36C25622R0003 Pre-Award RFI Register.docx

DOCX document 211 KB Posted

Attached to
Z1DA--Project #629-22-123 Replace Flooring Various Surgery Service Areas
Solicitation number
36C25622R0003
Issued by

View the file

Other files

File Type Posted
36C25622R0003 0009.docx DOCX document
36C25622R0003 Pre-Award RFI Register 021822.docx DOCX document
36C25622R0003 Specifications 021822.docx DOCX document
36C25622R0003 Revised SOW 021822.pdf PDF
36C25622R0003 0008.docx DOCX document
36C25622R0003 SOW rev3 021422.pdf PDF
36C25622R0003 Specifications Rev2 Final 021122.pdf PDF
36C25622R0003 0007.docx DOCX document
36C25622R0003 0006.docx DOCX document
36C25622R0003 0005.docx DOCX document
36C25622R0003 0004.docx DOCX document
Pre Bid Site Visit Sign In Sheet 011222.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors rev2.docx DOCX document
SLVHCS Restricted Visitation Rules.pdf PDF
36C25622R0003 0003.docx DOCX document
36C25622R0003 0002.docx DOCX document
36C25622R0003 0001.docx DOCX document
36C25622R0003 2AI103E2 - S02.pdf PDF
36C25622R0003 EXHIBIT A.docx DOCX document
36C25622R0003 ICRA ILSM NEPA FY 22 OR Floors 081321 v3-S02.pdf PDF
36C25622R0003 EXHIBIT F.docx DOCX document
36C25622R0003 EXHIBIT D.docx DOCX document
36C25622R0003 EXHIBIT E.docx DOCX document
36C25622R0003 2AI103D2- S02.pdf PDF
36C25622R0003 SOW 10222021 - S02.pdf PDF
36C25622R0003 WDLA20210041 Mod 2 06182021 - S02.pdf PDF
36C25622R0003 EXHIBIT C.docx DOCX document
36C25622R0003 2AI103F2- S02.pdf PDF
36C25622R0003 RFP.docx DOCX document
36C25622R0003 EXHIBIT B.docx DOCX document
36C25622R0003 Specifications Final 82721 v2 - S02.pdf PDF
36C25622R0003 Pre-Sol.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 36C25622R0003 RFI Register Project 629-22-123 Replace OR/Cath Lab Flooring

RFI Question
VA Response
1. Exhibit B – Past Performance Questioner. The current form requires that the contractor sends this form to his clients and for the clients to fill out the form and send directly to the VA’s Contracting Specialist/Officer via email. This process creates additional workload for the contractor and contracting officers of multiple agencies and many small business may be at a disadvantage, if the past performance questioner is not returned in time by the contractor’s previous clients. Our suggestions: allow as equivalent submission of NAVFAC / USACE Past Performance Questionnaire (PPQ) Form PPQ -0 (See attached).
Confirmed as acceptable to use equivalent submission.
2. Manufacture Restrictions. The project is currently specified for Stonhard, Inc.; Stonres RTZ® or equivalent. Stonehard, Inc. is a large business that manufactures and installs high performance coatis and is publicly traded under RPM International Inc. (NYSE: RPM). Stonehard, Inc. does not sell its products to other flooring contractors or allows installers to work for another manufactures which limits completion and restricts small business. Our recommendation is that either Stonehard, inc. provides the Salient characteristics of Stonres RTZ® to include those qualities that are essential to ensure that the intended use can be satisfactorily realized, or (and) that the general description of those salient physical, functional, or performance characteristics of the brand name item that an "equal" item must meet to be acceptable for award are included in the solicitation. (See FAR 11.104(b))
All products shall meet all of the specifications and characteristics as defined in paragraph 2.3. If an equal product meets all of the specifications and characteristics as defined in paragraph 2.3 then it will be an acceptable equal. Color is referenced as “Stonres RTZ Solitude or Equal and STR Creek or Equal.”

3. Including other equivalent manufactures – The only manufacture included in the final specifications, Div. 096700 section 2.1(B)(1) (Page 104 of 123) is Stonhard, Inc.; Stonres RTZ®. We suggest that other manufactures of equivalent products are included in this section. Such as: 1. POLY-CRETE® MDC from Dur-A-Flex or FasTop Multi Topfloor SL23 from Sherwin Williams.

Specification Section 09 67 00 has been deleted as per Rev. 1 dated 1/25/22. The specification section 09 67 23. 30 paragraph 2.1 titled System Description For Resinous Flooring.

As indicated in the response to RFI #2, if an equal product meets all of the specifications and characteristics as defined in paragraph 2.1 then it will be an acceptable equal.

4. Please confirm the time of the site visit changed in Amendment 0001 is 1700 hrs or 5:00pm
Confirmed.
5. What machinery is considered “stationary" and must be protected/covered? Quantities?
All items mechanically fastened to the floor are considered stationary. Quantities are not known.
6. What are the sizes/dimensions and quantities of the surgery tables referenced in 2.3.1 of spec
Please see table below:
AEMS_MERS RefI
Description
Mfg Name
Model
Serial #
Location
629 MX1784888
PAIN MANAGEMENT C-ARM TABLE
Biodex Medical Systems Inc
058-640
1704433
3E220-02DT
629 MX665699
C-ARM TABLE
Biodex Medical Systems Inc
058-870
1606512
3E100B-02DT
629 MX665698
C-ARM TABLE
Biodex Medical Systems Inc
058-870
1606513
3E100A-02DT
629 MX690810
C-ARM TABLE
Biodex Medical Systems Inc
058-870
1606511
3E100C-02DT
629 EE7875831
TABLES: OPERATING, 3501C
Skytron
3501C
3501C12F163T
3E230-02DT
629 MX2539903
MIZUHO ORTHOPEDIC TABLE
Mizuho OSI
6875
2021-439571
3E220-02DT
629 MX1802759
TRIOS, TOP, SPINAL Surgical Table
Mizuho OSI
7803
679
3E127-02DT
629 MX437220
TABLES: OPERATING, AMSCO 3085 SP
STERIS Corp
AMSCO 3085 SP
0422316010
3E230.1-02DT
629 MX437217
TABLES: OPERATING, AMSCO 3085 SP
STERIS Corp
AMSCO 3085 SP
0427216012
3E226-02DT
629 MX437216
TABLES: OPERATING, AMSCO 3085 SP
STERIS Corp
AMSCO 3085 SP
0414816021
3E238-02DT
629 MX437212
TABLES: OPERATING, AMSCO 3085 SP
STERIS Corp
AMSCO 3085 SP
0427216014
3E220-02DT
629 MX437218
TABLES: OPERATING, AMSCO 3085 SP
STERIS Corp
AMSCO 3085 SP
0427216013
3E229-02DT
629 MX1784897
SURGICAL TABLE
STERIS Corp
OT 1200
0421816034
3E232-02DT
629 MX429880
TABLE, OPERATING HOSPITAL
TRUMPF Medical Systems Inc
TRUSYSTEM 7000
102897869
3E223.1-02DT
7. What is the desired pattern under the surgery tables? Is there a diagram available?
Follow currently installed layout dimensions under and surrounding the surgery tables. No diagram is available.
8. Is 480V /30 amp/ 3 phase power available in the work areas?
Yes on Level 3 in the electrical room, areas D1, E1, and F1 there are 480v, 3-phase power. If 30amp breakers are needed Contractor to provide the electrical wiring, subpanel and breakers. Also an electrical outage request is required at least 2 weeks in advance.
9. Construction schedule is listed as 60 days with work taking place only on Mon-Fri. If weekends are not allowed, schedule will be reduced by 16 days to 44 days (not considering holidays). The nature of the spec'd floor could require up to 80 days of installation/workdays (depending on desired pattern). Can schedule be revised?
Schedule Construction Completion time will be revised to 150 days. Requests to work the weekend and after normal hours can be requested and taken under review. At least a one-week notice is required for stakeholder review of the request.
10. Will the hospital staff empty all rooms, or will contractor be responsible?
The VA Surgery Service and/or Environmental Management Service will empty all rooms of moveable items and equipment.
11. Could the VA provide details on how you’d like the stationary equipment trimmed out? Some of the equipment was installed after initial construction and is set on the existing flooring. How is that to be handled?
Termination of resinous flooring at stationary items shall be in accordance with manufacturer’s installation instructions. The stationary items will remain in place during construction.
12. Is the contractor responsible for terminal cleaning? If so, who is the VA preferred vendor?
The VA Environmental Management Service is responsible for terminal cleaning. Contractor is responsible for daily cleaning.
13. Is there a phasing plan?
Phasing is to be accomplished based upon the Surgery Service scheduling. Contractor shall develop a phasing plan with VA Surgery Service and Engineering Service approval.
14. Could the VA provide an ICRA plan? There are no ante rooms on the drawings.
A preliminary ICRA has been completed as part of the project application to Contracting and was published with the solicitation. Contractor is responsible for completing the project ICRA based upon the Solicitation in particular the phasing requirements. Ante rooms are required as this is considered Project Class IV.
15. The project draft schedule has a fictitious start date of January 3, 2022. Since this date has passed will it be acceptable for contractors to use fictitious date of March 3, 2022?
Yes. Please use the fictitious date of 03/03/2022 for the draft schedule.
16. Due to the nature of the requested floors and manufacturer's recommended process for installation (removal of existing, grind/prep of substrate, two primer coats, lay mortar base, several sanding steps, multiple seal coats), 80 workdays will not be adequate time to complete the work indicated in the SOW. Given their recommendation, can the Period of Performance be extended to at least 100 workdays.
See response to RFI question 9 above.
17. The statement of work (SOW) states that “The Contractor shall provide the work in six (6) phases”. What is the anticipated down time between phases? A day, week or month? Suggestions: Once the contractor is getting to the towards the final stages of Phase 1, allow the contractor to start demolition of phase 2. This will help get the project completed much faster and reduce demobilization and remobilization cost. If these is not feasible because the risk of having to many surgical rooms down at one time, establish how many days will it take to inspect/approve each phase before being allowed to move towards the next phase.
The VA will coordinate and approve the start of all phases based upon availability of space(s). It is highly likely we can combine phases depending on Surgery Service scheduling.
18. Who will be responsible for moving the Government’s furniture, tools and equipment from each surgical room prior to demolition and after completion? Will it be moved withing the building or to an off-site location? If the Government will be responsible, what is the anticipated time frame of this movement per each phase?
The VA Environmental Management Service is responsible for moving the VA owned furniture, tools and equipment from each room both prior to demolition and after completion of flooring installation. It will be moved to another location in the general vicinity of the room(s) being worked. The time frame is based upon staff availability and will be coordinated accordingly.

19. Electric connection capacity considerations. Does the facility have access to connections of multiple outlets that can power 30 amp – 125/250-volt equipment? Also 3 and 4 prong connections such as the pictures below? Suggestions: External power source is highly recommended such as generator or equipment that is powered by natural gas/liquid propane Allowing the contractor to connect to the hospital’s power grid is high risky for both the VAMC and the contractor. Power overload and logistics of connecting the equipment could cause delays and damage to the power grid.

Access to multiple outlets that can power 125/250-volt equipment can be found in the D,E, and F Electrical rooms on the floor. The Contractor shall isolate the power from the Hospital Critical Loads and install a separate electrical sub panel for each area as needed. An electrical outage is required 2 weeks in advance and coordinated with the VA Electrical Shops. No generator is feasible.

20. If use of external generator is allowed. What will be the designated location of the generator during each phase? The location during each phase should be one that is at the outside of the building withing the minimum distance that safety laws require, and consideration of noise pollution, fumes and potential trip hazard caused by the cable of the equipment. Suggestion: Allow a portable 12-14 kW, Diesel Generator similar to the picture below. This generator is an efficient diesel engine with quiet operation for powering tools and other equipment. The generator will be moved to designated areas assigned by the contracting officer representative for each phase. Electrical cables should be covered and bundled together along the hospital halls towards the jobsite or permit access via the closest window, tape and free of damage to avoid trip hazards.

See Response to RFI 19 above. No generator is feasible.

21. Encapsulation of work area. Is encapsulation of work area for each phase and use of air scrubber to eliminate construction dust and fumes mandatory?
A HEPA-filtered air scrubber is acceptable for worker protection while working in the isolation work areas. There are purge fans that the VA will operate in the areas of work to exhaust the fumes and dust.
22. Are offerors expected to furnish their subcontractors' Past Safety Record information including a completed Exhibit D for each subcontractor and EMR data?
EMR data is only required for the proposed prime contractor.
23. Please clarify whether the mailed or hand delivered bid bonds are due January 31 or February 7.
A copy of the bid bond is required to be submitted with the proposal. Hard copy bonds are to be delivered by the final day of receipt of proposals.
24. Please confirm that the fictitious start date offerors should assume is still January 3.
Please use the fictitious date of 03/03/2022 for the draft schedule.
25. Is this project sales tax exempt? If the project is sales tax exempt can the government provide a sales tax exemption certificate?
Negative, this project is not tax exempt.
26. Will the Government provide comprehensive written badging requirements for the project if badging is required?
See SOW section 9 for further details.
27. Where will the designated parking area be for workers accessing the construction site?
There is no designated parking at the facility. All workers and visitors must park on their own.
28. Has the work area been checked for asbestos?
See response to RFI question 29 below.
29. What is the Governments’ policy if asbestos products are encountered during construction?
The dateline of construction of the Facility 2012-2015 ensures no asbestos is installed in building components.
30. Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin.
An economic price adjustment shall not be incorporated into this project.
31. Describe any and all tasks that may be required for this project as it relates to infectious control?
An ICRA is required for this work with a full list of precautions that need to be implemented to avoid the risk of infection with staff, patients, and contractors. All barriers to prevent air, surface, and noise contamination should be implemented.

All current facility COVID-19 regulations in place should be followed by staff working on project. Staff are to enter facility at first floor visitor screening stations. Contractors are to wear a mask at all times while within the facility except for when taking breaks to eat or drink. Fabric face coverings are not permitted on the SLVHCS campus. Please perform hand hygiene upon entering and exiting the OR area. Please cover all vents and equipment that cannot be removed.

32. Will the VA please confirm that spec section 09 67 23.20 is applicable to the flooring materials required on this project, including the following excerpt: 1.4 Quality Assurance (B): “4. Installer of flooring shall only work for manufacturer of these resins.”
Confirmed as accurate.
33. Can the VA please confirm this project’s NAICS code, 238190, represents a specialty trade solicitation, and thus requires 25% self-performance by any SDVOSB contractor?
Confirmed. The prime (SDVOSB) contractor shall be responsible for 25% of the work.
34. Prior to award, will the VA accept an alternate flooring material product deemed equal by the contractor, but not meeting all requirements specified within spec section 09 67 23?
No. The “or equal” product must meet the prescriptive specification requirements.
35. The solicitation, section “A.6 Proposal Preparation”, subsection “Evaluation Factors” utilizes Subfactors 2a and 2b within Factor 2 and Factor 3. Does the government deem it acceptable to utilize Subfactor 3a and 3b within Factor 3, instead of a duplication of Subfactors 2a and 2b?
Please see revised Factors:

FACTOR 1— Technical Factor 1

Evaluations will be based on the following subfactors and are in descending order of importance:

SUBFACTORS:

· Subfactor 1a. Management Approach Narrative

· Subfactor 1b. Schedule

Subfactor 1a Management Approach Narrative: Contractor shall demonstrate/explain how this project will be accomplished, based on the contractors best interpretation of the solicitation documents, with no interruptions of services in adjacent patient care areas. Provide techniques for maintaining on-time schedule performance and provide a detailed explanation as to how the project will be implemented and managed to ensure compliance with all OSHA Construction Standards, Fire and Life Safety Issues, and Security Measures.

Subfactor 1b – Schedule: Contractor shall demonstrate a clear understanding of the project requirements including critical milestones provided in a Proposed Draft Project Schedule with a January 03, 2022 Notice to Proceed fictitious Start Date (for purposes of the Proposed Draft Schedule only) that covers the project’s entire period of performance (to include the completion of any anticipated Punch List Items within the period of performance).

FACTOR 2— Technical Factor 2:

Evaluations will be based on the following subfactors and are in descending order of importance:

SUBFACTORS

· Subfactor 2a. Key Prime Contractor Staff

· Subfactor 2b. Subcontractors

Subfactor 2a – Key Prime Contractor Staff: Provide names on an Organizational Chart (structured with the below Subcontractors) and Resumes of the offeror’s proposed project management personnel (i.e. Site Superintendent, Project Manager, Quality Control Manager, etc.);narrative description of the individual’s management and construction capabilities and how they will be best utilized to obtain project completion with the proposed subcontractors.

· Project Manager and Project Superintendent shall have a minimum of five (5) years of experience managing or supervising multiple projects of similar size, scope, and complexity (or greater). If the person listed as proposed Project Manager or Project Superintendent is not a current employee of the offeror but intends to become one upon award of the contract, OFFEROR SHALL SUBMIT A COPY OF A COMMITMENT LETTER FROM THAT PERSON AS A PART OF THE TECHNICAL PROPOSAL to verify Offeror will be hiring him/her and he/she intends to accept the position.

Subfactor 2b – Subcontractors: Identify the key subcontractors and its associated socioeconomic status for the chosen for the project. Submit no more than five (5) Subcontractor Consent Forms (Exhibit C) for each Key Subcontractor. Each consent form shall have a narrative consisting of the locality, experience with construction at medical centers, and resumes of the proposed staff of the subcontractor.

Factor 3— Past Performance Vol 2:

Evaluations will be based on the following subfactors and are in descending order of importance.

Subfactors:

· Subfactor 3a. Previous Recent/Relevant construction experience with VA Construction Contracts

· Subfactor 3b. Demonstrated Past Performance Information

Tab A Subfactor 3a Previous Recent/Relevant construction experience with VA Construction Contracts completed at VA Medical Centers.

· List of Contract Names (and Brief Description) & Contract Numbers

· Date of Contract Awards

· Contract Dollar Amounts & Date Completed

· Contract Completed in Delinquent Status: Yes or No

Tab B Subfactor 3b – Demonstrated Past Performance Information

· Letters of Recommendation and/or Referrals from previous customers

· Letters and/or Referrals

· Names, Phone Numbers, & Email Addresses of Persons Authoring Letters and/or Referrals

· Previous Contractor Performance Assessments Reports

· Past Performance Questionnaire (Exhibit B): Past Performance Questionnaires (Exhibit B) – Offerors shall prepare and forward to prior client(s) for submission to the Contracting Office EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE for all the projects listed by contractor and submitted using EXHIBIT A PERFORMANCE RELEVANCY SURVEY. This includes correspondence explaining the requirement to obtain an independent evaluation of prior contract performance and the Past and Present Performance Questionnaire for use in evaluating Past Performance. It is preferred that these are the same projects for ease of evaluation and comparison.***PPQ may have been completed be no later than one (1) year prior to the effective date of this action***

· Performance Relevancy Survey (Exhibit A): Utilizing Performance Relevancy Survey (Exhibit A). The offeror shall demonstrate completed/or ongoing (>50% complete) recent and relevant projects at a hospital/ medical center (VA or Non-VA) project of this same size, scope, and complexity (or greater). Note: Clearly identify those examples where an Offeror’s proposed Subcontractor was the Prime (or the Subcontractor) on the Project Examples if utilizing Subcontractor Construction Project Capability.

· An offeror with limited or no past performance may receive a rating based on the evaluation of its subcontractors and/or key personnel, provided an EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT FORM has been executed and included in the proposal for proposed subcontractors and/or potential key personnel not employed by the offeror. These ratings shall have the same weight as the ratings of the offeror. Offerors without a record of relevant past performance will be assigned a neutral rating in accordance with FAR 15.305(a)(2)(iv). However, the proposal of an offeror with no relevant Past Performance history, while rated “Neutral” in Past Performance, may not represent the most advantageous proposal to the Government and thus, may be an unsuccessful proposal when compared to the proposal of other offerors.

The Government may evaluate Past/Present Performance information through the use of Exhibit A & B completed by the offeror's references; The Government may evaluate Key Staff-Subcontractor Performance information through the use of Exhibit C completed by the offeror; use data independently obtained from other Government or commercial sources, including, but not limited to, Government databases; and/or rely upon personal business experience with the offeror. The evaluation may take into account Past Performance information regarding predecessor companies, key personnel who have relevant experience, and/or subcontractors that will perform major or critical aspects of the requirement when such information is relevant to this acquisition.

Past Performance information on contracts not listed by the offeror, or that of planned subcontractors, may also be evaluated. The Government may contact references and contact parties other than those identified by the offeror and information received may be used in the evaluation of the offeror’s Past Performance. While the Government may elect to consider data obtained from other sources, the burden of providing current accurate and complete Past Performance information rests with the offeror. The Government reserves the right to obtain and evaluate Past Performance information from any source it deems appropriate.

In accordance with FAR 15.306(a)(2), if award will be made without conducting discussions, an offeror may be given the opportunity to clarify certain aspects of their proposal (i.e. the relevance of an offeror's past performance information) as related to this acquisition, address adverse past performance information to which the offeror has not previously had an opportunity to respond or to resolve minor clerical errors.

Performance Currency, Trends, and Relevancy: The Government will consider the currency, trends and relevancy of the performance information while conducting its performance evaluation. For the purpose of this solicitation, performance currency is performance occurring within the last five (5) years from the proposal issuance date. Within this period, performance occurring later in the period may have greater significance than work occurring earlier in the period. For example, performance information for work occurring during March 2020 may have greater importance than performance information for work occurring during March 2017. Performance Trends may, depending upon the circumstances, have greater significance than sporadic incidents of "Exceptional" or "Unsatisfactory" performance. For the purpose of this solicitation, Performance Relevancy is defined as contracts (ongoing or completed) which are similar in scope, magnitude, and complexity to the current requirement. Higher relevancy will be assessed for contracts that are similar to the effort, or portion of effort, for which that contractor is being proposed, and may contribute to an overall higher relevancy score for the offeror. Based on the evaluation of offers, the Government will assign a performance confidence rating for each proposal at the factor level. The evaluation will consider the sub-factors as described herein. Following assignment of the performance confidence rating for each proposal, each offeror will receive a final risk rating for performance based on the cumulative rating of performance currency, trends, and relevancy.

Factor 4 – Price Vol 3: Offerors shall submit pricing in the Schedule, the SF1442 Back, and in the continuation page of SF 1442 (Block 17) as a part of their price proposal. The purpose of the price evaluation is to provide an assessment of the completeness and reasonableness of the proposed price in relation to the solicitation requirements. Price proposals will be evaluated to determine if the prices and support costs areas are:

· Complete – The proposal contains costs to perform all tasks required by the Scope of Work (SOW), specifications, and design drawings if provided.

· Reasonable – The price is determined fair and reasonable using cost or price analysis techniques described in FAR 15.404.

36. The solicitation SOW, paragraph 2.1, second sentence, calls for six phases. For manpower budgeting and planning purposes, will the VA expand their spreadsheet on page 1 and add a column identifying which phase each room will be accomplished in or is the contractor responsible for deciding this?
These are for conceptual purposes only and shall be confirmed and verified by the Contractor:

Phase 1 - Area D Rooms and Perimeter Corridors;

Phase 2 - Area E Rooms and Perimeter Corridors;

Phase 3 - Area F Rooms, Perimeter Corridors, and 3 Procedure Rooms West;

Phase 4 - Area F Rooms, Perimeter Corridors, and 3 Procedure Rooms East;

Phase 5 - Areas D and E Clean Corridor; and Phase 6 - Area F Clean Corridor

37. Can the contractor move ahead by initiating floor demo in one phase while the epoxy crew is working the areas in a different phase?
See responses to RFI Questions 13 and 17 above.
38. Prior to COVID and the era of supply chain disruptions, lead times on resinous materials after ordering were roughly 2-4 weeks. The contractor cannot order material until submittals are approved. Now with the supply chain issues that resinous flooring contractors experience, contractors cannot get materials for sometimes up to six to eight weeks. The VA’s PoP is 90 days, leaving 30-60 for installation. This is a 60-day installation job if working 7 days a week with no down time. With supply chain issues the way they are it is not possible to accomplish this project in 90 days Period of Performance. Will the VA consider a longer, more realistic period of performance to account for submittals and lead time?
See response to RFI Question 9 above.
39. Can the contractor perform floor preparation with propane powered prepping equipment?
No
40. Embedded in some of the drawing files attached/included with this solicitation are notes that reference paint, doors, corners guards, etc.. The SOW for this solicitation only references the resinous flooring. Will the VA clarify if the notes apply to this scope of work and if so, please provide more details and specifications for this work?
It is confirmed that the SOW for this solicitation is only for the resinous flooring. Care shall be undertaken as to not damage existing walls, doors, equipment, etc. as the contractor is responsible for repairs.
41. What ICRA level is required to maintain for this scope of work?
See response to RFI Question 14 above.
42. There are two 09 67 23 specifications in the specification manual. There is conflicting information when dealing with warranty and installer credentials. Which of these two specifications applies to this project?
Only one 09 67 23. 30 specification is provided. 09 67 00 has been deleted as per rev.1 dated 1/25/22.
43. Stonhard installers are not directly employed by Stonhard. Stonhard is notorious for pulling the bait & switch tactic after bids are turned in, based on which installer is available, and which one will buy the job for the best price. Will the VA mandate that the subcontracted Stonhard installer must also provide key past performance information prior to the bids being turned in, and that Stonhard is held to that crew qualification standard or higher after contract award?
Please refer to specification section 09 67 23. 30 paragraph 1.4.B. titled Installer Qualifications.
44. The Stonrez RTZ is very specific to Stonhard and not a system used by other manufacturers. Therefore, the VA has created a roadblock for other competitive offerors based on the lack of flexibility written into the specifications. Other manufacturers offer comfort floor systems, but many of them do not have rubber aggregates. In fact, Torginol, a leading manufacturer of aggregates in the US, no longer sells this type of rubber aggregates because of their failure rate and lack of popularity. The comfort floor system itself makes up less than 20% of the resinous flooring system, or 4,200 sqft of the 23,000 sqft total. Will the VA consider comfort floor systems from other manufacturers as a substitution for the Stonhard RTZ product?
See response to RFI question 34 above.
45. Will the VA allow after hours and weekend work to accommodate the schedule?
See SOW section 3.1.2 regarding requesting work after hours and weekends.
46. The schedule is not long enough for the flooring contractor to complete could the VA consider extending project to 120 calendar days?
See response to RFI Question 9 above.
47. How much time will flooring contractor have between phases?
See responses to RFI Questions 13, 17, and 37 above.
48. Will a STARC system be allowed to use for ICRA/infection control?
Yes
49. How many rooms have lead lined floors?
Walls are lined. No indication of lead lined floors in any of the rooms in the area of construction (see Shielding Table below).
50. On sheet 1 of the SOW the square footage is 32,692. But on sheet 2, it states about 24.000 sf of work that needs to be done. Which one is right?
The 24,000-sf number will be deleted from the forthcoming Rev3 SOW.
51. Based off the provided information and scope of the project is there an opportunity for a period of performance of 120 days due to the necessary shutdowns to coordinate with the medical staff and COR and allow for maintaining operability of the designated facility locations.
See response to RFI Question 9 above.
52. In rooms with permanent fixtures is there a preference for coving or would there be a terminating strip adjacent to the equipment?
Termination strip adjacent and abutting the permanent items.
53. Is the contractor responsible for moving the furniture and equipment? Section 1.8 para. 3 states that the VA is responsible for moving furnishings but during the walk through it was stated the contractor is. Seeking clarification.
See response to RFI Question 18 above.
54. To uphold compliance and a patient friendly environment what is the max dB level allowed?
VA has set the action level and permissible exposure limit at 85 dBA for an 8-hour Time-Weighted Average (TWA)
55. Are there any design specifics in the pattern in which the tile is to be placed?
Follow existing layout of the sheet vinyl for the new Resinous Flooring.
56. On sheet 1 of the SOW the square footage is 32,692. But on sheet 2, it states about 24.000 sf of work that needs to be done. Which one is right?
See Response to RFI 50 above.