539-19-101 ADDENDUM 1 2020.0818.pdf

PDF 98 KB Posted

Attached to
Z1DA--Reconfigure Primary Care to PACT Model - Project # 539-19-101
Solicitation number
36C25020B0064
Issued by

View the file

Other files

File Type Posted
36C25020B0064 0003.docx DOCX document
RFI 8.pdf PDF
RFI 9.pdf PDF
36C25020B0064 0002 - Attachment.pdf PDF
36C25020B0064 0002.docx DOCX document
36C25020B0064 0001.docx DOCX document
Closet - 2.jpg JPG image
Staging and Dumpster Designated Area.png PNG image
Pre-Bid RFI 7_Response.pdf PDF
Pre-Bid RFI 3_Response.pdf PDF
Pre-Bid RFI 6_Response.pdf PDF
JA - ARJO.pdf PDF
Pre-Bid RFI 2_Response.pdf PDF
539-19-101 ADDENDUM 1 DRAWINGS 2020.08.pdf PDF
Pre-Bid RFI 1_Response.pdf PDF
Closet - 3.jpg JPG image
Pre-Bid RFI 5_Response.pdf PDF
Closet - 1.jpg JPG image
Closet - 4.jpg JPG image
Pre-Bid RFI 4_Response.pdf PDF
Attachment 4 - EMR Attachment.pdf PDF
Attachment 3 - RFI Form.pdf PDF
36C25020B0064_1.docx DOCX document
Attachment 1 - SPECIFICATIONS.pdf PDF
Attachment 5 - DBA WD - OH20200082.pdf PDF
Attachment 2 - DRAWINGS.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 01

August 18, 2020

VA PROJECT # 539-19-101

RECONFIGURE PRIMARY CARE TO PACT

CINCINNATI VA MEDICAL CENTER

3200 VINE ST.

CINCINNATI, OHIO 45220

LEVIN PORTER ASSOCIATES, INC

3011 NEWMARK DRIVE

DAYTON, OHIO 45342

LPA PROJECT NO. 205612.00

TO ALL BIDDERS:

This addendum including all items listed hereinafter, shall become a part of the documents, shall be taken into account in preparing the Proposal, and shall become a part of the Contract. The work under each branch shall be in accordance with the original specifications unless excepted in this Addendum.

This Addendum consists of 3 pages plus (11) 30X42 drawing attachments:

ARCHITECTURAL

DRAWINGS

ITEM NO.1 Drawing No. A507

A. Added additional detail 11 – PATIENT LIFT DETAIL 1

B. Added additional detail 16 – PATIENT LIFT DETAIL 2

C. Added additional detail 17 – PATIENT LIFT DETAIL 3

PLUMBING

ITEM NO. 1 Drawing No. P100

A. Removed crawl space notations and added plan note 2 to new sanitary piping indicating the requirements for modifying/ repairing the existing floor slab.

HVAC

ITEM NO. 1 Drawing No. M601

A. Revised ‘Air Terminal Unit Schedule’.

ELECTRICAL

ITEM NO. 1 Drawing No. E402

A. Removed receptacle for monitor adjacent to cart in Detail 1 - ENLARGED PCR-E EXAM ROOM –

POWER.

B. Added receptacle for patient portal in Detail 6 – ENLARGED PCR-T CONSULT ROOM –

POWER.

C. Added receptacle for patient portal in Detail 9 – ENLARGED PCR-WBP ROOM – POWER.

ITEM NO. 2 Drawing No. E602

A. Revised panel schedule with load value for the existing circuit.

B. Revised existing Single-line Diagram.

C. Revised POKE-THRU SCHEDULE to FLOOR BOX SCHEDULE.

ITEM NO. 3 Drawing No. ED101

A. Added boundary line detailing deduct alternate of the west offices.

ITEM NO. 4 Drawing No. EL101

A. Revised Type A2 pedant light fixture locations over workstations at CHECK-IN C1003.

B. Revised exit signs along STAFF CORRIDOR C*1*19.

ITEM NO. 5 Drawing No. EP101

A. Revised receptacle locations at CHECK-IN C1003.

B. Revised receptacles in OFFICE C1004, C1005, C1006, and 1007.

C. Revised receptacles in PCR-E C1008 and C1009.

D. Revised receptacles in HUDDLE AREA C168.

E. Revised symbol for lift to include disconnect switch in PCR-E C1027, PCR-W/B/P C1030, and C1051.

F. Revised receptacles in ALCOVE C170.

G. Revised Plan Note #2.

H. Revised poke-thru devices to floor boxes.

ITEM NO. 6 Drawing No. EY101

A. Revised fire alarm strobe location in HUDDLE AREA C168 and C176.

B. Revised fire alarm audible/visual device near north end of STAFF CORRIDOR C*1*19 to strobe device.

C. Revised fire alarm audible/visual device near STORAGE C171 to strobe device.

TECHNOLOGY

ITEM NO. 1 Drawing No. E501

A. Corrected the plan note labeling on the CCTV details to avoid confusion.

ITEM NO. 2 Drawing No. ET101

A. Adjusted data outlets located in the office areas shown as part of Alternate #2.

B. Revised plan notes 13 and 14 to better reflect conduit routing.

C. Revised conduit routing for workstation cabling in the Team Areas to utilize full height walls.

END OF ADDENDUM NO. 02