36C25625R0126 667-25-190 ICRA - ISO Valves.pdf

PDF 167 KB Posted

Attached to
Z2DA--Project 667-25-190 Install Isolation Valves, B1 (Con) Federal contract opportunity
Solicitation number
36C25625R0126
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document is an Infection Prevention & Control document for the Overton Brooks VA Medical Center, detailing construction and renovation project guidelines for installing isolation valves on the domestic water system in Building 1, dated 02/06/2025. The document outlines four construction project types (Type A through Type D) with increasing complexity and potential for dust/debris generation, ranging from simple inspection activities to major demolition and construction work. A risk matrix categorizes patient areas into four risk levels (Low, Medium, High, Highest Risk), with corresponding infection control precaution classes (I-V) based on the construction type and patient risk area. The matrix provides a systematic approach for managing infection control during construction activities, with specific guidance for different areas like public hallways, patient care rooms, operating suites, and specialized units such as transplant and oncology areas. The document requires selecting the appropriate precaution class and includes provisions for environmental conditions that could affect human health.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project 667-25-190 Install Isolation Valves, B1 (Con), newest first.
File Type Posted
36C25625R0126 0002.docx DOCX document
RFI Register 667-25-190_Install Iso Valves 090225.docx DOCX document
Sign in Sheet 667-25-190.pdf PDF
36C25625R0126 0001.docx DOCX document
36C25625R0126 667-25-190 Combined Specs 02102025.pdf PDF
36C25625R0126 667-25-190 Class IV Precautions - ISO Valves .pdf PDF
36C25625R0126 EXHIBIT E.docx DOCX document
36C25625R0126 EXHIBIT F.docx DOCX document
36C25625R0126 EXHIBIT C.docx DOCX document
36C25625R0126 EXHIBIT A.docx DOCX document
36C25625R0126 667-25-190 ISO Valves - Drawings.pdf PDF
36C25625R0125 WD LA20250031 070425.pdf PDF
36C25625R0126 EXHIBIT D.docx DOCX document
36C25625R0126 667-25-190 BLDG 1 Asbestos Report.pdf PDF
36C25625R0126 667-25-190 SOW 02102025 .doc DOC document
36C25625R0126.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VA Medical Center Infection Prevention & Control

Step One: Install Isolation Valves on Domestic Water System Building 1 Date: 02/06/2025

Type A

Inspection and non-invasive activities. Includes but is not limited to:

• Removal of ceiling tile for visual inspection-limited to 1 tile/50 square feet with limited exposure time.

• Limited building system maintenance (e.g., pneumatic tube station, HVAC, fire suppression system, electrical and carpentry work to include painting without sanding) that does not create dust or debris.

• Clean plumbing activity limited in nature.

Type B

Small-scale, short duration activities; minimal dust and debris. Includes but not limited to:

• Work conducted above the ceiling (e.g., prolonged inspection/repair of firewalls and barriers, install conduit/cabling, & access to mechanical and/or electrical chase spaces).

• Fan shutdown/startup.

• Installation of electrical devices or new flooring that produces minimal dust and debris.

• The removal of drywall where minimal dust and debris is created.

• Controlled sanding activities (e.g., wet or dry sanding) that produce minimal dust and debris.

Type C

Large-scale, long duration activities; moderate amount of dust and debris. Includes but not limited to:

• Removal of preexisting floor covering, walls, casework, or other building components.

• New drywall placement.

• Renovation work in a single room.

• Non-existing cable pathway or invasive electrical work above ceilings.

• The removal of drywall where a moderate amount of dust and debris is created.

• Dry sanding where a moderate amount of dust and debris is created.

• Work creating significant vibration and/or noise.

• Any activity that cannot be completed in a single work shift.

Type D

Major demolition and construction activities. Includes but is not limited to:

• Removal or replacement of building system component(s).

• Removal/installation of drywall partitions.

• Invasive large-scale new building construction.

• Renovation work in two or more rooms.

Step Two: Circle the Risk Group(s) affected. Select the higher group, when more than one group will be affected.

Low Risk* Medium Risk High Risk Highest Risk

*Not in patient care areas

• Public hallways & gathering areas

• Office areas

• Breakrooms

• Bathrooms or locker rooms

• Mechanical rooms

• EMS closets

• Waiting areas

• Clinical engineering

• Materials management.

• SPS Decon area

• Kitchen, cafeteria, gift shop, coffee shop, food kiosks.

• Patient care rooms/clinics

• All acute inpatient units

• Emergency department

• Occupation Health

• Pharmacy general areas

• Medication, clean utility & sterile supply rooms

• Imaging/diagnostic suites

• Laboratory.

• All transplant & ICUs

• All oncology units.

• OR suites & restricted areas.

• Procedural suites.

• Pharmacy compounding areas

• SPS: Prep and HLD areas

• Transfusion services.

• Dedicated isolation wards/units.

• Invasive imaging suites:

Step Three: Using the IC Matrix CIRCLE the Class of Precautions as determined by Construction Type and Patient Risk.

Construction Project Type

Patient Risk Group Type A Type B Type C Type D

IC

M a tr ix LOW Risk Group1 I II II III

MEDIUM Risk Group1 I II III2 IV2

HIGH Risk Group1 I III IV2 V2

HIGHEST Risk Group1 III IV2 V2 V2

1. Amend as follows for environmental conditions that could affect human health (i.e., sewage, mold, asbestos, gray water, and black water). Class IV Precautions for LOW and MEDIUM Risk Groups and Class V Precautions for HIGH and HIGHEST Risk Groups.

2. Infection Control documents required for Class III Precautions in Type C projects and all Class IV & V Precautions.

2025-02-06T09:00:54-0600
CAROL PHILLIPS