Open MRI Site Prep-ICRA.pdf
PDF 206 KB Posted
- Solicitation number
- 36C25621R0066
About this file
This document outlines the requirements for an open MRI site preparation project at the Michael E. DeBakey VA Medical Center in Houston, Texas. The project includes preparing site 1C-386C for the replacement of an existing open MRI and involves specialized construction labor, supervision, and work in architectural, mechanical, electrical, plumbing, medical gas, radiation protection, fire protection and demolition. The period of performance is 150 calendar days from notice to proceed. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and requires that at least 15% of contract costs be spent on disabled veteran employees or other eligible SDVOSB concerns. The estimated value is between $500,000 and $1,000,000. Offerors must be registered in the Vendor Information Pages, System for Award Management, and have completed online Representations and Certifications by the solicitation due date. The North American Industry Classification System code assigned is 236220 with a small business size standard of $39.5 million in average annual receipts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GI-002 ICRA.pdf | ||
| ASI-2 DECK INFILL.pdf | ||
| M-101 MECH PLAN.pdf | ||
| Ext-Window.pdf | ||
| 000110 TOC.pdf | ||
| AD-101 DEMO PLAN-REV 1.pdf | ||
| 010000 Gen Reqs R1.pdf | ||
| 100-S164R.PDF | ||
| ASI 1 RF WINDOW.pdf | ||
| Ferroguard Installation.pdf | ||
| 220511 common sprinkler.pdf | ||
| 100-S119R.PDF | ||
| CASEWORK.pdf | ||
| Site Visit Sign-In Sheet.pdf | ||
| Dimplex MRI Chiller Installation Guide.pdf | ||
| 36C25621R0066 0002.docx | DOCX document | |
| MD-101 MECH DEMO R1.pdf | ||
| 36C25621R0066 0001.docx | DOCX document | |
| 580-18-119_Open MRI_Wage Determinaiton TX20210253 01_01_2021.pdf | ||
| 36C25621R0066.docx | DOCX document | |
| 580-18-119_Open MRI_Site Visit Instructions.docx | DOCX document | |
| 580-18-119 Project Specifications.pdf | ||
| 580-18-119 Project Drawings.pdf | ||
| 580-18-119_Open MRI_Statement of Work.docx | DOCX document | |
| 580-18-119_Open MRI_SF24 BID BOND.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No.
Date:
C Medium
TYPE A TYPE B TYPE C TYPE D
I II II III/IV
I II III IV
I II III/IV IV
II III/IV III/IV IV
Pre-Construction Risk Assessment for the Transmission TB to Contracted Construction Workers
Is PPD skin testing necessary for contract workers?
1st floor area M. 1C-386C
Location and brief description of the construction or maintenance project:
Highest
Air Quality
Noise
This will be reviewed with safety
Change Lock to construction core
Emergency procedures
Security
Construction Site Location:
High
Other Comments
Notes:
Patient Population Near Construction Site: Yes TB Risk Level of Facility:
Yes
Infection Control Risk Assessment (ICRA) Checksheet
Patient Risk Group Construction Project Type
Project Class
Open MRI Site Prep
Mark Landwert
Project Title or Type of Work:
COR:
Type of construction project--choose from drop-down box (see "Types & Risk" tab):
580-18-119
March 7, 2021
Prepare the site 1C-386C for replacment MRI
Patient Risk Group--choose from drop-down box (see "Types & Risk" tab):
Use Negative Air, walk off mats and PPE as required. Cover demo cart prior to removal from room
Risk for TB exposure to Contractors?
Pre-Construction Risk Assessment (to be filled out by COR)
Class of Infection Control Precautions (select from grid)
Vibrations
Utilities
Neg air required
After hours work for demolition in some areas
Coordinate with COR for all shut down requests
III
After hours work for demolition in some areas
Low Medium
Project Title or Type of Work:
March 7, 2021
Class I X Execute work by methods to minimize raising dust from construction operations. Immediately replace ceiling tile displaced for visual inspection.
X Provide active means to prevent airborne dust from dispersing into atmosphere. X Wipe work surfaces with disinfectant.
X Water mist work surfaces to control dust while cutting. Wet mop and/or vacuum with HEPA-filtered vacuum before leaving work area.
X Seal unused doors with duct tape. Remove isolation of HVAC system in areas where work is being performed.
X Block off and seal air vents. X Contain construction waste before transport in tightly covered containers.
X Place dust mat at entrance and exit of work area.
X Remove or isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
Class II (those checked) plus: X Do not remove barriers from work area until completed project is inspected by Safety and Infection Control and thoroughly cleaned by Environmental Management.
X
Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
X Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
X Maintain negative air pressure within work site utilizing HEPA equipped air filtration units. X Vacuum work area with HEPA filtered vacuums.
X Cover transport receptacles or carts. Tape covering unless solid lid. Wet mop area with disinfectant.
Class III (those checked) plus: See other Classes.
X Seal holes, pipes, conduits, and punctures appropriately.
Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time the worker leaves the worksite.
All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.
III
IV
Infection Control Risk Assessment (ICRA) Checksheet (check appropriate requirements)
During Construction Project Upon Completion of Project
II
Open MRI Site Prep
Project Title or Type of Work:
Deficiency Y or N? Deficiency Y or
N?
Blocking an approved exit path Y Rerouting internal patient/staff/visitor traffic flows N A large section of the fire alarm system is out of service N Rerouting external access to the hospital N
A large section of the sprinkler system is out of service N Fire alarm system out of service > 4 hours N
Major renovation of an occupied floor N Sprinkler system out of service > 4 hours N Significantly modifying smoke barriers or fire walls N One fire alarm zone out of service > 4 hours N
Adding an addition to an existing and occupied building N A few sprinkler zones out of service > 4 hours N
Other system (kitchen hood, FM 200, etc.) out of service
X 3
X 6
X 7
X 8
X 14
Signature and Date
Conduct organization wide safety education programs to promote awareness of fire safety building deficiencies, construction hazards and temporary measures implemented to maintain fire safety.
Train staff to compensate for impaired structural or compartmental fire safety features.
The hospital has a written ILSM policy identifying when and to what extent ILSM are implemented.
Evaluate the project using the criteria below to determine which ILSM are applicable.
Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
Provide additional training to staff on the use of firefighting equipment.
Conduct one additional fire drill per shift per quarter.
Inspect and test temporary systems monthly. Document the completion date.
Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
Provide additional firefighting equipment.
Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
Interim Life Safety Measures (ILSM) Assessment for Construction and Maintenance
580-18-119
Notify the fire department and initiate a fire watch. Document notification and fire watch times.
Post signage identifying the location of alternative exits.
Inspect exits in affected areas on a daily basis.
Open MRI Site Prep
Date of this Formal Contract:
Yes No
1 X
2 X 3 X 4 X 5 X
6 X
7 X
8 X
9 X
10 X 11 X
12 X
13 X
14 X
Time Time
Interim Life Safety Measures Required? Responsibility
Safety
Safety
Notify the fire department and initiate a fire watch. Document notification and fire watch times.
Post signage identifying the location of alternative exits.
Inspect exits in affected areas on a daily basis.
Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
Provide additional fire-fighting equipment.
Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
Provide additional training to staff on the use of firefighting equipment.
Conduct one additional fire drill per shift per quarter.
Inspect and test temporary systems monthly. Document the completion date.
Conduct organization wide safety education programs to promote awareness of fire safety building deficiencies, construction hazards and temporary measures implemented to maintain fire safety.
Train staff to compensate for impaired structural or compartmental fire safety features.
The hospital has a written ILSM policy identifying when and to what extent ILSM are implemented.
Contractor, COR and Safety
Safety
Safety
Contractor
Safety
Prepare the site 1C-386C for replacment MRI
DateNames/Groups Trained
ILSM Formal Contract
580-18-119Project Title / Open MRI Site Prep Project No.:
COTR: Mark Landwert Contractor:
Location and Description of Work:
March 7, 2021
Staff Training
Safety
COR
Date Area Date Dates of Fire Drills
Area
COR
Contractor
Safety
Contractor
Contractor, COR and Safety
Project Title: Open MRI Site Prep Project #: 580-18-119
Yes No No
Fire Protection Engineer or Safety staff:
Date completed:
Yes No If yes, then:
No Must provide safe access to and egress from excavation. See FMS Policy 138S- 022, Excavation Safety Program.
No Daily excavation permit required. See FMS Policy 138S-022, Excavation Safety Program.
X Permit required. See FMS Policy 138FMS-029, Barrier Penetration Permit Policy.
No Refer to FMS Policy 138FMS-021, Confined Spaces.
X Refer to FMS Polcy 138ENG-026, Hot Work Policy
No Refer to FMS Policy 138S-033, FMS Electrical Safety Program.
No Before releasing the site, flush domestic water lines and provide documentation to COR. Observe Note 2.
No Before releasing the site, flush and sanitize domestic water lines and provide documentation to COR. Observe Note 2.
No Notify COR of exact location(s) and type(s) so dampers may be inspected in 1 year.
Will this project require:
Note 1 (see VHA Directive 2005-007 and SCVAHCN Policy 16-ES-30) :
a) All delegated construction projects must be provided fire code reviews. Delegated construction projects include projects funded from the Major, Minor or NRM programs that are managed at the facility level and other projects completed with local operating funds.
b) A qualified fire protection engineer must conduct the fire protection and life safety review for all Major and Minor projects and any NRM project where the scope of work is primarily (greater than 50 percent of the total project cost) fire protection (i.e., fire alarm or sprinkler systems, etc.) or includes significant renovation and construction where specific fire code and standard requirements would be applicable.
c) Facility safety staff will conduct fire code reviews for all other delegated projects and for locally funded projects.
Fire Prevention Review (see Note 1)
Permits and Other Requirements
Permit and Policy Requirements
Note 2: From FMS Policy 138FMS-002, Infection Control, paragraph II.F.: In the event of maintenance or repair work on existing water lines, Engineering Section [Contractor, if construction project] will accomplish proper disinfection of the affected water lines through the Safety Manager and follow-up bacteriological testing through a certified water testing laboratory or City of Houston... Infection Control will be notified of such maintenance or repair work. The water test results will be reviewed with Infection Control prior to placing new or repaired lines into service. All potable water test results shall be maintained and available from the Safety Section.
Has a fire prevention review been conducted?
Any excavations greater than 4 feet below grade level?
Any excavations greater than 5 feet below grade level?
Either above ceiling work or fire or smoke barrier penetrations?
Entry into permit required confined spaces?
Welding, soldering or other hot work?
Work on energized electrical circuits?
Modification of domestic water lines?
Installation of new domestic water lines?
Installation of new fire or smoke dampers or replacement of existing dampers?
Date:
Type of Project (check appropriate box):
Operation and Maintenance Lease X Repairs/Renovation Other
New Construction
Level of NEPA Analysis: Other Environmental Permits/Analysis Needed:
X Categorical Exclusion (see next page)
Environmental Assessment (EA) Needed Environmental Impact Statement (EIS) Needed
Would the proposed activity involve or generate any of the following?
Y/N Y/N Y/N
N N N N N N N N N N N N N N N N N N N
COR:
GEMS Coordinator:
Source Source Source
Determination
Mark Landwert
I find the proposed project qualifies as a CATEGORICAL EXCLUSION with no extraordinary circumstances.
I find that the proposed project MAY have a significant effect on the environment; therefore, an ENVIRONMENTAL ASSESSMENT (EA) will be prepared.
ENVIRONMENTAL IMPACT STATEMENT (EIS)
Specify which CATEX: 5
Biological Resources Radioactive Waste Mixed Waste
Project Impacts
Soil Disturbance Water Treatment Water Flow
RCRA or CERCLA Sites
Wetlands Permit Modification Chemical Use/Storage Water/Well use Other:
National Environmental Policy Act (NEPA) Risk Assessment Project Title:
COR:
Air Emissions including GHGs Asbestos
Prepare the site 1C-386C for replacment MRI
Petroleum Storage
Open MRI Site Prep Mark Landwert
Liquid Effluent
Utility Modification
580-18-119 March 7, 2021
Location and Description of Work:
Excessive Noise Solid Waste Hazardous Waste
*38CFR Part 26.6(b)(1)
13. Actions, activities. Or programs that do not require expenditure of Federal funds.
CATEX Form Categorical Exclusions List*
8. Actions which involve support or ancillary appurtenances for normal operation;
9. Leases, licenses, permits, and easements;
10. Reduction in force resulting from workload adjustments, reduced personnel or funding levels, skill imbalances or other similar causes;
11. VA policies, actions and studies which do not significantly affect the quality of the human environment;
12. Preparation of regulations, directives, manuals, or other guidance that implement, but do not substantially change, the regulations, directives, manuals, or other guidance of higher organizational levels or another Federal agency, and
3. Routine VA grounds and facility maintenance activities;
4. Procurement and activities for goods and services for routing facility operations maintenance and support;
5. Interior construction or renovation;
6. New construction of 75,000 gross square feet or less;
7. Development of 20 acres of land or less within an existing cemetery, or development on acquired land of five acres or less.
1. Repair, replacement and new installation of primary or secondary electrical distribution systems;
2. Repair, replacement and new installation of components such as windows doors, roofs, and site elements such as sidewalk, patios, fences, retaining walls, curbs, water distribution line and sewer lines which involve work totally within VA property boundaries;
| 1-ICRA |
| 2-ICRA2 |
| 3-ILSM |
| 4-ILSM Contract |
| 5-Permits, etc. |
| 6-NEPA |
File details come from the government source that posted it. Updated .