About this file
This document is an Amendment of Solicitation for the Department of Veterans Affairs (VA) Network Contracting Office 17, specifically for access control system installation at Waco Building 8. The solicitation seeks a contractor to install an access control system with 8 doors, integrating with the existing CCURE 9000 system and using PIV Class 200 Bit readers. Key technical requirements include using an IStar Ultra g2 controller, installing electric strikes, running network drops to an adjacent OIT closet, and following standard VA cybersecurity protocols.
The amendment provides detailed responses to 29 contractor questions covering system specifications, installation details, work hours, and project logistics. Notable details include a 60-day performance period, work to be completed from 8am to 3:30pm Monday-Friday, contractor-supplied hardware, VA-provided escort access, digital or print O&M manual acceptance, and a 1-year warranty after system acceptance. The Service Contract Labor Standards will cover the contract, and a site visit was conducted on November 24, 2025. The VA will provide floor plans, door schedules, and other supporting documentation to the selected contractor.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Waco Bldg 8 Site Visit Sign In.pdf | ||
| 674A4-25-001 - Renovate Waiting Space Basement bldg 8.pdf | ||
| 36C25726Q0121.pdf | ||
| 36C25726Q0121_1.pdf | ||
| P07 WD 2015-5261 Rev 27 dated 7-8-2025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODECODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 5
0001 12-02-2025 674-26-1-5066-0008
36C257
Department Of Veterans Affairs Network Contracting Office 17
1901 Veterans Memorial Drive Temple TX 76504
To all Offerors/Bidders
36C25726Q0121
11-19-2025
X
X X
X 1
This amendment provides responses to questions received regarding the solicitation 36C25726Q0121.
This amendment includes the site visit sign-in sheet for the site visit on November 24, 2025.
All other terms and conditions remain unchanged.
Waco Building 8 Access Questions
Access Control Platform & Hardware Requirements
1. Existing Platform
Please confirm the access control platform currently deployed at CTX VAMC (LenelS2, DSX, Hirsch/Identiv, RS2, Kantech, etc.) that Building 8 must integrate with.
Government Response: CCURE 9000
2. Reader Type Requirement
Should the new readers be standard proximity, iClass SE, HID Signo, PIV/CAC-capable, or OSDP-compatible?
Government Response: PIV Class 200 Bit
3. Approved Manufacturers
Is this project restricted to VA-approved hardware (Mercury/Lenel, LifeSafety Power, HID), and if so, could you provide the approved list?
Government Response: N/A
4. Controller Requirements
Are Mercury-based controllers (LP1501/1502/4502, MR52 boards) required, or will equivalent compatible hardware be accepted?
Government Response: IStar Ultra g2
Door Hardware & Installation Details
5. Door Count & Locations
Please confirm the total number of doors requiring access control and whether a door schedule is available.
Government Response: due to spacing we will need to mount the access control panel in a separate closet that requires a card reader. Total doors 8.
6. Existing Door Hardware
Are existing locks/strikes/exits already electrified, or must the contractor furnish new electrified hardware?
Government Response: contractor must supply
7. Door/Frame Modifications
Are any physical modifications anticipated for door frames or storefront systems? If so, please provide drawings or details.
Government Response: cut in electric strikes
Network, IT, and Cybersecurity
8. Network Drops
Will VA IT provide network drops for controllers, or must the contractor furnish and install them?
Government Response: Drop will need to be ran to adjacent OIT closet, VA will provide switch and port info.
9. IP Addressing & VLAN
Will IP addresses, VLAN assignments, and network configuration be provided by VA IT?
Government Response: Yes this will be provided once the hardware MAC address is given to VA to get hardware on approved access list.
10. Cybersecurity Compliance
Are there additional cybersecurity requirements beyond the standard VA 6500 series, Section 889, and FAR 52.204 clauses?
Government Response: No
Power, Enclosures, and Wiring Infrastructure
11. Power Supply Requirements
Is a LifeSafety Power (LSP) FPO enclosure mandatory, or are equivalent UL 294-listed panels acceptable?
Government Response: UL294 is acceptable
12. Battery Backup
Please confirm the required backup runtime (typically 4 hours). Is a longer duration required for Building 8?
Government Response: standard 4 hrs is acceptable
13. Pathway Requirements
Should the contractor furnish new conduit/J-hooks/EMT, or are pathways already installed?
Testing, Commissioning, and Deliverables
Government Response: New hook where there are none available, otherwise cabling can follow existing pathways.
14. Testing Requirements
Should testing follow 100% point-to-point verification, VA commissioning procedures, and full integration testing?
Government Response: Full testing of all doors with Electronics personnel will be completed prior to acceptance of system.
15. Training Requirements
What level of system training is required for VA personnel?
Government Response: N/A
16. O&M Manual Format
Please confirm required formats and quantities for submittals, as-builts, O&M manuals, and programming documentation.
Government Response: digital or print is fine.
Site Access, Work Hours, and Coordination
17. Work Hours
Will this work require after-hours scheduling or can it be performed during normal business hours?
Government Response: from 8am to 330pm Mon-Friday. If there are circumstances where after hours work must be completed it can be arranged.
18. Badging / Escort Requirements
Will contractor staff require PIV credentials, escort-only access, or fingerprint/background checks?
Government Response: an escort/access will be available/ provided
19. Access Restrictions
Are any areas within Building 8 clinical or administrative spaces that require special scheduling or infection control procedures?
Government Response: No
Solicitation Clarifications
20. Drawings & Plans
Will the VA be providing floor plans, door schedules, riser diagrams, or existing system maps?
Government Response: Yes
21. Warranty Requirements
Please confirm the required warranty period for equipment and workmanship.
Government Response: 1 Year after acceptance
22. Wage Determination
Will Davis-Bacon wage requirements apply to this contract?
Government Response: The Davis-Bacon Act does not apply because the Service Contract Labor Standards cover this contract.
23. Site Visit
Will a formal site visit be scheduled? If so, please provide date and registration information.
Government Response: Yes, site visit was on November 24, 2025.
24. The Scope of Work calls for 6 doors to be worked on however the Cost Schedule calls for 7 doors (CLIN 0002). Which is the correct number?
Government Response: total of 8 doors due to unforeseen circumstances
25. The Scope of Work on Page 4 states this is for 6 doors, however the Price/Cost Schedule line item 0002 states install service for 7ea access control doors. Can you please clarify and revise either the Scope of Work or the Price/Cost Schedule accordingly?
Government Response: after walking around the area there is a requirement for 8 doors.
26. Is this to be a standalone system or is it required to be integrated into another access control system?
Government Response: integrated in preexisting CCURE 9000 system
27. What type of ceiling construction are the rooms where the work is being performed and where cabling is run above ceilings (drywall, ceiling tiles, exposed)?
a. If drywall, are we required to install access panels in rooms to provide access above the ceiling to run cabling? Or are access panels already present?
Government Response: mixture of drywall and open area. Contractor will install in area with drywall and above ceiling panels.
28. Can you please clarify the period of performance? On Page 4, Scope of Work, under Requirements it states 4 weeks, however on Page 7, third bullet point from the bottom states 60 days.
Government Response: 60 days
29. Are plans or photos available?
Government Response: See attachment.
See attached document: 674A4-25-001 - Renovate Waiting Space Basement bldg 8.
See attached document: Waco Bldg 8 Site Visit Sign In.