PAST PERFORMANCE SURVEY SPS.docx
DOCX document 22 KB Posted
- Solicitation number
- 36C25620R0044_1
About this file
This document contains a past performance survey for a federal construction contract to renovate an expanded SPS facility for the Department of Veterans Affairs. The survey requests feedback on a contractor's past performance on one or more similar projects. It includes 30 questions regarding the contractor's resources, responsiveness, management, reporting, safety record, employee qualifications, and any issues. Respondents are asked to rate performance on a scale and also answer yes or no questions. Space is provided for comments. The signature and return of the completed survey directly to the contracting officer by a specified due date is requested to be considered in evaluating offerors for the related solicitation to renovate an expanded SPS for the VA for $586,180.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25620R0044 0003.docx | DOCX document | |
| RFI Questions Renovate for Expanded SPS RFI (003).docx | DOCX document | |
| Wage Determination Jackson.txt | TXT text file | |
| Bid Schedule SPS.docx | DOCX document | |
| SPS Addendum No. 2.pdf | ||
| 36C25620R0044 0002.docx | DOCX document | |
| Statement of Work.pdf | ||
| 36C25620R0044 0001.docx | DOCX document | |
| 586-18-102 Addendum 0001 03.26..20.pdf | ||
| Specifications.pdf | ||
| Asbestos Spec--Jackson--February 2019--Large Projects.pdf | ||
| Asbestos warning statement--Renovate for Sterile Processing_edit.pdf | ||
| SPS Renovation Geotechnical Report.pdf | ||
| SPS Renovations Combined Dwg Set.pdf | ||
| 36C25620R0044_1.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25620R0044
PAST PERFORMANCE SURVEY
Renovation of SPS in Jackson MS
To: ____________________ (Point of Contact)** ____________________ (Company)** ____________________ (Phone) ____________________ (Fax) ____________________ (E-Mail)** _____________________ (Name of Company requesting survey)**
The company from which you received this survey is competing for award of a contract with the Department of Veterans Affairs, Jackson, MS. As part of the process for screening potential Offerors, this company is soliciting your input and assessment of its past performance for one or more projects they performed for your firm. Please respond to each of the questions below and forward the completed survey directly to the CAVHS Contract Specialist.
To consider your responses, the Contract Officer must receive your responses, either by fax or e-mail.
If you have any questions or comments, feel free to contact me. Thank you in advance for your assistance.
Benjamin Dufour Contracting Officer Email: Benjamin.Dufour@va.gov
Please identify the project(s) that this company has performed for your organization, description, city, state, and award amount and final dollar value at completion of contract:
Respond to the question using the following scale: O- Outstanding, A- Acceptable, S-Satisfactory, M- Marginal, U-Unacceptable.
1. Did the contractor commit adequate resources in timely fashion to the contract to meet the requirements and to successfully solve problems? O A S M U
2. To what extent did the contractor respond positively and promptly to technical direction, contract change orders, etc.?
O A S M U
3. How reliably did the contractor follow through on commitments?
| O A S M U | ||
| 4. | To what extent did the contractor’s management system provide visibility into problems and risks? |
O A S M U
5. How responsive do you think the contractor was to information requests, issues, or problems during the course of the contract? O A S M U
6. How effective has the contractor been in identifying requirements?
O A S M U
| 7. | To what extent did the contractor have the ability to administer and manage the contract? |
| O A S M U |
8. To what extent did the contractor issue professional correspondence?
O A S M U
9. How well did the contractor adhere to the Statement of Work? O A S M U
| 10. | What was your level of satisfaction with the contractor’s management and support staff? |
| O A S M U |
| 11. | What was your level of satisfaction with the contractor’s Supervisor(s)? |
| O A S M U |
12. To what extent did the contractor submit required reports and documentation in a timely manner? O A S M U
| 13. | To what extent were the contractor’s reports and documentation accurate and complete? |
| O A S M U |
| 14. | To what extent was the contractor’s maintenance and problem tracking/reporting documentation timely, accurate and of appropriate content? |
| O A S M U |
| 15. | To what extent did the contractor comply with safety requirements? |
| O A S M U |
| 16. | What was your level of satisfaction with the contractor’s overall quality of service? |
| O A S M U |
17. To what extent was the contractor effective in interfacing with the Government staff? O A S M U
18. What was your level of overall customer satisfaction? O A S M U
| 19. | To what extent were the contractor’s employees experienced and qualified? | |
| O A S M U |
Respond: Yes or No.
20. Were there any cure notices issued? Yes: ____ No: ____
21. Was contractor pro-active? Yes: ____ No: ____
22. Did contractor suggest cost-saving changes? Yes: ____ No: ____
23. Would you recommend this contractor? Yes: ____ No: ____
For Federal contracts:
24. Were there any Labor Department Investigations? Yes: ____ No: ____
24a. If yes, please describe reason and final outcome.
25. Were there any safety investigations? Yes: ____ No: ____
25a. If yes, please describe reason and final outcome.
26. Were there any security investigations? Yes: ____ No: ____
26a. If yes, please describe reason and final outcome.
27. Was there a partial or complete termination for default or convenience?
Yes: ____ No: ____
27a. If yes, please describe reason and final outcome.
28. Are there any pending terminations? Yes: ____ No: ____
29. What is/was the duration of the contract? _____________________
30. Were there any performance issues regarding the contractor’s work? If yes, please describe (use a separate sheet of paper if necessary).
Please provide other comments (Use a separate sheet of paper if necessary):
Signature: ____________________________
Date: ____________________________
**Required
File details come from the government source that posted it. Updated .