580-16-102 Statement of Work.docx

DOCX document 27 KB Posted

Attached to
Y1LB--580-16-102 Road Repairs on VA Campus
Solicitation number
36C25623R0048
Issued by

About this file

This statement of work and pre-solicitation notice outline requirements for a road repair project at a Department of Veterans Affairs medical center. The project involves full depth road repairs and alterations, with work including general construction, civil works, walks, grading, drainage, mechanical, electrical work, and utility relocation. The construction documents and drawings provide additional details. Interested parties should monitor the website for solicitation release on or around February 1, 2023. The solicitation will be a request for proposals with a 90-day acceptance period. A 100% service-disabled veteran-owned small business set-aside contract is anticipated with a value between $2-5 million. The contract period is 180 calendar days, and the project must follow all applicable federal, state, and local requirements regarding construction, safety, and COVID-19 protocols.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Road Repair Project No: 580-16-102 Scope of Work 1 Foreword

1.1 Contractor shall provide all labor, materials, tools, equipment, expertise, administration, supervision, and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.

1.2 This document does not relieve the contractor of their professional responsibility to comply with all local and federal construction and environmental codes and to perform and complete a fully coordinated job.

2 General Project Description

2.1 Contractor shall completely prepare site for uninterrupted building and traffic operations, including demolition, relocation and removal of existing structures and/or utility systems, and furnish labor and materials and perform work for construction of road repairs as required by provided drawings and specifications.

2.2 Work includes general construction, full depth roads repairs and alterations, civil works, walks, grading, drainage, mechanical and electrical work, relocation of existing and/or new utility systems, and certain other items as required by provided construction documents. This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed per the plans/drawings and specifications.

2.3 Work includes specialized construction labor & supervision for civil, mechanical, electrical, and demolition work as required by provided construction documents. This Scope of Work is not considered to be a comprehensive description of work details for this project. All work shall be completed per the plans/drawings and specifications.

3 General Construction Requirements

3.1 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the VAMC. Also project/construction schedule, schedule of values/prices and construction phases have to be provided and approved by VA’s COR/Project Engineer and/or Contracting Officer.

3.2 Contractor shall completely prepare site, and furnish labor, equipment, and materials to perform work for this specific project as required by construction documents.

3.3 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.

3.4 Project Record Drawings: The Contractor will maintain a set of Record Drawings. The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process. The project record drawings will be available for review by the VA Project Manager at all times.

3.5 The following milestone dates shall be incorporated into the contractor’s schedule.

3.5.1 Submittal Schedule and log shall be provided within ten (10) calendar days after Notice to Proceed. The contractor shall provide it to the Contracting Officer’s Representative (COR) for approval, and shall include the dates for submission of Shop Drawings, Product Data, and Samples.

3.5.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within sixty (60) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 15 business days after receiving each submittal.

3.5.3 The Contractor shall submit a construction schedule within ten (10) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no lateness in the schedule shall be tolerated without the CO’s approval.

3.5.4 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.

4 General Contract Requirement

4.1 VA’s Normal Working Hours are 7:00 am to 4:30 p.m., Monday through Friday. Contractor may work earlier or later in the day, after business hours, on weekends or on Federal Holidays with prior approval from the Contracting Officer’s Representative at no additional cost to the VA.

4.2 The following legal holidays are observed by this Government Agency:

New Year's Day January 1st Martin Luther King's Birthday Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Juneteenth Independence Day June 19th Independence Day July 4th Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th and any day declared by the federal government as holiday.

5 Project Meetings

5.1 Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.

5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer (CO). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and telephone numbers; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to all attendees within 48 hours after change notice.

6 Safety and Security

6.1 Contract workers under this project may require a VA issued identification card before the start of construction work at the Houston VAMC. There is no charge for the badges; however, multiple trips to MEDVAMC facility maybe required.

6.2 Contract employees, including all subcontractor employees, must be TB tested and receive a flu shot (each year under the contract performance) if they will work within the VA Hospital Building 100. A letter from the prime contractor shall be submitted to the CO prior to work commencing that all staff members are TB negative and the flu shot was received.

6.3 All contract personnel are subject to inspection of personal effects when entering or leaving the project site.

6.4 Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for unloading equipment necessary to perform the work will be authorized in advance by the COR prior to starting the project.

6.5 Contractor shall abide by MEDVAMC’s policy for measures to prevent the spread of COVID. Policies may change during contract performance. COR and/or CO will provide updates as they are issued by the Facility Director. Contractor shall follow the CDC guidelines for COVID found here:

Coronavirus Disease 2019 (COVID-19) | CDC The contractor shall provide the name and telephone number of any employee who tests positive that was on the VA campus. Contractor shall also identify the number of contractor and subcontractor employees who had contact with the positive COVID-19 person(s) and remove/replace the employee(s) for 14 days of when the positive employee(s) was last onsite.

--- End---