About this file

36C25819B0015 0005 S02_ATTACHMENT 14_ Specifications _ Bldg 500 North Tower 691-19-111.pdf

View the file

Other files

File Type Posted
36C25819B0015-0005003.pdf PDF
36C25819B0015-0005004.pdf PDF
36C25819B0015-0005000.docx DOCX document
36C25819B0015-0005005.pdf PDF
36C25819B0015-0005001.pdf PDF
36C25819B0015-0004000.docx DOCX document
36C25819B0015-0003008.pdf PDF
36C25819B0015-0003007.pdf PDF
36C25819B0015-0003006.docx DOCX document
36C25819B0015-0002000.docx DOCX document
36C25819B0015-0001000.docx DOCX document
36C25819B0015-012.pdf PDF
36C25819B0015-005.pdf PDF
36C25819B0015-003.pdf PDF
36C25819B0015-001.docx DOCX document
36C25819B0015-004.pdf PDF
36C25819B0015-010.pdf PDF
36C25819B0015-006.pdf PDF
36C25819B0015-011.pdf PDF
36C25819B0015-008.pdf PDF
36C25819B0015-009.pdf PDF
36C25819B0015-002.pdf PDF
36C25819B0015-007.pdf PDF
36C25819B0015-000.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 14

SPECIFICATIONS

01 00 00 General Requirements

01 91 00 General Commissioning

Requirements 01 33 23 Shop Drawings, Product Data and Samples 02 41 00 Demolition

01 35 26 Safety Requirements

02 82 13.19 Asbestos Floor Tile and Mastic Abatement

01 45 00 Quality Control 02 82 13-13 Glovebag Asbestos Abatement 01 45 29 Testing Lab Services 07 81 00 Applied Fireproofing

01 57 19 Temporary Environmental Controls

07 84 00 Firestopping

01 81 13 Sustainable Construction Requirements

07 92 00 Joint Sealants

691-19-111

Part 1 of 1

277 pages

6 Aug 2019

Greater Los Angeles, California VA Health Care System (691)

North Tower Building 500

CONSTRUCTION

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS ......................................................................................................................................... iii

1.2 GENERAL INTENTION .............................................................................................................................................. iii

1.3 STATEMENT OF BID ITEM(S) ............................................................................................................................. v

1.5 CONSTRUCTION SECURITY REQUIREMENTS ............................................................................................................ v

1.6 OPERATIONS AND STORAGE AREAS ...................................................................................................................... vii

1.8 DISPOSAL AND RETENTION ..................................................................................................................................... xi

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS............. xii

1.14 AS-BUILT DRAWINGS .......................................................................................................................................... xiii

1.15 USE OF ROADWAYS ............................................................................................................................................ xiv

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT ................................................................... xiv

1.21 AVAILABILITY AND USE OF UTILITY SERVICES ...................................................................................................... xv

1.23 TESTS .................................................................................................................................................................... xv

1.24 INSTRUCTIONS .................................................................................................................................................... xvi

1.29 SAFETY SIGN ...................................................................................................................................................... xvii

1.32 HISTORIC PRESERVATION ................................................................................................................................. xviii

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. This requirement is for construction services for project 691-19-111, Reconstruction B500

Medical Services North Tower Pod-C, is an emergency that addresses demolition with abatement, and restoration of destroyed patient care areas in Main Hospital, adjacent to Chase-

15 from Sixth to Pipe-Basement floor. This is an urgent need since patients’ medical services on each floor have been interrupted and/or dispersed, postponed or referred to external service.

Restoration and Removal of hazardous waste clean-up must be completed at earliest time possible to eliminate subsequent contamination. Cleanup, demolition, abatement and removal shall strip floors bare and limited to areas identified by VA’s Industrial Hygienist (IH) & COR such as: Painted Wall system (Metal framed partitions, drywall, electrical, communication), T-bar ceiling system, lighting, doors, flooring, nurses station, bathroom & utility room, HVAC registers, duct & pipe’s insulations, pipes inside Chase-15 with isolation valves at each floor (Storm drain, sewer lines, cold & hot water lines, hot return line, natural Gas, medical air & vacuum lines) lockers, cabinets, furniture and, fixtures. The reconstruction shall replace & include all removed systems and elements for fully functional code compliant environment, equal or better prior the contamination.

B. Remove all contaminated materials within area from splashed and propagated sewage through

I-Beams, columns, pipes and internal metal frames walls prior construction starts. Industrial

Hygienist pointed out all areas contaminated that must be demolish stripped to expose concrete slab floor decks, affected structural steel to be striped of Monokote insulation, Hot water lines insulation, HVAC duct insulation and pipe lines inside chase 15. Decontamination, demolition, removal and disposition of waste shall be documented and meet all local City and County, State, DOT and Federal regulations.

C. Reconstruction shall rebuild all removed Wall system, ceiling system, lighting, doors, flooring, nurses station, bathroom & utility room, HVAC registers & duct insulations, pipes inside Chase-

15 with isolation valves at each floor (Storm drain, sewer lines {Chemical resistant drain on ABS lines}, {cold & hot water lines copper Type-L, hot return line}, natural Gas with black pipe, {medical air & vacuum lines copper Type-K}) lockers, cabinets, furniture, plumbing fixtures, and painting. All devices and components must be tested and in place ready to use such as:

communication ports, fire alarm components, including metal structure’s fire proofing insulation, HVAC insulation and pipe stacks inside chase 15 must meet fire penetration codes and regulations. Rebuild nurse station with solid surface counter top and with storage lockable under-counter pull out drawer cabinets with built in letter size hanging rack. Provide and install patient’s lockers to replace existing Quad-metal units 12” W x 72” H x24” D per division. Provide and install two complete dental exam suite units to include Exam-chair with delivery system & instrumentation, Track mounted exam lights, Doctor’s and Assistant’s stool, assistant’s instrument’s cart. Provide and install wall to wall, Base & Wall powder coated metal Cabinets on

East wall and on West wall. four walls base and wall cabinets in laboratory room. Visits to the site by Bidders may be made only by appointment with the Medical Center CO.

D. VA Engineering Office will render certain technical services during construction. Such services shall be considered as advisory and shall not be construed as expressing or implying a contractual act by the Government without affirmations by Contracting Officer or his duly authorized representative.

E. All testing shall be by certified testing laboratories subcontracted by the Contract. The

Government shall not be required to contract testing for any trade.

F. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

G. Comprehensive 3rd party inspections, testing and written reports for all Divisions (paid by the General Contractor). Contractor shall employ third party inspection consultants to perform all inspections required by this contract. The VA has no inspection capability. Any reference to VA inspections shall be by a third-party inspector qualified to perform the work.

Credentials shall be supplied to the VA/AE as required by this contract. All inspections, testing, certifications, and permits are to be paid for by the General Contractor. An air quality permit is required for the generator. The VA will not pay for or perform any required inspections. VA inspections are for VA use only, when performed, and do not reduce the inspection burden on the Contractor. Third party inspection services must be submitted for acceptance by the VA after award. Submission to include resumes of inspectors, with alternates, projected days on site, qualifications of inspector’s, Minimum inspections required for Utilities (sewer, water, gas, electric, etc.) and Safety (All contractors must provide proof of OSHA and infection control training).

H. Contractor to provide Submittal for approval by Engineering or appointed VA representative, or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract. Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.

I. Contractor to provide Infection Control Plan as required by Memorandum 111-40, Subj: VHA

Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.

J. Pricing Proposal transparency requirements: this project requires pricing proposals to include breakdown pricing for the General Contractor and all subcontractors. All price proposals, including subcontractor pricing must include a breakdown of pricing per the format included with this specification. Third party inspections must be included as a line item in the price proposal. See example at the end of GENERAL REQUIREMENTS section.

A.3 STATEMENT OF BID ITEM

Contractor shall furnish Construction service for “Reconstruction B500 Medical Services North

Tower Pod-C”, that addresses demolition with abatement, and restoration of destroyed patient care areas in Main Hospital, adjacent to Chase-15 from Sixth to Pipe-Basement floor. This is an urgent need since patients’ medical services on each floor have been interrupted and/or dispersed, postponed or referred to external service. Restoration and Removal of hazardous waste clean-up must be completed at earliest time possible to eliminate subsequent contamination. Contractor is renovating fifth and second floor under separate contract, but would need pipe portion to complete the work to replace other piping inside chase 15.The general contractor shall provide all labor, materials, expertise, equipment and containment capabilities to address removal and replacement main riser number 15 on North Side in building

500. Additionally, prime contractor shall provide all necessary due diligence work including phasing the replacement of the sections of sewer lines per original drawings to accomplish

Repair Replacement of Riser 15 Sewer Drain in main hospital. GENERAL CONTRACTOR TO

PROVIDE TEMPORARY SEWER BYPASS PLAN AND VENTILATION DURING REPLACEMENT

PROCESS. CONTRACTOR TO PROVIDE PROPOSED SOLUTION PRIOR TO THE START OF WORK.

CONTRACTOR SHALL PRESENT AN ACCEPTABLE, SCHEDULE AND PHASED SOLUTION PRIOR TO

THE START OF WORK. PROJECT IS LOCATED AT GREATER LOS ANGELES HEALTHCARE SYSTEM

(GLAHS), 11301 WILSHIRE BLVD., LOS ANGELES, CA 90073.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted.

Additional copies can be reproduced by Contractor.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the

Contracting Officer so that security arrangements can be provided for the employees.

This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the

Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency. The

General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law

Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the

Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

3. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems

(except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

G. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

H. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

I. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; it is anticipated that no more than an 8 hour loss of chilled water should occur with this project. Contractor’s proposed schedule shall reflect this limitation. This project shall be scheduled with night and weekend work for all utility interruptions and

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of

COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical

Center Director’s prior knowledge and written approval. Refer to specification Sections

26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS

FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical

Center. Interruption time approved by Medical Center may occur at other than

Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of

COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the

Government and not the Contractor.

J. Abandoned Lines: All service lines such as pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

K. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

L. Coordinate the work for this contract with other construction operations as directed by COR.

This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

A. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and

"CHANGES" (FAR 52.243-4 and VAAR 852.236-88).

B. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by

Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.

Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.

Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)

disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS"

(FAR 52.236-2).

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the

Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with

NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations.

Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the

Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

1.23 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building.

Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.24 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished.

Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site.

These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the

VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.29 SAFETY SIGN

A. Provide a Safety Sign where directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.

B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.

C. Maintain sign and remove it when directed by COR.

D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign shown on the drawings.

E. Post the number of accident free days on a daily basis.

1.32 HISTORIC PRESERVATION

Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.

Price Proposal format:

Proje c t

Loc a tion

Owne r:

Proj. # :

0 0 0 1

Ba sic Ba se

DIV IS ION SUBCONTRACTOR LABOR EQUIPMENT TOTAL

DIV 1

DIV 2

DIV 3

DIV 4

DIV 5

DIV 6

DIV 7

Bid Da te :

Contra c tua l Proje c te d

Dura tion:

ITEM DESCRIPTION SUBCONTRACT MATERIAL OTHER

0 10 0 0 Ge ne ra l c onditions

Site Ma na ge me nt

Mobiliza itonl| /De mobliza tion

Te sting (Conc , Soils)

Te mpora ry Fe nc ing

Te mpora ry Powe r

Dumpste rs

Job c le a nup (Distribute d)

Fina l Cle a nup ($ /SF)

Surve ying

Re nta l Equipme nt

Sa fe tyl| /Se c urityl| / ICRAl| / ILSM

Ba rric a de s - Sa fe ty Se c ure of S ite

Ma te ria l Use Ta x (%)

NMGRT

0 2 0 0 0 Existing Conditions

Site De molition

Building De molition

0 3 0 0 0 Conc re te

Conc re te forming

0 4 0 0 0 Ma sonry

EIFS

0 5 0 0 0 Me ta ls

Struc tura l S te e l - Ma te ria l Night a nd We e ke nd

Ca nopy R a nd R

0 6 0 0 0 Wood, P la stic s, a nd Composite s

Rough Ca rpe ntry - Bloc king

Finish Ca rpe ntry

Millworkl| /Ca se work

0 7 0 0 0 The rma l a nd Moisture Prote c tion

Roof

Wa ll Sc re e n

Owne r:

Proj. # :

Ba sic Ba se

DIV IS ION SUBCONTRACTOR LABOR EQUIPMENT TOTAL

DIV 8

DIV 9

DIV 10

DIV 12

DIV 2 1

DIV 2 2

DIV 2 3

DIV 2 6

DIV 2 7

Bid Da te :

Contra c tua l Proje c te d

Dura tion:

ITEM DESCRIPTION SUBCONTRACT MATERIAL OTHER

0 8 0 0 0 Ope nings

Doors

Gla ssl| /S tore fronts

Coiling Grille

0 9 0 0 0 Finishe s

Me ta l stud frmgl| /Drywa ll

Ac oustic a l c e ilings

Pa inting

10 0 0 0 Spe c ia ltie s

Column Cove rs

Corne rgua rds

Wa ll Prote c tionl| /Cove ring

Re loc a te Mirror

12 0 0 0 Furnishings

Blinds

Entra nc e ma ts

2 10 0 0 Fire Suppre ssion

Fire Sprinkle r Syste m

2 2 0 0 0 Plumbing

Plumbing

Ga s piping Inc lude d a bvoe

2 3 0 0 0 HVAC

HVAC

Controls

2 6 0 0 0 Ele c tric a l

Ele c tric a l

2 7 0 0 0 Communic a tions

Phone a nd Da ta Syste m

- - - E N D - - -

Owne r:

Proj. # :

Ba sic Ba se

DIV IS ION SUBKTR LABOR EQUIPMENT TOTAL

DIV 2 8

DIV 3 1

Ba se Va lue Subtota l

Va lue Ove rhe a d

Subtota l

Profit

Subtota l

Bond

Tota l

Bid Da te :

Contra c tua l Proje c te d

Dura tion:

ITEM DESCRIPTION SUBCONTRACT MATERIAL OTHER

2 8 0 0 0 Ele c tronic Sa fe ty a nd Se c urity

Fire Ala rm (in div 2 6 )

3 10 0 0 Ea rthwork

Finishe s

Ma rgina l

Va lue Pre mium

SECTION 01 33 23

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

PART 1 – GENERAL

1.1 DESCRIPTION

A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.

B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.

C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.

Non-compliant material incorporated in the work will be removed and replaced at the Contractor’s expense.

1.2 DEFINITIONS

A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.

B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.

C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.

D. Samples: Physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed to establish standards by which the ensuing work can be judged.

E. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.

F. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

G. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.

H. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.

I. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.

J. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.

K. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.

1.3 SUBMITTAL REGISTER

A. The submittal register will list items of equipment and materials for which submittals are required by the specifications. This list may not be all inclusive and additional submittals may be required by the specifications. The Contractor is not relieved from supplying submittals required by the contract documents but which have been omitted from the submittal register.

B. The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.

C. The VA will provide the initial submittal register in electronic format. Thereafter, the Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the

VA.

D. The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by Contracting Officer.

E. The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.

1.4 SUBMITTAL SCHEDULING

A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.

B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.

C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.

D. All submittals are required to be approved prior to the start of the specified work activity.

1.5 SUBMITTAL PREPARATION

A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.

C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.

D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned with review.

E. Provide a transmittal form for each submittal with the following information:

1. Project title, location and number.

2. Construction contract number.

3. Date of the drawings and revisions.

4. Name, address, and telephone number of subcontractor, supplier, manufacturer, and any other subcontractor associated with the submittal.

5. List paragraph number of the specification section and sheet number of the contract drawings by which the submittal is required.

6. When a resubmission, add alphabetic suffix on submittal description.

For example, submittal 18 would become 18A, to indicate resubmission.

7. Product identification and location in project.

F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified.