This solicitation package outlines requirements for an SDVOSB set-aside construction project to expand an emergency distribution panel board and add cooling to a substation room at the Chalmers P. Wylie VA Ambulatory Care Center in Columbus, Ohio. The project number is 757-19-202 and has a magnitude between $500,000 and $1,000,000. The solicitation will be issued on March 22, 2021 with a bid opening approximately 30 days later. Interested parties must register at SAM.gov and the SDVOSB prime contractor must be verified in VIP and SAM databases. The solicitation and any amendments will be posted at SAM.gov. A site visit will be scheduled and the notice will be in the solicitation package. The NAICS code is 238210 and the size standard is $16.5 million. The SDVOSB must perform a minimum of 25% of the construction work. Bonds will be required. Questions must be submitted in writing to the contracting officer by the specified deadline.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 09-10-2021 757-19-202 36C250 Department of Veterans Affairs VA Healthcare System Network Contracting Office (NCO) 10 2780 Airport Dr - Suite 340 Columbus OH 43219 36C250 Department of Veterans Affairs VA Healthcare System Network Contracting Office (NCO) 10 2780 Airport Dr - Suite 340 Columbus OH 43219 To all Offerors/Bidders
36C25021B0019 08-11-2021
X X X
X The purpose of this solicitation amendment is to:
1). Provide details about construction fencing: Construction fencing can be installed approximately as shown in drawing AS101 (attached) to include contractor laydown area. Exact location to be confirmed onsite & approved by the VA. If additional space is required, the VA will allow for 4 parking spots to be blocked off for the additional space. The exact location will be determined by the VA & may be anywhere on the campus of the VAACC.
2). Provide the pre-award RFI questions & answers to all interested parties. Please see the continuation pages of this document, for details.
All other terms & conditions remain unchanged & in full effect.
CONTINUATION PAGE
CONTINUATION PAGES
EXPAND EMERGENCY DISTRIBUTION PANEL BOARD & ADD COOLING TO SUBSTATION ROOM FOR THE CHALMERS P. WYLIE VETERANS AFFAIRS AMBULATORY CARE CENTER (VAACC)—COLUMBUS, OH
PROJECT NUMBER: 757-19-202
QUESTIONS AND RESPONSES TO INVITATION FOR BID (IFB) NUMBER
36C25021B0019
IFB AMENDMENT NUMBER 00003
1. QUESTION – Sheet AE202 call for the screen wall to be a perforated aluminum anodized panel. There is no spec for this. What are the specs for the aluminum, perforations and anodizing to be?
Response: Please see the attached specification section for the requirements.
2. QUESTION – AE101 note 3 says to remove and replace existing planter. The existing planters are cracked and will most likely break when being moved. Please give a direction given the planters are cracked.
Response: Existing planters and bollards are removed as shown. New planters and bollards are to be installed per details 7 & 8 on AE101.
See attached document: AS101.
See attached document: SECTION 05 50 00 METAL FABRICATIONS.