EXHIBIT B.docx

DOCX document 31 KB Posted

Attached to
Project 667-24-255 Building 55 Accessibility Ramp
Solicitation number
36C25625R0002
Issued by

About this file

This document is a Past and Present Performance Questionnaire for a federal contract opportunity involving an accessibility ramp project at the Overton Brooks VA Medical Center. The procurement is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a construction cost range between $250,000 and $500,000, using NAICS Code 236220. The project involves constructing an accessibility ramp at Building 55, located at 510 E. Stoner Avenue in Shreveport, Louisiana.

Key procurement details include a tentative Phase I RFP issuance date of 11-08-2024, with proposals due approximately 15 calendar days later on 11-25-2024. The anticipated contract award will occur approximately 30 calendar days after Phase II proposal receipt, with a contract performance period of 180 calendar days after the Notice to Proceed. Interested offerors must be certified SDVOSB firms registered in the System for Award Management (SAM), meet the $45M small business size standard, and submit an executed VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction with their proposal.

View the file

Other files

File Type Posted
S02 Cancel RFP 36C25625R0002 0002_2.docx DOCX document
P07 WD LA20250001 05-02-2025.pdf PDF
S02 RFP Phase II 36C25625R0002 0002 06-06-2025.pdf PDF
S06 RFIs 04-10-2025.pdf PDF
S06 667-24-255 Topography-Grading_RFI Answer.pdf PDF
S06 36C25625R0002 0001.pdf PDF
S02 Wage Determination 667-24-255 -01-03-2025.pdf PDF
EXHIBIT C.docx DOCX document
S02 2016-03-21 Utilities Drawing.pdf PDF
S02 SOW 10-03-2024.pdf PDF
EXHIBIT E.docx DOCX document
EXHIBIT D.docx DOCX document
EXHIBIT F.docx DOCX document
EXHIBIT A.docx DOCX document
S02 RFP 36C25625R0002_1 03-25-2025.pdf PDF
S02 B55 Ramp-Existing Drawing.pdf PDF
P09 2016-03-21 Utilities Drawing.pdf PDF
P09 Statement of Work_Bldg 55 Ramp 08-14-2024.docx DOCX document
P09 B55 Ramp-Existing Drawing.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

Source Selection Sensitive Information—See FAR 2.101 & 3.104 Project No. 667-24-255 Bldg. 55 Accessibility Ramp 36C25625R0002

EXHIBIT B

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

INSTRUCTIONS TO CONTRACTOR

Complete the CONTRACTOR INFORMATION section, below (type answers into light blue shaded boxes). Save the document. Send an electronic or hard copy print of the form to each of your reference contacts, asking them to please complete the form and submit it according to the instructions, below.

INSTRUCTIONS TO REFERENCE CONTACT

The contractor named below is submitting an offer for a United States Department of Veterans Affairs contract requirement, and has sent this form to you, in your role as a past performance reference contact. Please complete this form in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contract Specialist via postal mail or email, directly to:

Department of Veterans Affairs NCO 16 Contracting Office Gulf Coast Veterans Health Care System ATTN: Tammy Tynes REF: 36C25625R0002 400 Veterans Avenue (NCO 16) Biloxi, MS 39531-2410 Email Address (preferred): Tammy.Tynes@va.gov

Please return the completed form no later than the time set for receipt of proposals. If you have any questions, please contact Tammy Saxon via email. Thank you for your assistance in this matter.

GENERAL INFORMATION [completed by Contractor]

Contractor Company Name

Street Address

Contractor Point of Contact Name

City

Point of Contact Phone Number

State

Reference Project Title

Zip Code

Contract Period of Performance (start to finish):

Email

Contract Number

Contract Dollar Value

Description of Work

Role of Contractor on This Project (check appropriate box) ☐ Prime Contractor ☐ Sub-contractor ☐ Key Personnel

RESPONDENT INFORMATION [completed by Reference Contact]

Company Name

Street Address

POC Name

City

Phone Number

State

Fax Number

Zip Code

Email

PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 6 that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF 1 OR 2 in the Remarks section, below (text box will expand to whatever extent is necessary).

1
2
3
4
5
6
UNSATISFACTORY
MARGINAL
SATISFACTORY
VERY GOOD
EXCEPTIONAL
NEUTRAL
Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective.
Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective.
Performance met contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory.
Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner.
Performance met all contract requirements and exceeded many to the government’s benefit. Problems, if any, were negligible and were resolved in a timely, highly effective manner.
No record of past performance or the record is inconclusive.[endnoteRef:1] [1: ]
The Contractor …
1
2
3
4
5
6
1.
Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
☐☐☐☐☐☐
2.
Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.
☐☐☐☐☐☐
3.
Delegated authority to project managers and supervisors commensurate with contract requirements.
☐☐☐☐☐☐
4.
Home office participated in solving significant local problems.
☐☐☐☐☐☐
5.
Followed approved quality control plan.
☐☐☐☐☐☐
6.
Provided effective quality control and/or inspection procedures to meet contract requirements.
☐☐☐☐☐☐
7.
Corrected deficiencies in timely manner and pursuant to their quality control procedures.
☐☐☐☐☐☐
8.
Provided timely resolution of contract discrepancies
☐☐☐☐☐☐
9.
Identified problems as they occurred.
☐☐☐☐☐☐
10.
Suggested alternative approaches to problems.
☐☐☐☐☐☐
11.
Displayed initiative to solve problems.
☐☐☐☐☐☐
12.
Developed realistic progress schedules.
☐☐☐☐☐☐
13.
Met established project schedules.
☐☐☐☐☐☐
14.
Provided timely resolution of warranty defects.
☐☐☐☐☐☐
15.
Was responsive to contract changes.
☐☐☐☐☐☐
16.
Provided adequate project supervision.
☐☐☐☐☐☐
17.
Obtained consent of surety for increases in bonding as work-in-progress increased.
☐☐☐☐☐☐
18.
Paid subcontractors/suppliers in a timely manner.
☐☐☐☐☐☐
19.
Provided accurate and complete line item cost proposals including all aspects of work required for each task.
☐☐☐☐☐☐
20.
Cooperated with Government personnel after award.
☐☐☐☐☐☐
21.
How would you rate the contractor's overall performance?
☐☐☐☐☐☐
22.
Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
☐YES
☐NO
23
Would you award another contract to this contractor? If not, please explain in “remarks.”
☐YES
☐NO
24
To the best of your knowledge, is the contractor rated in CPARS?
☐YES
☐NO

REMARKS (Please use as much space as is needed – the box will expand as you type).

File details come from the government source that posted it. Updated .