36C25723B0045 0002.docx
DOCX document 294 KB Posted
- Solicitation number
- 36C25723B0045
About this file
This document contains questions and responses related to a solicitation for renovations to a basement mechanical room at a Department of Veterans Affairs medical facility. The solicitation involves renovating three rooms totaling approximately 1,200 square feet to modernize the aging mechanical systems and improve efficiency. Work includes demolishing old piping and equipment; installing new plumbing, ductwork and controls; upgrading lighting; and performing related mechanical, electrical and architectural tasks. The period of performance is 310 days after notice to proceed. The solicitation was issued to all offerors and includes responses that clarify the scope of work, provide additional details, and resolve conflicts between documents. Hazardous materials abatement is limited to asbestos pipe insulation removal. The project is not design-build in nature and contractors can rely on the provided plans and specifications.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 671A4-22-106 36C257 Department of Veterans Affairs NCO 17 North Texas Healthcare System Regional Procurement Office West (RPO-W) 124 E. Hwy 67, Suite 100 Duncanville
TX
75137 36C257
NCO 17
Department of Veterans Affairs North Texas Veterans Health Care Center 124 E. Hwy 67, Suite 100 Duncanville
TX
75137 To all Offerors/Bidders
36C25723B0045 08-10-2023
X X X
X Amendment 0002 is issued to update the Period of Performance: 310 days after Notice to Proceed is issued (this includes material purchase). This amendment also provides answers to Requests for Information (RFI's).
See Continuation Pages.
Makarim Abdul-Jabbar Contracting Officer
AMENDMENT 36C25723B0045 0002
SF30 BLOCK 14 CONTINUATION PAGE(S):
RFI RESPONSES
1. Are we to dispose/abate of any asbestos, lead, mold, or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.
Response: Yes, refer to hazardous material report.
1. What will the ICRA level be for this project?
Response: Category D, High Risk Level, Patient Risk Category IV
1. Are there any required/proprietary subcontractors the general contractor is to hire associated with this project?
Response: No
1. Will all work associated with this project able to be performed during regular working hours?
Response: Work would be performed during regular hours (part of engineering team is in the office from 0600 – 1630 hrs.) Depending on time frame of demo, shutdowns of systems for connection to temporary bypasses and reconnecting to upgraded systems etc. may need to be a timeframe that would limit the disruptions to the long-term care residence. Possible work may be required after hours. Advance notice of two weeks will be required for coordination will VA police, engineering, and VA medical staff.
1. It is our understanding that the Solicitation is a negotiated Bid (RFP) design-bid-build project with the Government's AE being responsible for the design portion (providing a full and complete set of Specifications and Plans) and the successful offeror being responsible for bidding and building the project based on the Specifications and Plans provided by the Government's AE. Put another way, the successful offeror will not be required to perform any design-build services as part of the contract - correct?
Response: All design services are covered by the AE. The solicitation is an IFB Invitation for bids not an RFP.
1. Drawing Number 11-M-102 Diagram 1 Point Matrix shows a High Hot Water Differential Pressure Alarm and a Low Hot Water Differential Pressure Alarm. This would require a Hot Water Pressure Transmitters to monitor pressure of the system in each branch. There is no reference to these pressure transmitters anywhere else in the scope. Furthermore, the Hot Water System uses two Hot Water Pumps, both constant volumes to independently serve two branches of Hot Water Supply to the building.
5. Is this pressure transmitter required?
5. If this pressure transmitter is required, assuming for each branch, where should the pressure transmitters be installed?
Response: a. & b. Delete/disregard high/low differential pressure sensors and alarms.
1. The standard 535 requires a minimum 60F delta between incoming and outgoing water. So, we need to confirm if what they put on the specification sheet are the correct temps. If those are correct temperatures we would need to use the digital version. This incorporates a Emech valve.
(Which requires electricity) to controls the temperature of the water going to building. Second link. For either version we also need to know if this is a recirculating system or not.
Response: The Steam to Water HX EWT condition should read 60 F. Provide the proper controls for a typical system. This is a (re)circulating system per detail 4/11-P-101.
1. In the specifications its is asking for 1/3rd 2/3rd control valves for the steam. This set up indicates.
using a temp transmitter that measures the outgoing water which would tell the control valves.
what to do to maintain temperature. With the 535 all that is required is a maximum of 15 psi steam which can be accomplished with just a pressure reducing valve. So, need to understand.
what they are asking for.
hRps://armstronginterna;onal.com/wpcontent/uploads/Data_ModelFRT535_FloRiteTemp_HeatExchanger_EN.pdf hRps://armstronginterna;onal.com/wp-content/uploads/Data_RT53525_NA_EN_20221229.pdf
Response: Provide the specified controls valves for bidding. Use of PRV may be discussed during submittal phase.
1. The duration of 130 days doesn’t seem to match the market nor the process. Submittals and approval are never less that 45 days. The delivery is Approximately 120 at least after approval. Can the duration be changed?
Response: Period of Performance should be Notice to Proceed plus 310 days.
1. The project is scheduled to bid on September 10th. That is a Sunday and appears to be incorrect or a Typo. Please issue a new bid date.
Response: Bid Date extended, see Amendment 0001.
1. If any PCB’s are to be disposed of, please indicate locations, quantities and requirements for disposal by amendment.
Response: Unknown, not tested for.
1. Will the owner accept any/all pcb’s found for owner removal and haul-off?
Response: No
1. Please provide as-built structural drawings for area identified as B061 Storage.
Response: There are no records of as-built drawings, but VA will continue in locating the as-built drawings.
1. Please provide steel sizing on galvanized shim plates shown on 4/11-S100.
Response: Shim sizing as needed to align elevation cover plate with existing floor.
1. Reference 1/11-AE100. Confirm no work is required at door labeled 108 in room 099G.
Response: Per drawings no work is being done on that door.
1. Please identify owner furnished equipment referenced by floor plan note 1/11-AE100.
Response: Equipment shown on 1/11-AE100 is for generic reference only. All existing equipment to be field verified and all new equipment is called out on MEP drawings.
1. Please confirm no new floor finish is required in rooms 099F, 099G or B061.
Response: Floors to only require path and repair as needed. Finish to match adjacent existing.
1. Architectural detail 1/11/AE500 dowel location differs from structural. If dowels are required per 1/11-AE500, please indicate spacing and size.
Response: Reference Structural for dowel spacing and size.
1. Please provide the basis of design handrail assembly, reference 6/11-AE500.
Response: Handrail to match detail and similar existing conditions on site.
1. If any pipe demolition is required by keynote 13/11-PD100 (“Demolish any pipe no longer in service. Coordinate with building engineers and COR.”), provide locations/quantities/sizing of pipe to be demolished by amendment.
Response: VA to provide information of any additional demo scope. OR disregard note and demolish systems and components as noted.
1. Keynote 3 on 11-PD101 is used at the trench in room 099F and indicates “Clean trench drain pit of sediment and debris. Flush and clear drainpipe back to main.” Please identify where the main is on a floor plan so that this work can be quantified and priced.
Response: Exact records do not exist. Estimate flushing up to 30 ft of pipe in any direction. Flush well enough to allow proper drainage.
1. We understand sanitary piping shown to be demolished on 11-PD101 is overhead piping and not under slab. If any under slab sanitary piping requires demolition on this sheet, please clarify by amendment.
Response: No below grade pipe to be demolished. All piping shown to be demolished is overhead piping. Demolish risers down to near floor, leaving more than sufficient pipe for reconnection of new pipe.
1. Sanitary sewer lines on PD101 and PP101 will be out of commission during the pipe replacement. What areas of the hospital do these sanitary sewer lines serve?
Response: Pipes primarily serve the floors above mechanical room, the central wing and Annex.
1. New light fixtures are white in color. Please confirm it is not the intent to paint all the new light fixtures black per lighting note 5/11-E-001.
Response: Do not paint light black. Lighting note 5/11-E-001 will be removed.
1. Keynote 9 and 1 on 11-ED100 call for removal of the electrical panel, the abandoned motor control center, transformer and pull box including removal of all abandoned conduits. Please provide as-built one-line diagrams and panel schedules to give an idea of scope of conduit/wire to be removed.
Response: The transformer is 150KVA, 480/208V, 3 phase. The SWBD is 208V, 3 phase, 600amp. Upstream feeder information is not available from the existing as-built drawings. Contractor to field verify connectivity.
1. Specifications Section 00 00 01 Seal Certifications indicate to add Architect and Engineer Seals at the 100% Final Construction Set.
AE seals / stamps are not provided on the issued plans or specifications. Please confirm the plans and specifications provided for contractor download are the 100% Final for Construction Set.
Response: The plans and specifications are for bidding and construction. Signed documents were provided to the VA.
1. We understand that this is not a design build project, and the contractor can rely on the designed plans and specifications for the scope of work.
Response: Yes, the intended full scope of work is within specifications and plans.
1. Current bid date of 9/10/23 in on the weekend. Can the bid date be moved to a workday?
Response: Bid date was extended.
1. Considering submittals, lead times on equipment and 12 phases, the completion date of 130 calendar days is not sufficient. Is this a typo? Should it be 310 days? Please increase the project completion period by amendment.
Response: Yes, it should be 310 day
1. We understand that this is not a design build project, and the contractor can rely on the designed plans and specifications for the scope of work.
Response: AE is responsible for the design and specs of this project and should be aligned with the VA requirements for this project.
1. Does the V.A. have a required mechanical controls contractor for this campus?
DorSun Automation David Dorband, (210) 900-5171, David@DorSunAutomation.com 15007 Pintail, San Antonio, TX 78253
1. Does the V.A. have a required fire alarm contractor for this campus?
Eric M. Cameron Operations Manager NICET # 152321 Level II Cameron Strategic Management LLC (CMS) (SDVOSB) 8 Salta Ct. Belton TX 76544 CELL760-792-27041
1. Does the V.A. have a required security contractor for this campus?
Response: Campus VA police
1. Does the V.A. have a required P.A. System contractor for this campus?
Response: No
1. General note 15 on 11-AD100 indicates work shall be nights/weekends and coordinated with the COR 2 weeks ahead of time. Attachment 1 Statement of Work paragraph 7.9.a indicates the project site’s normal working hours to be between 8am and 4:30pm. Please confirm all work including demolition can be performed between 8am and 4:30pm.
Response: Contractor will need to coordinate with COR on demo schedule to review possible affects on daily operations of the hospital. Depending on scope of demo, the contractor may need to perform demo or other work after hours. Part of the engineering team is present from 0600 hrs. to 1630 hrs. The Basement mechanical room will be access throughout the work the day and possible evenings to perform their duties.
1. We understand that the ICRA requirements for this project can be met by sealing the existing double doors per keynote 20/11-AD100.
Response: Sealing the double doors may not meet the ICRA requirements as access into the mechanical room is through the double doors and may require a hard barrier between the double door and area outside of mech room per Infection Control team. Outside of the double doors are the elevators and corridor where staff and patients will be utilizing the area and elevators.
1. Demolition plan sheet 11-AD100 keynote 19 shown to be used in all three rooms states, “Repair Deteriorating Concrete Slab”, but provides no plan details or specifications on how to do the repair or what the expectation is. Please confirm Repair of Deteriorating Concrete Slab only occurs in room 099F and is limited to the spalling concrete floor adjacent the existing trench.
Response: Contractor to survey site and propose recommendations for concrete repair as needed. Clarify bid with recommendation proposed.
1. What material should be used to keep the deteriorated floor (spalls) patches from re-spalling? Please provide plans and specify material required for repairing the deteriorated (spalled) concrete floors.
Response: Grout per specification 03 30 53
1. Confirm scaffolding will be allowed inside the deep service pit in room 099G so that demolition and spray insulation of the structure above can be performed.
Response: Yes.
1. Please confirm that asbestos abatement is limited to abating asbestos pipe insulation on piping shown to be demolished within the 3 rooms of this project.
Response: Yes, abatement is limited to demolition and replacement scope per hazardous materials survey.
1. Please provide equipment lift pit dimensions (Length, Width, Depth).
Response: Generic sizes are shown on plans, however the final size to be determined by selection of equipment lift.
1. The concrete basement walls have several openings to the crawlspace. Crawlspace dirt is covered with plastic. Signs are posted at the openings to the crawlspace warning of the presence of asbestos in the crawl space. Cool air is blowing into the mechanical room from the crawlspace. Confirm the basement mechanical rooms are not contaminated with asbestos and it is safe to work in these areas.
Response: Asbestos Report conducted by ARGUS ENVIRONMENTAL CONSULTANTS; LLC dated 1 Sep 2022 is attached.
1. Is new spray insulation required on the underside of the concrete deck above including the sides of the concrete joists/pans?
Response: Yes.
1. Please confirm acoustic spray insulation is not required in B061 Storage.
Response: spray insulation is not required in B061 Storage
1. Please provide a copy of the structural as-built drawings showing concrete joist and pan locations and depth of the joists/pans so that the acoustic spray insulation can be quantified.
Response: There are no records of as-built drawings, but VA will continue in locating the as-built drawings.
1. Keynote 18 on 11-AD100 indicates to “Remove all unused piping, conduit, alarm, etc.. Refer to MEP&FP drawings.” We understand that removal of all unused piping, conduit, alarm, etc. is limited to the items shown for demolition on the MEP & FP drawings. If additional items are required to be demolished which are not shown, please revise plans to show this work.
Response: Contractor to survey site and provide proposal on additional items to be removed. Provide estimated costs associated with additional removal.
1. Keynote 1 on 11-MP100 states “Upblast fan set on curb on existing concrete well wall controlled by thermostat. Duct into mechanical room and provide with motorized damper.” Plan detail 1/11-M-101 does not show any ducting to the motorized damper. If required, please show requirements on a plan detail.
Response: Duct is not required. The existing concrete shaft walls are sufficient.
1. From the site visit, it appears that the existing concrete shaft walls are not as depicted on plan detail 1/11-M-101. Shaft wall appears to be on three sides only. What is to support the custom exhaust fan curb on the fourth side?
Response: Provide a galvanized steel frame (angle or tube, 2”x2” min. cross.) with flanges on ends for fastening into concrete shaft walls, to serve as fourth side.
1. How much space must be provided/allowed between the face of the existing exterior wall and the new exhaust fan housing? Response: Approximately 1 inch.
1. How tall is the exhaust fan curb required to be?
Response: 12” to 18” tall. Curb may serve as transition fitting between shaft opening and fan intake.
1. Please provide the basis of design manufacturer and model number of the new exhaust fan.
Response: Greenheck - CUE-240-VG
1. General note 12 on 11-AD100 states “All cabling, PA System, Conduit, Piping, etc. shall be removed back to point of origin (which may require work outside this footprint). Ref, to MEP & FP Demolition Drawings.” This is not a design build project. Please identify by amendment on a reflected ceiling plan any areas outside the footprint which will require work so that this work can be quantified and priced.
Response: Contractor to survey site and provide proposal on additional items to be removed. Provide estimated costs associated with additional removal. Review and confirm with VA all work to be done beyond scope of work.
1. Reference General Note 3/11-AD100. This is not a design build project. Confirm contractors are not required to retain a delegated design structural engineer to determine concrete floor patch at steel column demolition and that this work has been or will be done by the A/E of record.
Response: Disregard this section of the note. This is the scope of the A/E of record.
1. If demolition of the steel columns will require concrete floor patch, please provide patching details by amendment. Reference GN3/11-AD100 and demo keynote 3 on detail 1/11-S100.
Response: Patch small holes with concrete specified, and larger patches per detail 3/11-S100.
1. Detail 1/11AE100 uses Plan detail 2 on 11-AE500 at left side of room 099F. This detail requires removal of existing grate and installation of new diamond steel plate at the existing trench. This conflicts with structural drawings on 11-S100 which show no work on trench at left side of room 099F. Please confirm structural drawings are correct and no work is intended on the trench at left side of room 099F except for protecting the trench and drains per keynote 4/11-AE100.
Response: Existing trench to receive new cover per plan detail. Refer to drawings for extent of new grate cover. No structural work is to be done on the existing trench.
1. Confirm horizontal lines on Details 2 and 7 on 11-AE500 are extraneous lines requiring no construction work.
Response: Horizontal lines are to show connection intent. Reference Structural drawings for final design of connection between new and existing concrete.
1. Detail 1/11-AE100 uses detail 7/11-AE500 on the portion of the floor going towards the new industrial sink. Detail 7 is for an existing trench. We did not notice an existing trench at this location at the walk-thru. Please confirm scope at this location is depicted per structural drawings (slab is to be cut and patched for new plumbing) and detail 7 is not applicable this location.
Response: Confirmed. Scope at this location is as depicted per structural drawings.
1. Should industrial cabinet model number HDC246066-3595 be HDC2460663S95? Reference kn 2/11-AE100.
Response: Correct. The model number is HDC-246066-3S95
1. Should industrial cabinet model number HDCD243678-7805 be HDCD243678-7B95? Reference kn 2/11-AE100.
Response: Correct. The model number is HDCD243678-7B95
1. Please provide plan detail and specification for under slab waterproofing required by keynote 10/11-AE100. What is required?
Response: Refer to specifications provided: Section 03 30 53 Cast in Place Concrete 2.1.(H) and Vapor Barrier 3.3
1. Detail 2/11-AE100 shows little circles spaced 4’o.c. Are these pipe bollards to be installed per details 5/11-AE500?
Response: Keynote changed to new note 24 - “NEW BOLLARDS. SEE DETAIL 5/11-AE500”
1. Please confirm Detail 5/11-AE500 which shows pipe bollards grouted to top of asphalt with bolts into dirt.
Response: Per text call out on detail 5/11-AE500: Bollard are to be bolted to “EXISTING ASPHALT ROAD”
1. Detail 7/11-S100 Roof Chase Slab Section indicates to see detail 9 for reinforcing. Confirm reference should be detail 8 requiring #5’s at 10”o.c. top and bottom.
Response: Correct.
1. Can the deadline for questions be extended one week?
Response: Not extended.
1. Section 00 01 15-2 lists fire alarm drawings 1-FA001, 1-FA101, 1-FA131 and 1-FA200 which have not been provided. If they are to be included in this project, please issue by amendment.
Response: Fire alarm systems are not in scope. Disregard reference.
1. The statement of work and life safety phasing (11/GI102) is remarkably different from the issued designed drawings. We understand the issued designed drawings are correct and the issued statement of work and life safety phasing are not accurate/not applicable. If any portion of the statement of work or life safety phasing is required to be incorporated into the project, revise plans by amendment to reflect these items. Some of the conflicts include:
1. Steel diamond plate (plans) over trough (versus new grating-SOW) Responses: Steel diamond plate is over a portion of the trench to allow movement of wheel equipment approx. 4’ wide, the remaining trench to get the new grate.
1. Solid concrete slab over back room (plans) versus leak proof door hatch (sow) Response: Slab roof over back room
1. Wall mounted fans at workstations (sow/phasing). Not required by plans.
Response: Not required
1. Designed sink is a sink without cabinet while sow refers to a cabinet at sink.
Response: To be a Cabinet Sink Station with two deep sinks, removable spray hose and counter space.
1. Designed drawings do not require the following at new room in back: cabinetry, workstation, sink station, exhaust fans and waterproofing.
Response: Correct
1. SOW refers to Noise reduction at some equipment. Which equipment? Not shown on drawings.
Response: To be Spray Noise reduction insulation.
1. Designed drawings requiring cork to be replaced by spray insulation. SOW calls for cork.
Response: To be Spray Noise reduction insulation.
1. Is converting pneumatic controls from pneumatic to ddc shown on designed drawings?
1. Designed drawings do not require a new minisplit system. SOW/Phasing refers to a minisplit.
Response: Removed from scope.
1. Removal of all coverings on piping, inspection of pipes and replaces (sic) as needed is not required by designed drawings, but is listed in SOW. How much is required? No way to quantify this. Not designed.
Response: Inspection of all is not required, replace what is required.
1. Fixing all deficiencies found during facility condition assessment, joint commission inspections is not a requirement of the design drawings. We assume the designed plans are fixing the deficiencies.
Response: It’s to address deficiencies and to modernize, streamline the mech room to be efficient.
1. Many other items not listed here…
1. If the conflicting portions of the statement of work or life safety phasing is required to be incorporated into the project, issue revised floor plans, door schedule, mechanical equipment schedules, power plans, etc by amendment.
Response: It’s to address deficiencies and to modernize, and streamline the mech room to be efficient.
1. 11-GI-102 life safety phasing indicates to layout all new lines next to existing to be replaced for hot water recirculation and potable hot water supply and to provide a more streamlined direct route for steam piping. The phasing does not provide this same wording for potable cold-water supply or for the sanitary sewer lines.
1. Is it also intended to layout new lines for cold-water supply and sanitary sewer lines next to existing or are these constrained to remain in existing locations because of?
Please clarify length of time each system can be out of commission at one time and when these outages can occur.
Response: a. The intent includes cold water supply and sanitary sewer, as with other pipes, if more time is needed than allowed for system shut down to avoid service interruption. (Per VA guidance. After hours expected.)
1. Please clarify what Life Safety note Phase 7.d means as it pertains to sanitary sewer lines?
“Add temporary shut off key locations to allow redirect for servicing to lines.”
Response: Delete the word “Key”
1. We understand the phasing provided on 11/GI102 is not a required phasing, but that contractor can provide phasing for approval (means and methods).
Response: Phasing plan specified is a reference. VA and Contractor shall coordinate exact phasing and modify per site requirements as needed.
1. Please identify on a plan sheet where the new data outlet runs to.
Response: Run data cables to IDF room 035 plan east by stair S-001, field verify.
1. Confirm hospital toilet facilities will be made available to contractor.
Contractor will need to provide own Porta Potties
1. Section 01 00 00-13 paragraph 1.15 A indicates no commissioning will be required. Please confirm.
Response: No commissioning required.
1. If commissioning is required, confirm it is only for work installed on this project and not the list of not applicable items listed such as fire pump, roof mounted ahu’s… in section 01 91 00.
Response: No commissioning required
1. Confirm the duties of the QC Manager and all CQC Team members can be performed by the project superintendent.
Response: Response: Yes, but a Quality Assurance Surveillance Plan must be submitted for approval.
1. Is Kerrville in seismic zone 0? Is Section 13 05 41 Seismic Restraint Requirements for Non-structural components applicable?
Response: Correct, not required.
1. Where does Section 32 31 40 High Security Fence and Gates apply?
Response: Fencing for construction purposes on site. Confirm extents with VA and provided plans.
1. Where does Section 04 20 00 Unit Masonry apply?
Response: Detail 01/11-AE500 calls for flashing at existing masonry wall.
1. Where does Section 06 10 00 Rough Carpentry apply?
Response: Specification not needed.
1. Section 09 91 00 Painting includes painting for things not included in this project. Please confirm painting is limited the new hollow metal doors.
Response: Verify painting extents per details provided.
What temporary fire alarm devices are required per Life Safety phasing 11-GI102 paragraph phase 1.h?
Response: The intention is to protect/cover existing fire alarm devices during construction from damage, and provide temporary fire alarm devices (heat detectors, smoke detectors) for use during construction.
See attached document: Asbestos Abatement Design Specification and Attachments.
See attached document: APPENDIX A - DRAWINGS - Signed.