36C25625R0001 Specifications 06192024 .pdf

PDF 3 MB Posted

Attached to
Z1DZ--Project #502-17-102 Replace Roof & HVAC Building 9 (Con)
Solicitation number
36C25625R0001
Issued by

About this file

This is a specifications document for a construction project at the Alexandria VA Health Care System in Pineville, LA to replace the roof and HVAC system in Building 9. The project involves replacing three attic air handling units and all fan coil units throughout the three-story Mental Health facility with new AHUs and variable volume air terminals, requiring replacement of all building ceilings. A new DDC control system will be installed to replace the existing system.

The work will be completed in four phases over approximately 28 months total: Phase 1 (2 months) involves installing temporary equipment; Phase 2 (10 months plus 2 months for VA relocation) covers attic and third floor renovations; Phase 3 (6 months) addresses second floor renovations; and Phase 4 (8 months total) includes first floor renovations and removal of temporary equipment. The contractor must maintain indoor temperatures between 70-75°F in occupied areas throughout construction. The project requires compliance with VA Design Guide for Mental Health Facilities standards and includes detailed requirements for construction security, safety protocols, documentation through photographic progression tracking, and coordination with VA operations to minimize disruption to the functioning medical facility.

View the file

Other files

File Type Posted
36C25625R0001 0006.docx DOCX document
36C25625R0001 0005.docx DOCX document
M-803.pdf PDF
M-112.4.pdf PDF
GI001.pdf PDF
232113 02-2020 Hydronic Piping.pdf PDF
M-801.pdf PDF
M-802.pdf PDF
36C25625R0001 0004.docx DOCX document
000115 07-2015 List of Drawing Sheets.pdf PDF
502-17-102 Running RFI Register 01152025 v2.docx DOCX document
232213 02-2020 Steam and Condensate Heating Piping.pdf PDF
36C25625R0001 0003.docx DOCX document
36C25625R0001 0002.docx DOCX document
502-17-102 Site Visit Sign in Sheet.jpg JPG image
36C25625R0001 0001.docx DOCX document
36C25625R0001 Drawing 1 - Copy.pdf PDF
36C25625R0001 RFP.docx DOCX document
36C25625R0001 Drawing M111.4 - Copy.pdf PDF
36C25625R0001 EXHIBIT B.docx DOCX document
36C25625R0001 Drawing M404 - Copy.pdf PDF
36C25625R0001 Drawing 3 - Copy.pdf PDF
36C25625R0001 Drawing 2 - Copy.pdf PDF
36C25625R0001 EXHIBIT D.docx DOCX document
36C25625R0001 EXHIBIT C.docx DOCX document
36C25625R0001 Drawing M502 - Copy.pdf PDF
36C25625R0001 Brand Name JA 10182024 Signed v2_Redacted.pdf PDF
36C25625R0001 Drawing M501 - Copy.pdf PDF
36C25625R0001 Drawing 9 - Copy.pdf PDF
36C25624R0001 WD LA30240051 Mod 2 07192024.pdf PDF
36C25625R0001 Drawing 5 - Copy.pdf PDF
36C25625R0001 Drawing M401 - Copy.pdf PDF
36C25625R0001 Drawing M402 - Copy.pdf PDF
36C25625R0001 EXHIBIT A.docx DOCX document
36C25625R0001 EXHIBIT F.docx DOCX document
36C25625R0001 Drawing 8 - Copy.pdf PDF
36C25625R0001 SOW 11222024 - Copy.docx DOCX document
36C25625R0001 Drawing M403 - Copy.pdf PDF
36C25625R0001 Drawing M405 - Copy.pdf PDF
36C25625R0001 EXHIBIT E.docx DOCX document
36C25625R0001 Drawing 7 - Copy.pdf PDF
36C25625R0001 Drawing 6 - Copy.pdf PDF
36C25625R0001 Drawing 4 - Copy.pdf PDF
36C25625R0001 PRA - Copy.pdf PDF
36C25625R0001 Drawing 10 - Copy.pdf PDF
36C25625R0001 Drawing M122.3 - Copy.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID DOCUMENTS

SPECIFICATIONS

REPLACE ROOF AND HVAC SYSTEM IN BUILDING 9

Project No. 502-17-102

Alexandria VA Health Care System Pineville, LA

Miller-Remick LLC 1010 Kings Highway South

Building Two – 2nd Floor Cherry Hill, New Jersey 08034

(856) 429-4000

August 10, 2020

Department of Veterans Affairs VA Project No. 502-17-102 Alexandria VA Health Care System Replace Roof and HVAC System in Bldg. 9 Pineville, LA Bid Documents: 08/10/20

03-01-20

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 Alexandria General Requirements 03-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 33 23.10 Submittal Register 01 35 26 Safety Requirements 03-20 01 42 19 Reference Standards 09-19 01 45 00 Quality Control 03-19 01 45 00.10 QCR Example Form 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 02-16

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17 06 16 63 Cementitious Sheathing 02-16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 02-16 07 21 13 Thermal Insulation 10-17 07 22 00 Roof and Deck Insulation 02-16 07 32 13 Clay Roof Tiles 02-16

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 08-16 07 60 00 Flashing and Sheet Metal 07-14 07 71 00 Roof Specialties 10-15 07 72 00 Roof Accessories 10-15 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 31 13 Access Doors and Frames 02-16 08 90 00 Louvers and Vents 05-15

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 06-18 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 19 Resilient Tile Flooring 05-18 09 68 00 Carpeting 10-15 09 91 00 Painting 01-16

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 02-20 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 02-20

00 01 10-3

SECTION NO. DIVISION AND SECTION TITLES DATE

23 21 23 Hydronic Pumps 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 25 00 HVAC Water Treatment 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 73 00 Indoor Central-Station Air-Handling Units 03-20 23 82 16 Air Coils 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 41 00 Facility Lightning Protection 01-17

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm 10-11

00 01 10-4

Page Intentionally Left Blank

07-01-15

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI001 COVER SHEET & DRAWING INDEX

GI002 CONSTRUCTION LOGISTICS PLAN

GC101 INFECTION CONTROL & PHASING PLAN

STRUCTURAL

S-001 ABBREVIATIONS & NOTES

SF111 FRAMING PLAN 1ST FLOOR

SF121 FRAMING PLAN 2ND FLOOR

SF131 FRAMING PLAN 3RD FLOOR

SF141 FRAMING PLAN ATTIC

SF151 FRAMING PLAN ROOF

S-501 SECTIONS & DETAILS

S-502 SECTIONS & DETAILS

ARCHITECTURAL

A-001 SYMBOLS, ABBREVIATIONS, & WALL TYPES

AD111.1 PHASE 1 – COORDINATION PLAN 1ST FLOOR

AD121.1 PHASE 1 – COORDINATION PLAN 2ND FLOOR

AD131.2 PHASE 2 – DEMOLITION PLAN 3RD FLOOR

AD132.2 PHASE 2 – DEMOLITION CEILING PLAN 3RD FLOOR

AD141.2 PHASE 2 – DEMOLITION PLAN ATTIC

AD151.2 PHASE 2 – DEMOLITION PLAN ROOF

AD121.3 PHASE 3 – DEMOLITION PLAN 2ND FLOOR

AD122.3 PHASE 3 – DEMOLITION CEILING PLAN 2ND FLOOR

AD111.4 PHASE 4 – DEMOLITION PLAN 1ST FLOOR

AD112.4 PHASE 4 – DEMOLITION CEILING PLAN 1ST FLOOR

00 01 15 - 2

AS131.2 PHASE 2 – FLOOR PLAN 3RD FLOOR & FINISH SCHEDULE

AS132.2 PHASE 2 – CEILING PLAN 3RD FLOOR

AS141.2 PHASE 2 – ATTIC PLAN

AS151.2 PHASE 2 – ROOF PLAN

AS121.3 PHASE 3 – FLOOR PLAN 2ND FLOOR

AS122.3 PHASE 3 – CEILING PLAN 2ND FLOOR

AS111.4 PHASE 4 – FLOOR PLAN 1ST FLOOR

AS112.4 PHASE 4 – CEILING PLAN 1ST FLOOR

A-301 EXTERIOR ELEVATIONS

A-401 ENLARGED SHAFT DETAILS

A-501 ROOF DETAILS

FIRE PROTECTION

F-001 DETAILS, GENERAL NOTES & LEGEND

FX111 PLAN 1ST FLOOR

FX121 PLAN 2ND FLOOR

FX131 PLAN 3RD FLOOR

FX141 PLAN ATTIC

MECHANICAL

M-001 ABBREVIATIONS, NOTES, & SYMBOLS

M-011.1 PHASE 1 - TEMPORARY DUCTWORK & PIPING PLAN 1ST FLOOR

M-021.1 PHASE 1 - TEMPORARY DUCTWORK & PIPING PLAN 2ND FLOOR

M-301.1 PHASE 1 - TEMPORARY DUCTWORK & PIPING DIAGRAM

M-301.2 PHASE 2 - DUCTWORK & PIPING DIAGRAMS

M-301.3 PHASE 3 - DUCTWORK & PIPING DIAGRAMS

M-301.4 PHASE 4 - DUCTWORK & PIPING DIAGRAMS

MD131.2 PHASE 2 - DEMOLITION DUCTWORK & PIPING PLAN 3RD FLOOR

MD132.2 PHASE 2 - DEMOLITION DUCTWORK & PIPING PLAN 3RD FLOOR

MD133.2 PHASE 2 - DEMOLITION PLAN 3RD FLOOR SHAFT WORK

MD141.2 PHASE 2 - DEMOLITION DUCTWORK & PIPING PLAN ATTIC

MD142.2 PHASE 2 - DEMOLITION DUCTWORK & PIPING PLAN ATTIC

MD121.3 PHASE 3 - DEMOLITION DUCTWORK & PIPING PLAN 2ND FLOOR

MD122.3 PHASE 3 - DEMOLITION DUCTWORK & PIPING PLAN 2ND FLOOR

MD123.3 PHASE 3 - DEMOLITION PLAN 2ND FLOOR SHAFT WORK

00 01 15 - 3

MD111.4 PHASE 4 - DEMOLITION DUCTWORK & PIPING PLAN 1ST FLOOR

MD112.4 PHASE 4 - DEMOLITION DUCTWORK & PIPING PLAN 1ST FLOOR

M-131.2 PHASE 2 - PARTIAL DUCTWORK & PIPING PLAN 3RD FLOOR

M-132.2 PHASE 2 - PARTIAL DUCTWORK & PIPING PLAN 3RD FLOOR

M-141.2 PHASE 2 - PARTIAL DUCTWORK & PIPING PLAN ATTIC

M-142.2 PHASE 2 - PARTIAL DUCTWORK & PIPING PLAN ATTIC

M-121.3 PHASE 3 - PARTIAL DUCTWORK & PIPING PLAN 2ND FLOOR

M-122.3 PHASE 3 - PARTIAL DUCTWORK & PIPING PLAN 2ND FLOOR

M-111.4 PHASE 4 - PARTIAL DUCTWORK & PIPING PLAN 1ST FLOOR

M-112.4 PHASE 4 - PARTIAL DUCTWORK & PIPING PLAN 1ST FLOOR

M-401 ENLARGED PLANS

M-402 ENLARGED PLANS

M-403 ENLARGED PLANS

M-404 ENLARGED PLANS

M-405 SECTIONSM-501

M-501 DETAILS

M-502 DETAILS

M-503 DETAILS

M-504 DETAILS

M-505 DETAILS

M-701 SCHEDULES

M-702 SCHEDULES

M-703 SCHEDULES

M-801 CONTROLS ABBREVIATIONS, NOTES, & SYMBOLS

M-802 CONTROLS AIR HANDLING UNIT DIAGRAM

ELECTRICAL

E-001 ABBREVIATIONS & SYMBOLS

E-002 NOTES

ED111 DEMOLITION PLAN 1ST FLOOR

ED121 DEMOLITION PLAN 2ND FLOOR

ED131 DEMOLITION PLAN 3RD FLOOR

ED141 DEMOLITION PLAN ATTIC

ED151 DEMOLITION PLAN ROOF

E-111 PLAN 1ST FLOOR

00 01 15 - 4

E-121 PLAN 2ND FLOOR

E-131 PLAN 3RD FLOOR

E-141 PLAN ATTIC

E-151 PLAN ROOF

E-501 DETAILS

E-601 SINGLE LINE DIAGRAM

E-701 SCHEDULES

E-702 SCHEDULES

- - - E N D - - -

10-01-17 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 USE OF ROADWAYS

1.16 RESIDENT ENGINEER'S FIELD OFFICE

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.18 TEMPORARY USE OF EXISTING ELEVATORS

1.19 TEMPORARY USE OF NEW ELEVATORS

1.20 TEMPORARY TOILETS

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

1.22 NEW TELEPHONE EQUIPMENT

1.23 TESTS

1.24 INSTRUCTIONS

1.25 GOVERNMENT-FURNISHED PROPERTY

ii

1.26 RELOCATED EQUIPMENT / ITEMS

1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT

1.28 CONSTRUCTION SIGN

1.29 SAFETY SIGN

1.30 PHOTOGRAPHIC DOCUMENTATION

1.31 FINAL ELEVATION DIGITAL IMAGES

1.32 HISTORIC PRESERVATION

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the “Replace Roof and HVAC

System in Building 9” project at the Alexandria VA Health Care System

(VAHCS) in Pineville, LA as required by drawings and specifications.

B. Offices of Miller-Remick LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: All work as required by drawings and specifications, including general construction, demolition and alteration of existing construction, structural, mechanical, electrical, plumbing, fire protection, utility systems, necessary

01 00 00 - 2 alteration of existing structure and construction, and certain other items.

Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project.

The project will provide for the replacement of Building 9’s roof and

HVAC system. Building 9 consists of three floors and an attic space currently housing the Alexandria VAHCS’s Mental Health facility. As part of the project, the (3) Attic air handling units (AHUs) and all fan coil units located throughout the building shall be replaced with new AHUs and new variable volume air terminals, which will require the replacement of all building ceilings. A new DDC control system will also be installed to replace the existing system.

The project will require phased construction in accordance with the latest DVA guidelines and VHA directives and will require the use of temporary equipment to allow for operations to continue in the building during construction. Work is to follow the requirements of the latest edition of the VA Design Guide for Mental Health Facilities and is to be completed as follows and as indicated on drawings:

Phase 1: All work to be completed within “Phase 1” as indicated on the drawings. Phase 1 includes all work associated with the installation of temporary equipment to remain throughout construction. Shaft work within Phase 1 will need to be staggered to allow for temporary relocation of first floor staff and second floor patients and staff to be coordinated with the VA. Work within Phase 1 will require evening and weekend shutdowns of building systems to be coordinated with VA.

Estimated Phase Construction Duration - 2 months

Phase II: All work to be completed within “Phase 2” as indicated on the drawings. Phase 2 includes all work associated with renovating the attic and the third floor. Shaft work within Phase 2 will need to be staggered to allow for temporary relocation of second floor patients and staff to be coordinated with the VA. Work within Phase 2 will require evening and weekend shutdowns of building systems to be coordinated with VA. At completion of Phase 2, and prior to the start of Phase 3, VA to require time to allow for relocating staff and patients from the second floor to the third floor.

01 00 00 - 3

Estimated Phase Construction Duration - 10 months

Estimated VA Relocation Duration (After Phase Construction Completion)– 2 months

Phase III: All work to be completed within “Phase 3” as indicated on the drawings. Phase 3 includes all work associated with renovating the second floor. Shaft work within Phase 3 will need to be staggered to allow for temporary relocation of third floor patients and staff, and first floor staff to be coordinated with the VA. Work within Phase 3 will require evening and weekend shutdowns of building systems to be coordinated with VA.

Estimated Phase Construction Duration – 6 months

Phase IV: All work to be completed within “Phase 4”, “4A”, “4B”, and “4AB” as indicated on the drawings. Phase 4 will require work to be completed in sub-phases as indicated on the drawings and includes all work associated with renovating the first floor and the removal of the temporary equipment.

Shaft work within Phase 4 will need to be staggered to allow for temporary relocation of second floor patients and staff to be coordinated with the VA. Work within Phase 4 will require evening and weekend shutdowns of building systems to be coordinated with VA. Work within Phase 4AB to completed within Phase 4A or Phase 4B.

Estimated Phase Construction Duration – “4A” - 4 months

Estimated Phase Construction Duration – “4AB” - 1 month

Estimated Phase Construction Duration – “4B” - 3 months

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

01 00 00 - 4

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

3. The general Contractor shall install equipment for recording guard rounds to ensure systematic checking of the premises.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative(COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the

01 00 00 - 5 approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

01 00 00 - 6

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as determined by the Contracting Officers Representative (COR).

E. Workmen are subject to rules of Medical Center applicable to their conduct.

01 00 00 - 7

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

H. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the COR and Contractor.

I. Construction Fences:

1. Before construction operations begin, Contractor shall provide a chain link temporary construction privacy fence, 10 feet minimum height, around the construction area indicated on the drawings

01 00 00 - 8

(along the front of the building facing the driveway). Provide gates as required for access with necessary hardware, including hasps and padlocks. Coordinate hardware with COR. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).

Bottom of fences shall extend to 25mm (one inch) above grade.

2. Before construction operations begin, Contractor to provide 14 foot high temporary construction privacy fence, to the requirements of the latest edition of the VA Design Guide for Mental Health

Facilities, around the construction area indicated on the drawings

(at the back of the building surrounding the temporary equipment).

Provide gates as required for access with necessary hardware, including hasps and padlocks. Coordinate hardware with COR.

Contractor to follow manufacturer’s installation instructions.

3. Contractor to remove the fences when directed by the COR.

4. All areas disturbed by construction of temporary construction fences must be restored to equal or better condition than existing, prior to completion of project.

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. During construction and the use of temporary equipment, the contractor shall maintain the indoor environment throughout all occupied areas within the building, at all times, in the temperature range of 70-75°F. During construction and the use of temporary equipment, the contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) throughout all unoccupied areas within the building, at all times.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

01 00 00 - 9

K. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

Engineer/COR in writing, 7 days n advance of proposed interruption.

Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

01 00 00 - 10

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

M. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

N. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

O. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period:

01 00 00 - 11

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both to the Contracting Officer. This report shall list all conflicts and remedies to all conflicts.

1. Prior to mobilization and commencement of any construction, the contractor shall conduct a thorough survey and investigation of all the work sites for the Emergency Generator Replacement Project.

This survey and investigation shall include verifying all utilities within the sites where generators, tanks and fuel lines are to be installed, all tie-in connection points, the depth, size and material of all piping and any structures that may conflict with the proposed construction. The contractor shall be responsible for choosing the process He / She deems necessary to employ that will provide the most accurate data of the existing condition at these sites. Once this information is obtain, the contractor shall prepare a report listing all discrepancies, conflicts and remedies to all conflicts. This report shall be submitted as Submittal #1. The COR will review for technical feasibility. Once approved, the CO will request a formal proposal for the corrective work. Approval of this cost proposal will be required prior to the commencement of any corrective construction.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by the Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of the

COR, to be in such condition that their use is impossible or

01 00 00 - 12 impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-

2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and the COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

01 00 00 - 13

1. Reserved items which are to remain property of the Government are identified by attached tags as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

01 00 00 - 14

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge

Elimination System (NPDES) permit is required for this project. The

Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.

Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the

Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

- Designating areas for equipment maintenance and repair;

- Providing waste receptacles at convenient locations and provide regular collection of wastes;

- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

- Providing adequately maintained sanitary facilities.

01 00 00 - 15

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(FAR 52.236-4)

01 00 00 - 16

B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of

Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.

If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations

01 00 00 - 17 established for each such structure and/or addition are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.

Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall furnish to the

COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to the COR.

01 00 00 - 18

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property and, when authorized by the COR such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

1.16 RESIDENT ENGINEER'S FIELD OFFICE (NOT USED)

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

01 00 00 - 19

1. Permission to use each unit or system must be given by the COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

01 00 00 - 20

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.18 TEMPORARY USE OF EXISTING ELEVATORS (NOT USED)

1.19 TEMPORARY USE OF NEW ELEVATORS (NOT USED)

1.20 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by the COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

A*. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and

01 00 00 - 21 associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the

Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by…

This is the start of the file's text. The full file is on GovTribe.