Consolidated RFI for 26R0024.docx

DOCX document 30 KB Posted

Attached to
Z2NB--674-23-255 NRM Improve RO-DI Recirculation
Solicitation number
36C25726R0024
Issued by

About this file

This is a Consolidated Request for Information (RFI) containing 46 questions and answers regarding Project 674-23-255, an Improve RO-DI (Reverse Osmosis Deionization) Recirculation project at a Department of Veterans Affairs facility. The RFI clarifies technical, scheduling, contractual, and operational requirements for bidders.

Key project requirements include: all work must be performed during weekend and night hours (Friday 5:00 PM through Sunday 8:00 AM) with possible exceptions requiring Contracting Officer/Contracting Officer's Representative approval; temporary construction barriers must meet Class IV requirements per specifications and VA Infection Control and Risk Assessment (ICRA) Level 4 standards; each containment area requires negative air pressure with respect to non-work areas, with VA infection control determining exhaust routing; new finished flooring must match existing flooring in areas where flooring is demolished; the carbon fiber reinforcement basis of design has a dry thickness less than 0.5mm with negligible height differences; UV system specifications include 40 mJ/cm² at 7 GPM for loop 1 and 30 mJ/cm² at 146 GPM for loop 2, with duplex redundancy for loop 2 and simplex for loop 1; and independent testing demonstrating compliance with AAMI TIR34 water quality standards is required. The contractor is responsible for providing and paying for carbon fiber manufacturer inspection, commissioning agent services, testing and laboratory services, temporary office/trailer space, and all materials and labor associated with premium time, facility access coordination, and security requirements. Warranty requirements specify one-year labor and construction coverage commencing at government acceptance, with equipment and materials covered under manufacturer's warranty for three years. The contract is firm-fixed-price with no Economic Price Adjustment clause; the 180-day period of performance will not be extended; Texas sales tax exemption applies to materials incorporated into VA real property; and payment for materials is issued only after installation. Contractor badging will not require PIV access, and all submittals and project communications must be submitted via email as the VA blocks third-party platforms like Procore.

View the file

Other files

File Type Posted
36C25726R0024 0004.docx DOCX document
36C25726R0024 0003.docx DOCX document
36C25726R0024 0002.docx DOCX document
36C25726R0024 0001.docx DOCX document
Site visit sign in sheet_02252026.pdf PDF
Attachment 5 Price Breakout.xlsx XLSX spreadsheet
36C25726R0024_1.docx DOCX document
Attachment 4 PCRA.pdf PDF
Attachment 1 Specifications.pdf PDF
Attachment 2 Drawings.pdf PDF
Attachment 6 Site Visit map.pdf PDF
Attachment 3 ICRA.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Consolidated Request for Information (RFI) for 674-23-255 M Improve RO-DI Recirculation

1Q.DO all of the temporary construction barriers have to be hard walls?
1A.Temporary construction barriers shall meet the requirements of Class IV as per Section 01 00 00, 01 00 01 and the VA ICRA form.
2Q.Will each phase have a place to install air scrubbers to achieve negative air pressure?
2A.Each containment area requires negative pressure with respect to the non-work area. VA infection control to advise if negative air must be routed to outside or can be exhausted into non-work area through HEPA filter
3Q.If there is no place to tie into for negative pressure, what will be acceptable for scrubbing the air?
3A.Each containment area requires negative pressure with respect to the non-work area. VA infection control to advise if negative air must be routed to outside or can be exhausted into non-work area through HEPA filter
4Q.If work is not complete before 8:00am Sunday, will the temporary construction barriers have to be removed and then reinstalled for work to finish on a different weekend?
4A.No, barriers are to remain in place for the duration of the period of work in the space.
5Q.Sheet AD112 shows to demo flooring as required and this appears to be a breakroom.
5QA.A. The floor plan sheets do not show any new flooring. If new flooring is required once the reinforcing is installed, this will change the height of on the slab in between the new and existing flooring. What will be the extent of flooring demo and new flooring installation?
5AA.In areas of demolished flooring, new finished flooring is to be installed to match existing. The basis of design for the high strength unidirectional carbon fiber fabric reinforcement has a dry thickness of less than 0.5mm so height difference of existing and new flooring will be negligible.
5QB.B. If new flooring is required, can the VA provide the product information and square footage?
5AB.VA can provide product information of existing flooring.
5QCC. Will the reinforcing product be capable per the manufacturer to receive flooring installation on top of it and what are those requirements?
5AC.The basis of design for the high strength unidirectional carbon fiber fabric reinforcement has a dry thickness of less than 0.5mm so height difference of existing and new flooring will be negligible.
6Q.The drawings call out to tie into the BAS but do not show where existing or new connections are located. Can the VA provide this information?
6A.Intent is for BACnet connection to RO/DI system controls for monitoring in BAS. There are existing BAS control panels in mech room 1C28
7Q.Sheet EP111 does not show where the existing fire alarm box is needed to relocate. Does the contractor need to find an acceptable place close to the air compressor or will the VA provide the new location?
7A.The contractor will need to coordinate with the manufacturer to find an acceptable location.
8Q.Sheet E-001 has general notes for lighting but there are no lighting plans and the reflected ceiling plans do not show any lighting as well. Is there any existing or new lighting changes required for this project?
8A.The lights are standard on sheet E-001. There are not lights in the project.
9Q.Sheet P-001 calls out to provide temporary heat detection and refers to the specs for requirements but there is no specific information on heat detection requirements. Can the VA provide what is expected?
9A.VA to provide site specs for temporary FA
10Q.Can the VA provide a list of each scope that requires shop drawings?
10A.New plumbing piping and equipment at a minimum require shop drawings coordinated with other trades in the layout area.
11Q.Once the new connections are made to each piece of equipment listed on PQ601, will it be required for the contractor to have each piece of equipment re-certified or will the VA do that? Will this also apply to the air compressors that relocate?
11A.Install and certify lab compressor system as a category 3 system per NFPA 99. VA to advise on SPS equipment.
12Q.Confirm required UV dosage (mJ/cm²) at design flow.
12A.Basis of design 40 mJ/cm2 at 7GPM for loop 1, 30 mJ/cm2 at 146 gpm for loop 2
13Q.Confirm whether UV units shall be duty/standby redundant.
13A.Basis of design is duplex for loop 2, simplex for loop 1
14Q.Confirm whether UV shall be provided integral to skid or field-installed.
14A.Basis of design is integral to skid
15Q.Confirm required alarm points to BAS (lamp failure, intensity monitor, high temp, etc.)
15A.Ref PI601 for minimum monitored points mapped to BAS
16Q.Confirm validation requirements for compliance with AAMI TIR34.
16A.Provide independent testing of completed system output water quality and submit report demonstrating compliance with AAMI TIR34 for critical SPD water, specifications, and VA plumbing design manual

17Q. Reference: Structural Sheet S-601 (Required Third Party Special Inspections Schedule); Structural Sheet S-001 (General Notes); 2021 IBC Chapter 17.

Structural sheets reference 'Required Third Party Special Inspections and Tests' per 2021 IBC Chapter 17. Please confirm whether the Owner or the Contractor is responsible for retaining and paying for all special inspections and testing agencies required under Chapter 17, including but not limited to concrete, reinforcing, anchors (cast-in and post-installed), welding, bolting, and soils inspections.

17A. JH recommends that the owner retain and pay for third party inspection services. VEG to confirm.

18Q. Reference: Structural Sheet S-001 (Carbon Fiber Polymer Reinforcement Notes).

Structural notes for carbon fiber polymer reinforcement state that the manufacturer’s representative shall inspect the work before, during, and after installation. Please confirm whether this inspection is to be provided and paid for by the Contractor, and whether documentation from the manufacturer’s representative is required for project closeout.

18A. The contractor shall provide and pay for the carbon fiber inspection services.

19Q. Reference: Sheet GI112 (Phasing Plan); Sheet GI111 (Equipment Removal Path); ICRA (Attachment 3); PCRA (Attachment 4).

Phasing plan sheet GI112 indicates that all work shall be performed over weekends and nights (Friday after 5:00 PM through Sunday before 8:00 AM). Please confirm:

19QA.a. 1) whether this requirement applies to all trades and all phases of construction, including structural, plumbing, electrical, demolition, and equipment installation activities; and
19AA.Applies to all trades within each containment area with those hours restrictions. Containment areas shown are for general starting reference and shall be adjusted as required to accomplish scope above ceiling or within occupied areas.
19QB.b.2) Confirm whether any exceptions to this schedule will be permitted.
19AB.Dependent on work area, exceptions could be made with CO/COR approval.

20Q. Reference: ICRA (Attachment 3); PCRA (Attachment 4); Sheet GI112 (Phasing Plan).

The ICRA and PCRA requirements reference infection control containment measures and construction barriers. Please confirm whether the Contractor is responsible for third-party air monitoring, environmental testing, negative air verification, and final infection control clearance, or whether these services will be provided by the VA.

20A. Refer also to specification section 01 35 16. Continuous negative air monitoring with alarmed digital display is required at minimum.

21Q. Reference: Plumbing Sheet PQ601 (Equipment & Fixture Schedules); General Notes Sheet GI002 (Discrepancy Clause – Specifications Govern).

The drawings include a plumbing equipment schedule identifying system components. Please confirm that in the event of any discrepancy between the equipment schedule shown on the drawings and the performance or material requirements described in the specifications, the specifications shall govern.

21A. For bidding purposes, the more restrictive requirement shall govern. Obtain clarification on individual discrepancies from VA before proceeding with work.

22Q. Reference: Sheet GI112 (Phasing Plan); Solicitation Section 01 11 00 (Summary of Work – if applicable).

Given the indicated requirement for weekend and night work, please confirm whether any premium time, facility access coordination, security requirements, badging, escort requirements, or temporary utility shutdown coordination should be included in the Contractor’s base bid.

22A. Yes, all should be included in base bid.

23Q. The Solicitation requires a minimum three (3) year warranty from both the manufacturer and installer including parts and labor, including normal, premium, and holiday hours, beginning at Substantial Completion (Ref: Solicitation Page 10, Section J – Warranty).

However, Specification Section 01 00 00 requires a standard one (1) year warranty of construction (Ref: Spec 01 00 00, 1.15 Warranty). Additionally, the specifications state the construction warranty period begins on the date of project acceptance (Ref: Spec 01 00 00).

To ensure all bidders are pricing the same requirement, please clarify:

23A (a-d).

a. What is the required warranty duration for:

i. General construction work? 1 year
ii. Mechanical piping and installation? 1 year
iii. RO skid, DI skid, UV system, pumps, controls and instrumentation?
33Manufacture’s Warranty
iv. Commissioned systems? Manufacture’s Warranty

Does the three (3) year warranty apply to:

i. Both parts and labor for the full duration? Parts
ii. Both manufacturer and installer responsibility for the full duration?
Manufacturer’s warranty
iii. Premium and holiday labor rates for the full duration? No

b. What is the official commencement date of the warranty period:

i. Substantial Completion? No
ii. Government Acceptance? Yes
iii. Completion of commissioning? No

d. If the one (1) year construction warranty differs from equipment warranties, please clearly define:

i. What is covered for one (1) year? Labor and construction
ii. What is covered for three (3) years? Equipment and materials
24Q.Given the extent of work that needs to be accomplished and the limited amount of time contractors will be allowed to work through much of the phasing, will the VA extend the period of performance beyond 180 days?
24A.No.

25Q. Tax Exemption Is this project exempt from sales tax? If so, will the VA provide a tax exemption certificate for material purchases?

25A.Yes all government projects are tax exempt, see below:
A.7 V.T.C.A. Tax Code §151.311

Offerors are hereby notified that in accordance with V.T.C.A., Tax Code §151.311, the purchase of tangible personal property for use in the performance of a contract for an organization exempted under Section 151.309 or 151.310 of this code is exempt if the tangible personal property is incorporated into realty in the performance of the contract. Additionally, the purchase of tangible personal property, other than machinery or equipment and its accessories and repair and replacement parts, for use in the performance of a contract for an improvement to realty for an organization exempted under Section 151.309 or 151.310 of the code is exempt if the tangible personal property is necessary and essential for the performance of the contract and completely consumed on the job. The VA is an exempt organization.

Therefore, the contractor’s purchase of such building and construction materials within the State of Texas to be incorporated into the real property belonging to the U.S. Department of Veterans Affairs (VA) or completely used in the performance of the contract is subject to exemption from Texas Sales and Use taxes under the code. To take advantage of the tax exemption the successful offeror under this solicitation must complete a Texas Sales and Use Tax Exemption Certificate when it purchases construction materials for this contract.

Notwithstanding FAR 52.229-3, all bids received in response to this solicitation are presumed to reflect this tax exemption, and therefore should not include Texas’ Sales or Use Taxes on sales of materials for incorporation into VA real estate under this contract or used in the performance of this contract.

26Q. Submittal Platform Will the VA permit the use of Procore or an equivalent construction management software platform for submittals and project communications?

26A. The contracting office cannot use Procore or any third party platforms they are blocked on our side by the VA, therefore contracting must receive minutes, to meetings and submittals, via email.

27Q. Stored Material Payment Will payment applications be accepted for materials stored on-site or in a bonded off-site warehouse?

27A. Payment is issued after installation of materials.

28A. Economic Price Adjustment Clause Will the Government consider including an Economic Price Adjustment (EPA) clause to address significant fluctuations in material pricing?

28A. No the clause will not be added.

29Q. Tariff-Based Price Escalation If tariffs are imposed on materials (e.g., steel, wood) after bid submission but before award, will the Government allow a price escalation even if the materials remain Buy American–compliant?

29A. This will be a firm-fixed price contract.

30Q. Contractor Badging / PIV Process Will the Government provide detailed requirements for contractor badging? Please clarify the PIV process, including documentation, background checks, and estimated processing time.

30A. Contractor will not require PIV access for this project.

31Q. Notice to Proceed (NTP) How soon after contract award does the Government anticipate issuing the official Notice to Proceed?

31A. Undeterminable due to many factors, however we like to proceed and get the project started as soon as possible.

32Q. Bid Validity Duration Will the Government consider reducing the required bid validity period (e.g., to 60 days) to account for inflation and contractor pricing risk?

32A. No.

33Q. Project Duration Can the Government confirm the stated contract duration is accurate, considering phased access and execution requirements?

33A. Confirmed.

34Q. CPARS and PPQs Can we use CPARS instead of PPQs?

34A.Please see the Instructions, to Offerors Proposal Preparation Instructions/
Evaluation factors for award line 2 Evaluation Factors, b Past Performance.

35Q. Previous PPQs If PPQs are required, can we use previously completed PPQs (from prior submissions or projects)?

35A. PPQ’s are not required.

36Q. SSHO, QCM, and Superintendent Roles (Triple Hatting) A. May one individual serve in dual or multiple roles (SSHO, QCM, Superintendent) if fully qualified?

36AA. Yes B. If not, may the Superintendent also serve as SSHO?

36BA. N/A

37Q. Alternate Coverage for SSHO/QCM Will the VA accept a designated alternate SSHO or QCM during off-hours/night shifts to satisfy continuous presence requirements?

37A. Yes

38Q. Temporary Facilities and Utilities A, Will the contractor be required to provide a site office/trailer, or will space within the facility be made available?

38AA. Contractor is to provide their own office/trailer space located inside the project laydown area.

B. Will the VA allow temporary connection to existing utility infrastructure, with the contractor responsible for metered usage?

38BA. Contractor can use temporary connections for job trailer.

39Q. Parking and Staging Will designated parking and staging areas be provided for contractor personnel and deliveries? Will the VA provide laydown space or containers, or must these be arranged off-site?

39A. The VA will provide laydown area.

40Q. Commissioning Agent Will the VA provide and hire the commissioning agent, or is the contractor responsible?

40A. Contractor is responsible

41Q. Testing and Laboratory Services Will the VA or the General Contractor be responsible for procuring and paying for testing and laboratory services?

41A. Contractor is responsible

42Q. Infection Control Measures (ICRA) What ICRA level is required for the project?

42A. ICRA level 4

43Q. Hazardous Materials A. Will the VA provide recent asbestos and lead survey reports?

43AA. VA will provide

B. If abatement is required, will the VA identify known ACM/LCM locations?

43BA. If abatement is required, VA will provide.

44Q. Fire Alarm and Security Coordination Does the VA have an existing fire alarm/security service provider? If so, please provide contact information for required coordination.

44A. VA will provide

45Q. Building Occupancy Will the facility remain occupied during construction, or will temporary relocation of staff/equipment be required?

45A. Facility will remain occupied.

46Q. Demolition & Phased Work Will demolition of major systems (e.g., AHUs, utilities) require after-hours or phased work to minimize disruption?

48A. Yes