This is a Department of Veterans Affairs (VA) Solicitation for Sealed Bid (IFB) for a construction project to create a Contractor Lay-Down Zone at Jesse Brown VA Medical Center in Chicago, IL. The solicitation (36C25225B0017) is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a project magnitude between $100,000 and $250,000 under NAICS code 236220.

Key project details include creating a contractor lay-down zone involving ground preparation, installing four 20-foot marine-grade storage containers, extending electrical power, fencing the area, and constructing a vehicle access ramp. The project has a 265-calendar day performance period, with a pre-bid site visit scheduled for July 16, 2025, and bid opening on August 27, 2025. Contractors must be certified SDVOSB, comply with VA specifications, and submit detailed documentation including safety records, insurance information, and capability statements. Specific requirements include installing electrical panels, energy meters, LED lighting, and ensuring proper ground preparation with drainage and bearing capacity specifications.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25225B0017

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATIONSOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 77

36C25225B0017 X 07-01-2025

537-25-2-6957-0001 537-24-106

36C252

Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101

Milwaukee WI 53214-1476

Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101

Milwaukee WI 53214-1476

Richard Goodman 414-844-4874

Project: 537-24-106 Create a Contractor Lay-Down Zone Construction at Jesse Brown VA Medical Center, Chicago, IL.

Contractor shall provide for and furnish all labor, materials, equipment, supervision, and other items designated in this contract in accordance with (IAW) the specifications and drawings to complete the project 537-24-106.

The project magnitude range is between $100,000 and $250,000.

NAICS 236220: Commercial and Institutional Building Construction/ Size Standard $39.5 million applies

This procurement is a 100% set aside for CVE-Verified Service-Disabled Veteran Owned Small Business (SDVOSB) firms per the authority of 38 U.S.C. 8127(d) Public Law 109-461. In accordance with VAAR 819.7003(b), at the time of submission of offers and prior to award of any contracts, the offeror must represent to the CO that it is a (1) SDVOSB eligible under VAAR Subpart 819-70; (2) Small business concern underthe North American Industry Classification System (NAICS) code assigned to this acquisition; and, (3) SDVOSB listed as verified in SBA DSBS/VETCERT.

Ensure you complete the certification for VAAR 852.219-75; failure to complete will result in your bid being non-responsive and not eligible for evaluation and award.

NOTICE: VA and/or a third party (support contractor) will require access to VA contractor records to assess contract compliance with the limitations on subcontracting requirements included in VAAR 852.219-75 LIMITATIONS ON SUBCONTRACTING

If submitting as a joint-venture, offerors must include a copy of the joint-venture agreement.

All offerors are responsible for monitoring and downloading all amendments from Contract Opportunities at the following website: https://sam.gov/content/opportunities

PRE-BID SITE VISIT: Wednesday July 16, 2025, at 1PM Local Time.

Check-in required at Ogden Visitors Desk. Bidders are encouraged to attend. SEE "SPECIAL INSTRUCTIONS TO BIDDERS"

REQUEST FOR INFORMATION (RFI): Due NLT July 28, 2025 at 4:00P.M. Local Time. All RFI's shall be submitted in writing via email to the Contract Specialist at richard.goodman1@va.gov. Please reference Solicitation # 36C25225B0017.

NO TELEPHONE INQUIRIES WILL BE ACCEPTED. ONLY WRITTEN INQUIRIES WILL BE ACCEPTED.

BID OPENING: DATE: August 27, 2025 at 11:00 A.M. Local Time.

BID OPENING LOCATION: 115 South 84th Street, Milwaukee, WI.53214.

Contractors please report to Suite 101, main entrance and to the left.

14 265

X X 52.211-10

X 10

1 11:00 CDT

08-27-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

See Bid Schedule

Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476

Department of Veterans Affairs Financial Services Center PO Box 149971 Austin TX 78714-9971

Ryan McMillin Contracting Officer

CONTRACTOR INFORMATION:

Name of Company:

Name:

Title:

Address:

E-Mail Address:

Phone Number:

Fax Number Tax ID Number Duns Number SAMs UEI Number

CONTRACT ADMINISTRATION DATA

1. CONTRACTOR REMITTANCE ADDRESS: Effective January 1, 1999 all payments by the Government to the contractor will be made in accordance with Federal Acquisition Regulation (FAR) Clause 52.232-34, Payment by Electronic Funds Transfer. Contractor must be registered in the System for Award Management (SAM) database in accordance with FAR Clause 52.212-1(k).

2. SUBMITTAL OF BIDS: All bids must be submitted to the attention of the Contract Specialist identified. Please submit the information in accordance with the "Bid Due Date" in Block 13 of the SF 1442. No Later Than the date/time specified.

3. REQUESTS FOR INFORMATION: Requests for Information (RFI) or clarifications to solicitation documents are to be submitted in writing to the Contract Specialist at:

Richard.goodman1@va.gov. Requests received after the deadline may not be addressed. NOTE:

All questions must reference in the Header or Opening Statement the Project #, the IFB #, and the Description of the project. No telephone inquiries will be accepted.

ONLY WRITTEN INQUIRIES WILL BE ACCEPTED.

4. CONTRACT AUTHORITY: The Contracting Officer is the only person authorized to approve changes or modify any of the requirements of this request. The Contractor shall communicate with the Contracting Officer on all matters pertaining to Contract Administration. Only the Contracting Officer is authorized to make commitments or issue changes that affect pricing, quantities or quality of performance of this contract.

BID SCHEDULE

VA Project Number: 537-24-106 Construct a Contractor Lay-Down Zone

Price Range: $100,000.00 to $250,000.00

001 All-Inclusive Base Bid: The contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with federal, state, and local authorities, project specifications, and drawings necessary to complete the construction of this project at the Jesse Brown VA Medical Center, Chicago, Illinois.

All work shall be completed within 265 calendar days after receiving the notice to Proceed

(NTP).

All-Inclusive Base Bid LUMP SUM: $ ___________________________

NOTICE TO BIDDERS: Award will be made to the responsible bidder who submitted the lowest responsive bid. Work shall not commence until all required submittals are approved by the Contracting Officer or the Contracting Officer’s Representative (COR). An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.

NOTICE TO BIDDERS: Additional information regarding the general and specific scope of work is defined in the specifications and drawings. This BID SCHEDULE is in addition to and augments the specifications and drawings. ONLY ONE AWARD WILL BE MADE AS A

RESULT OF THIS SOLICITATION.

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE

AND BONDS

(a) This solicitation & all associated bid documents are available to interested parties in electronic file format from www.fedbizops.gov. No hard copy documents will be provided by the government.

(b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $2,000,000. Failure to furnish the required bid guarantee on form SF24, in the proper amount, by the time set for opening of bids, will result in rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) The bidder to whom a contract is awarded will be required to furnish a Payment Bond, on form SF25A, and a Performance Bond, on form SF25. Each bond shall be issued for a penal sum equal to the value of the awarded contract. Copies of forms SF25 and SF25A may be obtained from the Contracting Officer upon request.

(d) Bidders are to ensure the most current version of SF24, SF25, and SF25A bond forms are used. Current versions of these forms can be found and downloaded from the GSA Forms Library (https://www.gsa.gov/portal/forms/type/TOP).

COMPLIANCE WITH VHA DIRECTIVE 1192.01

VHA Directive 1192.01 issued August 10, 2020, requires all contractor personnel to receive annual seasonal influenza vaccinations or obtain an exemption for medical or religious reasons. Compliance with this directive is a requirement of this contract. A copy of VHA Directive 1192.01 is available at this link:

https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=&ved=2ahUKEwi0t7CAj_DrAh XDgnIEHbVSCwgQFjAAegQIBRAB&url=https%3A%2F%2Fwww.va.gov%2Fvhapublications%2FVie wPublication.asp%3Fpub_ID%3D8948&usg=AOvVaw1Rwijbc9Z5WL5ilsgWoagN

Federal Acquisition Regulation (FAR) Class Deviation to Implement Section 2 of Executive Order (E.O.) 14148, “Initial Rescissions of Harmful Executive Orders and Actions,” which revoked Executive Order 14057, and Section 2 of E.O. 14208, “Ending Procurement and Forced Use of Paper Straws,” February 10, 2025 System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications— Commercial Products and Commercial Services.

Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Contracting Officer’s Special Instructions as follows:

After compiling all required information, submit the information in accordance with Block 13 of the SF 1442 (page 1 of this solicitation). Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442 (page 1 of this solicitation).

INQUIRIES:

Written requests for information or clarifications to solicitation documents are requested to be submitted to the Contracting Officers at ryan.mcmillin@va.gov and Contract Specialist, at Richard.goodman1@va.gov for action no later than 4:00 pm July 28, 2025. Requests received after this deadline may not be addressed. Telephone inquiries will not be accepted.

Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contracting Officer referenced in the solicitation. YOU ARE INSTRUCTED

SPECIFICALLY TO CONTACT ONLY THE CONTRACTING OFFICER ISSUING THE

SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT

AWARD.

CONTRACTOR'S SIGNATURE:

In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows:

(a) Individuals. A contract with an individual shall be signed by that individual. A contract with an individual doing business as a firm shall be signed by that individual, and the signature shall be followed by the individual’s typed, stamped, or printed name and the words “, an individual doing business as _______________________________” [insert name of firm].

(b) Partnerships. A contract with a partnership shall be signed in the partnership name. Before signing for the Government, the contracting officer shall obtain a list of all partners and ensure that the individual(s) signing for the partnership have authority to bind the partnership.

(c) Corporations. A contract with a corporation shall be signed in the corporate name, followed by the word “by” and the signature and title of the person authorized to sign. The contracting officer shall ensure that the person signing for the corporation has authority to bind the corporation.

(d) Joint venturers. A contract with joint venturers may involve any combination of individuals, partnerships, or corporations. The contract shall be signed by each participant in the joint venture in the manner prescribed in paragraphs (a) through (c) of this section for each type of participant.

When a corporation is participating, the contracting officer shall verify that the corporation is authorized to participate in the joint venture.

(e) Agents. When an agent is to sign the contract, other than as stated in paragraphs (a) through

(d) of this section, the agent’s authorization to bind the principal must be established by evidence satisfactory to the contracting officer.

ADDITIONAL PRIME CONTRACTOR INFORMATION - Safety or Environmental Violations and Experience Modification Rating Information

1.) All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

2.) All Bidders/Offerors shall submit information regarding their current Experience

Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

3.) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

4.) If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.

5.) The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

6.) This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

PRE-AWARD CONTRACTOR SAFETY AND ENVIRONMENTAL RECORD

EVALUATION FORM

Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ DUNS Number: ________________________________________________ SAM’s UEI Number: ____________________________________________ Contact: ______________________________________________________

1. Utilizing your OSHA 300 Forms, please complete the following information:

Category 2022 2023 2024 Number of man hours (jobsite and office).

Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).

Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.

Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page:

http://www.osha.gov/pls/publications/publication.html.

2. Provide your six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________

3. Who administers your company’s Safety and Health Program?

4. Company’s Insurance Experience Modification Rate (EMR): _____________

Illinois State Sales Tax Exemption:

The Illinois Administrative Code, 130.2075 allows construction contractors to be exempt from Retailers Occupation Tax and Use Tax within the State of Illinois when the materials are for Incorporation into real estate owned by Governmental bodies. For purposes of this authority, a Construction Contractor is defined as a General Contractor or a Subcontractor 86 Ill.Adm.Code 130.1940(a)(1). Materials, are defined as all of the tangible personal property, including fixtures, which enter into a structure or otherwise become incorporated into real estate 86 Ill.Adm.Code 130.1940(a)(5), but do not include tools, fuel, lumber for forms and other end use or consumption items which are not incorporated into the real property 86 Ill.Adm.Code 130.2075(d)(3).

Prospective offerors are notified that under 86 Ill.Adm.Code 130.2075, purchase of applicable materials within the State of Illinois to be incorporated into the real property of Jesse Brown VA Medical Center may be exempt from Illinois Retailers’ Occupation Tax and Use Tax. VA will furnish a Certificate to the successful awardee under this solicitation that contains appropriate information that will allow the awardee to take advantage of this tax exemption within the State of Illinois for the project identified in this solicitation. Prime contractors may furnish the certificate to its subcontractors for use on this project. All offers received in response to this solicitation are presumed to reflect any tax benefit that may be realized upon receipt of this certificate.

CONSTRUCTION STATEMENT OF WORK FOR

Project Name: Create a Contractor Lie-Down Zone

Project Number: 537-24-106

Place of Performance: Building 1A, Eastern Exterior Grounds.

Jesse Brown VA Medical Center 820 S. Damen Ave Chicago IL 60612

Part 1: Project Scope of Work Overview Prepare the ground in the designated zone.

Extend Electric Power to designated Trailer locations.

Place Trailers in designated locations.

Fence and Gate the designated zone.

Ramp the curb to give easy access to vehicles entering/exiting the zone.

Part 2: Period of Performance (POP) and Project Construction Cost Magnitude Complete all work including submittals and quality control reviews within the calendar days from Notice to Proceed (NTP) as shown below.

537-24-106 Construction Period of Performance (PoP)

Level Complete Calendar Days for the

Work VA Review

Total days after

NTP

Task 1 – Project Kick-off submittals 7 14 21

Task 2 – Coordination 14 14 49

Task 3 – Pre-Construction submittals 45 14 108

Task 4 – Mobilizations and Performance of Work 115 14 237

Task 5 – Closeout Submittals 14 14 265

Part 3: Detailed Project Scope of Work The contractor must meet all the requirements of the following construction documents:

1. 537-24-106 Construction Document Issued for Bid, Design and Construction.

2. 537-24-106 Specifications listed for Bid, Design and Construction.

GENERAL PROJECT GOALS

The goal of this project is to create a “Lie-Down” Zone for temporary construction/utility activities.

The Contractor/Builder is required to:

1. Design and Provide all Permits, Plans, Tools, Materials, Components, Labor, and Supervision for Creating a Contractor Lie-Down Zone.

2. Scan and Mark Underground Utilities throughout the Designated Plot.

3. Clear the Designated Plot of Trees, Roots, and any large debris that may obstruct the scope of work. Dispose of all waste. Refer to Exhibit B – Site Pictures.

4. A licensed GEOTECHNICAL ENGINEER (hired by GC) shall examine soil type.

5. Excavate, and dispose of soil to the depth specified by the licensed GEOTECHNICAL

ENGINEER to achieve the specified drainage and bearing pressure rating.

6. Compact the ground, lay a weed barrier fabric, fill to level with Heavy-Duty Gravel, utilize a Heavy-Duty gravel grid and sand. The finished product shall be able to efficiently drain and have a minimum bearing pressure rating of 8000 PSF, no mud/pooling/ settling shall occur. Refer to VA Specifications Section 31 20 00 (Earthwork).

7. Furnish and install four (4) Marine Grade, 20 feet Long by 8 feet Wide, High-Cube Storage Containers. The Containers shall be brand new. Each Container shall rest on footings, raised eight (8) inches from the ground, refer to Exhibit A - Plot Layout.

8. Furnish and install a 9 Gauge, 7-feet high Chain Link Fence around the Designated Plot, install a 20-Ft Gate as noted in Exhibit A – Plot Layout, and per VA Specifications Section 32 31 13 (Chain Link Fences And Gates). Provide A Sliding Gate lock with a Best 7-pin Mortise.

9. Furnish and Install three (3) 200A, 110V, 12 space Breaker Panels in Closet 14E6 to feed the Contractor Lay-Down Zone. The new panels shall be fed from Switch Gear LP- 1-1 located in Closet 14E5. VA will provide names to the new panels. Refer to VA Specifications Section 26 05 11 (REQUIREMENTS FOR ELECTRICAL

INSTALLATIONS)

The new panels shall have excess capacity for the outlined Breaker-Equipped Enclosures, lights, and the future expansion of an equal number of Breaker-Equipped Enclosures. Refer to VA Specifications Section 26 24 13 (Distribution Switchboards) and Section 26 11 16 (SECONDARY UNIT SUBSTATIONS).

10. Furnish and Install four (4) Energy Meters, one meter to feed and monitor energy usage for every container. Use Honeywell E-Mon™ Class 1000 Single Phase Pulse Meter or an approved equivalent.

11. Feed Power from the aforementioned subpanels to the Containers via the Energy Meters. Conductors shall exit the building via a Weather Head. Use Outdoor-rated Armored Cable to feed each Container. Lay the Cable atop containers, connect each cable to a Container via a Weather Head according to VA Specifications Sections 26 27 26 (Wiring Devices) and Section 26 05 19 (Low-Voltage Electrical Power Conductors and Cables).

12. Terminate the Armored Cable inside Each Container with two Contractor Furnished double gang boxes and four GFCI outlets in accordance with VA Specifications Section 26 27 26 (Wiring Devices) and Section 26 29 21 (Enclosed Switches And Circuit Breakers). Junction Boxes shall be installed 12 inches above floor and five feet from each end of container. Each Container shall have a dedicated breaker on the corresponding subpanel to control its outlets.

13. Furnish and install LED Shop Light Fixtures inside each container. Light Fixtures shall be centered along the ceiling. Illumination level shall be 60 lumens per square-foot. Lights inside each Container shall be controlled by two light switches in a 3-pole fashion. Install one light switch on each side, within eight inches from the entrance. Each Container shall have a dedicated breaker on the corresponding subpanel to control its lights.

14. Furnish and install Photocell Light Fixtures. Position the light fixtures to achieve full illumination of the Contractor Lay-Down Zone – pull feed from new subpanels. Refer to VA Specifications Section 26 56 00 (EXTERIOR LIGHTING) and SECTION 26 09 23

(LIGHTING CONTROLS).

15. Refinish/demolish and reconstruct sidewalk and curb to fit a ramp to ease vehicles access to the gated zone. Refer to SECTION 32 05 23 (CEMENT AND CONCRETE

FOR EXTERIOR IMPROVEMENTS)

List of Exhibits included for reference:

a. Plot Layout

b. Site Pictures

c. Specifications

Record Documents: Recording as-built drawings is a responsibility of the general contractor during the construction process.

Construction Progress Meetings: The Contractor’s Superintendent and Project Manager must provide biweekly teleconference construction progress meetings with the COR for the period of Construction. Attendees list will be modified based on the phase needs.

a. Submit construction progress meeting minutes issued not later than one day after the meeting using Jesse Brown Construction Project Tracker. Meetings minutes must contain:

a. List of attendees

b. Contract Status: percentage of completion, days remaining per the contract, original contract amount, modifications to date, payment amount to date.

c. List any issues or concerns.

d. Safety incidents.

e. RFI Log.

f. Submittal Log.

g. Detailed 2-week look ahead and shutdown schedule.

b. Field crews must collect data and information as job progresses capturing all changes and modifications during construction on red line drawing plan set. Red-line drawings will be reviewed by the COR during each progress meeting.

Task 1 – Project Kick-off: Contractor’s Quality Control Manager and Superintendent must attend an on-site kick-off meeting, to discuss the project details.

a. Submit construction baseline schedule fulfilling the requirements of the contract.

b. Submit a schedule of values matching the format of VA Form 10-6001a. The schedule of value must match construction activities shown on the baseline schedule.

c. Submit VA Great Lakes Acquisition Center Subcontractor Payment Summary Form.

d. Submit a list of all contractors and subcontractors: company names, office address and main point of contact name with telephone number.

e. Submit all required key field staff Resumes for VA approval.

f. Provide a comprehensive submittal and RFI logs.

g. Submit scanned copy of all workers OSHA construction safety training certificates.

h. Submit copies of all required state license and registrations. See Requirements on Project

Specifications and Part 6.

Task 2 – Coordination: Contractor must make all necessary field measurements and investigations to create work zones to minimize shutdowns.

1. Submit comprehensive site visit schedule. The VA will provide escorts and provide access to the areas as shown on the approved site visit schedule.

2. Submit shop drawing identifying work zones. Provide a table with rooms numbers per zone.

3. Submit a detailed construction schedule showing specific work zones and the proposed work zone sequence.

a. Show all anticipated system shutdowns. See Part 6 for system shutdown requirements.

b. Show VA inspection schedule per work zone.

Task 3 – Pre-Construction: Contractor must not mobilize on site until all Pre-Construction requirements are met.

1. Submit product data, shop drawings, finishes samples and all other required documentation.

See project constructing drawings and specification manual for all requirements. See Part 4 for submittal procedures.

All construction submittals must be reviewed and approved by the VA prior to issuance of the Mobilization Authorization Letter. Contractor must not begin Task 4 until all the requirements of tasks 1, 2 and 3 have been fulfilled.

Task 4 – Mobilization and Performance of the Work: Contractor must meet all the requirements of the construction documents. See Part 3 for construction documents list.

1. Contractor must not start the work in any area of the campus without VA COR approval.

2. At entry points to the work zone post and maintain emergency contact information, VA

Project Risk Assessment, and any other information required by the COR.

3. The Contractor must furnish to the COR, for each workday, a consolidated report for the preceding workday. Reporting must begin from date of contractor mobilization until the date of final acceptance. VA Form 10101, Contractor Production Report must be signed, dated, and submitted by the Contractor’s Superintendent. Each report must include and specifically identify at least one safety topic germane to the jobsite that day.

4. VA will perform site inspections. Contractor must address deficiencies or policies violations identified the same day the deficiency notice is issued. The Contracting Officer may issue and order stopping all or part of the work until satisfactory corrective action has been taken.

No part of the time lost due to such stop order is acceptable as the subject for claim for extension of time, for excess cost or damages by the Contractor.

5. Prior to each inspection and at date of demobilization, the Contractor must deep clean all disturbed areas to a condition equal to or better than original condition.

Task 5 – Closeout: Provide three printed sets and upload to Submittal Exchange each closeout submittal. See project specification manual for all other Close Out requirements.

1. As-built Drawings must be in PDF and .DWG file formats. As-built drawings must show the tag number for all shutoff valves installed and identify the isolation zone for each shut-off valve.

2. The Contractor must provide an itemized table with all installed equipment and parts. The table must include but not to be limited to manufacturer, model number, serial, number, location (building and room number), tag number, capacity, setting, pressure, flow, voltage, amperage, etc. PDF and excel spreadsheet are required.

3. Operations and Maintenance Manuals (all cut sheets must have the installed product highlighted)

All construction submittals must be reviewed and approved by the VA prior to issuance of the Acceptance Letter.

Part 4: Procedures Submittals: The Contractor must provide all shop drawings and product submittals via Submittal Exchange. All submittals’ deadlines per Part 2 Period of Performance. Allow 14 calendar days for VA review of each submittal.

Work Zone Acceptance: The Contractor must schedule walk through inspection with the VA COR for each work zone (Inpatient Room). The VA COR will coordinate with the VA Maintenance and Operations team and all VA staff required to attend to the inspection.

1. Submit work zone substantial completion letter certifying the Contractor has completed their quality control measures.

2. Room final cleanup as described in Section 01 35 26 must be completed by the Contractor prior to pre-final inspection.

3. Schedule work zone pre-final inspection at 8:00am on a Weekday.

a. Contractor must demonstrate the operation of the existing system(s). One demonstration of the correct operation of the system is required. If the demonstration does not show expected operation, the Contractor must make required system adjustments and schedule a retest.

b. Submit construction inspection findings and identified deficiencies (“Punchlist”) for COR review.

4. Punchlist items must be addressed before the final inspection can be scheduled.

5. Work Zone must be accepted prior to beginning work on next work zone as identified in the approved construction scheduled, work zone sequence.

6. All work will be provided with, at minimum, 1-year parts and labor warranty from date of acceptance by the VA.

Part 5: Applicable Performance Standards

Contractor must comply with all applicable federal, state, and local codes and regulations, and VA Codes, Standards and Executive Orders including but not limited to:

1. PG-18-3 Design and Construction Procedures

a. Local Code: VA must function as the Authority Having Jurisdiction (AHJ) and thus has the responsibility to guard public health and safety through enforcing its adopted codes.

VA will adopt the following: Department of Labor Occupational Safety and Health Administration, City of Chicago Building Code, Illinois Plumbing Code, and Illinois Professions, Occupations, and Business Operations.

2. Jesse Brown VAMC Construction Safety Policy including but not limited to:

a. Key Contractor and Subcontractor Staff shall have completed the 30 Hour OSHA Construction Safety Training program.

b. The Prime Contractor must always have a Competent Site Safety and Health Officer on site when any worker(s) or sub-contractors are present.

c. Individuals working on any electrical systems rated 50 volts or more must have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, all activities must follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

3. Jesse Brown VAMC site-specific requirements and Standard Operation Procedures, including but not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy. Use clip on badge holders so the adhesive sign-in badges do not fall off and are in view.

4. All work will be provided with one-year parts and labor warranty from date of acceptance by

VA.

Part 6: Jesse Brown VAMC Requirements

1. General Requirements

a. Approval to mobilize must be in writing by the VA.

b. Project number and the contract number must be in the subject line of all emails.

c. Recycling and receipts from the salvage / deposal service in compliance with VA’s

GEMS must be provided with every payment request.

d. No speakers or radios for the playing of music must be allowed on the job site. Two-way communications radios are allowed where broadcast frequency is approved by

COR.

2. Work Hours Restrictions

a. Normal construction hours are flexible an can be planned with the COR . Weekend work can be planned if deemed necessary.

b. No work by the Contractor on Federal Holidays, and no work on the associated weekend when the Federal Holiday is on the respective Monday or Friday unless otherwise specified by COR.

c. Any work including, but not limited to: Noise, vibration, dust, odors, core drilling, hammer-drilling, saw-cutting, equipment moving in public corridors, or similar noise-producing activities adjacent to a patient room (floor above and below included) must be performed when such room is unoccupied.

3. Site Access

a. Before starting work at each work zone, the Contractor must post signs on all doors within the zone no later than 7 calendar days in advance to notify users. See project specification manual for sign template. This notice is separate from any notices required for utility shutdown described later in this section.

b. For work taking place inside the Hospital, the Contractor must check in (in person) with the Ogden Security Desk which is located on the Ogden Entrance main lobby for any work and site visit. Contractor must present their ID to get a Vendor’s Day Pass.

Vendors that have a VA issued ID are still required to get a Day Pass.

c. For work taking place inside the Hospital, the Contractor must check-in (in person) with the Administrative Officer of the Day (AOD) which is in Patient Admitting for any work between 5:00 PM to 6:00 AM, Monday through Friday and any time on weekends.

Provide the name and cell number of the on-site supervisor to the AOD. At the completion of the workday, check out with the AOD.

4. Shutdowns

a. All building systems will always be maintained in full operation.

b. Request system shutdowns in writing not less than 14 calendar days in advance.

c. System shutdown work must be during low patient demand times performed starting

Saturday 10PM to Sunday 3AM unless otherwise authorized in writing by the COR.

5. Safety and Security

a. The Contractor must submit a project specific Safety Plan per Project Specification

Manual. Contractor must provide mitigating activities as outlined in the Project Risk Assessment for Safety and Interim Life Safety Measures including but not less than the following:

Fire extinguishers, pedestal mounted in the area of work.

Provide uniform heat detection in the area of work, connected to the existing supervised building master fire alarm system, for the duration of the work whenever the: Ceiling tiles are removed, or sprinkler system is disabled.

Fire-seal all penetrations through any wall or floor with UL Listed fire-rated materials or assemblies manufactured for the purpose.

b. No on-site office is allowed. No on-site storage of tool or material is allowed. Provide ‘just-in-time delivery and pickup’. Coordinate with COR for staging within the work zone 4 days prior to the beginning of the work.

c. The floor slabs are not water-tight and will leak to the floor below. Provide precautions to prevent spills.

d. No photography of VA premises is allowed without written permission of the COR.

e. VA reserves the right to close or shut down the project site and ask Contractor’s employees to leave the premises in the event of an emergency, or operational requirement. The Contractor may return to the site only with the written approval of the

CO.

f. Immediately stop work and notify the CO/COR if asbestos is noticed or suspected in the area of work.

6. Deliveries, Parking, Elevators

a. Deliveries are to be coordinated with COR. Use only the Polk Street dock. Coordinate with the COR minimum 4 days prior to the delivery date.

b. At time of delivery: provide vehicle information to the COR and remove the vehicle as soon as delivery is complete.

c. Delivered materials cannot be staged longer than 7 calendar days. Do not move materials in public corridors between 7:00AM and 6:00PM.

d. Vendors are not allowed to park anywhere on-site or in the VA garage. Utilize street parking or other parking structures such as the Cook County Juvenile Parking Garage at their daily rate. It is the General Contractor’s responsibility to ensure that all project workers are aware and follow this requirement.

e. Contractor must only use Freight Elevators. Do not move materials and employees in passenger elevators unless written approval by COR.

7. Infection Control

a. Risk classifications of this project is Class II.

b. Provide mitigation activities as outlined in the Project Specifications.

c. Walk-off dust mats, inside and outside all entry / exit points to the workspace, changed not less than daily or more as required by the construction or COR.

d. Contractor must clean and disinfect all rooms and corridors before removing infection control barriers. Cleaning, sanitizing, and disinfecting procedure written narrative and product data sheets must be included in the infection control plan for VA review and acceptance.

Cleaning: Remove debris, organic substances, and other visible soil directly from surfaces and objects. A mixture of soap or detergent with water must be used to scrub and wipe down surfaces.

Disinfecting: A hospital-grade disinfectant must be used. Disinfectant product must not leave a residue behind and must not require any further rinsing or wiping after it has been applied. Remove and disinfect every detachable item in the room and then properly disinfect air ducts, light fixtures, and all surfaces from the ceiling down to the floor. Thoroughly wipe down doorknobs and railings using a disposable wipe soaked in disinfectant cleaner. High-touch areas must also be wiped down.

e. The entire work zone must be vacuum cleaned with HEPA filtered vacuums and wet mop with disinfectant every workday before the end of the workday. See Part 6 Item 2 for workday hours.

f. Infection control barriers in areas impeding VA staff from performing their duties must be removed every day before the end of the workday and reinstall at the beginning of the following workday if work within that area has not been completed.

g. No trash, used packaging, or construction debris must be stored on site. Remove trash and construction debris each day using covered gondolas. No dumpster will be allowed onsite.

h. See project specification manual for all other infection control requirements.

8. Compatible System procurements must be as follows:

a. Security Card Access Control: provide a complete and fully functional extension of the existing card access control system including card access readers and electric door strikes. Include programming, licenses, and startup. The existing system is compatible with the VA identification cards is Avigilon Security System.

9. All field staff is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.2 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I

(FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— July 16, 2025, at 1pm local time.

(c) Participants will meet at— Ogden entrance of Jesse Brown VA Medical Center at 820 S

Damen Avenue, Chicago, IL 60612.

(End of Provision)

2.3 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN

2025) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $45 Million.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award…