36C25225B0017_1.docx

DOCX document 117 KB Posted

Attached to
Z2DA--537-24-106 Create a Contractor Lay-Down Zone
Solicitation number
36C25225B0017
Issued by

About this file

This is a Solicitation (Standard Form 1442) for a construction project to create a Contractor Lay-Down Zone at Jesse Brown VA Medical Center in Chicago, Illinois. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) firms, with a project magnitude range between $100,000 and $250,000 under NAICS code 236220. Key project details include constructing a designated zone with four marine-grade storage containers, installing electrical infrastructure, fencing, and associated site improvements.

Critical dates include a pre-bid site visit on July 16, 2025, Request for Information (RFI) deadline of July 28, 2025, and bid opening on August 27, 2025 at 11:00 AM CDT. The contract requires completion within 265 calendar days after receiving the Notice to Proceed. Contractors must be CVE-Verified SDVOSB firms, small businesses under the assigned NAICS code, and listed in the SBA's verification database. The project involves detailed electrical, site preparation, and infrastructure work, with specific requirements for container placement, power distribution, fencing, and site access modifications.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

None 36C25225B0017 X 07-01-2025 537-25-2-6957-0001 537-24-106 36C252 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee

WI

53214-1476 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee

WI

53214-1476 Richard Goodman 414-844-4874 Project: 537-24-106 Create a Contractor Lay-Down Zone Construction at Jesse Brown VA Medical Center, Chicago, IL.

Contractor shall provide for and furnish all labor, materials, equipment, supervision, and other items designated in this contract in accordance with (IAW) the specifications and drawings to complete the project 537-24-106.

The project magnitude range is between $100,000 and $250,000.

NAICS 236220: Commercial and Institutional Building Construction/ Size Standard $39.5 million applies

This procurement is a 100% set aside for CVE-Verified Service-Disabled Veteran Owned Small Business (SDVOSB) firms per the authority of 38 U.S.C. 8127(d) Public Law 109-461. In accordance with VAAR 819.7003(b), at the time of submission of offers and prior to award of any contracts, the offeror must represent to the CO that it is a (1) SDVOSB eligible under VAAR Subpart 819-70; (2) Small business concern underthe North American Industry Classification System (NAICS) code assigned to this acquisition; and, (3) SDVOSB listed as verified in SBA DSBS/VETCERT.

Ensure you complete the certification for VAAR 852.219-75; failure to complete will result in your bid being non-responsive and not eligible for evaluation and award.

NOTICE: VA and/or a third party (support contractor) will require access to VA contractor records to assess contract compliance with the limitations on subcontracting requirements included in VAAR 852.219-75 LIMITATIONS ON SUBCONTRACTING

If submitting as a joint-venture, offerors must include a copy of the joint-venture agreement.

All offerors are responsible for monitoring and downloading all amendments from Contract Opportunities at the following website: https://sam.gov/content/opportunities

PRE-BID SITE VISIT: Wednesday July 16, 2025, at 1PM Local Time.

Check-in required at Ogden Visitors Desk. Bidders are encouraged to attend. SEE "SPECIAL INSTRUCTIONS TO BIDDERS"

REQUEST FOR INFORMATION (RFI): Due NLT July 28, 2025 at 4:00P.M. Local Time. All RFI's shall be submitted in writing via email to the Contract Specialist at richard.goodman1@va.gov. Please reference Solicitation # 36C25225B0017.

NO TELEPHONE INQUIRIES WILL BE ACCEPTED. ONLY WRITTEN INQUIRIES WILL BE ACCEPTED.

BID OPENING: DATE: August 27, 2025 at 11:00 A.M. Local Time.

BID OPENING LOCATION: 115 South 84th Street, Milwaukee, WI.53214.

Contractors please report to Suite 101, main entrance and to the left.

X X 52.211-10 X 11:00

CDT

08-27-2025 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

See Bid Schedule Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee

WI

53214-1476 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin

TX

78714-9971 Ryan McMillin Contracting Officer

CONTRACTOR INFORMATION:

Name of Company:

Name:

Title:

Address:

E-Mail Address:

Phone Number:

Fax Number

Tax ID Number

Duns Number

SAMs UEI Number

CONTRACT ADMINISTRATION DATA

1. CONTRACTOR REMITTANCE ADDRESS: Effective January 1, 1999 all payments by the Government to the contractor will be made in accordance with Federal Acquisition Regulation (FAR) Clause 52.232-34, Payment by Electronic Funds Transfer. Contractor must be registered in the System for Award Management (SAM) database in accordance with FAR Clause 52.212-1(k).

2. SUBMITTAL OF BIDS: All bids must be submitted to the attention of the Contract Specialist identified. Please submit the information in accordance with the "Bid Due Date" in Block 13 of the SF 1442. No Later Than the date/time specified.

3. REQUESTS FOR INFORMATION: Requests for Information (RFI) or clarifications to solicitation documents are to be submitted in writing to the Contract Specialist at: Richard.goodman1@va.gov. Requests received after the deadline may not be addressed. NOTE: All questions must reference in the Header or Opening Statement the Project #, the IFB #, and the Description of the project. No telephone inquiries will be accepted.

ONLY WRITTEN INQUIRIES WILL BE ACCEPTED.

4. CONTRACT AUTHORITY: The Contracting Officer is the only person authorized to approve changes or modify any of the requirements of this request. The Contractor shall communicate with the Contracting Officer on all matters pertaining to Contract Administration. Only the Contracting Officer is authorized to make commitments or issue changes that affect pricing, quantities or quality of performance of this contract.

BID SCHEDULE

VA Project Number: 537-24-106 Construct a Contractor Lay-Down Zone Price Range: $100,000.00 to $250,000.00 001 All-Inclusive Base Bid: The contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with federal, state, and local authorities, project specifications, and drawings necessary to complete the construction of this project at the Jesse Brown VA Medical Center, Chicago, Illinois.

All work shall be completed within 265 calendar days after receiving the notice to Proceed (NTP).

All-Inclusive Base Bid LUMP SUM: $ ___________________________

NOTICE TO BIDDERS: Award will be made to the responsible bidder who submitted the lowest responsive bid. Work shall not commence until all required submittals are approved by the Contracting Officer or the Contracting Officer’s Representative (COR). An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.

NOTICE TO BIDDERS: Additional information regarding the general and specific scope of work is defined in the specifications and drawings. This BID SCHEDULE is in addition to and augments the specifications and drawings. ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) This solicitation & all associated bid documents are available to interested parties in electronic file format from www.fedbizops.gov. No hard copy documents will be provided by the government.

(b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $2,000,000. Failure to furnish the required bid guarantee on form SF24, in the proper amount, by the time set for opening of bids, will result in rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) The bidder to whom a contract is awarded will be required to furnish a Payment Bond, on form SF25A, and a Performance Bond, on form SF25. Each bond shall be issued for a penal sum equal to the value of the awarded contract. Copies of forms SF25 and SF25A may be obtained from the Contracting Officer upon request.

(d) Bidders are to ensure the most current version of SF24, SF25, and SF25A bond forms are used. Current versions of these forms can be found and downloaded from the GSA Forms Library (https://www.gsa.gov/portal/forms/type/TOP).

COMPLIANCE WITH VHA DIRECTIVE 1192.01

VHA Directive 1192.01 issued August 10, 2020, requires all contractor personnel to receive annual seasonal influenza vaccinations or obtain an exemption for medical or religious reasons. Compliance with this directive is a requirement of this contract. A copy of VHA Directive 1192.01 is available at this link:

https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=&ved=2ahUKEwi0t7CAj_DrAhXDgnIEHbVSCwgQFjAAegQIBRAB&url=https%3A%2F%2Fwww.va.gov%2Fvhapublications%2FViewPublication.asp%3Fpub_ID%3D8948&usg=AOvVaw1Rwijbc9Z5WL5ilsgWoagN Federal Acquisition Regulation (FAR) Class Deviation to Implement Section 2 of Executive Order (E.O.) 14148, “Initial Rescissions of Harmful Executive Orders and Actions,” which revoked Executive Order 14057, and Section 2 of E.O. 14208, “Ending Procurement and Forced Use of Paper Straws,” February 10, 2025 System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications— Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Contracting Officer’s Special Instructions as follows:

After compiling all required information, submit the information in accordance with Block 13 of the SF 1442 (page 1 of this solicitation). Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442 (page 1 of this solicitation).

INQUIRIES:

Written requests for information or clarifications to solicitation documents are requested to be submitted to the Contracting Officers at ryan.mcmillin@va.gov and Contract Specialist, at Richard.goodman1@va.gov for action no later than 4:00 pm July 28, 2025. Requests received after this deadline may not be addressed. Telephone inquiries will not be accepted.

Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contracting Officer referenced in the solicitation. YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT AWARD.

CONTRACTOR'S SIGNATURE:

In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows:

(a) Individuals. A contract with an individual shall be signed by that individual. A contract with an individual doing business as a firm shall be signed by that individual, and the signature shall be followed by the individual’s typed, stamped, or printed name and the words “, an individual doing business as _______________________________” [insert name of firm].

(b) Partnerships. A contract with a partnership shall be signed in the partnership name. Before signing for the Government, the contracting officer shall obtain a list of all partners and ensure that the individual(s) signing for the partnership have authority to bind the partnership.

(c) Corporations. A contract with a corporation shall be signed in the corporate name, followed by the word “by” and the signature and title of the person authorized to sign. The contracting officer shall ensure that the person signing for the corporation has authority to bind the corporation.

(d) Joint venturers. A contract with joint venturers may involve any combination of individuals, partnerships, or corporations. The contract shall be signed by each participant in the joint venture in the manner prescribed in paragraphs (a) through (c) of this section for each type of participant. When a corporation is participating, the contracting officer shall verify that the corporation is authorized to participate in the joint venture.

(e) Agents. When an agent is to sign the contract, other than as stated in paragraphs (a) through (d) of this section, the agent’s authorization to bind the principal must be established by evidence satisfactory to the contracting officer.

ADDITIONAL PRIME CONTRACTOR INFORMATION - Safety or Environmental Violations and Experience Modification Rating Information 1.) All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

2.) All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

3.) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

4.) If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.

5.) The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

6.) This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

PRE-AWARD CONTRACTOR SAFETY AND ENVIRONMENTAL RECORD EVALUATION FORM

Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ DUNS Number: ________________________________________________ SAM’s UEI Number: ____________________________________________ Contact: ______________________________________________________

1. Utilizing your OSHA 300 Forms, please complete the following information:

Category
2022
2023
2024

Number of man hours (jobsite and office).

Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).

Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.

Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.

2.Provide your six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________
3.Who administers your company’s Safety and Health Program? __________________________________
4.Company’s Insurance Experience Modification Rate (EMR): _____________

Illinois State Sales Tax Exemption:

The Illinois Administrative Code, 130.2075 allows construction contractors to be exempt from Retailers Occupation Tax and Use Tax within the State of Illinois when the materials are for Incorporation into real estate owned by Governmental bodies. For purposes of this authority, a Construction Contractor is defined as a General Contractor or a Subcontractor 86 Ill.Adm.Code 130.1940(a)(1). Materials, are defined as all of the tangible personal property, including fixtures, which enter into a structure or otherwise become incorporated into real estate 86 Ill.Adm.Code 130.1940(a)(5), but do not include tools, fuel, lumber for forms and other end use or consumption items which are not incorporated into the real property 86 Ill.Adm.Code 130.2075(d)(3).

Prospective offerors are notified that under 86 Ill.Adm.Code 130.2075, purchase of applicable materials within the State of Illinois to be incorporated into the real property of Jesse Brown VA Medical Center may be exempt from Illinois Retailers’ Occupation Tax and Use Tax. VA will furnish a Certificate to the successful awardee under this solicitation that contains appropriate information that will allow the awardee to take advantage of this tax exemption within the State of Illinois for the project identified in this solicitation. Prime contractors may furnish the certificate to its subcontractors for use on this project. All offers received in response to this solicitation are presumed to reflect any tax benefit that may be realized upon receipt of this certificate.

Date: 07/02/2024

CONSTRUCTION STATEMENT OF WORK FOR

Project Name:Create a Contractor Lie-Down Zone
Project Number:537-24-106
Place of Performance:Building 1A, Eastern Exterior Grounds.
Jesse Brown VA Medical Center
820 S. Damen Ave

Chicago IL 60612

Part 1: Project Scope of Work Overview

· Prepare the ground in the designated zone.

· Extend Electric Power to designated Trailer locations.

· Place Trailers in designated locations.

· Fence and Gate the designated zone.

· Ramp the curb to give easy access to vehicles entering/exiting the zone.

Part 2: Period of Performance (POP) and Project Construction Cost Magnitude Complete all work including submittals and quality control reviews within the calendar days from Notice to Proceed (NTP) as shown below.

537-24-106 Construction Period of Performance (PoP)

Level Complete
Calendar Days for the Work
VA Review
Total days after NTP
Task 1 – Project Kick-off submittals
7
14
21
Task 2 – Coordination
14
14
49
Task 3 – Pre-Construction submittals
45
14
108
Task 4 – Mobilizations and Performance of Work
115
14
237
Task 5 – Closeout Submittals
14
14
265

Part 3: Detailed Project Scope of Work The contractor must meet all the requirements of the following construction documents:

1.537-24-106 Construction Document Issued for Bid, Design and Construction.
2.537-24-106 Specifications listed for Bid, Design and Construction.

GENERAL PROJECT GOALS

The goal of this project is to create a “Lie-Down” Zone for temporary construction/utility activities.

The Contractor/Builder is required to:

1. Design and Provide all Permits, Plans, Tools, Materials, Components, Labor, and Supervision for Creating a Contractor Lie-Down Zone.

2. Scan and Mark Underground Utilities throughout the Designated Plot.

3. Clear the Designated Plot of Trees, Roots, and any large debris that may obstruct the scope of work. Dispose of all waste. Refer to Exhibit B – Site Pictures.

4. A licensed GEOTECHNICAL ENGINEER (hired by GC) shall examine soil type.

5. Excavate, and dispose of soil to the depth specified by the licensed GEOTECHNICAL ENGINEER to achieve the specified drainage and bearing pressure rating.

6. Compact the ground, lay a weed barrier fabric, fill to level with Heavy-Duty Gravel, utilize a Heavy-Duty gravel grid and sand. The finished product shall be able to efficiently drain and have a minimum bearing pressure rating of 8000 PSF, no mud/pooling/ settling shall occur. Refer to VA Specifications Section 31 20 00 (Earthwork).

7. Furnish and install four (4) Marine Grade, 20 feet Long by 8 feet Wide, High-Cube Storage Containers. The Containers shall be brand new. Each Container shall rest on footings, raised eight (8) inches from the ground, refer to Exhibit A - Plot Layout.

8. Furnish and install a 9 Gauge, 7-feet high Chain Link Fence around the Designated Plot, install a 20-Ft Gate as noted in Exhibit A – Plot Layout, and per VA Specifications Section 32 31 13 (Chain Link Fences And Gates). Provide A Sliding Gate lock with a Best 7-pin Mortise.

9. Furnish and Install three (3) 200A, 110V, 12 space Breaker Panels in Closet 14E6 to feed the Contractor Lay-Down Zone. The new panels shall be fed from Switch Gear LP-1-1 located in Closet 14E5. VA will provide names to the new panels. Refer to VA Specifications Section 26 05 11 (REQUIREMENTS FOR ELECTRICAL INSTALLATIONS) The new panels shall have excess capacity for the outlined Breaker-Equipped Enclosures, lights, and the future expansion of an equal number of Breaker-Equipped Enclosures. Refer to VA Specifications Section 26 24 13 (Distribution Switchboards) and Section 26 11 16 (SECONDARY UNIT SUBSTATIONS).

10. Furnish and Install four (4) Energy Meters, one meter to feed and monitor energy usage for every container. Use Honeywell E-Mon™ Class 1000 Single Phase Pulse Meter or an approved equivalent.

11. Feed Power from the aforementioned subpanels to the Containers via the Energy Meters. Conductors shall exit the building via a Weather Head. Use Outdoor-rated Armored Cable to feed each Container. Lay the Cable atop containers, connect each cable to a Container via a Weather Head according to VA Specifications Sections 26 27 26 (Wiring Devices) and Section 26 05 19 (Low-Voltage Electrical Power Conductors and Cables).

12. Terminate the Armored Cable inside Each Container with two Contractor Furnished double gang boxes and four GFCI outlets in accordance with VA Specifications Section 26 27 26 (Wiring Devices) and Section 26 29 21 (Enclosed Switches And Circuit Breakers). Junction Boxes shall be installed 12 inches above floor and five feet from each end of container. Each Container shall have a dedicated breaker on the corresponding subpanel to control its outlets.

13. Furnish and install LED Shop Light Fixtures inside each container. Light Fixtures shall be centered along the ceiling. Illumination level shall be 60 lumens per square-foot. Lights inside each Container shall be controlled by two light switches in a 3-pole fashion. Install one light switch on each side, within eight inches from the entrance. Each Container shall have a dedicated breaker on the corresponding subpanel to control its lights.

14. Furnish and install Photocell Light Fixtures. Position the light fixtures to achieve full illumination of the Contractor Lay-Down Zone – pull feed from new subpanels. Refer to VA Specifications Section 26 56 00 (EXTERIOR LIGHTING) and SECTION 26 09 23 (LIGHTING CONTROLS).

15. Refinish/demolish and reconstruct sidewalk and curb to fit a ramp to ease vehicles access to the gated zone. Refer to SECTION 32 05 23 (CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS)

List of Exhibits included for reference:

a. Plot Layout

b. Site Pictures

c. Specifications

Record Documents: Recording as-built drawings is a responsibility of the general contractor during the construction process.

Construction Progress Meetings: The Contractor’s Superintendent and Project Manager must provide biweekly teleconference construction progress meetings with the COR for the period of Construction. Attendees list will be modified based on the phase needs.

a. Submit construction progress meeting minutes issued not later than one day after the meeting using Jesse Brown Construction Project Tracker. Meetings minutes must contain:

a. List of attendees

b. Contract Status: percentage of completion, days remaining per the contract, original contract amount, modifications to date, payment amount to date.

c. List any issues or concerns.

d. Safety incidents.

e. RFI Log.

f. Submittal Log.

g. Detailed 2-week look ahead and shutdown schedule.

b. Field crews must collect data and information as job progresses capturing all changes and modifications during construction on red line drawing plan set. Red-line drawings will be reviewed by the COR during each progress meeting.

Task 1 – Project Kick-off: Contractor’s Quality Control Manager and Superintendent must attend an on-site kick-off meeting, to discuss the project details.

a. Submit construction baseline schedule fulfilling the requirements of the contract.

b. Submit a schedule of values matching the format of VA Form 10-6001a. The schedule of value must match construction activities shown on the baseline schedule.

c. Submit VA Great Lakes Acquisition Center Subcontractor Payment Summary Form.

d. Submit a list of all contractors and subcontractors: company names, office address and main point of contact name with telephone number.

e. Submit all required key field staff Resumes for VA approval.

f. Provide a comprehensive submittal and RFI logs.

g. Submit scanned copy of all workers OSHA construction safety training certificates.

h. Submit copies of all required state license and registrations. See Requirements on Project Specifications and Part 6.

Task 2 – Coordination: Contractor must make all necessary field measurements and investigations to create work zones to minimize shutdowns.

1. Submit comprehensive site visit schedule. The VA will provide escorts and provide access to the areas as shown on the approved site visit schedule.

2. Submit shop drawing identifying work zones. Provide a table with rooms numbers per zone.

3. Submit a detailed construction schedule showing specific work zones and the proposed work zone sequence.

a. Show all anticipated system shutdowns. See Part 6 for system shutdown requirements.

b. Show VA inspection schedule per work zone.

Task 3 – Pre-Construction: Contractor must not mobilize on site until all Pre-Construction requirements are met.

1. Submit product data, shop drawings, finishes samples and all other required documentation. See project constructing drawings and specification manual for all requirements. See Part 4 for submittal procedures.

All construction submittals must be reviewed and approved by the VA prior to issuance of the Mobilization Authorization Letter. Contractor must not begin Task 4 until all the requirements of tasks 1, 2 and 3 have been fulfilled.

Task 4 – Mobilization and Performance of the Work: Contractor must meet all the requirements of the construction documents. See Part 3 for construction documents list.

1. Contractor must not start the work in any area of the campus without VA COR approval.

2. At entry points to the work zone post and maintain emergency contact information, VA Project Risk Assessment, and any other information required by the COR.

3. The Contractor must furnish to the COR, for each workday, a consolidated report for the preceding workday. Reporting must begin from date of contractor mobilization until the date of final acceptance. VA Form 10101, Contractor Production Report must be signed, dated, and submitted by the Contractor’s Superintendent. Each report must include and specifically identify at least one safety topic germane to the jobsite that day.

4. VA will perform site inspections. Contractor must address deficiencies or policies violations identified the same day the deficiency notice is issued. The Contracting Officer may issue and order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop order is acceptable as the subject for claim for extension of time, for excess cost or damages by the Contractor.

5. Prior to each inspection and at date of demobilization, the Contractor must deep clean all disturbed areas to a condition equal to or better than original condition.

Task 5 – Closeout: Provide three printed sets and upload to Submittal Exchange each closeout submittal. See project specification manual for all other Close Out requirements.

1. As-built Drawings must be in PDF and .DWG file formats. As-built drawings must show the tag number for all shutoff valves installed and identify the isolation zone for each shut-off valve.

2. The Contractor must provide an itemized table with all installed equipment and parts. The table must include but not to be limited to manufacturer, model number, serial, number, location (building and room number), tag number, capacity, setting, pressure, flow, voltage, amperage, etc. PDF and excel spreadsheet are required.

3. Operations and Maintenance Manuals (all cut sheets must have the installed product highlighted)

All construction submittals must be reviewed and approved by the VA prior to issuance of the Acceptance Letter.

Part 4: Procedures Submittals: The Contractor must provide all shop drawings and product submittals via Submittal Exchange. All submittals’ deadlines per Part 2 Period of Performance. Allow 14 calendar days for VA review of each submittal.

Work Zone Acceptance: The Contractor must schedule walk through inspection with the VA COR for each work zone (Inpatient Room). The VA COR will coordinate with the VA Maintenance and Operations team and all VA staff required to attend to the inspection.

1. Submit work zone substantial completion letter certifying the Contractor has completed their quality control measures.

2. Room final cleanup as described in Section 01 35 26 must be completed by the Contractor prior to pre-final inspection.

3. Schedule work zone pre-final inspection at 8:00am on a Weekday.

a. Contractor must demonstrate the operation of the existing system(s). One demonstration of the correct operation of the system is required. If the demonstration does not show expected operation, the Contractor must make required system adjustments and schedule a retest.

b. Submit construction inspection findings and identified deficiencies (“Punchlist”) for COR review.

4. Punchlist items must be addressed before the final inspection can be scheduled.

5. Work Zone must be accepted prior to beginning work on next work zone as identified in the approved construction scheduled, work zone sequence.

6. All work will be provided with, at minimum, 1-year parts and labor warranty from date of acceptance by the VA.

Part 5: Applicable Performance Standards Contractor must comply with all applicable federal, state, and local codes and regulations, and VA Codes, Standards and Executive Orders including but not limited to:

1. PG-18-3 Design and Construction Procedures

a. Local Code: VA must function as the Authority Having Jurisdiction (AHJ) and thus has the responsibility to guard public health and safety through enforcing its adopted codes. VA will adopt the following: Department of Labor Occupational Safety and Health Administration, City of Chicago Building Code, Illinois Plumbing Code, and Illinois Professions, Occupations, and Business Operations.

2. Jesse Brown VAMC Construction Safety Policy including but not limited to:

a. Key Contractor and Subcontractor Staff shall have completed the 30 Hour OSHA Construction Safety Training program.

b. The Prime Contractor must always have a Competent Site Safety and Health Officer on site when any worker(s) or sub-contractors are present.

c. Individuals working on any electrical systems rated 50 volts or more must have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, all activities must follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

3. Jesse Brown VAMC site-specific requirements and Standard Operation Procedures, including but not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy. Use clip on badge holders so the adhesive sign-in badges do not fall off and are in view.

4. All work will be provided with one-year parts and labor warranty from date of acceptance by VA.

Part 6: Jesse Brown VAMC Requirements

1. General Requirements

a. Approval to mobilize must be in writing by the VA.

b. Project number and the contract number must be in the subject line of all emails.

c. Recycling and receipts from the salvage / deposal service in compliance with VA’s GEMS must be provided with every payment request.

d. No speakers or radios for the playing of music must be allowed on the job site. Two-way communications radios are allowed where broadcast frequency is approved by COR.

2. Work Hours Restrictions

a. Normal construction hours are flexible an can be planned with the COR . Weekend work can be planned if deemed necessary.

b. No work by the Contractor on Federal Holidays, and no work on the associated weekend when the Federal Holiday is on the respective Monday or Friday unless otherwise specified by COR.

c. Any work including, but not limited to: Noise, vibration, dust, odors, core drilling, hammer-drilling, saw-cutting, equipment moving in public corridors, or similar noise-producing activities adjacent to a patient room (floor above and below included) must be performed when such room is unoccupied.

3. Site Access

a. Before starting work at each work zone, the Contractor must post signs on all doors within the zone no later than 7 calendar days in advance to notify users. See project specification manual for sign template. This notice is separate from any notices required for utility shutdown described later in this section.

b. For work taking place inside the Hospital, the Contractor must check in (in person) with the Ogden Security Desk which is located on the Ogden Entrance main lobby for any work and site visit. Contractor must present their ID to get a Vendor’s Day Pass. Vendors that have a VA issued ID are still required to get a Day Pass.

c. For work taking place inside the Hospital, the Contractor must check-in (in person) with the Administrative Officer of the Day (AOD) which is in Patient Admitting for any work between 5:00 PM to 6:00 AM, Monday through Friday and any time on weekends. Provide the name and cell number of the on-site supervisor to the AOD. At the completion of the workday, check out with the AOD.

4. Shutdowns

a. All building systems will always be maintained in full operation.

b. Request system shutdowns in writing not less than 14 calendar days in advance.

c. System shutdown work must be during low patient demand times performed starting Saturday 10PM to Sunday 3AM unless otherwise authorized in writing by the COR.

5. Safety and Security

a. The Contractor must submit a project specific Safety Plan per Project Specification Manual. Contractor must provide mitigating activities as outlined in the Project Risk Assessment for Safety and Interim Life Safety Measures including but not less than the following:

· Fire extinguishers, pedestal mounted in the area of work.

· Provide uniform heat detection in the area of work, connected to the existing supervised building master fire alarm system, for the duration of the work whenever the: Ceiling tiles are removed, or sprinkler system is disabled.

· Fire-seal all penetrations through any wall or floor with UL Listed fire-rated materials or assemblies manufactured for the purpose.

b. No on-site office is allowed. No on-site storage of tool or material is allowed. Provide ‘just-in-time delivery and pickup’. Coordinate with COR for staging within the work zone 4 days prior to the beginning of the work.

c. The floor slabs are not water-tight and will leak to the floor below. Provide precautions to prevent spills.

d. No photography of VA premises is allowed without written permission of the COR.

e. VA reserves the right to close or shut down the project site and ask Contractor’s employees to leave the premises in the event of an emergency, or operational requirement. The Contractor may return to the site only with the written approval of the CO.

f. Immediately stop work and notify the CO/COR if asbestos is noticed or suspected in the area of work.

6. Deliveries, Parking, Elevators

a. Deliveries are to be coordinated with COR. Use only the Polk Street dock. Coordinate with the COR minimum 4 days prior to the delivery date.

b. At time of delivery: provide vehicle information to the COR and remove the vehicle as soon as delivery is complete.

c. Delivered materials cannot be staged longer than 7 calendar days. Do not move materials in public corridors between 7:00AM and 6:00PM.

d. Vendors are not allowed to park anywhere on-site or in the VA garage. Utilize street parking or other parking structures such as the Cook County Juvenile Parking Garage at their daily rate. It is the General Contractor’s responsibility to ensure that all project workers are aware and follow this requirement.

e. Contractor must only use Freight Elevators. Do not move materials and employees in passenger elevators unless written approval by COR.

7. Infection Control

a. Risk classifications of this project is Class II.

b. Provide mitigation activities as outlined in the Project Specifications.

c. Walk-off dust mats, inside and outside all entry / exit points to the workspace, changed not less than daily or more as required by the construction or COR.

d. Contractor must clean and disinfect all rooms and corridors before removing infection control barriers. Cleaning, sanitizing, and disinfecting procedure written narrative and product data sheets must be included in the infection control plan for VA review and acceptance.

· Cleaning: Remove debris, organic substances, and other visible soil directly from surfaces and objects. A mixture of soap or detergent with water must be used to scrub and wipe down surfaces.

· Disinfecting: A hospital-grade disinfectant must be used. Disinfectant product must not leave a residue behind and must not require any further rinsing or wiping after it has been applied. Remove and disinfect every detachable item in the room and then properly disinfect air ducts, light fixtures, and all surfaces from the ceiling down to the floor. Thoroughly wipe down doorknobs and railings using a disposable wipe soaked in disinfectant cleaner. High-touch areas must also be wiped down.

e. The entire work zone must be vacuum cleaned with HEPA filtered vacuums and wet mop with disinfectant every workday before the end of the workday. See Part 6 Item 2 for workday hours.

f. Infection control barriers in areas impeding VA staff from performing their duties must be removed every day before the end of the workday and reinstall at the beginning of the following workday if work within that area has not been completed.

g. No trash, used packaging, or construction debris must be stored on site. Remove trash and construction debris each day using covered gondolas. No dumpster will be allowed onsite.

h. See project specification manual for all other infection control requirements.

8. Compatible System procurements must be as follows:

a. Security Card Access Control: provide a complete and fully functional extension of the existing card access control system including card access readers and electric door strikes. Include programming, licenses, and startup. The existing system is compatible with the VA identification cards is Avigilon Security System.

9. All field staff is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

A.3 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.

(End of Clause)

A.4 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision) A.5 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)

(a) Definition. for the Department of Veterans Affairs, ‘‘Service-disabled Veteran-owned small business concern or SDVOSB’’:

(1) Means a small business concern—

(i) Not less than 51 percent of which is owned by one or more service-disabled Veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled Veterans or eligible surviving spouses (see VAAR 802.201, Surviving Spouse definition);

(ii) The management and daily business operations of which are controlled by one or more service-disabled Veterans (or eligible surviving spouses) or, in the case of a service-disabled Veteran with permanent and severe disability, the spouse or permanent caregiver of such Veteran;

(iii) The business meets Federal small business size standards for the applicable North American Industry Classification System (NAICS) code identified in the solicitation document;

(iv) The business has been certified for ownership and control pursuant to 38 U.S.C. 8127, 13 CFR 128, and is listed as certified in the SBA certification database at https://veterans.certify.sba.gov/; and

(v) The business agrees to comply with VAAR subpart 819.70 and Small Business Administration (SBA) regulations regarding small business size, government contracting, and the Veteran Small Business Certification Program at 13 CFR parts 121, 125, and 128.

(2) The term ‘‘Service-disabled Veteran’’ means a Veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).

(3) The term ‘‘small business concern’’ has the meaning given that term under section 3 of the Small Business Act (15 U.S.C. 632).

(4) The term ‘‘small business concern owned and controlled by Veterans with service-connected disabilities’’ has the meaning given the term ‘‘small business concern owned and controlled by service-disabled veterans’’ under section 3(q)(2) of the Small Business Act (15 U.S.C. 632(q)(2)).

(5) The term “SDVOSB participant” or certified SDVOSB means a small business that has been certified in the SBA Veteran Small Business Certification Program and listed in the SBA certification database (see 13 CFR 128.102).

(b) General. In order for a concern to submit an offer and be eligible for the award of an SDVOSB set-aside or sole source contract, the concern must qualify as a small business concern under the size standard corresponding to the NAICS code assigned to the contract and be listed as an SDVOSB participant in the SBA certification database as set forth in 13 CFR 128.

(1) Offers received from entities that are not certified SDVOSBs and listed in the SBA certification database at the time of offer shall not be considered.

(2) Any award resulting from this solicitation shall be made to a certified SDVOSB listed in the SBA certification database who is eligible at the time of submission of offer(s) and at the time of award.

(3) The requirements in this clause apply to any contract, order or subcontract where the firm receives a benefit or preference from its designation as an SDVOSB, including set-asides, sole source awards, and evaluation preferences.

(c) Representation. Pursuant to 38 U.S.C. 8127(e), only certified SDVOSBs listed in the SBA certification database are considered eligible to receive award of a resulting contract. By submitting an offer, the prospective contractor represents that it is an eligible and certified SDVOSB as defined in this clause, 13 CFR 121, 125, and 128, and VAAR subpart 819.70.

(d) Agreement/LOS certification. When awarded a contract action, including orders under multipleaward contracts, an SDVOSB agrees that in the performance of the contract, the SDVOSB shall comply with requirements in VAAR subpart 819.70 and SBA regulations on small business size, and government contracting programs at 13 CFR part 121 and part 125, including the non-manufacturer rule and limitations on subcontracting (LOS) requirements in 13 CFR 121.406(b) and 13 CFR 125.6. For the purpose of limitations on subcontracting, only certified SDVOSBs listed in the SBA certification database (including independent contractors) shall be considered eligible and/or ‘‘similarly situated’’ (i.e., a firm that has the same small business program status as the prime contractor). An otherwise eligible firm further agrees to comply with the required LOS certification requirements in this solicitation (see 852.219–75 or 852.219–76 as applicable).