Pre-Bid RFI 550-26-120CON Amend 0006.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Z1DA--550-26-120 Emergent South Water Tower Repairs
Solicitation number
36C25226B0002
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) for a VA water tower repair project located at the VA Illiana Healthcare System in Danville, IL. The solicitation is a 100% set-aside for Certified Service-Disabled Veteran-Owned Small Businesses (SDVOSB), with an estimated award timeframe of approximately 30 days after bid opening. The project involves emergent repairs to the South Water Tower, including interior and exterior coating work, with specific technical requirements such as abrasive blasting to SSPC-SP10/SP7 standards and applying epoxy primer and liner coatings.

Key project details include a site visit scheduled for 12/3/2025, a pre-bid conference on 11/17/2025, and an estimated project start date 14 days after Notice to Proceed. The VA will be responsible for draining and refilling the water tower, maintaining water pressure during construction, and ensuring the tower is operational by the end of the performance period. Contractors must provide on-site superintendent and Site Safety Health Officer (SSHO), with the option for one person to serve in both roles if adequately qualified. The contractor will also be responsible for water testing and ensuring the tank passes bacterial testing before being placed back into service.

View the file

Other files

File Type Posted
36C25226B0002 0007.docx DOCX document
36C25226B0002 0006.docx DOCX document
36C25226B0002 0005.docx DOCX document
36C25226B0002 0004.docx DOCX document
Site Visit Sign In 12.3.25.pdf PDF
36C25226B0002 0003.docx DOCX document
Pre-Bid RFI 550-26-120CON Amend 003.xlsx XLSX spreadsheet
Attachment Pre-Bid RFI 550-26-120CON Amend 00002.xlsx XLSX spreadsheet
36C25226B0002 0002.docx DOCX document
36C25226B0002 0001.docx DOCX document
Pre-Bid RFI 550-26-120CON.xlsx XLSX spreadsheet
550-26-120 Drawings.pdf PDF
550-26-120 SOW.pdf PDF
36C25226B0002_1.docx DOCX document
S02 Wage Determination 11.10.25.pdf PDF
550-26-120 Specifications.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid RFIs

550-26-120 Emergent repairs South Water Tower
Pre-Bid RFIs
No.Date SubmittedRequested By: (Name of Firm)SUBJECT/COMMENTAmendment #
111/14/25J & G Solutions, LLCThe Solicitation states that the pre-bid conference will occur on Tuesday November 17, 2024, at 1:00 PM CST. Does this mean Tuesday November 17, 2025, at 1300 CST?Amend 001the Pre-Bid Conference is on Tuesday November 17, 2025
211/14/25J & G Solutions, LLCIs attendance at the pre-bid conference mandatory or optional for bidders?Amend 001No, attendance is not required
311/14/25J & G Solutions, LLCAre there any advance registration requirements or facility access procedures attendees must follow?Amend 001No
411/14/25J & G Solutions, LLCWill a site walk or facility tour be included as part of the pre-bid conference?Amend 001Site visit will start in the conference room afterwards contractors will be lead to the south water tower.
511/14/25J & G Solutions, LLCIf not, will a separate site visit be scheduled?Amend 001There will not be another site visit scheduled
611/14/25J & G Solutions, LLCAre PPE, visitor badges, or additional documentation required for the site visit?Amend 001Visitors will need to check in with police to get a temporary badge. If visitor has a badge from a previous project they need to bring the badge to the site visit.
711/14/25J & G Solutions, LLCIs in-person attendance required for the pre-bid conference and bid opening?Amend 001No, attendance is not required for either Pre-Bid conferrence or BID opening
811/14/25J & G Solutions, LLCWill a virtual platform (Teams, Zoom, WebEx, etc.) be available for bidders unable to attend
physically?Amend 001No, there will not be a virtual platform for either the Pre-Bid conferrence or BID opening
911/14/25J & G Solutions, LLCWill hand-delivered or commercial carrier submissions (FedEx, UPS) be accepted, or is USPS the only authorized method?Amend 001Any Commercial Carrier is acceptable.
1011/14/25J & G Solutions, LLCShould bidders use certified/priority/overnight USPS mail to ensure timely delivery?Amend 001Any Commercial Carrier is acceptable.
1111/19/25Underground LLCI would like to bid on this work. I am not Service Disabled Veteran Status. Am I still allowed to bid?Amend 002Per the first page of the solicitation Standard Form 1442: This procurement is an 100% set -aside for CVE Verified Service-Disable Veteran-Owned Small Business Firm (SDVOSB) per the Authority 38 U.S.C 8127 (Public Law 109-461
1211/19/25Underground LLCI would like to bid on this work. I am not Service Disabled Veteran Status. Am I still allowed to bid?Amend 002Per the first page of the solicitation Standard Form 1442: This procurement is an 100% set -aside for CVE Verified Service-Disable Veteran-Owned Small Business Firm (SDVOSB) per the Authority 38 U.S.C 8127 (Public Law 109-461
1311/20/25Eleven Bravo Group, LLCWould another Site Visit be considered?Amend 002yes, another Site visit is scheduled for 12/3/2025 from 2:30-3:30. Meet at Bldg. 102, in the Project Section Project Room (B102 102G) at the VA Illiana

Healthcare System (VAIHCS), Danville, IL. Please check in with VA Police (B102 Lobby) for a temporary day pass.

1411/21/25J&G SolutionsIs temporary water service or temporary water pressure required while the tank is offline for
renovations?Amend 002No
1511/21/25J&G SolutionsIs lead present on any of the existing interior or exterior coatings on the tank?Amend 002No
1611/21/25J&G SolutionsWhen does the VA anticipate issuing the Notice to Proceed, or what is the estimated project start date?Amend 002There will be a notice to proceed meeting held after contract award. Time will be discussed after award. Estimated project start day is 14 days after the NTP per the first page of the solicitation SF 1442.
1711/21/25J&G SolutionsIs there a required or mandated date by which the tank must be placed back into service?Amend 002Water tower must be operational at the end of period of performance.
1811/21/25J&G SolutionsWho will be performing the inspections for this project?Amend 002The COR will be performing two daily inspections during construction.
1911/21/25J&G SolutionsWill inspections be conducted full-time, or will they be hold-point based?Amend 002The COR will be performing two daily inspections during construction.
2011/21/25J&G SolutionsIs dehumidification required for the interior coating system during application and curing?Amend 002Interior coating system must adhere to NSF 600 regulations. Humidification should be controlled based off of manufacture instructions and industry standards.
2111/21/25Panacea Construction GroupDoes the Superintendent need to be directly employed by the Prime Contractor?Amend 003No
2211/21/25Panacea Construction GroupMust the Superintendent be on site at all times?Amend 003Yes
2311/21/25Panacea Construction GroupDoes the SSHO (Site Safety Health Officer) need to be directly employed by the Prime Contractor?Amend 003No
2411/21/25Panacea Construction GroupMust the SSHO be on site at all times?Amend 003Yes
2511/21/25Panacea Construction GroupCan the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles?Amend 003The VA will accept the superintendent as SSHO provided that adequate qualifications are provided.
2611/21/25Panacea Construction GroupAre there any other mandatory on-site roles required in this contract?Amend 003Any roles laid out in Specifications must be filled.
2711/21/25Panacea Construction GroupWhen does the VA expect to make an award for this project?Amend 003Approximately 30 days after the bid opening date.
2811/21/25Panacea Construction GroupWhen does the VA expect the project to start following the award?Amend 003There will be a notice to proceed meeting held after contract award. Time will be discussed after award. Estimated project start date is 14 days after the NTP per the first page of the solicitation SF 1442.
2911/21/25Panacea Construction GroupAre there any concerns for Asbestos Containing Material or Lead in the areas being worked in?Amend 003No
3011/21/25Panacea Construction GroupIs temporary fencing required to secure the construction area?Amend 003There is a fence surrounding the south water tower. Any materials outside of the existing fence must be inside an area with temporary fencing. If part of the existing fence is removed for construction reasons, temporary fencing must be used for security when contractors are not present.
3111/21/25Panacea Construction GroupWill the VA be responsible for draining the tower prior to construction?Amend 003Yes
3211/21/25Panacea Construction GroupWill the VA be responsible for refilling the tower following construction?Amend 003Yes
3311/21/25Panacea Construction GroupWill the VA be responsible for maintaining pressure to the facility while the tower is out of service?Amend 003Yes
3411/21/25Panacea Construction GroupThe spec document (550-26-120+Specifications.pdf) calls for the interior to be a full 10, but the scope of work (550-26-120+SOW.pdf) calls for a 10/7. Could we get clarification on which is wanting to be priced?Amend 003Abrasive blast all rusted and abraded interior areas to SSPC-SP10 and brush blast all remaining interior areas to SSPC-SP7; then apply one spot coat of epoxy primer to all areas blasted to #10, Strip coating at all weld seams, and apply an epoxy liner to the entire tank, to achieve 8 to 10 mils of total dry film thickness. Total mil thickness will include a combination of the existing and new coating.
3511/21/25Panacea Construction GroupThe spec document also calls for an exterior coating system and an interior dry coating system. The scope of work doesn’t mention anything about either and the tank doesn’t have an interior dry, so we need some clarification on this as wellAmend 003Abrasive blast all rusted and abraded interior areas to SSPC-SP10 and brush blast all remaining interior areas to SSPC-SP7; then apply one spot coat of epoxy primer to all areas blasted to #10, Strip coating at all weld seams, and apply an epoxy liner to the entire tank, to achieve 8 to 10 mils of total dry film thickness. Total mil thickness will include a combination of the existing and new coating.
3611/21/25Panacea Construction GroupWill the site visit sign in sheet be posted?Amend 003no Contractors showed up to the 1st site visit dated 11/17/25. The 2nd site is 12/03/25 and sign-in sheet will be posted online after.
3711/21/25Panacea Construction GroupIs it permissible for an offeror to hand-deliver a physical copy of their bid at the bid opening location prior to the scheduled commencement of the bid opening?Amend 003Yes hand-delivered (hard copy) of bids will be acceptable. Bid must be delievered to the GLAC, 115 South 84th Street (Suite 101), Milwaukee, WI 53214. See page 5 of solictation for information.
3811/21/25Panacea Construction GroupCan you please confirm the federal signage (Task #16) legally does not need to be provided or installed by a federal employee?Amend 003The contractor is allowed to provide and install signage.
3911/21/25Panacea Construction GroupProposal instructions require OSHA 300 Data from 2025, however, OSHA 300 logs are not available until 2025 is over. Would 2020-2024 be sufficient with known data of 2025-year to date?Amend 003Yes
4012/4/25Eleven Bravo Group, LLCDoes the existing exterior or interior coating contain lead, chromium, or any other materials deemed hazardous? The exterior coating system is specified as a Prime Coat of Tnemec Series 91-H2O Hydro-Zinc, additional spot prime coat of Tnemec Series 135-color Chembuild, Intermediate Coat of Tnemec Series N69-color Hi-Build Epoxoline II, First Finish Coat of Tnemec Series 1075 -color* Endura-Shield II, and Second Finish Coat of Tnemec Series 1074U-11WH Tnemec White Endura-Shield. Tnemec Series 1075 and 1075U have been discontinued by Tnemec Company. The similar products available are Tnemec Series 1094 and Series 1095. Please confirm if these products are approved from your end.Amend 006The interior and exterior coating do not contain hazardous material. Products should be submitted for approval after bid award.
4112/4/25Eleven Bravo Group, LLCThe Interior Wet coating system is specified as Prime Coat of Tnemec Series 91-H2O Hydro-Zinc, Stripe Coat of Tnemec Series N140- 39BL Delft Blue Pota-Pox Plus, Intermediate Coat of Tnemec Series N140-1255 Chicago Beige Pota-Pox Plus, and a Finish Coat of Tnemec Series N140-15BL Tank White Pota-Pox Plus. Tnemec Series N140 is not longer NSF 600 approved for potable water over a total milage of 5.0. The replacement products for Tnemec Series N140 is either Series L140 or Series 21. Please confirm if these products are approved from your end.Amend 006Interior coating system must adhere to the most recent NSF 600 regulations and industry standards. Products should be submitted for approval after bid award.
4212/4/25Eleven Bravo Group, LLCTask #17 is for the Water Test: Water is to be tested after above task are completed to ensure water is safe for human consumption. This requires a certified operator to take the water samples a certified lab to test the water. This is typically handled by the VA as you might already have an established contract with a local lab to take samples and test their water. Please confirm if we are to include this scope of work in our offer or if you would prefer to remove the water sampling and testing and self-perform. Even if you take and test the samples, we would be responsible for disinfecting the tank and the samples passing BAC-T testing before the tank could be put in service. If they don’t pass, we would be responsible to re-disinfect the tank until they do pass BAC-T’s.Amend 006Contractor is responsible for testing water and ensuring it passes test.
4312/5/25B&B IndustriesPlease clarify if the cathodic protection system blocks on the interior of the tank need to be removed while blasting and painting. Essentially they are sacrificial blocks that are bolted to the shell/bowl/riser areas. Would the existing need to be reinstalled or are new “sacrificial blocks” in the tank required?Amend 006If blocks interfere with the contractors ability to blast and coat the interior bowl then they should be removed and reinstalled. If they are not in the way then they do not need to be removed.
4412/5/25B&B IndustriesPlease clarify of the superintendent can serve as the QCM and SSHO. One person, onsite fulltime with all three roles.Amend 006The VA will accept the superintendent as SSHO and QCM provided that adequate qualifications are provided.

&F &P of &N