPE OF WORK.
8. DO NOT MEASURE DRAWINGS. ALL DIMENSIONS SHALL BE FIELD VERIFIED. ALL DISCREPANCIES
SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT AND COR.
9. FIELD VERIFICATION: BEFORE BIDDING AND DURING CONSTRUCTION, CONTRACTOR SHALL VERIFY
THAT ACTUAL CONDITIONS ARE THOSE REFLECTED BY THE CONTRACT DOCUMENTS. REPORT
DISCREPANCIES TO ARCHITECT AND COR PRIOR TO BIDDING OR PERFORMING WORK RELATED TO
ANY DISCREPANCIES. SEE SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.
10. MOST EXPENSIVE BID: IF THERE ARE SCHEDULES, SYSTEMS, SUBCONTRACT, OR MATERIAL CONFLICTS NOT BROUGHT TO THE ARCHITECT'S AND COR'S ATTENTION PRIOR TO BIDDING, THE
CONTRACTOR WILL BE DEEMED TO HAVE ELECTED THE MORE COSTLY TIME, METHOD, SYSTEM,
PRODUCT, SUBCONTRACT AND/OR MATERIAL.
11. NIC: CONSTRUCTION OF WORK INDICATED ON DRAWINGS AS "NIC" IS NOT IN THE CONTRACT.
HOWEVER, THE CONTRACTOR SHALL COORDINATE ITS WORK, WITH WORK INDICATED AS NIC.
12. SITE COORDINATION: COORDINATE ALL SITE OPERATIONS WITH OWNER, INCLUDING STAGING
AREAS, MATERIAL STORAGE, ACCESS TO WORK, TIMING OF WORK, NOISY OPERATIONS,
INTERRUPTION OF UTILITIES, ETC. SEE SPECIFICATIONS.
13. TRADE COORDINATION: CONTRACTOR SHALL COORDINATE THE PLACEMENT OF EACH TRADE'S WORK SO THAT THERE ARE NO CONFLICTS AND NO SYSTEM'S OPERATION OR FUNCTION IMPAIRED. IT IS ESPECIALLY IMPORTANT TO COORDINATE PENETRATIONS THROUGH FOUNDATIONS, FLOORS, WALLS
AND CEILING SPACES. SEE SPECIFICATIONS.
14. PROVIDE GALVANIC SEPARATION MATERIAL, ACCEPTABLE TO ARCHITECT AND COR, BETWEEN
DISSIMILAR METALS. SEE SPECIFICATIONS.
15. ALL WOOD IN CONTACT WITH CONCRETE OR MASONRY SHALL BE FIRE TREATED. SEE
SPECIFICATIONS. ALL SURFACE ATTACHED METAL SHALL BE SEPARATED FROM CONCRETE OR
MASONRY BY NON-METALLIC MATERIAL SUCH AS #30 FELT, "PEEL AND STICK" OR OTHER MATERIAL AS
APPROVED BY ARCHITECT AND COR.
16. EXTERIOR / INTERIOR ELEVATIONS DO NOT SHOW ALL EQUIPMENT, FIXTURES, DEVICES,
MECHANICAL, PLUMBING OR ELECTRICAL ITEMS. SEE ARCHITECTURAL, INTERIOR, MECHANICAL AND
ELECTRICAL PLANS FOR ADDITIONAL ELEVATION COORDINATION.
17. ANY CUTTING/WELDING WILL REQUIRE DAILY BURN PERMITS TO BE COORDINATED WITH COR.
SUBMIT CERTIFICATIONS AS REQUIRED BY THE SPECIFICATIONS.
18. AN AIR QUALITY PERMIT WILL BE REQUIRED FOR THE GENERATOR FOR THIS PROJECT. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATION WITH THE ALBUQUERQUE VA AND AIR QUALITY
AUTHORITY HAVING JURISDICTION.
FIRE LIFE SAFETY NOTES
1. IF ENCOUNTERED, FIRE RATED ASSEMBLIES, INCLUDING FIREPROOFING, DAMAGED DURING
CONSTRUCTION MUST BE RESTORED TO THEIR ORIGINAL CONDITION.
2. FIRE RESISTIVE ASSEMBLIES, FIRE-RESISTIVE CONSTRUCTION, AND THE MEANS OF EGRESS MUST BE MAINTAINED AT ALL TIMES. WHEN IT IS NOT POSSIBLE TO MAINTAIN FIRE RESISTIVE
ASSEMBLIES, FIRE-RESISTIVE CONSTRUCTION AND/OR MEANS OF EGRESS, TEMPORARY
CONSTRUCTION BARRIERS AND/OR A FIRE WATCH MUST BE PROVIDED.
3. VHA DIRECTIVE 7715 SAFETY AND HEALTH DURING CONSTRUCTION DATED APRIL 6, 2017,
REQUIRES VA MASTER SPECIFICATIONS, DIVISION 1 - GENERAL REQUIREMENTS, SECTION 01 35 26 -
SAFETY REQUIREMENTS MADE SPECIFIC FOR THE ASSOCIATED CONSTRUCTION WORK.
FIRE SAFETY DURING CONSTRUCTION, ALTERATIONS AND DEMOLITION
1. FIRE DEPARTMENT ACCESS ROADS SHALL BE ESTABLISHED AND MAINTAINED AT ALL TIMES PER
LOCAL FIRE DEPARTMENT.
2. FIRE DEPARTMENT WATER MAINS AND FIRE HYDRANTS SHALL BE OPERATIONAL AT ALL TIMES
AND SHALL BE IN ACCORDANCE WITH LOCAL FIRE DEPARTMENT.
3. FIRE EXTINGUISHERS SHALL BE PROVIDED FOR BUILDINGS UNDER CONSTRUCTION. THE NUMBER AND TYPE OF EXTINGUISHERS SHALL BE AS REQUIRED BY THE STATE FIRE MARSHAL OR LOCAL
FIRE DEPARTMENT.
4. COMBUSTIBLE DEBRIS SHALL NOT ACCUMULATE WITHIN BUILDINGS.
5. CUTTING AND WELDING OPERATIONS SHALL BE IN ACCORDANCE WITH LOCAL FIRE CODES.
6. FIRE PROTECTION SYSTEMS SHALL BE MAINTAINED OPERATIONAL AT ALL TIMES PER LOCAL FIRE
CODES.
7. REQUIRED MEANS OF EGRESS COMPONENTS SHALL BE MAINTAINED AT ALL TIMES. TEMPORARY EXITING SHALL BE APPROVED BY THE STATE FIRE MARSHAL OR BY THE LOCAL FIRE DEPARTMENT.
8. FIRE-RESISTIVE ASSEMBLIES AND CONSTRUCTION SHALL BE MAINTAINED.
9. PLASTIC FILM (VISQUEEN) WHEN USED FOR DUST PROTECTION, SHALL BE FLAME RETARDANT.
10. SMOKE DETECTORS SHALL BE COVERED OR REMOVED DURING ALTERATIONS. WHEN
REQUIRED BY THE STATE FIRE MARSHAL OR LOCAL FIRE DEPARTMENT, HEAT DETECTORS MAY BE
SUBSTITUTED FOR SMOKE DETECTORS DURING ALTERATIONS.
11. ALL FIRE HYDRANTS, WATER SUPPLY TO FIRE HYDRANTS, AND FIRE DEPARTMENT VEHICLE
ACCESS ROADWAYS SHALL BE INSTALLED, TESTED AND PLACED IN SERVICE PRIOR TO AND
DURING THE TIME OF CONSTRUCTION. INSTALLATION MUST BE COORDINATED WITH LOCAL FIRE
DEPARTMENT IN THE FIELD.
FIRE ALARM
1. DESIGN SHALL BE AN APPROVED FIRE ALARM SYSTEM IN ACCORDANCE WITH CLASS "a" PROTECTION
OF THE INTERNATIONAL BUILDING CODE.
2. SUBMIT FOUR SETS OF PLANS TO STATE FIRE MARSHAL FOR APPROVAL PRIOR TO THE INSTALLATION.
3. SUBMITTAL SHALL INCLUDE FM LISTING NUMBER FOR ALL COMPONENTS, A SINGLE-LINE DIAGRAM SHOWING PRIMARY POWER, EMERGENCY POWER RISER DIAGRAM, DETAILS OF TROUBLE SUPERVISION &
POWER LIMITED/NON POWER LIMITED CIRCUITRY, FLOOR PLANS SHOWING LOCATION OF ALL
COMPONENTS AND METHOD OF ALARM TRANSMISSION TO STATE FIRE MARSHAL OR LOCAL FIRE
DEPARTMENT.
4. THE FIRE ALARM SYSTEM SHALL CONFORM TO IFC 2012 STANDARDS AND APPLICABLE NFPA
STANDARDS. FIRE ALARM SHOP DRAWINGS SHALL BE SUBMITTED TO STATE MARSHAL FOR APPROVAL PRIOR TO INSTALLATION. UPON COMPLETION OF THE INSTALLATION OF THE FIRE ALARM SYSTEM, A
SATISFACTORY TEST OF THE ENTIRE SYSTEM WILL BE PERFORMED IN THE PRESENCE OF THE
ENFORCING AGENCY.
FIRE EXTINGUISHERS
1. TEMPORARY- CONTRACTOR SHALL PROVIDE JOB SITE WITH TEMPORARY PORTABLE FIRE
EXTINGUISHERS AND SHALL MAINTAIN THEM DURING THE COURSE OF CONSTRUCTION. EACH
EXTINGUISHER SHALL BE 10 lb. CAPACITY, CAPABLE OF EXTINGUISHING CLASS A, B & C FIRES. ALL
EXTINGUISHERS SHALL BE U.L. LABELED AND SHALL BE DRY CHEMICAL TYPE.
FIRE SPRINKLER SYSTEM
1. FM200 SYSTEM TO BE INSTALLED IN ACCORDANCE WITH 2018 NFPA 2001.
2. ALL NEW SPRINKLER HEADS, HANGERS AND RESTRAINTS TO BE INSTALLED IN ACCORDANCE WITH 2016
NFPA 13.
3. ALL NEW PIPING FOR SPRINKLER HEADS SHALL BE HARD PIPED, NO FLEXIBLE CONNECTIONS ARE
PERMISSIBLE.
FIRE & SMOKE DAMPERS
1. EXISTING FIRE & SMOKE DAMPERS ARE TO BE RETAINED AND REUSED.
2. THE BUILDING IS EQUIPPED WITH A FIRE ALARM SYSTEM. THE OFFICE BUILDING IS EQUIPPED WITH A
FIRE SPRINKLER AND FIRE ALARM SYSTEM.
EXIT AND EMERGENCY LIGHTING
1. EXIT SIGNS SHALL CLEARLY INDICATE DIRECTION LEADING TO EXTERIOR WITH MINIMUM 6" HIGH LETTERS AT REQUIRED EXITS, EXIT DISCHARGE AND AT ALL CORRIDOR INTERSECTIONS AND CHANGES OF DIRECTION. EXIT WAY; CORRIDORS AND STAIRS SHALL BE ILLUMINATED BY A SUITABLE EMERGENCY LIGHTING SYSTEM TO OPERATE WHEN NORMAL POWER IS INTERRUPTED. EMERGENCY LIGHTING SHALL PROVIDE A MINIMUM OF 5 FOOT CANDLE POWER AT FLOOR LEVEL. EXIT DOOR SHALL SWING IN THE
DIRECTION OF EXIT OVER A LANDING NOT MORE THAN 1/2" BELOW THE THRESHOLD.
2. EXIT AND EMERGENCY LIGHTING SHALL CONFORM WITH THE LOCAL AND CURRENT NEC GUIDELINES.
RATED DOOR AND WINDOW ASSEMBLIES
2. THE ROOM BUILDING IS EQUIPPED WITH RATED DOOR ASSEMBLIES. EXISTING RATINGS ARE TO BE MAINTAINED. NEW RATED DOORS SHALL CLEARLY LABEL DOOR AND FRAME RATING, DO NOT PAINT.
FIRE STOPPING
1. FIRE STOPPING IS REQUIRED.
GENERAL
1. ANY DECORATIONS USED SHALL BE NON-COMBUSTIBLE OR FLAME-PROOFED IN AN APPROVED MANNER.
2. INSULATION APPLIED TO EXTERIOR SURFACE OF DUCTS LOCATED IN BUILDINGS SHALL HAVE A FLAME SPREAD OF NOT MORE THAN 25 AND SMOKE-DEVELOPED RATING OF NOT MORE THAN 50 WHEN TESTED AS A COMPOSITE INSTALLATION, INCLUDING INSULATION, FACING MATERIALS, TAPES AND ADHESIVES
NORMALLY APPLIED.
3. ALL INSULATION MATERIALS INSTALLED WITHIN FLOOR-CEILING ASSEMBLIES, ROOF CEILING ASSEMBLIES, WALLS SHALL HAVE A FLAME-SPREAD RATING NOT TO EXCEED 25 AND A SMOKE DENSITY
NOT TO EXCEED 50 WHEN TESTED IN ACCORDANCE WITH ASTM E 84.
4. HAND-ACTIVATED, DOOR-OPENING HARDWARE SHALL BE CENTERED BETWEEN 30" AND 44" ABOVE THE FLOOR. LATCHING AND LOCKING DOORS THAT ARE HAND-ACTIVATED AND WHICH ARE IN A PATH OF TRAVEL SHALL BE OPERABLE WITH A SINGLE EFFORT BY LEVER-TYPE HARDWARE, PANIC BARS, PUSH- PULL PASSAGE WITHOUT REQUIRING THE ABILITY TO GRASP THE OPENING HARDWARE. LOCKED EXIT DOORS SHALL OPERATE AS ABOVE IN EGRESS DIRECTION. DOOR CLOSERS (EXCEPT FIRE DOORS) SHALL HAVE SWEEP PERIOD SO THAT FROM AN OPEN POSITION OF 70 DEGREES, THE DOOR WILL TAKE AT LEAST 3 SECONDS TO MOVE TO A POINT 3" FROM THE LATCH, MEASURED FROM THE LEADING EDGE OF
THE DOOR.
5. LEVEL FLOOR OR LANDING: THIS STRUCTURE IS AN UN-OCCUPIED BUILDING AND NOT REQUIRED TO BE
ACCESSIBLE.
6. MAXIMUM EFFORT TO OPERATE DOORS SHALL NOT EXCEED:
A. INTERIOR DOORS - 5 lbs.
B. EXTERIOR DOORS - 8.5 lbs.
C. FIRE DOORS - 15 lbs.
7. ALL FLOOR, WALL, AND CEILING PENETRATIONS FOR PIPING, DUCTS, CONDUIT, ETC. SHALL BE SEALED
WITH A UL APPROVED METHOD AND MATERIAL APPROVED BY BUILDING.
1. ALTHOUGH SIGNIFICANT EFFORTS HAVE BEEN MADE TO COORDINATE DIMENSIONS, THERE MAY BE DISCREPANCIES AND/OR OMISSIONS. IF ENCOUNTERED, CONTACT THE ARCHITECT AND COR FOR ADDITIONAL INFORMATION. IF THERE IS A DIMENSIONAL VARIANCE BETWEEN DISCIPLINES OR SIGNIFICANT OMISSION OR CONFLICT WITHIN A DISCIPLINE, CONTACT ARCHITECT AND COR PRIOR TO BID. IF DISCREPANCIES ARE DISCOVERED AFTER THE BID, CONTRACTOR SHALL CONFIRM DIMENSIONS WITH
ARCHITECT AND COR PRIOR TO CONSTRUCTION OF THE AFFECTED AREA.
2. ACTUAL CONSTRUCTION CONDITIONS AND/OR MATERIAL AND EQUIPMENT SIZES MAY NOT BE THOSE ANTICIPATED BY THE DESIGNERS. THROUGH FIELD INVESTIGATION AND SHOP DRAWINGS CONTRACTOR
SHALL VERIFY DIMENSIONS AND RECOMMEND DIMENSIONAL MODIFICATIONS AS REQUIRED.
3. ARCHITECTURAL DIMENSIONS MAY BE FOUND ON FLOOR PLANS, EXPANDED PLANS, REFLECTED CEILING PLANS, SECTIONS, DETAILS, DOOR SCHEDULES, INTERIOR ELEVATIONS AND EXTERIOR ELEVATIONS.
4. ADDITIONAL DIMENSIONS MAY BE SHOWN ON STRUCTURAL, MECHANICAL AND ELECTRICAL DRAWINGS.
MECHANICAL AND ELECTRICAL EQUIPMENT SCHEDULES MAY ALSO CONTAIN DIMENSIONAL INFORMATION
RELATED TO EQUIPMENT SIZES AND CLEARANCES.
5. DESIGNATIONS ARE NOTED AS NOMINAL, NOT ACTUAL (2 X 4 STUD); DIMENSIONS ARE SHOWN AS ACTUAL, NOT NOMINAL (1 1/2" X 3 1/2" STUD). DIMENSIONS ARE NOT ROUNDED, BUT UN-ROUNDED DIMENSIONS SHOULD NOT BE VIEWED AS MAXIMUM CONSTRUCTION TOLERANCE. (FOR INSTANCE, MASONRY OPENING DIMENSIONS MAY BE SHOWN IN THE 16THS OF AN INCH, BUT STANDARD MASONRY CONSTRUCTION
TOLERANCES MAY BE +/- 1/4").
FLOOR PLAN DIMENSIONS
1. THE LOWEST FLOOR OVERALL BUILDING DIMENSIONS ARE FROM THE OUTSIDE FACE OF THE FOUNDATION WALL TO THE OPPOSITE OUTSIDE FACE OF THE FOUNDATION WALL (OR, FROM OUTSIDE GRIDLINE TO
OUTSIDE GRIDLINE) AS SHOWN.
2. DIMENSIONS FOR NON-LOAD BEARING WALLS ARE TO ONE FACE OF THE STUDS, BOTH FACES OF
MASONRY WALLS, OR BOTH FACES OF CONCRETE WALLS, ETC, UNLESS NOTED OTHERWISE.
3. WALL DIMENSIONS ARE ACTUAL, NOT NOMINAL (UNLESS NOTED AS "NOM").
4. DOOR OPENING DIMENSIONS IN FRAME CONSTRUCTION (WOOD OR STEEL STUDS) ARE TYPICALLY SHOWN AT THEIR CENTERLINES. HOWEVER, WHEN THE EDGE OF THE DOOR IS IMPORTANT, OR MAKES THE
PLACEMENT CLEARER, THE DIMENSION MAY BE TO THE ACTUAL FRAME EDGE.
5. DOOR DIMENSIONS IN LOAD-BEARING MASONRY AND CONCRETE WALLS ARE TO "ROUGH" OPENINGS (FACES OF MASONRY OR CONCRETE). TYPICAL DOOR ROUGH OPENING DIMENSIONS ARE THE FRAME WIDTH PLUS 1/2" (1/4" CLEARANCE EACH SIDE) AND PLUS 1/2" TOTAL FOR THE HEAD/SILL DIMENSIONS.
6. "TYPICAL" DOOR FRAME CLEARANCE DIMENSIONS TO ADJACENT WALLS: BETWEEN FRAME FACES AND FACES OF STUDS, OR FACES OF MASONRY OR CONCRETE, AT NEARBY PERPENDICULAR WALLS ARE TYPICALLY 4", DEPENDING ON HARDWARE CLEARANCES AND FRAME REQUIREMENTS (2.5"-DOOR HANDLE
PLUS 1" -WALL STOP PLUS 1/2" GB=4.0")
7. SOME DIMENSIONS REQUIRED TO BE CLEAR, SUCH AS AT REQUIRED EXIT WAYS, APPLIANCE COVES OR PREFABRICATED STAIR ENCLOSURES, ARE NOTED "CLR" OR "CLEAR" AND ARE SHOWN TO THE FACES OF
FINISHES.
8. DIMENSIONS DESIGNATED WITH "MIN" INDICATE THE MINIMUM CLEARANCE OR SEPARATION REQUIRED.
ROOF PLAN DIMENSIONS
1. UN-DIMENSIONED LOCATIONS OF ROOFTOP EQUIPMENT AND CONSTRUCTION OFTEN MAY BE DETERMINED BY THE FLOOR PLAN BELOW, SUCH AS ROOF HATCH DETERMINED BY REFERENCE TO A FIXED WALL AND
LADDER, OR MECHANICAL EQUIPMENT DETERMINED BY DUCT PENETRATIONS BETWEEN JOISTS.
2. UN-DIMENSIONED ITEMS SUCH AS EQUIPMENT RAILS, HVAC EQUIPMENT, SCREEN WALLS, ANTENNAS, WALK PADS, LADDERS, SCUPPER LOCATIONS, ETC., MAY BE LOCATED FROM MECHANICAL AND ELECTRICAL DRAWINGS OR LOCATED BY SCALING. CONFIRM ALL ROOF ITEM DIMENSIONS WITH THE ARCHITECT AND COR
PRIOR TO CONSTRUCTION.
VERTICAL DIMENSIONS
1. UNLESS NOTED OTHERWISE, THE FIRST FLOOR REFERENCE ELEVATION IS 100'-0". THIS IS REFERENCED TO A GROUND ELEVATION ABOVE MEAN SEA LEVEL (MSL), AS SHOWN IN CIVIL OR STRUCTURAL DRAWINGS.
ELEVATIONS BELOW 0'-0" ARE "-" (PREFIXED WITH A MINUS SIGN).
2. BUILDING, FLOOR AND ROOF HEIGHTS SHOWN ON ARCHITECTURAL DRAWINGS ARE TO TOP OF DECKING
OR SHEATHING, BUT DO NOT INCLUDE FINISHES OR ROOFING MATERIAL.
3. WALL OPENINGS: DOOR AND LOUVER HEIGHTS ARE TO FINISH HEIGHTS (UNLESS THEY ARE IN LOAD- BEARING MASONRY OR CONCRETE WALLS, WHERE THEY ARE TO ROUGH OPENINGS). HEIGHT REFERENCES
SHOULD BE TO THE NEXT LOWER FINISH FLOOR ELEVATION
4. LIGHTING HEIGHTS ON WALLS ARE TO CENTERLINES OF THE ELECTRICAL BOXES, UNO. EQUIPMENT, VENT, PLUMBING AND FIXTURE ELEVATIONS ARE TO CENTERLINES OF THE WALL PENETRATIONS, UNO.
5. SOME VERTICAL DIMENSIONS ARE SHOWN ON PLANS FOR DEPRESSIONS, RIDGES, CURBS, AND ELEVATION CHANGES. A PLAN ELEVATION CHANGE SYMBOL LOOKS LIKE A STEP OR VERTICAL "Z" AND INDICATES THE + OR - ELEVATION CHANGE IN INCHES FROM THE FINISHED FLOOR ELEVATION (FFE) NEXT TO IT.
1. STANDARDS: GENERAL PAINTING SPECIFICATIONS FOR THIS PROJECT ARE DEFINED BY THE PROJECT MANUAL AND ARE BASED ON THE MPI ARCHITECTURAL PAINTING SPECIFICATION MANUAL FOR NEW WORK AND THE MPI MAINTENANCE REPAINTING MANUAL FOR RENOVATION OR REPAINTING
WORK.
2. PAINTING WORK: INCLUDES TAPING, SURFACE PREPARATION, CLEANING, DE-RUSTING, PRIMING, FIELD PAINTING AND FINISHING AS REQUIRED BY STANDARD PRACTICE, MANUFACTURER OR
SPECIFICATION. REQUIRED COATS OF PAINT OR STAIN ARE IN ADDITION TO SHOP PRIMING, SURFACE
TREATMENT AND FINISHING. THE WORK ALSO INCLUDES PAINTING CLEANUP AND REMOVAL OF
OVERSPRAY, DRIPS AND SPLATTERS. THE SPECIFICATIONS MAY REQUIRE OTHER TYPES OF
PAINTING, INCLUDING, BUT NOT LIMITED TO, FIELD APPLIED SPECIAL COATINGS AND FACTORY
PRIMING.
3. PROJECT PAINTING SCOPE: EXCEPT AS NOTED OTHERWISE, CONTRACTOR IS TO FIELD PAINT
INTERIOR AND EXTERIOR EXPOSED ITEMS AND BUILDING SURFACES, WHETHER OR NOT
PREVIOUSLY PAINTED, AND ALL NEW ITEMS AND SURFACES. THIS INCLUDES, BUT IS NOT LIMITED TO, FACTORY-PRIMED ITEMS, GALVANIZED SHEET METAL AND EXPOSED PIPING AND FITTINGS
(INCLUDING IRON AND PVC). EXTERIOR EXPOSED MASONRY AND CONCRETE SHALL BE SEALED,
UNLESS NOTED OTHERWISE OR NOT RECOMMENDED BY MANUFACTURER. PAINTING SCOPE ITEMS
MAY BE FOUND IN FINISH SCHEDULES, DRAWINGS, SPECIFICATIONS AND PAINTING GENERAL NOTES.
THESE SOURCES ARE COMPLEMENTARY, NOT MUTUALLY EXCLUSIVE.
4. MECHANICAL AND ELECTRICAL PAINTING: INCLUDES FIELD PAINTING OF INTERIOR AND EXTERIOR
EXPOSED PIPES, DUCTS, HANGERS, EXPOSED STEEL AND IRON WORK AND PRIMED METAL
SURFACES OF EQUIPMENT IN EXPOSED AREAS INSTALLED UNDER MECHANICAL AND ELECTRICAL
WORK, EXCEPT AS OTHERWISE INDICATED. PAINTING OF ELECTRICAL AND MECHANICAL WORK IN
ELECTRICAL AND MECHANICAL ROOMS IS NOT REQUIRED UNLESS NOTED OTHERWISE IN THE
PROJECT MANUAL. COLOR-CODING OF PIPING FOR MECHANICAL AND PLUMBING WORK IS COVERED
IN THE MECHANICAL OR PLUMBING SPECIFICATIONS.
5. APPLICATION: EACH COAT OF PAINT SHALL TERMINATE AT AN EDGE, CORNER, CHANGE OF
MATERIALS OR CHANGE OF PAINT COLOR. COMPLETED PAINTING SHALL NOT IMPEDE THE INTENDED
OPERATION OF ANY ITEM, SUCH AS WINDOWS, DRAWERS, HINGES, DOORS, ETC.
6. TOUCH-UP: SURFACES REQUIRING TOUCH-UP SHALL BE REPAIRED AS REQUIRED. PAINT
TEXTURE, GLOSS AND COLOR SHALL MATCH EXISTING. IF TOTAL TOUCH-UP AREA ON ONE SURFACE IS LARGER THAN 1 SQUARE FOOT, OF IF TEXTURE, GLOSS AND COLOR CANNOT BE MATCHED, THE
ENTIRE SURFACE SHALL BE REPAINTED TO ENCLOSING EDGES OR CORNERS.
7. DO NOT PAINT: UNLESS OTHERWISE INDICATED, DO NOT PAINT ITEMS THAT ARE SPECIFIED FACTORY-FINISHED OR INSTALLER-FINISHED. ALSO, UNLESS OTHERWISE INDICATED, DO NOT PAINT SUCH ITEMS AS ACOUSTIC MATERIALS, HARDWARE, PRE-FINISHED FIXTURES AND EQUIPMENT, PRE- FINISHED MECHANICAL AND ELECTRICAL EQUIPMENT, SWITCH AND OUTLET PLATES, THERMOSTATS, LIGHTING FIXTURES, SWITCHGEAR, MOTORS, DISTRIBUTION PANELS AND INTERIOR AND EXTERIOR SIGNAGE. IF THERE IS A QUESTION WHETHER OR NOT TO PAINT AN ITEM OR SURFACE, CONTACT THE
ARCHITECT FOR INSTRUCTIONS PRIOR TO PAINTING.
8. EXPOSED FINISH METAL SURFACES: UNLESS OTHERWISE INDICATED, DO NOT PAINT METAL
SURFACES OF ANODIZED ALUMINUM, STAINLESS STEEL, NICKEL, CHROMIUM PLATE, COPPER,
BRASS, BRONZE AND SIMILAR FINISHED MATERIALS.
9. CONCEALED SURFACES: UNLESS OTHERWISE INDICATED, DO NOT PAINT SURFACES SUCH AS
WALLS AND CEILINGS IN CONCEALED AND GENERALLY INACCESSIBLE AREAS, INCLUDING FURRED
AREAS, UTILITY TUNNELS, PIPE SPACES, CHASES AND DUCT SHAFTS. WATERPROOF SEAL
CONCRETE IN PIPE SPACE.
10. OPERATING PARTS AND SENSING DEVICES: UNLESS OTHERWISE INDICATED, DO NOT PAINT MOVING PARTS OF OPERATING UNITS SUCH AS VALVES, DAMPER OPERATORS, LINKAGES, MOTOR AND FAN SHAFTS, LIGHT SENSING OR EMITTING DEVICES THAT MIGHT NOT FUNCTION PROPERLY IF
PAINTED.
11. CODE-REQUIRED LABELS: DO NOT PAINT OVER CODE-REQUIRED LABELS.
12. ALL FLOORS ARE TO BE CLEANED AND SEALED AT COMPLETION OF WORK. NO EPOXY PAINT.
1. THE PRIMARY OBJECT OF APPLYING SEALANT IS TO FACILITATE WEATHER TIGHTNESS AT THE EXTERIOR BUILDING ENVELOPE AND WATER TIGHTNESS AT INTERIOR WET\DAMP LOCATIONS. PROPER
PRIMING MUST BE USED WITH SEALANTS.
2. THE PRIMARY OBJECT OF APPLYING CAULKING IS TO ENHANCE APPEARANCE AND FINISH AT INTERIOR APPLICATIONS AND IN SOME SITUATIONS TO REDUCE AIRFLOW, SUCH AS AT DUCTS, INTERIOR SIDES OF THE EXTERIOR ENVELOPE AND AT FIREWALL/SMOKE BARRIER PENETRATIONS (FIRE CAULKING) AND TO DECREASE SOUND TRANSMISSION THROUGH WALLS AND CEILINGS. OTHER USES MAY BE NOTED IN THE SPECIFICATIONS AND/OR ON THE DRAWINGS. IF THERE ARE QUESTIONS
ABOUT WHERE OR WHAT TYPE OF SEALANT OR CAULKING SHOULD BE USED, CONTACT THE
ARCHITECT.
3. SPECIFIED SEALANT (AND BACKER RODS, AS REQUIRED) SHALL BE USED AT HORIZONTAL AND
VERTICAL CONCRETE JOINTS AND AS NOTED.
4. SPECIFIED SEALANT AND BACKER RODS, OR EXPANSION JOINT MATERIAL, AS REQUIRED, SHALL BE
USED AT MASONRY AND CONCRETE CONTROL JOINTS.
5. APPLY SEALANT TAPE OR TWO CONTINUOUS BEADS OF SEALANT BETWEEN PERIMETER SOLE
PLATES AND FOUNDATIONS, SLABS AND FLOOR DECKS. SET EXTERIOR THRESHOLDS IN SEALANT
UNLESS NOTED OTHERWISE.
6. SPECIFIED SEALANT OR CAULK SHALL BE USED ALL AROUND BOTH SIDES OF DOOR FRAMES.
7. SPECIFIED SEALANT OR CAULK SHALL BE USED ALL AROUND INTERIOR WALL MOUNTED EQUIPMENT
FRAMES AND EXPOSED SUPPORTS.
8. SPECIFIED SEALANT OR CAULK SHALL BE USED AT JOINTS BETWEEN DIFFERENT WALL MATERIALS
(TILE TO BRICK, CMU TO GYPSUM BOARD, WOOD TO STONE, METAL PANEL TO P-LAM, ETC).
9. USE SPECIFIED CAULK OR SEALANT AT WALL MATERIAL GAPS OR 1/16TH INCH OR MORE.
10. SEAL ALL AROUND ATTACHMENTS TO, AND PENETRATIONS THROUGH, FLOORS AND WALLS.
11. USE SPECIFIED SEALANT AROUND WALL, FLOOR AND CEILING PIPE PENETRATIONS. WHERE
ESCUTCHEONS ARE SPECIFIED OR PROVIDED, SET THE ESCUTCHEONS IN A BED OF SEALANT.
12. USE SPECIFIED CAULK OR SEALANT AROUND PENETRATIONS IN EXTERIOR WALLS AND SOFFITS, SUCH AS AT HOSE BIBS, FD CONNECTIONS, ELECTRIC SERVICE ENTRIES, GAS PIPE ENTRIES, ELECTRIC OUTLETS, LIGHTING, VENTS, ETC.
1 HALF-TONED OR LIGHT LINES INDICATE EXISTING CONSTRUCTION TO REMAIN. DASHED BOLD LINES INDICATE EXTENT OF DEMOLITION.
2. TEMPORARY BRACING OR SHORING MAY BE NECESSARY, AND SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
3. CONTRACTOR SHALL COORDINATE DEMOLITION ACTIVITIES TO MEET APPROVAL OF CODE AGENCIES. COORDINATE DEMOLITION WORK WITH ALL DISCIPLINES. CONTRACTOR SHALL DISPOSE OF ALL ITEMS PER SPECIFICATIONS. THE OWNER RESERVES THE RIGHT TO SELECT SPECIFIC ITEMS FOR SALVAGE. THESE ITEMS SHALL BE IDENTIFIED DURING THE PRE-CONSTRUCTION WALK THROUGH.
4. CONTRACTOR SHALL PATCH AND REPAIR ALL OPENINGS, VOIDS OR PENETRATIONS LEFT BY THE INSTALLATION OR CONSTRUCTION OF EQUIPMENT, PIPING, DUCTS, ETC. TO MAINTAIN THE INTEGRITY OF THE WALL
AND/OR ROOF.
5. THE ACCESSIBLE PARKING AREA AND PUBLIC RIGHT-OF-WAY OF THE PROJECT SITE WILL BE IMPACTED BY CONSTRUCTION ACTIVITIES. TEMPORARY BARRICADES PERTAINING TO THE CONTRACTOR'S ACTIVITIES SHALL BE INSTALLED TO PREVENT POSSIBLE INJURY IN AND AROUND DEMOLITION AND CONSTRUCTION AREAS IN ACCORDANCE WITH THE LATEST OSHA REQUIREMENTS. COORDINATE CONTRACTOR STAGING AREA WITH TEMPORARY ACCESSIBLE PARKING AND PUBLIC ACCESS WITH OWNER PRIOR TO CONSTRUCTION. PROTECT PARKING SIGNAGE WITHIN PROJECT AREA.
6. SEE SPECIFICATIONS FOR CUTTING AND PATCHING AND DEMOLITION FOR RELATED DEMOLITION WORK.
7. CONTRACTOR TO PROVIDE INFECTION CONTROL PLAN AS REQUIRED BY MEMORANDUM 111-40, SUBJ: VHA DIRECTIVE 7715 SAFETY AND HEALTH DURING CONSTRUCTION DATED APRIL 6, 2017. SUBMIT TO COR
PRIOR TO START OF WORK.
GENERAL NOTES GENERAL FIRE AND LIFE SAFETY NOTESGENERAL DIMENSIONING NOTES GENERAL PAINTING NOTES
GENERAL SEALANT / CAULKING NOTES
GENERAL DEMOLITION AND PHASING NOTES
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
B
IM
/5
-1
-1
U p g ra d e I T
C lo s e ts
/5
-1
-1
V
A -A
B Q
B ld g
M
E P
.r v t
/2
/2
:5 :3
P
M
G-010
GENERAL PROJECT NOTES
TRIPLE C The A/E Group
2266 S. Dobson Rd, Suite. 200
Mesa, AZ 85202
307-460-2054
Mat Perkins
UPGRADE IT CLOSET AREAS
1501 San Pedro Dr. SE, Albuquerque, NM 87108
501-17-110
07/02/2019 M. PERKINS F. CLARK
ISSUED FOR
CONSTRUCTION
Revisions: Date: Expires 6.30.16Expires: 6/30/1821
7/2 /19
Issue Date
01/21/2020 Expires 6.30.16Expires: 6/30/1821
1/2 1/2
Expires 6.30.16Expires: 6/30/1821
6/2 4/2
06/24/2020
/2
4/
1/2 1/2
Expires 6.30.16Expires: 6/30/1821
6/2 4/2
Expires 6.30.16Expires: 6/30/1821
7/0 8/2
07/08/2020
WEEKLY CHANGED
OR MORE AS
NEEDED PRE-FILTER
FLEX DUCT
MONTHLY CHANGED
HEPA FILTER
HEPA NEGATIVE AIR
UNIT
PROVIDE STICKY MATS (CHANGED
END OF EVERY SHIFT OR MORE IF
NECESSARY TO MAINTAIN
CLEANLINESS).
INDICATOR SHALL BE AT 0.01 OR
GREATER (VERIFY DAILY). IF NOT
VERIFY ALL OPENING SUCH AS DOOR
ARE CLOSED AND/OR CHANGE OUR
NEGATIVE AIR PRE-FILTER.
SUPPLY DUCTS EITHER
KEEP RUNNING OR
COVER WHEN
RUNNING TO KEEP
DUST OUT.
A
V
O
TAPE ALL SERVICES
TO PROTECT AGAINST
CONTAMINATION
E
FIRE EXTINGUISHER ON
PORTABLE FLOOR BRACKET
(SHALL REQUIRE MORE THAN
ONE.)
PROVIDE TEMPORARY
ENCLOSURE AT AREAS TO REMAIN
OPERATIONAL, SEE DETAIL
D7
G-011
TEMPORARY WALL
FLOOR LINE
CEILING SYSTEM
AS SCHEDULED
EXISTING
STRUCTURE
FIRE RATED PLASTIC
TO PREVENT DUST
INSTALL PRIOR TO
CONSTRUCTION
/1
F
IN
IS
H E
D F
L O
O R
T O
U N
D E
R S
ID
E
O F
S T
R U
C T
U R
E
V E
R
IF
Y F
L O
O R
T O
F L O
O R
H E
IG
H
T RENOVATED
SPRINKLER SYSTEM
INFECTION CONTROL / DUST
CONTROL PARTITION / BARRIER
INFECTION CONTROL/DUST
CONTROL EGRESS DOOR NON-
TRANSFERRING MULTI-SHEETED
ADHESIVE FLOOR PADS
CONSTRUCTION LIMIT LINE
NOT IN CONTRACT AREA
STICKY
MAT
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
B
IM
/5
-1
-1
U p g ra d e I T
C lo s e ts
/5
-1
-1
V
A -A
B Q
B ld g
M
E P
.r v t
/2
/2
:5 :3
P
M
G-011
GENERAL INFECTION CONTROL NOTES AND
SYMBOLS
TRIPLE C The A/E Group
2266 S. Dobson Rd, Suite. 200
Mesa, AZ 85202
307-460-2054
Mat Perkins
UPGRADE IT CLOSET AREAS
1501 San Pedro Dr. SE, Albuquerque, NM 87108
501-17-110
07/02/2019 M. Perkins K. Luke
ISSUED FOR
CONSTRUCTION
A. IMPLEMENT INFECTION CONTROL RISK ASSESSMENT (ICRA)
PROCEDURES AS PER THE ALBUQUERQUE VA MEDICAL CENTER
ICRA PLAN AND AS DIRECTED BY THE CONTRACTING OFFICER
REPRESENTATIVE (COR).
B. COORDINATE ALL DEMOLITION/ CONSTRUCTION DEBRIS PATH
OF TRAVEL AND INTERIM LIFE SAFETY MEASURES (ILSM) WITH
THE COR. ALL INTERIOR DOORS THAT LEAD TO THE
CONSTRUCTION SITE SHALL BE POSTED AS PER THE ISLM PLAN.
C. OBTAIN INFECTION CONTROL PERMIT PRIOR TO BEGINNING
WORK.
D. THE ONE HOUR FIRE RATED CONSTRUCTION BARRIERS SHALL
BE CONSTRUCTED PRIOR TO BEGINNING OTHER WORK.
E. CONSTRUCT ANTEROOM AT ENTRANCES TO CONSTRUCTION
AREAS AND REQUIRE ALL CONSTRUCTION PERSONNEL TO PASS
THROUGH THIS ROOM TO BE VACUUMED WITH HEPA VACUUM
CLEANER PRIOR TO LEAVING THE SITE.
F. FIRE PROTECTION SYSTEMS SHALL REMAIN FUNCTIONAL FOR
OCCUPIED AREAS ON THE FLOOR.
G. PROVIDE FIRE EXTINGUISHERS IN CONSTRUCTION AREAS;
REVIEW WITH COR AND VA SAFETY GROUP.
H. MAINTAIN EXIT LIGHTS IN CONSTRUCTION AREA.
I. MAINTAIN NEGATIVE AIR PRESSURE IN CONSTRUCTION AREA AT
ALL TIMES (24/7). WHETHER OCCUPIED OR NOT, THROUGHOUT
DURATION OF PROJECT USING HEPA EQUIPPED AIR FILTRATION
UNITS.
J. CONSTRUCTION AREA SHALL REMAIN ISOLATED FROM THE
OTHER AREAS OF THE MEDICAL CENTER; NO RETURN AIR OR
EXHAUST SHALL PASS INTO THE AREAS OUTSIDE THE
CONSTRUCTION AREA. ISOLATE HVAC SYSTEM WITHIN
CONSTRUCTION AREA TO PREVENT CONTAMINATION OF
EXISTING DUCT SYSTEM.
K. REDIRECT ALL MEDICAL CENTER PERSONNEL. PATIENTS AND
VISITORS SO THEY DO NOT EXIT THROUGH THE CONSTRUCTION
AREA. PROVIDE SIGNS ON DOORS INTO THE CONSTRUCTION
AREA THAT READS: "CONSTRUCTION AREA-DO NOT ENTER".
L. GENERAL CONTRACTOR SHALL MAINTAIN DAILY LOGS AND
KEEP A CURRENT HOT WORK PERMIT ON SITE.
M. TACKY MATS SHALL BE PLACED AT ALL DOORS INTO THE
CONSTRUCTION AREA AND SHALL BE MONITORED TO MAKE
SURE THEY REMAIN EFFECTIVE.
N. MAINTAIN A CLEAN AND ORDERLY CONSTRUCTION AREA. ALL
DEBRIS REMOVAL SHALL BE IN COVERED CARTS AND/OR
CONTAINERS.
O. SEAL ALL HOLES, PUNCTURES, AND PENETRATIONS FROM
PIPES AND CONDUITS APPROPRIATELY AND IMMEDIATELY TO
MAINTAIN DUST PROTECTION AND NEGATIVE AIR PRESSURE.
P. MAINTAIN STAFFING AND EQUIPMENT INCLUDING DUST MOPS,
WET MOPS, BROOMS, BUCKETS AND CLEAN WIPING RAGS FOR
CLEANING FINE DUST FROM FLOORS AND ADJACENT OCCUPIED
AREAS. ANY DUST TRACKED OUTSIDE OF CONSTRUCTION AREA
SHALL BE CLEANED IMMEDIATELY.
Q. AFTER COMPLETION OF WORK: VACUUM CONSTRUCTION AREA
WITH HEPA FILTERED VACUUMS, WET MOP WITH DISINFECTANT,
REMOVE CONSTRUCTION BARRIERS (UPON APPROVAL). PATCH
OR REPAIR ANY DAMAGE FROM CONSTRUCTION BARRIER
REMOVAL AND REMOVE ISOLATION OF VAC SYSTEM.
R. CONSTRUCTION BARRIERS SHALL NOT BE REMOVE UNTIL
PROJECT IS COMPLETED AND INSPECTED BY VA SAFETY
PERSONNEL, INFECTION CONTROL GROUP, AND COR.
ICRA NOTES:
ICRA SYMBOL LEGENDINFECTION CONTROL RISK
ASSESSMENT:
STEP 1: (CONTRACTOR A SHALL SUBMIT FOR EACH BUILDING )
IDENTIFY THE TYPE OF CONSTRUCTION PROJECT
ACTIVITY (TYPE A–D)
TYPE A: INSPECTION AND NONINVASIVE ACTIVITIES.
TYPE B: SMALL-SCALE, SHORT-DURATION ACTIVITIES
THAT CREATE MINIMAL DUST.
TYPE C: WORK THAT GENERATES A MODERATE TO HIGH
LEVEL OF DUST OR REQUIRES DEMOLITION OR
REMOVAL OF ANY FIXED BUILDING COMPONENTS OR
ASSEMBLIES.
TYPE D: MAJOR DEMOLITION AND CONSTRUCTION
PROJECTS.
STEP 2: (CONTRACTOR A SHALL SUBMIT FOR EACH BUILDING )
IDENTIFY THE PATIENT RISK GROUPS THAT WILL BE
AFFECTED.
IF MORE THAN ONE RISK GROUP WILL BE AFFECTED,
SELECT THE HIGHER RISK GROUP.
STEP 3: (CONTRACTOR A SHALL SUBMIT FOR EACH BUILDING )
MATCH THE PATIENT RISK GROUP (LOW, MEDIUM, HIGH,
HIGHEST) WITH THE PLANNED CONSTRUCTION
PROJECT TYPE (A, B, C, D) ON THE FOLLOWING
MATRIX, TO FIND THE CLASS OF PRECAUTIONS (I, II, III
OR IV) OR LEVEL OF INFECTION CONTROL ACTIVITIES
REQUIRED.
STEP 4: IDENTIFY THE AREAS SURROUNDING THE PROJECT
AREA, ASSESSING POTENTIAL IMPACT.
BELOW ABOVE NORTH SOUTH EAST WEST
_______________________RISK GROUP_____________________
LOW N/A N/A LOW LOW N/A
STEP 5: MECHANICAL ROOM
IDENTIFY SPECIFIC SITE OF ACTIVITY, FOR EXAMPLE, PATIENT
ROOMS, MEDICATION ROOM, AND SO ON.
STEP 6: IDENTIFY ISSUES RELATED TO: VENTILATION,
PLUMBING, AND ELECTRICAL IN TERMS OF THE OCCURRENCE
OF PROBABLE OUTAGES.
STEP 7. IDENTIFY CONTAINMENT MEASURES, USING PRIOR
ASSESSMENT. WHAT TYPES OF BARRIERS (FOR EXAMPLE,
SOLIDS WALLS)? WILL HEPA FILTRATION BE REQUIRED?
STEP 8. CONSIDER POTENTIAL RISK OF WATER DAMAGE. IS
THERE A RISK DUE TO COMPROMISING STRUCTURAL INTEGRITY
(FOR EXAMPLE, WALL, CEILING, ROOF)?
NOTE: RENOVATION/CONSTRUCTION AREA SHALL BE ISOLATED
FROM THE OCCUPIED AREAS DURING CONSTRUCTION AND
SHALL BE NEGATIVE WITH RESPECT TO SURROUNDING AREAS.
STEP 9. WORK HOURS: CAN OR WILL THE WORK BE DONE
DURING NON-PATIENT-CARE HOURS?
STEP 10. DO PLANS ALLOW FOR ADEQUATE NUMBER OF
ISOLATION/NEGATIVE AIRFLOW ROOMS?
STEP 11. DO THE PLANS ALLOW FOR THE REQUIRED NUMBER
AND TYPE OF HAND-WASHING SINKS?
STEP 12. DOES THE INFECTION PREVENTION AND CONTROL
STAFF AGREE WITH THE MINIMUM NUMBER OF SINKS FOR THIS
PROJECT? (VERIFY AGAINST FACILITY GUIDELINES INSTITUTE
(FGI) DESIGN AND CONSTRUCTION GUIDELINES FOR TYPES AND
AREA.)
STEP 13. DOES THE INFECTION PREVENTION AND CONTROL
STAFF AGREE WITH THE PLANS RELATIVE TO CLEAN AND
SOILED UTILITY ROOMS?
STEP 14. PLAN TO DISCUSS THE FOLLOWING CONTAINMENT
ISSUES WITH THE PROJECT TEAM, FOR EXAMPLE, TRAFFIC
FLOW, HOUSEKEEPING, DEBRIS REMOVAL (HOW AND WHEN).
CLASS I - PRECAUTIONS REQUIRED DURING
CONSTRUCTION:
1. EXECUTE WORK BY METHODS TO MINIMIZE RAISING DUCT.
2. IMMEDIATELY REPLACE CEILING TILE IF DISPLACED.
CLASS I - PRECAUTIONS UPON COMPLETION:
1. CLEAN WORK AREA UPON COMPLETION OF TASK.
2. REMOVE ALL VISIBLE DEBRIS WITH A WET TOWEL AND/OR
MOP.
3. ENVIRONMENTAL MANAGEMENT SERVICE TO WIPE WORK
SURFACES AND FLOORS WITH DISINFECTANT.
CLASS II - PRECAUTIONS REQUIRED DURING
CONSTRUCTION:
1. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST
FROM DISPERSING INTO ATMOSPHERE
2. WATER-MIST WORK SURFACES TO CONTROL DUST WITH
CUTTING.
3. SEAL UNUSED DOORS WITH DUCT TAPE.
4. PLACE STICKY MAT AT ENTRANCE AND EXIT OF WORK
AREA.
5. REMOVE AND ISOLATE HVAC SYSTEM IN AREAS WHERE
WORK ID BEING PERFORMED.
6. COVER CONSTRUCTION WASTE BEFORE TRANSPORT IN
COVERED CONTAINERS.
CLASS II - PRECAUTIONS UPON COMPLETION:
1. WIPE WORK SURFACES WITH CLEANER/DISINFECTANT.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN
TIGHTLY COVERED CONTAINERS
3. WET MOP AND/OR VACUUM WITH HEPA FILTER BEFORE
LEAVING WORK AREA.
4. RESTORE HVAC SYSTEM WHERE WORK WAS PERFORMED.
5. ENVIRONMENTAL MANAGEMENT SERVICE SHALL WIPE
WORK SURFACES AND FLOORS WITH DISINFECTANT.
CLASS III - PRECAUTIONS REQUIRED DURING
CONSTRUCTION:
1. REMOVE OR ISOLATE HVAC SYSTEM IN AREA WHERE WORK
IS BEING DONE TO PREVENT CONTAMINATION OF DUCT
SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,
PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK AREA
OR IMPLEMENT CONTROL CUBE METHOD (CART WITH
PLASTIC COVERING AND SEALED CONNECTION TO WORK
SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT)
BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE
UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.
4. NEGATIVE PRESSURE MONITORING DEVICES SHOULD BE
VISIBLE FROM OUTSIDE THE WORK SITE AND READINGS
SHOULD BE DOCUMENTED AT LEAST DAILY.
5. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN
TIGHTLY COVERED CONTAINERS.
6. MAINTAIN CLEAN STICKY MAT AT ENTRANCE AND EXIT OF
WORK AREA.
7. COVER CONSTRUCTION WASTE BEFORE TRANSPORT IN
COVERED CONTAINERS.
CLASS III - PRECAUTIONS UPON COMPLETION:
1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL
COMPLETED PROJECT IS INSPECTED BY THE SAFETY
DEPARTMENT AND INFECTION PREVENTION AND CONTROL
AND THOROUGHLY CLEANED BY THE ENVIRONMENTAL
MANAGEMENT SERVICE.
2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE
SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH
CONSTRUCTION.
3. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.
4. WET MOP AREA WITH CLEANER/DISINFECTANT.
5. UPON COMPLETION, RESTORE HVAC SYSTEM WHERE WORK
WAS PERFORMED.
CLASS IV - PRECAUTIONS REQUIRED DURING
CONSTRUCTION:
1. INSTALL AND MAINTAIN CONSTRUCTION CRITICAL BARRIERS
AND CEILING PROTECTION.
2. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING
DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM.
3. SEAL DOORS OPENING TO ADJACENT AREAS WITH DUCT
TAPE.
4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES.
5. BLOCK OFF AND SEAL HVAC REGISTERS, GRILLES AND ANY
OPENINGS IN DUCTWORK TO REMAIN
6. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE
UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.
7. NEGATIVE PRESSURE MONITORING DEVICES SHOULD BE
VISIBLE FROM OUTSIDE THE WORK SITE AND READINGS
SHOULD BE DOCUMENTED AT LEAST DAILY.
8. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN
TIGHTLY COVERED CONTAINERS.
9. MAINTAIN CLEAN STICKY MAT AT ENTRANCE AND EXIT OF
WORK AREA.
10. COVER CONSTRUCTION WASTE BEFORE TRANSPORT IN
COVERED CONTAINERS.
11. PROVIDE MONITORING AND CLEARANCE SAMPLES FOR
MOLD/ASBESTOS.
12. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO
PASS THROUGH THIS ROOM SO THEY CAN BE VACUUMED
USING A HEPA VACUUM CLEANER BEFORE LEAVING WORK
SITE OR THEY CAN WEAR CLOTH OR PAPER COVERALLS
THAT ARE REMOVED EACH TIME THEY LEAVE WORK SITE.
13. ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO
WEAR SHOE COVERS. SHOE COVERS MUST BE CHANGED
EACH TIME THE WORKER EXITS THE WORK AREAS.
CLASS IV - PRECAUTIONS UPON COMPLETION:
1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL
COMPLETED PROJECT IS INSPECTED BY THE SAFETY
DEPARTMENT AND INFECTION PREVENTION AND CONTROL
AND THOROUGHLY CLEANED BY THE ENVIRONMENTAL
MANAGEMENT SERVICE.
2. REMOVE BARRIER MATERIALS CAREFULLY TO MINIMIZE
SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH
CONSTRUCTION.
3. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN
TIGHTLY COVERED CONTAINERS.
4. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE
COVERING UNLESS SOLID LID.
5. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.
6. WET MOP AREA WITH CLEANER/DISINFECTANT.
7. UPON COMPLETION, RESTORE HVAC SYSTEM WHERE WORK
WAS PERFORMED.
INFECTION CONTROL RISK
ASSESSMENT:
NTS
B7
INFECTION CONTROL MEASURES, TYPICAL CONSTRUCTION LAYOUT
NTS
D7
INFECTION CONTROL MEASURES, TEMPORARY WALL SECTION
1. PROJECT SPECIFIC PLANS ARE REQUIRED FOR THIS PROJECT. CONTRACTOR
TO SUBMIT INFECTIOUS CONTROL PLAN, SAFETY PLAN AND QUALITY CONTROL
PLAN PRIOR TO CONSTRUCTION. THE CONTRACTOR SHALL MEET AND
DISCUSS EXTENT OF ABATEMENT WITH ALL PARTIES TO COORDINATE WITH
THE FACILITY INFECTION CONTROL TO CONDUCT AN INFECTION CONTROL
RISK ASSESSMENT PRIOR TO BEGINNING ANY ABATEMENT, REMOVAL, AND / OR
REPAIRS PER MCM 111-40.
2. THE CONTRACTOR SHALL WRITE THE ASBESTOS HAZARD ABATEMENT
PLAN (AHAP) AND DEVELOP A SCHEDULE FOR APPROVAL BY THE VETERANS
PROFESSIONAL INDUSTRIAL HYGIENIST (VPIH).
3. THE CONTRACTOR SHALL PERFORM NEGATIVE EXPOSURE ASSESSMENTS
(NEA) AND MONITORING PER OSHA 1926.1101(f) FOE EACH REMOVAL WORK
OPERATION IN EACH WORK AREA.
4. THE CONTRACTOR SHALL MONITOR AND SAMPLE AIRBORNE ASBESTOS LEVEL
PER OSHA 1926.1101 UTILIZING THE POINT COUNT METHOD (PCM). SITE VISITS
AND INSPECTIONS OF CONTAINMENT BARRIERS, ANTE-ROOMS, HEPA
EQUIPMENT AND CONTROL EQUIPMENT SHALL BE PER THE ASBESTOS HAZARD
ABATEMENT PLAN.
5. THE CONTRACTOR SHALL PERFORM THE ABATEMENT CLOSEOUT AND
CERTIFICATION OF COMPLIANCE AND FINAL AIR CLEARANCE TESTING WITH
VETERANS PROFESIONAL INDUSTRIAL HYGIENIST AS PER SPECIFICATION
SECTION 02 82 11.
6. THE CONTRACTOR SHALL MAINTAIN SAFETY DATA SHEETS.
7. THE CONTRACTOR SHALL STORE, TRANSPORT, REMOVE ANY MATERIAL AND
WASTE, AND CLEAN WORK AREA UPON COMPLETION OF EACH ABATEMENT.
8. THE CONTRACTOR SHALL MAINTAIN INTEGRITY OF ALL FIRE OR SMOKE
RESISTANT PENETRATIONS THAT ARE AFFECTED BY WORK WITHIN AREA.
REMOVE AND REPLACE OR REPAIR ANY UNSATISFACTORY SEALS WITHIN
AREAS OF WORK. REPORT AREAS AND UNSATISFACTORY CONDITIONS THAT
ARE NOT IN SCOPE PROMPTLY TO COR.
9. SAFETY (ILSM) PLAN IS REQUIRED. ICRA REQUIREMENTS MUST BE INCLUDED.
PROVIDE SIGNAGE SUBMITTAL PRIOR TO THE START OF WORK.
10. CONTRACTOR TO ENSURE DOOR IS LOCKED AND CLOSED WHEN NOT IN USE.
CONTRACTOR SHALL KEEP ALL DOORS SECURE IN ALL AREAS AT ALL TIMES.
11. CONTRACTOR TO VERIFY QUANTITIES AND LOCATIONS OF EXISTING
DUCTWORK, PIPING, AND EQUIPMENT THAT REQUIRES ABATEMENT PRIOR TO
COMMENCEMENT OF WORK.
12. CONTRACTOR WILL BE HELD RESPONSIBLE IF ACM IS USED ON THIS PROJECT.
ALL WORK TO REMOVE AND REPLACE ACM WILL BE AT THEIR COST IF ACM IS
USED.
13. CONTRACTOR TO PREPARE AND MAINTAIN A WASTE MANIFEST PER VA ACM
ABATEMENT REQUIREMENTS IN THE SPECIFICATIONS.
GENERAL ABATEMENT NOTES
APPLICABLE STANDARDS:
1. DEPARTMENT OF VETERANS AFFAIRS (VA) EXPERIENCE
A. ASSESSING AND IMPLEMENTING INFECTION CONTROL RISK
ASSESSMENT (ICRA)
2. OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) TRAINING
A. OSHA 30-HOUR FOR ALL EMPLOYEES
B. TITLE 29 CFR 1926.1101 - CONSTRUCTION STANDARD FOR
ASBESTOS
C. TITLE 29 CFR 1910.132 - PERSONAL PROTECTIVE EQUIPMENT
D. TITLE 29 CFR 1910.134 - RESPIRATORY PROTECTION
E. TITLE 29 CFR 1926 - CONSTRUCTION INDUSTRY STANDARDS
F. TITLE 29 CFR 1910.20 - ACCESS TO EMPLOYEE EXPOSURE AND
MEDICAL RECORDS
G. TITLE 29 CFR 1910.1200 - HAZARD COMMUNICATION
H. TITLE 29 CFR 1910.151 - MEDICAL AND FIRST AID
I. TITLE 29 CFR 1910.151 – ASBESTOS
3. ENVIRONMENTAL PROTECTION AGENCY (EPA) PERMITS, TRAINING, AND
CERTIFICATIONS
A. 40 CFR 61 SUBPART A AND M (REVISED SUBPART B) -…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .