36C25626R0019 0003.docx
DOCX document 454 KB Posted
- Solicitation number
- 36C25626R0019
About this file
This is Amendment 0003 to Solicitation 36C25626R0019 issued by the Department of Veterans Affairs Veterans Health Administration Network Contracting Office in Fayetteville, Arkansas. The amendment extends the receipt of offers deadline to June 1, 2026 at 3:00 PM CDT and posts responses to 85 Requests for Information (RFIs) submitted by potential offerors regarding the Pharmacy Physical Security Upgrade project at the Veterans Healthcare System of the Ozarks.
The RFI responses provide clarification on project requirements including: phased construction scheduling (Phases 1-7 with Phases 4-6 to be performed during weekends with 1-2 day intervals between phases); infection control and ICRA requirements with negative air HEPA filtration; existing system vendors and contacts (SIEMENS Firefinder for fire alarm, Software House for access control, Vicon for CCTV, Johnson Controls for HVAC); contractor responsibilities for access control, CCTV, door hardware coordination, and electrical work; pharmacy temporary relocation locations during construction; sprinkler system requirements with existing head repositioning; concrete slab moisture and pH testing included in base bid with remediation work as a separate change order if needed; Level 3 ballistic-rated doors for the dispensing window wall; alternates pricing submitted separately from base bid; full-time on-site quality control and safety personnel (superintendent may serve dual/triple roles); coordination with VA Contracting Officer for phasing, work hours, utility shutoffs, and system vendor contacts; and clarification that no commissioning is required on the project. The amendment confirms that no additional RFIs will be accepted due to time constraints.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626R0019 0002.docx | DOCX document | |
| Pre-bid conference site visit 4.13.26 sign in.pdf | ||
| 36C25626R0019 0001.docx | DOCX document | |
| WD MS20260051 Hinds.pdf | ||
| 36C25626R0019 EXHIBIT B.docx | DOCX document | |
| 36C25626R0019 EXHIBIT D.docx | DOCX document | |
| 36C25626R0019 To Post.docx | DOCX document | |
| 586-22-105 Specifications Revised.pdf | ||
| Scope of Work Pharmacy Physical security Redlines updated.docx | DOCX document | |
| 586-22-105 Drawings edited tl.pdf | ||
| 010000 11-2021 General Requirements - R2.pdf | ||
| WD MS20260052.pdf | ||
| 36C25626R0019 EXHIBIT C.docx | DOCX document | |
| 36C25626R0019 EXHIBIT A.docx | DOCX document | |
| 36C25626R0019 EXHIBIT E.docx | DOCX document | |
| 36C25626R0019 EXHIBIT F.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
05-15-2026
586-22-105
Department of Veterans Affairs Veterans Health Administration Network Contracting Office 16 2575 Keystone Crossing Fayetteville AR 72703
Department of Veterans Affairs Veterans Healthcare System of the Ozarks Network Contracting Office 16 2575 Keystone Crossing Fayetteville AR 72703 To all Offerors/Bidders
36C25626R0019
X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 06-01-2026 15:00 CDT
This amendment posts the questions and answers to the RFI's. Due to time restraints no additional questions will be responded to.
CONTINUATION PAGE
RFI 1. The time set for receipt of bids is 10:00am. Can this time change to 3:00 PM on same day?
Yes, the time set has been shifted to 3:00PM.
RFI 2. In review of subcontractor Information (Subfactor 2b) which must be submitted with bid, we find this information will be almost impossible to obtain prior to bid for submission with bid documents. Usually, subcontractors do not release their quote until just prior to bid time. It would be impossible to incorporate this information with bid documents. Can this information be submitted seven days after bid submission?
Identifying key subcontractors and submitting required documentation at the proposal stage is a long‑standing federal construction requirement. Historically, offerors have been able to comply by coordinating early with potential subcontractors or using existing teaming relationships. Offerors intending to self‑perform may indicate that in their proposal. This requirement will remain unchanged.
RFI 3. Drawings phasing notes / pharmacy scope notes; revised specs pharmacy scope notes: Please confirm who is responsible for relocation, removal, and reinstallation of pharmacy casework and workstations. Is this by the contractor, a third-party vendor hired by the contractor, or VA's furniture vendor? The drawings/specs conflict on who carries this scope. That affects labor, coordination time, protection, and any temporary disconnect/reconnect work around casework.
The Contractor will coordinate and hire the Vendor RFI 4. Drawings phasing notes: Please identify the exact temporary locations for Filling and Comm Care during phased construction. The phasing notes reference these functions relocating to TBD locations. Without final temporary locations, temporary power/data/security/fire alarm impacts cannot be fully priced.
Filling will temporarily relocate to in-patient pharmacy. Comm care will be relocated within the outpatient pharmacy.
RFI 5. Drawings phased demolition/new work notes marked 'By VA 3/2/2026: Please provide a clear division-of-work matrix for each phase showing what is by VA versus by Contractor for ceilings, salvaged light fixtures, ceiling grid/tile, HVAC, and electrical removals/reinstallation. Multiple notes assign portions of ceiling, fixture, HVAC, and electrical work to VA while other notes assign new installation to the contractor. The set needs one clean responsibility matrix.
A/E does not agree a responsibility matrix is needed. “BY VA” is noting that VA added a comment and does not mean the responsibility is on the VA. Vendor is to meet all the notes and specifications no matter if the VA or AE made those notes.
RFI 6. Specs Section 28 13 00 / access control notes on drawings: Please confirm the exact existing access-control panel locations, available spare capacity, available power, and whether additional controller/reader expansion hardware is required for this project. The documents identify existing Software House hardware and also direct the access-control vendor to verify existing panels and replace devices. Capacity and expansion needs are not fully defined in the bid set.
Contractor shall coordinate with the VA COR the contact information of the vendor who currently supports the existing system for required information.
RFI7. Security system continuity notes on drawings: Please define the required outage limitations and temporary coverage requirements for existing cameras, duress, and intrusion systems that must remain operational during construction. The set requires these systems to remain live during construction, but it does not define permitted outage windows, bypass procedures, temporary monitoring, or temporary device requirements.
No outages are anticipated.
RFI 8. Video surveillance notes / specs Section 28 23 00: Please clarify who is responsible for software licensing, workstation programming, recording/storage expansion, server/NVR modifications, and VA-IT/network coordination for the new cameras. The drawings reference programming a new camera view into the workstation, but the set does not clearly assign software, storage, cybersecurity, and network responsibilities.
The system vendor procured by the successful shall provide all required hardware & program modifications to the system. The vendor shall also coordinate with the VA’s OIT group if any of this work impacts the OIT system or requires their assistance. Coordinate with the VA COR the contact information of the vendor who currently supports the existing system for required information & support RFI 9. Duress / Lynx notes on drawings; Specs Section 28 26 00: Please clarify the exact furnish/install/program scope for the Lynx duress expansion, including whether the contractor provides only raceway/power or also provides vendor equipment, cloud programming, subscriptions, and final commissioning. The set references a new LynxNet 4 vendor panel/power supply and dedicated power, but ownership of vendor-furnished equipment and programming is not clearly separated.
The LYNX system components shall be furnished/programmed by the successful bidder’s vendor and installed by the electrical contractor under the supervision of the system vendor. Any modifications required on VA’s network shall be coordinated with the VA’ s OIT group. All raceways and cabling required to support these systems shall be provided by the successful bidder and coordinate with their respective vendors.
RFI 10. Door control / fire alarm interface notes on drawings; Specs Section 28 31 00: Please confirm the full fire alarm integration scope for delayed-egress doors, magnetic hold-opens, and any door-release interfaces, including who furnishes interface modules and who programs the existing fire alarm system. The set requires release upon fire alarm activation and says to coordinate with the fire alarm contractor, but it does not fully define responsibility for modules, panel programming, testing, and spare system capacity.
The electrical contractor shall be responsible for providing all aspects of this work, including all labor, materials, equipment, software, and associated system programming modifications required for a complete and operational installation. The electrical contractor shall retain the services of the facility’s preferred service provider/vendor for this system, who is currently under contract with the facility for system maintenance and support. The vendor shall provide the electrical contractor with all required technical information, replacement parts, installation support, system integration assistance, and programming services necessary to complete the work and place the system into full operation.
RFI 11. Access control / door automation / hardware coordination notes: Please provide a final door-by-door furnish/install/integrate matrix showing what is by Division 8 hardware supplier, by security/access-control vendor, and by electrical contractor for locks, readers, DPS, REX, automatic operators, power supplies, and final connections. The set mixes electrified hardware, access control, automatic operators, delayed egress, and fire alarm release functions. A clean matrix is needed to avoid scope gaps and double-carry.
The electrical contractor shall be responsible for providing all aspects of this work, including all labor, materials, equipment, software, and associated system programming modifications required for a complete and operational installation. The electrical contractor shall retain the services of the facility’s preferred service provider/vendor for this system, who is currently under contract with the facility for system maintenance and support. The vendor shall provide the electrical contractor with all required technical information, replacement parts, installation support, system integration assistance, and programming services necessary to complete the work and place the system into full operation.
RFI 12. Alternates on drawings: Please confirm how Alternate No. 1 (delete access control, including new readers and electrified hardware) is to be priced and submitted relative to the base bid. The alternate changes major portions of the low-voltage/electrified hardware scope. The pricing form should clearly state whether this is a deduct alternate carried separately from the base bid.
Alternate No. 1 is a deduct alternate and shall be priced separately from the base bid. Submit pricing in accordance with the price schedule instructions.
RFI 13. Phasing / dust-control / active-pharmacy operational notes: Please confirm approved work hours, shutdown windows, infection-control requirements, and any mandatory night/weekend work for electrical, security, and fire alarm work inside the active pharmacy areas. Because this is active pharmacy space, restrictions on noise, dust, ceiling access, and shutdown timing can materially affect labor productivity and sequencing.
VA’s Normal Working Hours are 8:00 am to 4:30 p.m., Monday through Friday. Contractor shall coordinate work with the COR in order to not disrupt the end user’s operations which may include work earlier or later in the day and on weekends or federal holidays at no additional cost to the VA. Noise disturbances and utility shutdowns/tie-ins shall be coordinated with the COR and not interfere with VA daily operations. See updated ICRA for infection control requirements.
RFI 14: Writing with a question on the NAICS requirements for this project. Would your office accept a formal teaming agreement to satisfy the construction NAICS requirement?
Teaming agreements are authorized assuming all meet the SAM/SDVOSB requirements.
RFI 15: Is any commissioning required on this project?
No.
RFI 16: Can the Superintendent also be the Prime Contractor’s Commissioning Manager during commissioning?
Yes.
RFI 17: Is a full-time on-site quality control manager required for this project?
Yes.
RFI 18: Can the Superintendent also be the quality control manager?
Yes.
RFI 19: Is a full-time on-site Safety and Health Officer required for this project?
Yes.
RFI 20: Can the Superintendent also be the site safety and Health Officer?
Yes.
RFI 21: Can the Superintendent be Triple hatted as the SSHO and QC Manager?
Yes.
RFI 22: As is typical for most VA projects can the QC plan be implemented by the onsite superintendent and administrated by the PM without additional staff (other than what is required for commissioning) as call for in 01 45 00.?
Yes.
RFI 23: What portions of this work have to be performed after hours or weekends?
Phases 4, 5, and 6 must be performed during weekends, it must comply with the ICRA and be operational by Monday morning. Multiple weekends could be required but Monday morning it must be operational workspace. Work above double doors in the inpatient pharmacy must also occur on weekends.
RFI 24: When one phase has been completed how long should the contractor anticipate having to wait before being able to start on the next phase?
1-2 days RFI 25: Is there any possibility that the contractor may be able to combine some of the phases of work.
Yes. Phases 4, 5, and 6 are to be performed during weekend hours. Phases 1, 2, 3, and 7 are to be performed during the week. A phase performed during the week (1, 2, 3, or 7) and a phase performed during weekends (4, 5, or 6) can be combined. For example, phase 1 can be performed alongside phase 4 with phase 1 being performed during the week and phase 4 on the weekends. Phases 5 and 6 can be performed alongside phases 2, 3, and 7, similarly to the combination of phases 1 and 4. Exact phase combinations are to be confirmed with VA COR prior to work.
The above are examples of how the process is envisioned.
RFI 26: Will each phase have to be partitioned off with a wall from floor to ceiling?
Yes, each phase must be separated with a full-height barrier.
a. If so, does the VA recognize that this will cause visible seams/joints in the flooring?
No, the VA does not expect visible flooring seams to be a long-term issue; any visible disruptions shall be repaired.
RFI 27: Will all work be completed on the Outpatient Pharmacy before work begins on the Inpatient Pharmacy?
Yes.
RFI 28: There is no outside walls in the work areas to vent the negative air outside. How would the VA prefer the contractor to vent the air from the space to achieve the negative pressure required by ICRA?
If exhaust is directed indoors, then the system must be HEPA filtered. Prior to start of work, including assembly of the ICRA barriers, initial baseline air sampling measurements for particulate levels must be taken in the planned area of discharge. Once containment is erected and completed, HEPA filtration must then be verified by particulate measurement, using particle counter with multi-channel capabilities to measure down to 0.3 microns, to confirm that the discharge of the HEPA unit does not exceed the baseline particulate count of the area to which the exhaust is directed. Verification must continue at least three times per day (once every 8 hours), 7 days per week, during the use of the negative air machine and HEPA filter. Any exceedance must trigger a work stoppage and an immediate response and resolution. All particulate measurements, including baseline measurement, must be documented and retrievable.
See updated ICRA for more information.
RFI 29: What openings can we use to vent our negative air to meet the ICRA requirements?
Select appropriate locations and obtain COR approval.
RFI 30: In ICRA areas that require Category B Level 1 or 2, can we use zip-walls or plastic sheeting as containment?
See updated ICRA.
RFI 31: In any ICRA areas that require above Category B containment, can plastic wall panels be used for the ICRA walls, such as STARC Panels or Temporary Wall System’s panels?
See Sheet IC101 Dust Control Plan Notes One.
RFI 32: Will temporary sprinklers be required during demolition?
Contractor will be required to turn the existing sprinkler heads up during construction once the ceiling is removed and provide NFPA 13 required coverages, or if the zone is not active, provide fire watch.
The VA will allow the Contractor to install heat sensors and drain the system in just the Pharmacy.
RFI 33: Will the contractor be required to turn the existing sprinkler heads up during construction once the ceiling is removed or can the contractor use heat sensors instead?
Contractor will be required to turn the existing sprinkler heads up during construction once the ceiling is removed and provide NFPA 13 required coverages, or if the zone is not active, provide fire watch.
RFI 34: Is there an RTLS system in the work area?
Yes RFI 35: If so, please provide contact name and phone number for who services the current RTLS System Tim Towers, Tim.Towers@agilerank.com RFI 36: Who is the manufacturer of the current Fire Alarm system SIEMENS Firefinder RFI 37: Please provide contact name and phone number for who services the current Fire Alarm System
SIEMENS
RFI 38: Who is the manufacturer of the current Security and Access Control system?
Software House RFI 39: Please provide contact name and phone number for who services the current Security and Access Control System?
Security101/ Tim Whalen 251-471-4323 RFI 40: Please confirm whether the Access Control work in this project is to be CFCI, OFCI, or OFOI?
Access control (and CCTV per RFI 43) is Contractor-Furnished, Contractor‑Installed (CFCI) in coordination with a VA‑approved system vendor.
RFI 41: Who is the manufacturer of the current CCTV system?
Vicon RFI 42: Please provide contact name and phone number for who services the current CCTV System?
Emerald Resource RFI 43: Please confirm whether the CCTV work in this project is to be CFCI, OFCI, or OFOI?
See response to #40.
RFI 44: Who is the manufacturer of the current HVAC Controls?
Johnson Controls Inc.
RFI 45: Please provide contact name and phone number for who services the current HVAC Controls?
Kevin Deasin/ 601-896-4968
RFI 46: Please provide an updated contact name and phone number for the JCI Metasys Building Automation System Representative that services this VA?
Kevin Deasin/ 601-896-4968 RFI 47: Please provide a copy of the Mabbett and Associates regulated building materials survey for VA project 586-22-105 Dated April 30, 2023?
Report is attached. This is not a BID Document. Release of this document is by VA only.
RFI 48: Who is the existing signage contractor for this VA?
Creative Signage.
RFI 49: Will the contractor be responsible for any city permits?
Yes, but no permits should be required.
RFI 50: Can the VA provide installation manuals or cut sheets for any Owner Equipment that the Contractor has to dismantle or re-install?
No RFI 51: What is the height from finished floor to bottom of deck above in the Work Areas?
±14’0” to be verified in the field.
RFI 52: Is there a floor or crawl space below the Work area or is it the bottom floor with slab on grade?
Floor below first floor and crawl space below basement.
RFI 53: Will the VA have each phase cleared out of furniture, loose items and equipment before the contractor begins construction?
See Phase Notes on Sheet PH-101 and specification section 01 00 00.
RFI 54: Will the contractor be required to move any of the existing furniture or equipment?
See Phase Notes on Sheet PH-101 and specification section 01 00 00.
RFI 55: If the contractor is responsible for moving the existing furniture, will storage be available from the VA for the furniture, equipment, or casework?
Contractor to coordinate with furniture vendor on options.
RFI 56: Is there any reason to believe the slab has moisture in it and moisture remediation will be needed?
No.
RFI 57: Have other areas on this floor needed moisture remediation on the concrete slab in past projects?
No.
RFI 58: Per spec 09 05 16 Section 3.3.A specifies the use of a moisture remediation coating only when the results of ASTM F2170 relative humidity testing exceed the requirements of the flooring manufacturer. Similarly, pH and moisture testing are outlined in Section 3.2.G–H. Can you confirm that moisture remediation coatings, pH neutralization treatments, or other corrective measures included in this specification are only required if slab test results are unsatisfactory?
Yes.
RFI 59: Specification Section 09 05 16 includes detailed descriptions and product requirements for both moisture remediation systems (Section 2.1) and underlayments (Section 2.2), yet it is unclear whether these items are part of the base bid or only applicable if testing shows deficiencies. Please clarify is the intent that all floor slab testing is to be included in the base bid, and any required remedial treatment (e.g., moisture remediation coating or underlayment) would be added by change order/modification if needed, based on test results?
Testing (ASTM F1869, ASTM F2170, and pH testing) shall be included in the base bid. Moisture remediation or underlayment work is not included in the base bid and, if required based on test results, will be addressed via modification RFI 60: The specification 09 05 16 calls out multiple tests ASTM F1869, F2170, and pH testing. Which of these test are required in our base bid price?
All.
RFI 61: Without knowing the actual moisture or pH conditions of the concrete prior to bid, there is significant risk in trying to price products like moisture remediation coatings (epoxy vapor barriers, etc.), cementitious self-leveling underlayment, or trowel-applied patches. Including these without confirmation could lead to either inflated pricing or post-award cost disputes. Thus, under FAR principles of clarity in solicitation documents and equitable risk distribution please provide clear direction on what is to be included in our base bid for subsurface preparation?
a. Would the Government clarify an allowance price for all bidding contractors to carry in order for fair bid leveling?
See response to #59.
RFI 62: Can the VA please provide a basis of design manufacturer for the Level 3 Package Receiver.
Meet the requirements of the specification section 11 17 36.
RFI 63: Will the VA please confirm that none of the new doors have to be Level 3 intrusion or bullet/ballistic rated?
Doors along the dispensing window wall must be UL 752 Level 3 ballistic construction and use 15-minute forced entry resistant construction.
RFI 64: Door Comment for A-121 states "match transom size and reinstall louver". Please provide the size of the transom window that the contractor is to match?
a. Will the transom window have to have any force or ballistic rating?
Field verify size. Intent is to replace the existing HM door and frame and reinstall the louver in the transom opening There is no existing window. See drawings and specifications for requirements.
RFI 65: The wood door spec says to match existing wood doors. Can the VA please disclose what species/veneer is needed?
White birch natural w/clear finish.
RFI 66: Please clarify “facility standard” hardware sets and whether electrified hardware is required for access control integration?
The electrical contractor shall be responsible for providing all aspects of this work, including all labor, materials, equipment, software, and associated system programming modifications required for a complete and operational installation. The electrical contractor shall retain the services of the facility’s preferred service provider/vendor for this system, who is currently under contract with the facility for system maintenance and support. The vendor shall provide the electrical contractor with all required technical information, replacement parts, installation support, system integration assistance, and programming services necessary to complete the work and place the system into full operation.
RFI 67: Please clarify material type, gauge, mounting method, and compliance criteria for security mesh installations?
See section 09 29 00, 2.3. Secure mesh to framing with clips with spacing per the manufacturers instructions (typically 12” OC).
RFI 68: .DWG Page P001 note 19 says to flush and disinfect the entire potable water system. Is this requirement for the entire building/s or for a certain zone? If for a zone please define the parameters of the zone and how many feet of piping is included that needs to be flushed and disinfected.
Contractor is required only to flush the affected sections of the Potable Water system.
RFI 69: Please provide locations of existing shutoff valves and if new valves are required for phased construction?
These will have to located in the field with the VA RFI 70: DWG Page P 001 Note 24 states “positive shut off of existing valves cannot be guaranteed. If existing valves fail to hold, contractor is responsible for cost and effort to freeze pipe as needed.” In order to provide far bidding for all contractors per the FAR, please provide a quantity of pipe freezes for all contractors to include in their bid?
Per drawing PD-111 there are 6 domestic water lines in question.
RFI 71: Does the existing HVAC serve any other areas outside the scope of work that will be effected by the HVAC Demolition Yes. Refer to all general sheet notes on demo and new mechanical work. Contractor to VIF all systems. AHU-18A and AHU-2A referenced.
RFI 72: Will any temporary HVAC be required to other phase during the Phase I, B-I, III or V?
Phasing of HVAC shall be coordinated with the Arch recommend phasing to align crossover of barriers and actively conditioned spaces in a downstream to upstream manner. Any predetermined and approved AHU system downtime shall be scheduled with VA and permissible construction hours to avoid additional temporary heating / cooling.
RFI 73: Page 23-05-93 -1-10 TAB spec section does not discuss testing by phasing. Will we have to re-TAB after each phase is completed or, can we simply re-TAB after the whole of a project on a floor is completed?
Air devices served by the same terminal unit but in separate phases must be rebalanced to turn over occupancy of the space. Final TAB will be required.
RFI 74: Please provide approved products for duct security barriers in details 10 & 11 on M-501, or confirm these will have to be custom fabricated?
Refer to Schedule on Sheet M‑701 for approved products for duct security barriers On M-701 Schedule
RFI 75: It is noted that the specifications state that it is strongly suggested that a full arc flash hazard analysis be conducted. Does this apply only to the electrical panels that affect this scope of work?
A study is not required due to the limited scope of work on this project.
RFI 76: What is the intent on the lighting controls for the Out Patient Pharmacy Room A119? Please advise?
The lighting control intent is to have dimmable controls and allow the egress powered lighting fixture to be switched via ul 924 relay. These lights will be automatically turned off with the occupancy sensor after a period of no physical motion or sound detected in the room.
RFI 77: Please clarify if contractor or VA IT is responsible for network switch configuration and cybersecurity compliance?
The successful vendor shall submit all documentation of proposed systems for formal review and approval by VA IT. Any configuration of network switches will be by the VA IT but shall be coordinated by the successful vendor(s) responsible for their respective system.
RFI 78: Is the contractor responsible for hiring the VA furniture Vendor or will the VA contract directly with the furniture vendor?
The Contractor is responsible for coordinating with and hiring the VA’s approved furniture vendor.
RFI 79: On Page 13 of the Solicitation it indicates that Exhibit C is to be used for Factor 3 past performance (if applicable), however it also states that Exhibit C is to be used in Factor 2, Subfactor 2b - Subcontractors. If the Prime contractors does not intend to use any subcontractor’s past performance, does the Prime contractor still have to submit Exhibit C in Factor 2, Subfactor 2b?
Yes, Exhibit C is required for the evaluation of subcontractors unless you identify as self-performing for specific trades.
RFI 80: In the price schedule, Alternate No.2 currently includes “delete the dismantling, removal, storage, and reassembly of the Pill Dispensing units located in the same area.” Will the VA please provide details for the Pill Dispensing units: manufacturer, cut sheets, shop drawings, installation instructions, etc. so the contractor will know how much work is required to disassemble and reassemble?
Pill Dispensing units will not be disassembled.
RFI 81: Are we to include the 1st page of the past performance questionnaires in our proposal to show proof that they were sent out?
This is not required.
RFI 82: Can the bid date for the project be extended to provide more time for contractors?
See Block 11.
RFI 83: Can a second round of RFIs be submitted once the initial RFI answers are provided as usually these answers call for more clarifications in most cases?
Due to time constraints additional questions will not be accepted.
RFI 84: Does the laydown area need to be fenced in?
Yes RFI 85: If damage to finishes surrounding work occurs who needs to make repair?
Contractor is responsible for repairing any of these damages.
image1.png