36C25219B0047-0002020.pdf
PDF 6 MB Posted
- Attached to
- TJC and Safety Corrections 695-19-102
- Solicitation number
- 36C25219B0047
About this file
36C25219B0047 0002 P01 - Drawings Part 1.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25219C0172-000.docx | DOCX document | |
| 36C25219B0047-0004002.pdf | ||
| 36C25219B0047-0004000.docx | DOCX document | |
| 36C25219B0047-0004003.pdf | ||
| 36C25219B0047-0004004.pdf | ||
| 36C25219B0047-0004001.pdf | ||
| 36C25219B0047-0003002.pdf | ||
| 36C25219B0047-0003001.pdf | ||
| 36C25219B0047-0003000.docx | DOCX document | |
| 36C25219B0047-0002022.pdf | ||
| 36C25219B0047-0002014.docx | DOCX document | |
| 36C25219B0047-0002021.pdf | ||
| 36C25219B0047-0002016.pdf | ||
| 36C25219B0047-0002015.pdf | ||
| 36C25219B0047-0002023.pdf | ||
| 36C25219B0047-0002018.pdf | ||
| 36C25219B0047-0002024.pdf | ||
| 36C25219B0047-0002019.pdf | ||
| 36C25219B0047-0002017.pdf | ||
| 36C25219B0047-0001016.docx | DOCX document | |
| 36C25219B0047-001.docx | DOCX document | |
| 36C25219B0047-000.docx | DOCX document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
G-001
COVER SHEET
A
F i l e
P a t h
P
M
BID DOCUMENTS
N/A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
321 4 5 6 7 8 9 10
FY19 TJC & SAFETY
CORRECTIONS
5000 W NATIONAL AVE
695-19-102
MULTIPLE
Project Director
4/1/2019 MAP ASBRevisions: Date:
DLK
CLEMENT J. ZABLOCKI VA MEDICAL CENTER
5000 W. NATIONAL AVE
MILWAUKEE, WI 53295-001
CONSTRUCTION DOCUMENTS
APRIL 1, 2019
695-19-102 FY19 TJC AND SAFETY CORRECTIONS
G-001 COVER SHEET
GENERAL
G-002 INFECTION CONTROL NOTES
G-003 GENERAL & FIRE PROTECTION NOTES
G-004 BUILDING 111 1ST FLOOR STATEMENT OF CONDITIONS
G-005 BUILDING 111 4TH FLOOR STATEMENT OF CONDITIONS
G-006 BUILDING 111 7TH FLOOR STATEMENT OF CONDITIONS
G-007 BUILDING 111 9TH FLOOR STATEMENT OF CONDITIONS
G-008 BUILDING 123 STATEMENT OF CONDITIONS- WINGS A & B
G-009 BUILDING 123 STATEMENT OF CONDITIONS- WINGS C & D
G-010 BUILDING 146 STATEMENT OF CONDITIONS
G-011 BUILDING 147 STATEMENT OF CONDITIONS
G-012 BUILDING 148 STATEMENT OF CONDITIONS
SUBTASK 1 PATIENT LIFTS
1-001 BUILDING 111 4TH FLOOR PLAN
1-002 BUILDING 111 4TH FLOOR WORK PLAN
1-003 BUILDING 111 8TH FLOOR PLAN
1-004 BUILDING 111 8TH FLOOR WORK PLAN
SUBTASK 2 9TH FLOOR BATHROOM REPAIRS
2-001 SUBTASK 2 GENERAL & INFECTION CONTROL NOTES
2-002 BUILDING 111 9TH FLOOR A-WING
2-003 TYPICAL BATHROOM LAYOUTS & DETAILS
SUBTASK 3 70 D-WING OPERATORS
3-001 BUILDING 70 BASEMENT FLOOR PLAN
3-002 BUILDING 70 BASEMENT FLOOR WORK PLAN
SUBTASK 4 CLC DOOR HARDWARE
4-001 BUILDING 146 FIRST FLOOR WORK PLAN
4-002 BUILDING 147 FIRST FLOOR WORK PLAN
4-003 BUILDING 148 FIRST FLOOR WORK PLAN
SUBTASK 5 FISHER HOUSE CARPET REPLACEMENT
5-001 BUILDING 150 (FISHER HOUSE) FIRST FLOOR WORK PLAN
5-002 TYPICAL ROOM LAYOUT
SUBTASK 6 AMBULANCE BAY DOOR REPLACEMENT
6-001 BUILDING 111 FIRST FLOOR PLAN
6-002 BUILDING 111 FIRST FLOOR WORK PLAN
6-003 BUILDING 111 ELEVATION 1 DEMO
MADISON
PROJECT
MILWAUKEE
WISCONSIN
LOCATION
GREEN BAY
APPLETON
LA CROSSE
PROJECT
LOCATION
SUBTASK 7 BUILDING 123 DISHROOM SANITARY REPAIR
7-001 BUILDING 123 1ST FLOOR PLAN
7-002 BUILDING 123 EQUIPMENT RELOCATION
7-003 BUILDING 123 PLUMBING DEMO
7-004 BUILDING 123 NEW PLUMBING
SUBTASK 8 REPLACE ROOFTOP EXHAUST FANS 112
8-001 BUILDING 112 ROOF PLAN/FAN INFORMATION
8-002 BUILDING 112 1ST FLOOR ELECTRICAL PANEL LOCATIONS
SUBTASK 9 INSTALL NEW VAV BUILDING 70 CONF. 1
9-001 BUILDING 70 2ND FLOOR PLAN
9-002 BUILDING 70 2ND FLOOR EXISTING/DEMO
9-003 BUILDING 70 2ND FLOOR NEW WORK
SUBTASK 10/10A EXTERIOR IMPROVEMENTS
10-001 10TH FLOOR WORK PLAN
10-002 SUBTASK 10 WORK PLAN
10-003 SUBTASK 10A WORK PLAN
AutoCAD SHX Text
DRAWING INDEX
AutoCAD SHX Text
NORTH
AutoCAD SHX Text
DRAWING INDEX
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
G-002
INFECTION CONTROL NOTES
A
F i l e
P a t h
P
M
N/A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
321 4 5 6 7 8 9 10
FY19 TJC & SAFETY
CORRECTIONS
5000 W NATIONAL AVE
695-19-102
MULTIPLE
Project Director
4/1/2019 MAP ASBRevisions: Date:
DLK
1. PER IC MATRIX THIS SHEET, PROVIDE NECESSARY INFECTION
CONTROL BARRIERS AT ALL PHASES OF CONSTRUCTION. REFER
TO SECTION 01 01 10 1SN AND 01 35 16 ARTICLE 1.12 FOR MORE
INFORMATION. EXISTING WALLS BEING USED AS PART OF THE
CONSTRUCTION BARRIER SHALL BE UPGRADED TO COMPLY WITH
1-HOUR FIRE RATED WALL REQUIREMENTS.
2. THE INTENT OF IC ISOLATION IS TO PROTECT PATIENTS WITH LOW
IMMUNE LEVELS. THEREFORE, CONTRACTOR SHALL ENSURE HIS IC
BARRIERS CONTAIN DUST AND PARTICULATE MATTER TO THE
CONSTRUCTION AREA.
3. PROVIDE TRIATEK NEGATIVE AIR ISOLATION MONITORS (MINIMUM
(1) ONE IN AREAS LESS THAN 1000 SF, (2) TWO MINIMUM IN AREAS
BETWEEN 1000 SF AND 5000 SF, AND (3) THREE FOR AREAS
BETWEEN 5000 SF AND 10000 SF.) DURING CLASS III OR CLASS IV
CONSTRUCTION OPERATIONS THAT LAST THREE DAYS OR MORE.
EACH AREA TO BE UNDER NEGATIVE PRESSURE (0.02" WC) DURING
THESE CONSTRUCTION OPERATIONS. MONITOR AND DOCUMENT
AS DIRECTED BY THE COR.
4. WHEN THE CONTRACTOR DESIRES TO REDUCE OR RELAX THE ICRA
PERMIT AS CONSTRUCTION PROGRESSES, PROVIDE A WRITTEN
REQUEST TO THE COR AND VA INFECTION CONTROL NURSE. ONLY
UPON AUTHORIZATION, PROCEED TO THE REDUCED CLASS OF
CONSTRUCTION. PROVIDE AT LEAST 10 DAYS NOTICE FOR EACH
PERMIT.
5. DETAILS FOR THE CONSTRUCTION OF INFECTION CONTROL AND
CONSTRUCTIN BARRIERS CAN BE FOUND IN NFPA 241, AND
SPECIFICATION SECTIONS 01 10 10 SN AND 01 35 26.
6. INFECTION CONTROL BARRIERS ARE TO BE INSTALLED AND
REMOVED ONLY BEFORE 7:30 A.M. AND AFTER 5:00 P.M. IN
OCCUPIED AREAS.
7. AS REQUIRED, PROVIDE BALANCING DAMPERS IN THE MAIN SUPPLY
AND EXHAUST DUCT WORK SERVING AREAS INSIDE THE IC/CN
BARRIERS. TEMPORARILY BALANCE AIR FLOW TO PROVIDE
NEGATIVE AIR FLOW IN CONSTRUCTION ZONE AT ALL TIMES AS
INDICATED BELOW. DAMPERS TO REMAIN IN DUCT AFTER
CONSTRUCTION IS COMPLETE AND IS TO BE SECURED IN FINAL
BALANCING POSITION PRIOR TO TURNING SYSTEM OVER FOR
OCCUPANCY
8. PROVIDE HEPA NEGATIVE AIR MACHINES WHEN REQUIRED.
9. THE CONTRACTOR SHALL PROVIDE ENOUGH NEGATIVE AIR
MACHINES TO COMPLETELY EXCHANGE THE REGULATED AREA AIR
VOLUME (4) FOUR ACTUAL TIMES PER HOUR. THE COMPETENT
PERSON SHALL DETERMINE THE NUMBER OF UNITS NEEDED FOR
EACH REGULATED AREA BY DIVIDING THE CUBIC FEET IN THE
REGULATED AREA BY (15) FIFTEEN AND THEN DIVIDING THAT
RESULT BY THE ACTUAL CUBIC FEET PER MINUTE (CFM) FOR EACH
UNIT TO DETERMINE THE NUMBER OF UNITS NEEDED TO EFFECT (4)
FOUR AIR CHANGES PER HOUR. PROVIDE A STANDBY UNIT IN THE
EVENT OF MACHINE FAILURE AND/OR EMERGENCY IN AN
ADJACENT AREA.
10. PRIOR TO ANY REMOVAL OF SMOKE BARRIER FIRE RATED WALLS,
CONSTRUCT NEW SMOKE BARRIER/APPROPRIATE FIRE RATED
WALLS PER NEW PLANS OR CONSTRUCT INFECTION CONTROL
BARRIER TO ACT AS SMOKE BARRIER.
11. ALL CONSTRUCTION DEBRIS, WASTE, AND TRANSPORTATION OF
DEMOLITION ITEMS SHALL BE CONVEYED IN COVERED DUMPSTER
CONTAINERS SUCH THAT NO DEBRIS/ITEMS ARE VISIBLE. ALL
CONTAINERS SHALL BE TRANSPORTED DOWN THE 'B' BANK
FREIGHT ELEVATORS. A MINIMUM OF ONE WALK-OFF MAT ON THE
INSIDE AND MINIMUM OF TWO WALK-OFF MATS ON THE OUTSIDE
SHALL BE PROVIDED FOR THE CONSTRUCTION ACCESS
LOCATIONS/OPENINGS.
12. A PORTION OF THE CORRIDOR MAY BE MADE AVAILABLE TO
CREATE AN INFECTION CONTROL AREA; HOWEVER, A MINIMUM OF 5
FT MUST BE MAINTAINED OPEN FOR THE MOVEMENT OF
PERSONNEL. THE CORRIDOR WILL NOT BE CLOSED OFF. POST
ILSM AS NEEDED.
1. CONTRACTOR IS RESPONSIBLE FOR COORDINATION AND
SEQUENCING OF CONSTRUCTION PHASING WITH THE VA'S SCHEDULE,
INFECTION CONTROL, AND INTERIM LIFE SAFETY REQUIREMENTS.
2. PROVIDE PHASING PLAN AS NEEDED TO COMPLETE WORK. REFER TO
SECTION 01 00 00 ITEM 1.6H FOR GENERAL PHASING REQUIREMENTS.
NOTE THAT SOME PHASES MAY BE CONCURRENT. ENSURE
SCHEDULE CLEARLY SHOWS CONCURRENT PHASES, FLOAT AND
CRITICAL PATH.
3. TEMPORARY CONSTRUCTION WALL AND INFECTION CONTROL (IC)
WALL REQUIREMENTS ARE NOT INCLUDED IN THE DRAWINGS. GC
SHALL SHOW IC/CN BARRIERS ON THEIR IC/WORKPLANS TO MEET
REQUIREMENTS OF SPECIFICATIONS & THE IC MATRIX ON THIS SHEET.
4. MAINTAIN EGRESS TO ALL STAIRWELLS.
5. MAINTAIN PUBLIC ACCESS TO ELEVATORS.
6. NORMAL WORKING HOURS FOR THE LABORATORY ARE 7:30 AM TO
5:00 PM, MONDAY THROUGH FRIDAY. OFF-SHIFT WORK SHALL BE
COMPLETED OUTSIDE OF THESE HOURS.
7. NOISE AND VIBRATION OPERATIONS ARE RESTRICTED TO OFF-SHIFT
HOURS. CONTRACTOR SHALL ALSO SCHEDULE SERVICE
INTERRUPTIONS OFF-SHIFT. TWO WEEK MINIMUM NOTICE IS
REQUIRED ON ALL OUTAGE REQUESTS.
8. CONTRACTOR IS RESPONSIBLE FOR ENSURING ILSM AND ICRA
PERMIT ARE POSTED AND CURRENT ALWAYS DURING
CONSTRUCTION.
INFECTION CONTROL GENERAL NOTES:
INFECTIOUS CONTROL DESIGN NOTES:
PHASING PLAN GENERAL NOTES:
BID DOCUMENTS
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
G-003
GENERAL & FIRE/SAFETY
NOTES
A
F i l e
P a t h
P
M
N/A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
321 4 5 6 7 8 9 10
FY19 TJC & SAFETY
CORRECTIONS
5000 W NATIONAL AVE
695-19-102
MULTIPLE
Project Director
4/1/2019 MAP ASBRevisions: Date:
DLK
GENERAL CONSTRUCTION NOTES
1. PATCH AND REPAIR ALL AREAS AFFECTED BY DEMO AND / OR CONSTRUCTION TO MATCH EXISTING. PATCHED AREAS ARE TO RECEIVE FINISHES AND TRIM TO
MATCH ADJACENT AREA, EXCEPT AS NOTED IN THE ROOM FINISH SCHEDULE. PATCH CEILINGS AND FLOORS TO ACHIEVE A CONTINUOUS FINISHED APPEARANCE.
2. ALL EQUIPMENT TO BE DISCONNECTED AND REMOVED BY CONTRACTOR. VA TO BE NOTIFIED WHEN EQUIPMENT IS AVAILABLE AND BE GIVEN THE OPTION TO TAKE
POSSESSION OF ALL EQUIPMENT. CONTRACTOR TO DISPOSE OF ALL EQUIPMENT THE VA DOES NOT WANT AND REMOVE ALL ITEMS WITH EXTREME CARE.
3. REMOVE, RELOCATE, STORE AND REINSTALL PORTABLE EQUIPMENT, FURNITURE, SHELVES, CURTAIN RODS, DRAPERY, BULLETIN BOARDS, WHICH WOULD
INTERFERE WITH DEMOLITION WORK.
4. REFER TO SPECIFICATIONS FOR SHORING REQUIREMENTS WHERE DEMOLITION WORK AFFECTS THE STRUCTURAL INTEGRITY OF WALLS OR FLOORS. IF NOT SO
INDICATED IN SPECIFICATIONS, CONTRACTOR SHALL SUBMIT SHORING PLAN AND SHOP DRAWINGS SIGNED BY AN ENGINEER FOR VA APPROVAL. ALL SHORING IS
CONTRACTOR'S RESPONSIBILITY.
5. PROTECT ALL EXISTING SURFACES FROM DAMAGE. ANY DAMAGED SURFACES SHALL BE REPLACED TO MATCH ORIGINAL ITEM OR REPAIRED TO MATCH EXISTING
OR ADJACENT MATERIAL AS APPROVED BY THE VA COR.
6. VERIFY EXISTING CONDITIONS AND LOCATIONS IN FIELD PRIOR TO SUBMITTING PROPOSAL. FAILURE TO DO SO SHALL NOT RELIEVE THIS CONTRACTOR FROM
PERFORMING THE WORK REQUIRED UNDER THIS CONTRACT.
7. ALL SUB-CONTRACTORS ARE ENCOURAGED TO VISIT AND ATTEND A PRE-BID WALK THRU TO INSPECT THE EXISTING AREA AND THOROUGHLY FAMILIARIZE
THEMSELVES WITH ACTUAL JOB CONDITIONS BEFORE SUBMITTING BID.
8. WHILE THE SIZE AND LOCATION OF NEW WORK AND EQUIPMENT IN THE EXISTING AREA HAS BEEN INDICATED ON THE DRAWINGS AS ACCURATELY AS POSSIBLE, CONTRACTOR SHALL ADJUST HIS WORK AS REQUIRED TO AVOID EXISTING UTILITIES, GAS LINES, SEWER, FIRE ALARM, ROOF DRAINS, ACCESS COVERS, AND OTHER
STRUCTURES NOT PARTICULARLY SHOWN ON THE PLAN AT NO ADDITIONAL COST. BEFORE CONSTRUCTION, INSPECT PREMISES MAKE A DETAILED EXAMINATION
OF ALL LOCATIONS WHERE NEW WORK IS TO BE INSTALLED, EXAMINE EXISTING PIPING, CONDUITS, STRUCTURAL SUPPORTING BEAMS, AND OTHER CONDITIONS.
9. DISCONNECT AT SOURCE AND REMOVE EXISTING MECHANICAL AND ELECTRICAL MATERIALS AND EQUIPMENT WHICH ARE RENDERED OBSOLETE BY THESE
ALTERATIONS AND ADDITIONS. VA TO BE GIVEN THE OPTION TO TAKE POSSESSION OF REMOVED EQUIPMENT AND MATERIALS. ANY EQUIPMENT THAT THE VA DOES
NOT WANT ARE THE PROPERTY OF THE CONTRACTOR AND SHALL BE REMOVED FROM THE SITE. NO MECHANICAL, ELECTRICAL, PLUMBING EQUIPMENT, ETC. SHALL
BE ABANDONED IN PLACE.
10. DISCONNECT, REMOVE AND RELOCATE EXISTING MECHANICAL AND ELECTRICAL MATERIALS AND EQUIPMENT WHICH INTERFERE OR ARE INTERFERED WITH, OBSTRUCT OR ARE OBSTRUCTED BY, THESE ALTERATIONS AND ADDITIONS. PERMANENTLY INSTALL SUCH ITEMS IN NEW LOCATIONS AS DIRECTED. RECONNECT
SUCH ITEMS IN PROPER OPERATING CONDITION AT NEW LOCATIONS.
11. DO NOT INTERFERE WITH EXISTING BUILDING'S MECHANICAL, ELECTRICAL, AND SECURITY SYSTEMS OPERATIONS. IF IT IS ABSOLUTELY NECESSARY TO SHUT
DOWN FACILITY SYSTEMS AT ANY TIME, CONSULT COR TO MAKE ARRANGEMENTS TO DO SO ON OFF WORKING HOUR PERIODS AT THE OWNER'S CONVENIENCE.
PRIOR NOTICE SHALL BE GIVEN TO THE COR (14) DAYS IN ADVANCE OF THE DESIRED SHUT-DOWN TIME. ANY PREMIUM OR OVERTIME COSTS NECESSARY TO
ACCOMPLISH THE ABOVE SHALL BE INCLUDED IN THIS BID. FAILURE TO PROCEED WITHOUT PROPER PRIOR NOTIFICATION MAY RESULT IN THE ASSESSMENT OF A
CREDIT TO THE CONTRACT.
12. TYPICAL EXISTING FLOOR TO FLOOR HEIGHTS FOR BUILDING 111 ARE 13'-9-3/8" (+/-) FROM BASEMENT TO SECOND FLOORS AND 11'-6-5/8" (+/-) FROM THIRD FLOOR
THRU TENTH FLOOR. FLOOR CONSTRUCTION IS 10" (+/-) CONCRETE FLOORS, WITH CONCRETE COLUMNS AND FLOOR BEAMS. ALL AS-BUILT CONDITIONS SHOULD BE
VERIFIED BY THE CONTRACTOR IN THE FIELD.
13. IN ALL CONSTRUCTION ZONES AND AREAS, CONTRACTOR RESPONSIBLE FOR MAINTAINING AN ACTIVE STROBE SPEAKER SYSTEM AT ALL TIMES. TYPICAL FOR ALL
CONSTRUCTION ZONES FOR BOTH BUILDINGS 102 & 111.
FIRE AND SAFETY NOTES
1. MAINTAINING THE INTEGRITY OF THE FIRE AND SAFETY SYSTEMS IN PLACE IN THE MEDICAL CENTER AND ALL OF ITS OUT BUILDINGS DURING
CONSTRUCTION SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR.
2. IN ADDITION TO ALL VA MEDICAL CENTER POLICIES, ALL NATIONAL, STATE, AND LOCAL CODES AND ORDINANCES SHALL APPLY TO ALL OF THEIR
CONTRACTORS AND SUB-CONTRACTORS.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MEETING ALL PERTINENT OSHA SAFETY REQUIREMENTS.
4. PROVIDE LOCKOUT-TAGOUT AND CONFINED SPACE ENTRY POLICIES AS APPLICABLE AND AS REQUIRED BY OSHA. THESE POLICIES SHALL BE
SUBMITTED FOR PRIOR APPROVAL BY THE VA SAFETY OFFICER / COR.
5. SUBMIT APPROPRIATE INTERIM LIFE SAFETY MEASURES. REFER TO SPECIFICATION 01 01 10 FOR MORE INFORMATION.
6. CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS OF NON-COMBUSTIBLE MATERIALS WHICH PROVIDE A SMOKE TIGHT SEPARATION
BETWEEN THE CONSTRUCTION AREAS AND ALL OTHER OCCUPIED AREAS. MAINTAIN INTEGRITY OF THE ENCLOSURE DURING THE
CONSTRUCTION. REFER TO SPECIFICATION SECTION 00 01 10-1HR.
7. EXISTING FIRE PROTECTION SYSTEMS, INCLUDING FIRE ALARM SYSTEMS, SMOKE DETECTION SYSTEMS, AND SPRINKLER SYSTEMS SHALL NOT BE
IMPAIRED DURING CONSTRUCTION. SMOKE DETECTOR DISABLE REQUESTS: OUTAGE REQUESTS TO BE SUBMITTED TO FM ENGINEER FOR
APPROVAL FOR SPECIFIC DATE AND TIME. ALARMS WILL ONLY BE TURNED OFF FOR SPECIFIC SHIFTS REQUESTED AND WHEN CONTRACTORS
ARE IN THE CONSTRUCTION AREA. ALARMS WILL BE RESTORED AT THE END OF THE WORK DAY BY CALLING THE SAME EXTENSION. AT NO TIME
WILL ALARMS REMAIN OFF OVERNIGHT. SMOKE DETECTORS AND OR SPRINKLER HEADS: DO NOT COVER BY BAGS, TAPE, AND PLASTIC OR IN ANY
OTHER MANNER THAT WILL DEFEAT THEIR ABILITY TO SENSE SMOKE OR HEAT AND OPERATE AS DESIGNED.
8. DAILY ACCUMULATIONS OF TRASH, COMBUSTIBLE MATERIALS, PACKAGING, AND DEBRIS SHALL BE REMOVED FROM THE CONSTRUCTION AREA ON
A DAILY BASIS. FLAMMABLE MATERIALS MAY BE STORED ON SITE IN AN APPROVED AND APPROPRIATELY MARKED FLAMMABLE MATERIALS
CABINET.
9. MILWAUKEE VA MEDICAL CENTER IS A TOBACCO FREE ZONE. USE OF TOBACCO PRODUCTS IS PROHIBITED, Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
G-004
BUILDING 111 1ST FLOOR
STATEMENT OF CONDITIONS
A
F i l e
P a t h
P
M
N/A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
321 4 5 6 7 8 9 10
FY19 TJC & SAFETY
CORRECTIONS
5000 W NATIONAL AVE
695-19-102
Project Director
4/1/2019 MAP ASBRevisions: Date:
DLK
File details come from the government source that posted it.