About this file

This is a civil site demolition plan (drawing CD-100) for a VA construction project to replace boilers and boiler plant at 1901 Veterans Memorial Drive in Temple, Texas. The drawing shows detailed demolition specifications for an area around Teague Place and adjacent roads.

The plan includes specific demolition notes requiring contractors to verify utilities, maintain temporary storm drainage, dispose of materials at approved landfills, and submit both a Storm Water Pollution Prevention Plan (SWPPP) and traffic control plan for approval. Key demolition elements include removal of existing roads, curbing, trees (with complete root system removal), and pavement materials. The drawing indicates areas where trees must be preserved with root systems protected. The project is being managed by the U.S. Department of Veterans Affairs Construction and Facilities Management, with Cox Design Associates as the Architect of Record. The drawing is dated September 23, 2022 and marked as "Phase IV 95% Construction Documents."

View the file

Other files

File Type Posted
CD-101.pdf PDF
36C25724R0077 0007.pdf PDF
36C25724R0077 0006.pdf PDF
36C25724R0077 0005.pdf PDF
36C25724R0077 0004.pdf PDF
36C25724R0077 0003.pdf PDF
36C25724R0077 RFI continuation sheet 20241126.xlsx XLSX spreadsheet
2021-624 Georeport_Final.pdf PDF
36C25724R0077 0002.pdf PDF
Pre-Bid RFI 20_Existing Fuel Tank details.pdf PDF
36C25724R0077 0001.pdf PDF
Pre-Bid RFI 24 and 48_ALUCOBOND Dry Reveal Specification.pdf PDF
Specifications_VOLUME 4.pdf PDF
36C25724R0077 Pre-Bid Sign-in Sheet.pdf PDF
ATTACHMENT 12 - PCRA_674-19-101 Replace Boilers and Boiler Plant.pdf PDF
ATTACHMENT 11 - Price Breakout.xlsx XLSX spreadsheet
ATTACHMENT 1 - SOW - Boiler Plant_rev02.pdf PDF
ATTACHMENT 7 - Wage Determination TX20240230 7.12.24.pdf PDF
ATTACHMENT 10 - Contractor Rules Of Behavior.pdf PDF
ATTACHMENT 4 - Specifications_VOLUME 3_01.pdf PDF
Solicitation 36C25724R0077.pdf PDF
ATTACHMENT 8 - S02 Self-Performed Work Calculations.docx DOCX document
ATTACHMENT 6 - 12-21-2022 Final Contract Documents Full Set_01.pdf PDF
ATTACHMENT 3 - Specifications_VOLUME 2_01.pdf PDF
ATTACHMENT 13 - Notice to SB Joint Venture.docx DOCX document
ATTACHMENT 2 - Specifications_VOLUME 1_01.pdf PDF
ATTACHMENT 9 - Past Performance Questionnaire.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEAGUE PLACE

R O

A D

R O

A D

ROAD 9

R O

A D

678 679 680

3 3

DEMO NOTES

1. CONTRACTOR TO FIELD VERIFY ALL UTILITIES

PRIOR TO PERFORMING WORK. POTHOLE TO

PINPOINT LOCATIONS OF LIVE UTILITIES IN DIG

AREAS.

2. COORDINATE STORM DRAIN WORK WITH

OTHER UTILITIES.

3. CONTRACTOR TO MAINTAIN TEMPORARY

STORM DRAIN DURING CONSTRUCTION, AND

COMPLY WITH ALL VA, STATE OF LOUISIANA,

AND FEDERAL SWPPP REQUIREMENTS.

4. CONTRACTOR TO DISPOSE OF ALL REMOVED

OR UNSUITABLE MATERIALS OFFSITE AT AN

APPROVED LANDFILL.

5. ALL KNOWN UTILITIES ARE SHOWN TO THE

BEST AVAILABLE INFORMATION, BUT

ACCURACY IS NOT GUARANTEED.

6. REMOVE AND DISPOSE OF EXISTING

VEGETATION OFF SITE.

7. STOCKPILE TOPSOIL FOR RE-USE AFTER

GRADING.

8. SAW CUT EXTENTS OF DEMO IN PAVEMENT TO

CREATE A NEAT LINE TO MATCH NEW WORK.

9. DISPOSE OF ALL REMOVED MATERIALS

OFFSITE ACCORDING TO STATE LAW.

10. COORDINATE UTILITY CAPPING OR SHUTOFFS

WITH APPROPRIATE SHOPS PERSONNEL.

11. CONTRACTOR TO PROVIDE A SWPPP AND

MAINTAIN BP THROUGHOUT PER VA AND EPA

REQUIREMENTS. SUBMIT FOR APPROVAL.

12. CONTRACTOR TO PROVIDE A TRAFFIC

CONTROL PLAN AND PERIMETER FENCING.

SUBMIT FOR APPROVAL.

LEGEND

TREE TO BE REMOVED

EXISTING ROAD TO BE REMOVED

CURBING TO BE REMOVED

KEYED NOTES

1. DEMO AND DISPOSE OF CURB AND GUTTER

AND SIDEWALK.

2. DEMO AND DISPOSE OF PAVEMENT

MATERIALS.

3. DEMO AND DISPOSE OF TREE AND ROOT

SYSTEM.

4. PRESERVE TREE AND AVOID DAMAGE TO

ROOT SYSTEM.

LIMITS OF DEMOLITION

Project Number

Building Number

Drawing Number

DrawnCheckedIssue Date

Location

Project Title

21 3 4 5 6 7 8 9 10

21 3 4 5 6 7 8 9 10

B

A

C

D

E

F

B

A

C

D

E

F

PhaseDrawing Title

Approved:

APPROVED: HRC DIRECTOR X__________________________

APPROVED: VA PROJECT MANAGER X__________________________

APPROVED: VA CHIEF ENGINEER X__________________________

APPROVED: CTVHCS DIRECTOR X__________________________

ARCHITECT OF RECORDCONSULTANTRevisions: Date:

U.S. Department of Veterans Affairs

Construction and Facilities Management

8718 Botts Lane Phone: (210) 816-4784 San Antonio, Texas 78217 Fax: (210) 881-6808 www.hfscompany.com jbianco@hfscompany.com

FULLY SPRINKLERED

674-19-101

23-SEP-2022

PHASE IV 95%

CONSTRUCTION

DOCUMENTSNOT FOR

CONSTRUCTION

REPLACE BOILERS AND

BOILER PLANT

1901 VETERANS MEMORIAL DRIVE

TEMPLE, TEXAS 76504

INTERIORSARCHITECTURE

COX DESIGN ASSOCIATES

PLANNING

Austin 5121 Bee Caves Road, Suite 203 Austin, Texas 78746 T: 512-327-4149 F: 512-327-7679e info@coxdesignassociates.com

BI

M

VA

T

EM

PL

E

R

EP

LA

C

E

BO

IL

ER

P

LA

N T/

Te m pl e, R ep la ce

B oi le r P la nt

.rv t

4/ 7/

:3

7:

A M

VA FORM 08 - 6231

5350 W. 94TH TERRACE #102

PRAIRIE VILLAGE, KS 66207

T 913.258.5026 www.rossbar.com CD-100

CIVIL SITE DEMO PLAN

RMJr

NJA

TRUE NORTH1 SITE DEMO PLAN

SCALE: 1" = 20'-0"

00 20' 40'

Phase

FINAL CONTRACT

DOCUMENTS

Issue Date

12-05-2022