S06 - 537-16-102A Construction Plans IFC - Photos - 5.pdf

PDF 16 MB Posted

Attached to
Z1DA--537-16-102A Corrections to Sprinkler System
Solicitation number
36C25222B0007
Issued by

About this file

This document outlines a federal contract opportunity for corrections to a sprinkler system. The solicitation number is 36C25222B0007 and is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12. The opportunity is for Project 537-16-102A which involves corrections to an existing sprinkler system. No other details are provided in the document regarding response dates, pricing terms, set asides, incumbent contractors, or work requirements.

View the file

Other files

File Type Posted
S06 - 537-16-102A Construction Plans IFC - Photos - 4.pdf PDF
36C25222B0007 0013.docx DOCX document
36C25222B0007 0012.docx DOCX document
S06 - 537-16-102A Construction Plans IFC - Photos - 6.pdf PDF
S06 - 537-16-102A Construction Plans IFC - Photos - 7.pdf PDF
S06 - 537-16-102A Construction Plans IFC - Photos - 2.pdf PDF
S06 - 537-16-102A Construction Plans IFC - Photos - 1.pdf PDF
36C25222B0007 0011.docx DOCX document
S06 - 537-16-102A Construction Plans IFC - Photos - 4.pdf PDF
S06 - 537-16-102A Construction Plans IFC - Photos - 3.pdf PDF
S06 - 537-16-102A Construction Plans Issued for Bid and Construction 02_11_2022 - (1).pdf PDF
S06 - 537-16-102A Construction Plans Issued for Bid and Construction 02_11_2022 - (2).pdf PDF
S06 - VA Responses to RFIs.pdf PDF
S06 - Wage Determination 01_14_2022.pdf PDF
36C25222B0007 0010.docx DOCX document
S06 - 537-16-102A Specifications Issued for Bid and Construction 02_03_2022.pdf PDF
36C25222B0007 0009.docx DOCX document
36C25222B0007 0008.docx DOCX document
36C25222B0007 0007.docx DOCX document
S06 - Campus Floor Plan 1 of 2.pdf PDF
S06 - Pre-Bid Site Visit Attendance Sheet - 1-14-22.pdf PDF
S06 - Record Drawings 1 of 8.pdf PDF
S06 - Pre-Bid Site Visit Attendance Sheet - 1-5-22.pdf PDF
36C25222B0007 0006.docx DOCX document
S06 - Attachments 0006.zip ZIP file
36C25222B0007 0005.docx DOCX document
537-16-102A Construction Plans IFC 08302020-2.pdf PDF
537-16-102A Construction Plans IFC 08302020 - 2.pdf PDF
36C25222B0007 0004.docx DOCX document
537-16-102A Construction Plans IFC 08302020 - 1.pdf PDF
S06 - Record Drawings 4 of 8.pdf PDF
36C25222B0007 0003.docx DOCX document
S06 - Record Drawings 8 of 8.pdf PDF
S06 - Record Drawings 5 of 8.pdf PDF
S06 - Record Drawings 7 of 8.pdf PDF
S06 - Record Drawings 6 of 8.pdf PDF
S06 - Attachments 0002.zip ZIP file
36C25222B0007 0002.docx DOCX document
36C25222B0007 0001.docx DOCX document
S06 - Attachments 0001.zip ZIP file
S02 - 537-16-102A Specifications IFC 02082020.pdf PDF
S02 - 537-16-102A Construction Plans IFC 08302020.pdf PDF
S02 - VHA Sup Con Req for Combatting COVID-19.pdf PDF
S02 - Statement of Work.pdf PDF
S02 - Wage Determination as of 12_3_21.pdf PDF
36C25222B0007.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jesse Brown Veteran’s Hospital Project 537-16-102A Sprinkler Corrections Field Report 10-02-2019 Areas of concern Building 40 – Basement

1 – Typical piping in ceiling of crawl space. Corrosion on piping, condensate everywhere.

3 – Condensation on piping throughout much of space

2 – Existing Jockey Pump

Field Report 12-09-2019

Building 40 – 2nd Floor

1 – 2nd Floor Stairwell 2 – Standpipe and Hose Valve in stairwell

3 – Floor Control Valve and Pressure gauge in Stairwell 4 – Close up of hose valve in stairwell

5 – Rusted piping and fittings to sprinkler head 6 – Rusted fitting to sprinkler head

7 – Rusted fitting to sprinkler head 8 – Rusted fitting to sprinkler head

9 – Rusted fittings to sprinkler head

Field Report 12-11-2019

10 – 2nd Floor Stairwell 11 – Standpipe and Hose Valve in stairwell, fittings rusted

12 – Floor Control Valve and Pressure gauge in Stairwell 13 – Close up of hose valve in stairwell

Field Report 12-11-2019

14 – Rusted fittings to sprinkler head 15 – Approximately 15 feet of rusty piping

Field Report 10-03-2019

Building 40 – 3rd Floor

1 – Insufficient sprinkler coverage under ductwork 2 – Missing sprinkler coverage under ductwork

3 – Missing sprinkler coverage under ductwork 4 – Missing sprinkler coverage under ductwork

5 – Missing sprinkler coverage under ductwork 6 – Missing sprinkler coverage under ductwork

7 – Missing sprinkler coverage under ductwork 8 – Missing sprinkler coverage under ductwork

9 – Missing sprinkler coverage under ductwork 10 – Missing sprinkler coverage under ductwork

11 – Missing sprinkler coverage under ductwork 12 – Missing sprinkler coverage under ductwork

13 – Sprinkler and light in conflict. Coverage 14 – Sprinkler support hanger for high pressure zone. This is not typical on floors with pressures over 125 psi.

15 – Improper sprinkler installation – cut insulation in ductwork for sprinkler clearance.

16 – 3rd floor Hose Valve – Chicago threads

Building 40 – 4th Floor

1 – Rusted fittings on piping. 2 – Sprinkler piping corroding from leaking mechanical unit.

3 – Sprinkler main in stairwell – Not properly fire sealed 4 – Fire riser and Sprinkler control valve.

5 – Sprinkler main not fire sealed to stairwell 6 – Sprinkler pressure valve for system

7 – Sprinkler control valve 8 – Multiple fire sealant used for penetration

9 – Sprinkler cover plate missing – stuffed with gloves 10 – Exposed sprinkler head with cover plate missing

Building 40 – 5th Floor

1 – Sprinkler head close to electrical equipment 2 – Proper bracing of sprinkler pipe. (not typical)

3 – Item removed from project 4 – Fire riser and Sprinkler control valve.

5 – Pressure valve on sprinkler main – greater than 100 psi 6 – Massive corrosion on sprinkler main and threaded outlet

7 – Sprinkler control valve and pressure gauge in stairwell 8 – Sprinkler main penetration through wall – properly done.

9 – Sprinkler pressure gauge – greater than 100 psi.

Field Report 10-17-2019

Building 40 – 6th Floor

1 – Sprinkler Standpipe and Hose Valve in stairwell 2 – Control Valve and Pressure Gauge on sprinkler supply to 6th floor

3 – Closer image of Pressure Gauge in stairwell 4 – Item removed from project

5 – Item removed from project 6 – Rust on reducer to sprinkler head

7 – Mechanical piping corroded 8 – Rusting of fittings and corrosion on Reducer

9 – Standpipe 6th floor stairwell 10 – Pressure gauge in th floor stairwell

11 – Pipe penetration in 6th floor stairwell wall 12 – no hanger bracing support on branchline, end of line

13 – No sprinkler end of lane hanger support 14 – Wall penetration not fire sealed – stuffed with paper.

15 – Wires taped to sprinkler piping 16 – Wires taped to sprinkler piping

17 – Unusual exterior piping corrosion 18 – Alternate view of piping corrosion

19 – Item removed from project

Building 40 – 7th Floor

1 – Vandal resistant access panels on 7th floor. 2 – vandal resistant sprinkler heads, insulation too close to head

3 – Skylights missing sprinkler heads 4 – Skylights missing sprinkler heads

5 – Non insulated vandal resistant sprinkler head 6 – Head located too close to wall. Minimum 4” to center.

7 – Full room view of sprinkler too close to wall. 8 – 7th Floor stairwell

9 – Hose Valve in stairwell 10 – Hole in ceiling, taped over

11 – Rusted coupling 12 – Reducer rusted

13 – No hangers on sprinkler piping 14 – Alternate view no hangers on sprinkler piping

15- Alternate view no hangers on sprinkler piping 16 – Alternate view no hangers on sprinkler piping

17 – Cavity adjacent to skylight – room for piping and sprinkler head

18 – 7th Floor Stairwell – Stair information missing. Stair 13

19 – Hose valve in stairwell 20 – Pressure Gauge in Stairwell

21 – Standpipe in stairwell 22 – Rusty fittings on standpipe in stairwell

23 – 7th Floor Stairwell 24 – Control Valve and Pressure Gauge in Stairwell

25 – Hose Valve in stairwell 26 – Top of standpipe – 7th Floor Stairwell

27 – Pressure gauge at top of standpipe – 100 psi.

Building 40 – 8th Floor

1 – PH Standpipe riser - Corroded 2 – PH Stairwell Riser fittings corroded

3 – Rusted fitting in penthouse 4 – Hanger to sprinkler head greater than 36”

5 – Sprinkler fitting rusted 6 – Sprinkler fitting rusted

7 – Sprinkler fitting rusted 8 – sprinkler fitting rusted

9 – Standpipe and hose valve 8th Floor Stairwell 10 – Control Valve in stairwell

11 – Pressure Gauge in stairwell 12 – Standpipe up to Roof in stairwell

10-02-2019 - Building 40 - Lower Level Field Report
12-09-2019 - Building 40 - 2nd Floor Field Report
12-11-2019 - Building 40 - 2nd Floor Field Report
10-03-2019 - Building 40 - 3rd Floor Field Report
10-03-2019 - Building 40 - 4th Floor Field Report
10-03-2019 - Building 40 - 5th Floor Field Report
10-17-2019 - Building 40 - 6th Floor Field Report
12-09-2019 - Building 40 - 7th Floor Field Report
10-17-2019 - Building 40 - 8th Floor Field Report