321216 - Asphalt Paving.pdf

PDF 16 KB Posted

Attached to
Y1LB--580-16-102 Road Repairs on VA Campus
Solicitation number
36C25623R0048
Issued by

About this file

This document provides specifications for asphalt paving work for road repairs on the campus of the Michael E. DeBakey VA Medical Center in Houston, Texas. The specifications cover the composition, mixing, construction, and protection of hot asphalt concrete pavement, including aggregate base course, asphaltic base course, and asphalt surface course. Requirements are defined for aggregates, asphalts, sealers, mixing asphaltic concrete materials, subgrade preparation, base courses, placement of asphaltic concrete paving, application of seal coat, and protections. Related work includes laboratory testing, subgrade preparation, and pavement markings. Submittals required include data and test reports on aggregates and asphalt, job-mix formula, and certifications. A pre-solicitation notice was also provided for solicitation number 36C25623R0048 for road repairs on the VA campus, to be set aside for Service-Disabled Veteran-Owned Small Businesses. The construction value is estimated between $2-5 million, to be awarded as a firm-fixed-price contract with a 180-day period of performance. The solicitation will be issued as a request for proposals on February 1, 2023.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF VETERANS AFFAIRS

MICHAEL E. DEBAKEY VA MEDICAL CENTER

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 1

SECTION 32 12 16

ASPHALT PAVING

PART 1 - GENERAL

1.1 DESCRIPTION

This work shall cover the composition, mixing, construction upon the prepared subgrade, and the protection of hot asphalt concrete pavement.

The hot asphalt concrete pavement shall consist of an aggregate or asphalt base course and asphalt surface course constructed in conformity with the lines, grades, thickness, and cross sections as shown. Each course shall be constructed to the depth, section, or elevation required by the drawings and shall be rolled, finished, and approved before the placement of the next course.

1.2 RELATED WORK

A. Laboratory and field-testing requirements: Section 01 45 29, TESTING

LABORATORY SERVICES.

B. Subgrade Preparation: Paragraph 3.3 and Section 31 20 11, EARTHWORK

(SHORT FORM).

C. Pavement Markings: Section 32 17 23, PAVEMENT MARKINGS.

1.3 INSPECTION OF PLANT AND EQUIPMENT

The COR shall have access at all times to all parts of the material producing plants for checking the mixing operations and materials and the adequacy of the equipment in use.

1.4 ALIGNMENT AND GRADE CONTROL

The Contractor’s Registered Professional Land Surveyor shall establish and control the pavement (aggregate or asphalt base course and asphalt surface course) alignments, grades, elevations, and cross sections as shown on the Drawings.

1.5 SUBMITTALS

A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES, furnish the following:

B. Data and Test Reports:

1. Aggregate Base Course: Sources, gradation, liquid limit, plasticity index, percentage of wear, and other tests required by State Highway

Department.

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 2

2. Asphalt Base/Surface Course: Aggregate source, gradation, soundness loss, percentage of wear, and other tests required by State Highway

Department.

3. Job-mix formula.

C. Certifications:

1. Asphalt prime and tack coat material certificate of conformance to

State Highway Department requirements.

2. Asphalt cement certificate of conformance to State Highway

Department requirements.

3. Job-mix certification - Submit plant mix certification that mix equals or exceeds the State Highway Specification.

D. One copy of State Highway Department Specifications.

E. Provide MSDS (Material Safety Data Sheets) for all chemicals used on the ground.

PART 2 - PRODUCTS

2.1 GENERAL

A. Aggregate base, asphaltic base and asphalt concrete materials shall conform to the requirements of the following and other appropriate sections of the latest version of the State Highway Material

Specifications, including amendments, addenda, and errata. Where the term "Engineer" or "Commission" is referenced in the State Highway

Specifications, it shall mean the VA COR or VA Contracting Officer.

2.2 AGGREGATES

A. Provide aggregates consisting of crushed stone, gravel, sand, or other sound, durable mineral materials processed and blended, and naturally combined.

B. Subbase aggregate (where required) maximum size: 38mm(1-1/2").

C. Base aggregate maximum size:

1. Base course over 152mm(6") thick: 38mm(1-1/2");

2. Other base courses: 19mm (3/4").

D. Asphaltic base course:

1. Maximum particle size not to exceed 25.4mm (1”).

2. Where conflicts arise between this specification and the requirements in the latest version of the State Highway

Specifications, the State Specifications shall control.

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 3

E. Aggregates for asphaltic concrete paving: Provide a mixture of sand, mineral aggregate, and liquid asphalt mixed in such proportions that the percentage by weight will be within:

Sieve Sizes Percentage Passing

19mm (3/4") 100

9.5mm (3/8") 67 to 85

6.4mm (1/4") 50 to 65

2.4mm (No. 8 mesh) 37 to 50

600µm (No. 30 mesh) 15 to 25

75µm (No. 200 mesh) 3 to 8 plus 50/60 penetration liquid asphalt at 5 percent to 6-1/2 percent of the combined dry aggregates.

2.3 ASPHALTS

A. Comply with provisions of Asphalt Institute Specification SS2:

1. Asphalt cement: Penetration grade 50/60

2. Prime coat: Cut-back type, grade MC-250

3. Tack coat: Uniformly emulsified, grade SS-1H

2.4 SEALER

A. Provide a sealer consisting of suitable fibrated chemical type asphalt base binders and fillers having a container consistency suitable for troweling after thorough stirring, and containing no clay or other deleterious substance.

B. Where conflicts arise between this specification and the requirements in the latest version of the State Highway Specifications, the State

Specifications shall control.

PART 3 - EXECUTION

3.1 GENERAL

The Asphalt Concrete Paving equipment, weather limitations, job-mix formula, mixing, construction methods, compaction, finishing, tolerance, and protection shall conform to the requirements of the appropriate sections of the State Highway Specifications for the type of material specified.

3.2 MIXING ASPHALTIC CONCRETE MATERIALS

A. Provide hot plant-mixed asphaltic concrete paving materials.

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 4

1. Temperature leaving the plant: 143 degrees C(290 degrees F) minimum, 160 degrees C(320 degrees F) maximum.

2. Temperature at time of placing: 138 degrees C(280 degrees F) minimum.

3.3 SUBGRADE

A. Shape to line and grade and compact with self-propelled rollers.

B. All depressions that develop under rolling shall be filled with acceptable material and the area re-rolled.

C. Soft areas shall be removed and filled with acceptable materials and the area re-rolled.

D. Should the subgrade become rutted or displaced prior to the placing of the subbase, it shall be reworked to bring to line and grade.

E. Proof-roll the subgrade with maximum 45 tonne (50 ton) gross weight dump truck as directed by VA COR or VA Contracting Officer. If pumping, pushing, or other movement is observed, rework the area to provide a stable and compacted subgrade.

3.4 BASE COURSES

A. Subbase (when required)

1. Spread and compact to the thickness shown on the drawings.

2. Rolling shall begin at the sides and continue toward the center and shall continue until there is no movement ahead of the roller.

3. After completion of the subbase rolling there shall be no hauling over the subbase other than the delivery of material for the top course.

B. Base

1. Spread and compact to the thickness shown on the drawings.

2. Rolling shall begin at the sides and continue toward the center and shall continue until there is no movement ahead of the roller.

3. After completion of the base rolling there shall be no hauling over the base other than the delivery of material for the top course.

C. Thickness tolerance: Provide the compacted thicknesses shown on the

Drawings within a tolerance of minus 0.0mm (0.0") to plus 12.7mm

(0.5").

D. Smoothness tolerance: Provide the lines and grades shown on the

Drawings within a tolerance of 5mm in 3m (3/16 inch in ten feet).

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 5

E. Moisture content: Use only the amount of moisture needed to achieve the specified compaction.

3.5 PLACEMENT OF ASPHALTIC CONCRETE PAVING

A. Remove all loose materials from the compacted base.

B. Apply the specified prime coat, and tack coat where required, and allow to dry in accordance with the manufacturer’s recommendations as approved by the Architect or Engineer.

C. Receipt of asphaltic concrete materials:

1. Do not accept material unless it is covered with a tarpaulin until unloaded, and unless the material has a temperature of not less than

130 degrees C (280 degrees F).

2. Do not commence placement of asphaltic concrete materials when the atmospheric temperature is below 10 degrees C (50 degrees F), not during fog, rain, or other unsuitable conditions.

D. Spreading:

1. Spread material in a manner that requires the least handling.

2. Where thickness of finished paving will be 76mm (3") or less, spread in one layer.

E. Rolling:

1. After the material has been spread to the proper depth, roll until the surface is hard, smooth, unyielding, and true to the thickness and elevations shown own the drawings.

2. Roll in at least two directions until no roller marks are visible.

3. Finished paving smoothness tolerance:

a. No depressions which will retain standing water.

b. No deviation greater than 3mm in 1.8m (1/8" in six feet).

3.6 APPLICATION OF SEAL COAT

A. Prepare the surfaces, mix the seal coat material, and apply in accordance with the manufacturer’s recommendations as approved by the

Architect or Engineer.

B. Achieve a finished surface seal which, when dry and thoroughly set, is smooth, tough, resilient, of uniform black color, and free from coarse textured areas, lap marks, ridges, and other surface irregularities.

C. When sealing new asphalt paving wait an entire year to allow for the expansion and contraction of a year’s cycle of both warm and cool

HOUSTON, TEXAS

22-008 ROAD REPAIRS VA CAMPUS

100% CONSTRUCTION DOCUMENTS – ADDENDUM 1 09-01-15

32 12 16 - 6 temperatures. This allows for the asphalt’s oils to properly cure and begin oxidation before applying a seal coat.

D. When seal coating in less than a year apply two coats, spray applied.

This application method is preferred for less than a year application when there is still plenty of asphalt cement present for the seal coat to bond to.

E. When seal coating existing paving that has new asphalt patches, apply two coats sprayed to the existing asphalt and a single lighter coat on new patch work, just enough to make the color of the new patches match the rest of the reseal coated paving.//

3.7 PROTECTION

Protect the asphaltic concrete paved areas from traffic until the sealer is set and cured and does not pick up under foot or wheeled traffic.

3.8 FINAL CLEAN-UP

Remove all debris, rubbish, and excess material from the work area.

- - - E N D - - -