Pre-Bid Site Visit Presentation - 583-24-527.pptx

PPTX presentation 135 KB Posted

Attached to
Z1DA--Renovate Space to Meet Hazardous Storage Room Requirements - 583-24-527
Solicitation number
36C25026B0025
Issued by

About this file

This is a pre-bid site visit presentation for VA contract solicitation 36C25026B0025, addressing the renovation of space to meet hazardous storage room requirements at the Richard L. Roudebush VAMC (Solicitation 583-24-527). The project scope requires demolition of the existing EMS storage closet (A-8085), installation of mechanical, electrical, and physical security systems to create a code-compliant, secure, negative-pressure hazardous drug storage room meeting USP 800 standards and VA requirements. Key general requirements include code compliance with VA HVAC Design Guide and VA Master Specs, modification of existing exhaust fans with tie-ins to facility systems, and BMS connection for the new exhaust fan. Physical security coordination with VA Police is mandated.

Critical planning considerations include AHU 50 shutdowns requiring at least two weeks' advance notice to stakeholders due to impact on patient services, and energized electrical work prohibitions during circuit installation for the hazardous storage room and exhaust fan power. HVAC tie-in work must be subcontracted to Johnson Controls, an approved/certified vendor, with local facility contractors preferred. Safety requirements mandate a Safety Plan/AHA before work commences, PPE specifications for existing exhaust fan modifications (gloves, coveralls, head covers, shoe covers, eye/face protection, respirators), fall protection documentation for roof work, and weather considerations. The contractor assumes full responsibility for project delivery including site verification, demolition, all building systems, controls coordination, testing and commissioning, infection control measures, temporary facilities, final cleaning, as-builts, O&M manuals, and warranties.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

583-24-527 Renovate Space to Meet Hazardous Storage Room Requirements Pre-Bid Site Visit 3/5/2026 Richard L Roudebush VAMC Engineering Department

General Requirements Demolition of existing EMS storage closet A-8085 Currently used to store cleaning equipment, will be vacated before construction Installation of mechanical, electrical, and physical security systems Code compliance with USP 800, VA HVAC Design Guide, VA Master Specs, etc.

Modification to existing Exhaust Fans Tie in with existing facility systems Physical security by VA Police BMS connection for new Exhaust Fan

General Considerations Shutdown Planning AHU shutdowns for AHU 50 required Serves many patient services, will require advance notice of at least 2 weeks to schedule with stakeholders Electrical shutdowns for installation for Hazardous Storage Room circuits and Exhaust Fan power Energized electrical work is prohibited HVAC Tie-In Sub-contract to Johnson Controls Approved/Certified Vendor Local facility contractor preferred

Safety Considerations Safety Plan/AHA for General Conditions Required before work can begin PPE only for existing EF modification Gloves, coveralls, head covers, shoe covers, eye/face protection, and respirators Roof Work Fall protection – specify necessary precautions or comment as to why they are unnecessary Weather considerations – wind, rain, thunderstorms, and extreme temperatures

Comments and Questions

The Site Inspection will begin now

Please submit any questions not covered in solicitation documents (SOW and Drawings, Specifications, etc.) as RFIs.