This is an Amendment to Solicitation/Modification of Contract (SF 30) issued by the Department of Veterans Affairs Veterans Health Administration Network Contracting Office on behalf of the Central Arkansas Veterans Healthcare System (CAVHS) in Little Rock, Arkansas. The amendment incorporates questions and answers from a site visit conducted on January 12, 2026, and replaces the original Statement of Work with a revised version dated January 21, 2026.
The contract requires a contractor to furnish all labor, materials, tools, equipment, and transportation to remove existing epoxy coating from the floor, base, and walls of Operating Room #17 at John L. McClellan Memorial Veterans Hospital (4300 West 7th Street, Little Rock, AR 72205) and apply a new epoxy coating. The project includes two epoxy colors—one for the center section and one for edges and wall borders. All work must be performed on weekends (Saturday and Sunday) only, scheduled within one week of contract award and approved by the VA Contracting Officer's Representative (COR). Equipment delivery is due within 30 days of award, Monday through Friday, 8 a.m. to 4:30 p.m., with 48-hour advance scheduling. The VA will provide ICRA barriers, negative air equipment, door storage, furniture removal, electrician support, and a POC to accompany contractors. The contractor must maintain an onsite supervisor at all times during work in the operating room. Payment follows delivery, installation, testing, and government acceptance, with invoices submitted after completion. The contract includes standard VA confidentiality, privacy, records management, and information security requirements applicable to all contractor personnel.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25626Q0260 0005.docx | DOCX document | |
| 36C25626Q0260 0003.docx | DOCX document | |
| 36C25626Q0260 0002.docx | DOCX document | |
| LR-01-02AR.pdf | ||
| 36C25626Q0260 0001.docx | DOCX document | |
| Wage Determination No 2015-5117.pdf | ||
| OR 17 Epoxy floor repair - SOW.docx | DOCX document | |
| 36C25626Q0260.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25626Q0260 – OR #17 Epoxy Floor Repairs | AVCOR RFIs
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) None Department of Veterans Affairs Veterans Health Administration Network Contracting Office 16 715 S. Pear Orchard Rd.
Ridgeland MS 39157 See block 6
To all Offerors/Bidders
36C25626Q0260
X X X The purpose of this amendment is to post Q&A from site visit and post the revised Statement of Work.
A. The attached questions and answers are hereby incorporated onto subject solicitation.
B. Replace the solicitations Statement of Work and replace it with the attached Statement of Work dated 1/21/2026.
C. All other terms and conditions remain unchanged.
Joseph Warren Contracting Officer
CONTINUATION PAGE
1. How long is the warranty period requested for this requirement? 1 year
2. Does the VA require an onsite superintendent to be at the job site at all times for this project?
Yes the contractor is required to be supervised while in the Operating rooms
3. Will the VA have all furniture and storage materials removed from the space or is it the responsibility of the contractor?
Yes, all materials will be removed by the VA
4. Will the VA prefer the floor under the desk to be epoxied?
Yes
5. In the below picture, the wire guard trim molding is circled. Will the contractor be responsible for replacing the existing molding once the epoxy floor has been completed?
No
6. The statement of work requires the contractor to remove the doors for better accessibility. Does the VA have a storage location for the doors once they are removed?
Yes.
7. Will any door hardware or electrical mechanisms need to be removed from the doors?
The VA will provide ICRA barriers and negative air for this project
8. Can the Contractor perform a localized electrical shutdown by turning off breakers for OR#17 to allow all wall-mounted outlets and switches to be unscrewed from the walls and prepped before the epoxy installation? Yes with the aid of our electricians
9. What is the maximum length run from the OR to the nearest window the Contractor can run flex duct for the negative air machine?
The VA will provide ICRA barriers and negative air for this project
10. For the negative air requirements, can the flex duct located outside of the OR be suspended from the ceiling grid, so the floor remains clear of obstructions?
See previous responses regarding ICRA requirements
11. If the flex duct cannot be suspended from the ceiling grid, it will have to be placed on the floor, which will shutdown that section of the corridor. Is the VA willing to allow the contractor to shutdown that section of the corridor if the flex duct has to be placed on the floor?
12. Will the VA confirm that there will be two (2) epoxy colors chosen for this project? One (1) for the center section of the floor and one (1) for the edges and wall border? See below for reference:
That’s correct
13. Removing the existing epoxy flooring will generate noise and vibrations. Are there any adjacent clinics that require quiet hours during which epoxy removal or replacement cannot take place?
Work will need to be done on weekends. The VA will provide a POC to accompany contractors during work
14. What is the max depth of the anteroom for the ICRA requirements? How far out into the corridor can the anteroom sit?
See previous responses regarding ICRA requirements
REVISED STATEMENT OF WORK
1/21/2026 OR #17 Epoxy Floor Repair John L. McClellan Memorial Veterans Hospital Central Arkansas Veterans Healthcare System (CAVHS) Little Rock, AR
1. Background: The flooring for Operating Room #17 in 2C is chipping due to wear and tear. The epoxy in the center of the room has cracked open, exposing the layer underneath. The room is currently not being operated in until the epoxy flooring is repaired.
2. Scope: The contractor shall furnish all labor, materials, tools, equipment, transportation to remove existing coating on the floor, base and walls and apply a new coat in John L. McClellan Memorial Veterans Hospital at 4300 West 7th Street Little Rock, AR 72205.
3. Delivery: Vendor shall deliver equipment no later than 30-days from the date of award.
One unit to be delivered to each of the following sites Monday – Friday (Excluding National Holidays), 8am – 4:30pm:
Central Arkansas Veterans Healthcare System 4300 West 7th street Little Rock, AR. 72205
4. Delivery Hours: All deliveries shall be scheduled 48 hours in advance. Deliveries pertaining to this contract will need to be performed Monday through Friday unless a Federal holiday falls on one of these days. Typical hours are between 8am and 4pm. If delivery is required outside of these hours of operations, it must be coordinated with the project Contracting Officer’s Representative (COR). On the days listed below delivery shall not be scheduled unless unique situations arise and prior approval between the delivery and CAVHS parties involved is agreed upon.
5. Scheduling Arrangements: Scheduled work will be performed only during weekends. (Saturday and Sunday) Contractor shall schedule all work within 1 week of contract award, approved by VA COR.
6. Government Observed Holidays: The Government hereby provides notice, and Contractor hereby acknowledges receipt that Government personnel observe the listed days as holidays:
| New Year's Day | January 1 | ||||
| Martin Luther King's Birthday | Third Monday in January | ||||
| President's Birthday | Third Monday in February | ||||
| Memorial Day | Last Monday in May | ||||
| Juneteenth National Independence Day | June 19 | ||||
| Independence Day | July 4 | ||||
| Labor Day | First Monday in September | ||||
| Columbus Day | Second Monday in October | ||||
| Veterans Day | November 11 | ||||
| Thanksgiving Day | Fourth Thursday in November | ||||
| Christmas | December 25 |
In addition to the days designated as holidays, the Government observes the following days:
1. Any other day designated by Executive Order.
2. Any other day designated by the President’s Proclamation; and
3. Any other day designated by the Federal Statute.
7. Changes to the Statement of Work: The Contracting Officer is the only person authorized to approve changes or modify any of the requirements under this contract and such changes will be executed bi-laterally in accordance with FAR 52.212-4(c). The Contractor shall communicate with the Contracting Officer on all matters pertaining to contract administration. Only the Contracting Officer is authorized to make commitments or issue changes, which will affect price, quantity, or quality of performance of this contract. In the event the contractor effects any such change at the direction of any person other than the Contracting Officer, the change shall be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof. Costs incurred by the contractor through the actions of parties other than the Contracting Officer shall be borne by the contractor.
8. Invoicing/Payment: Contractor shall submit invoices after delivery, installation, testing and acceptance by government representative. No advance payments shall be authorized. A proper invoice must include:
a) Name and address of Contractor
b) Facility’s name and address where supply was delivered
c) Invoice date
d) Contract number and Purchase Order (PO) number
e) Contract Line-Item Number (LIN)
f) Description, quantity, unit of measure, unit price and total price of item(s) ordered.
g) Name and address of authorized official to whom payment is to be sent.
h) Name, title, phone number, email of person to be notified if invoice is defective.
9. Delivery Location: Central Arkansas Veterans Healthcare System 4300 West 7th street Little Rock, AR. 72205
10. Confidentiality and nondisclosure: The contractor understands and agrees that confidential information (patients, employee, or facility) must always be secured and protected. The contractor r and its personnel shall be held liable in the event a breach of confidentiality occurs as a result of the Supplier or its employees. Each contract employee will be required to read and sign the Contractor Rules of Behavior and provide the original signature page to the COR.
11. Information System Officer /Protection: The Supplier will not have access to VA Desktop computers, nor will they have access to online resources belonging to the government while conducting services.
12. Privacy Officer: The contractor will not have access to protected Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA.
13. RECORDS MANAGER:
13.1. Supplier shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. Chapters. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
13.2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
13.3. In accordance with 36 CFR 1222.32, Supplier shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
13.4. Central Arkansas Veterans Healthcare System and its contractors/suppliers are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of Central Arkansas Veterans Healthcare System or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Supplier must report to Central Arkansas Veterans Healthcare System. The agency must report promptly to NARA in accordance with 36 CFR 1230.
13.5. The Supplier shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Supplier shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Supplier shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government's behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to Central Arkansas Veterans Healthcare System control or the Supplier must hold it until otherwise directed. Items returned to the Government shall be hand-carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
13.6. The Supplier is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Supplier (and any sub-contractor) is required to abide by Government and Central Arkansas Veterans Healthcare system guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
13.7. The Supplier shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with Central Arkansas Veterans Healthcare System policy.
13.8. The Supplier shall not create or maintain any records containing any non-public Central Arkansas Veterans Healthcare System information that are not specifically tied to or authorized by the contract.
13.9. The Supplier shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
13.10. The Central Arkansas Veterans Healthcare System owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which Central Arkansas Veterans Healthcare System shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Supplier rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
Post Q&A from site visit and post revised SOW.
Page 1 of image1.png image2.png
File details come from the government source that posted it. Updated .