515-18-109 Bid Drawings - Signed_Part1 - reissue.pdf
PDF 15 MB Posted
- Solicitation number
- 36C25020B0058
About this file
This document outlines a federal contract opportunity for renovation services. The solicitation seeks bids to furnish all labor, materials, supervision, equipment, tools, and other necessary resources to renovate the outpatient pharmacy and urgent care areas at the Battle Creek Healthcare System located in Battle Creek, Michigan. Key details include a solicitation number of 36C25020B0058, NAICS code 236220 with a $39.5 million small business size standard, and a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. An organized site visit is scheduled and sealed bids must be delivered to the Network 10 Contracting Office by 2:00PM on September 10, 2020. The place of performance is 5500 Armstrong Road in Battle Creek. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10 is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Covid Instructions.docx | DOCX document | |
| 36C25020B0058 0002.docx | DOCX document | |
| 515-18-109 Pre-Bid Attendance Sheet.pdf | ||
| RFi Answers.docx | DOCX document | |
| 36C25020B0058 0001.docx | DOCX document | |
| 515-18-109 Bid Specifications_Part3.pdf | ||
| WD MI20200079 7-24-20.pdf | ||
| Contractor EMR Certification Form 2020.docx | DOCX document | |
| 515-18-109 Bid Drawings - Signed_Part1.pdf | ||
| 515-18-109 Bid Drawings - Signed_Part2.pdf | ||
| 515-18-109 Bid Drawings - Signed_Part5.pdf | ||
| 515-18-109 Bid Drawings - Signed_Part3.pdf | ||
| S02 - RFI Form 515-18-109.docx | DOCX document | |
| 515-18-109 Bid Specifications_Part1.pdf | ||
| 515-18-109 Bid Specifications_Part2.pdf | ||
| 36C25020B0058.docx | DOCX document | |
| 515-18-109 Bid Drawings - Signed_Part6.pdf | ||
| 515-18-109 Bid Drawings - Signed_Part4.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REF.REF.
REF.
REF.
UP
UP
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
REFER TO VA MANUAL PG-18-3 FOR ADDITIONAL CODES, STANDARDS, GUIDELINES AND
REGULATIONS, BELOW LISTING IS NOT COMPREHENSIVE.
ICC, INTERNATIONAL BUILDING CODES, 2018 EDITION (IBC)
ASCE-07-10
ACI 318-11
ACI 530-11
AISC 341-10
AISC 360-10
PCI MNL 120-10, DESIGN HANDBOOK
NFPA 10, STANDARD FOR PORTABLE FIRE EXTINGUISHERS, 2018 EDITION
NFPA 13, STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS, 2019 EDITION
NFPA 14, STANDARD FOR THE INSTALLATION OF STANDPIPE AND HOSE SYSTEM, 2019
EDITION
NFPA 20, STANDARD FOR THE INSTALLATION OF STATIONARY PUMPS FOR FIRE
PROTECTION, 2019 EDITION
NFPA 24, STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND
THEIR APPURTENANCE, 2019 EDITION.
NFPA 54 NATOINAL FUEL GAS CODE, 2018 EDITION
NFPA 70, NATIONAL ELECTRIC CODE, 2017 EDITION
NFPA 72, NATIONAL FIRE ALARM CODE, 2019 EDITION
NFPA 75, STANDARD FOR THE PROTECTION OF ELECTRICAL COMPUTER/DATA
PROCESSING EQUIPMENT, 2017 EDITION
NFPA 77, RECOMMENDED PRACTICE ON STATIC ELECTRICITY, 2019 EDITION
NFPA 80, STANDARD FOR FIRE DOORS AND FIRE WINDOWS, 2019 EDITION
NFPA 90A, STANDARD FOR THE INSTALLATION OF AIR-CONDITIONING AND VENTILATING
SYSTEMS, 2018 EDITION.
NFPA 92, STANDARD FOR SMOKE CONTROL SYSTEMS, 2018 EDITION
NFPA 99, STANDARD FOR HEALTHCARE FACILITIES, 2018 EDITION
NFPA,99B, STANDARD FOR HYPOBARIC FACILITIES, 2018 EDITION
NFPA 101, LIFE SAFETY CODE, 2018 EDITION
NFPA 110, STANDARD FOR EMERGENCY AND STANDBY POWER SYSTEMS
NFPA 220, STANDARD TYPES OF BUILDING CONSTRUCTION, 2018 EDITION.
NFPA 780, STANDARD FOR INSTALLATION OF LIGHTING PROTECTION SYSTEMS, 2017
EDITION
NFPA 54 TYPE 2 CLOTHES DRYER UL 705 DEDPY, 2015 EDITION
MOST RECENT EDITION OF NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA
5000 AND NFPA 900
ASHRAE 90.1-2016 HVAC SYSTEMS
ASHRAE 62.1 - 2016 VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY
ASHRAE 170 - 2013 VENTILATION OF HEALTH CARE FACILITES
ANSI A117.1-2017 STANDARD ON ACCESSIBLE & USABLE BUILDINGS AND FACILITIES
2010 ADA STANDARDS FOR ACCESSIBLE DESIGN
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS
ENERGY POLICY ACT OF 2005 (EPACT)
EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY, AND
TRANSPORTATION MANAGEMENT.
VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD
STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL
INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).
VA MENTAL HEALTH FACILITIES DESIGN GUIDE, DECEMBER 2010 (REV. 08/01/2014)
VA BARRIER FREE DESIGN GUIDE PG-18-13, ABAAS
ARCHITECTURAL, AUGUST 1, 2014
ASBESTOS ABATEMENT, JULY 2011
CMP SCHEDULE AND RISK MANAGEMENT, VOL. 1 & 2, DECEMBER 2012
ELECTRICAL, DECEMBER 2015
ENERGY SUSTAINABILITY, MAY 2014
EQUIPMENT, JANUARY 2006
ESTIMATING, MARCH 8, 2011
NFPA INTERIM GUIDANCE FOR PROJECTS, PG-18-17, SEPTEMBER 30, 2010
FIRE PROTECTION, SEVENTH EDITION REVISED DECEMBER 2015
HVAC FOR NEW, REPLACEMENT, ADD. AND REN. OF EXIST. CA FACILITIES, MARCH 2011
INTERIOR DESIGN, MAY 2008
PHYSICAL SECURITY DESIGN MANUAL, JANUARY 2015
PLUMBING, NOVEMBER 2014
STRUCTURAL, FEBRUARY 1, 2014
WAY FINDING AND SIGNAGE, INTERIOR, DECEMBER 2012
SEISMIC DESIGN REQUIREMENTS, H-18-8, AUGUST 2013
ENVIRONMENTAL PLANNING GUIDANCE PG-18-17 NEPA INTERIM GUIDELINES FOR
PROJECTS SEPTEMBER 30, 2010
EPA GUIDELINES CHECKLIST
VA DESIGN MANUALS PG-18-10:
GOVERNING CODES:CODE ANALYSIS - NFPA 101, BUSINESS CHAPTER 38 & AMBULATORY HEALTH CARE OCCUPANCY CHAPTER 20
CODE CRITERIA
GENERAL: THIS SUMMARY OF CODE REQUIREMENTS IS BASED PRIMARILY ON NFPA 101 (LSC). DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE IDENTIFIED. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES.
NOTES:
CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
CODE REVIEW
THE 2018 EDITION OF THE LIFE SAFETY CODE, NFPA 101, HAS BEEN USED TO REVIEW THIS PROJECT FOR COMPLIANCE WITH THE FIRE AND LIFE SAFETY REQUIREMENTS.
FOR FEATURES NOT ADDRESSED BY NFPA 101 AND THE REFERENCED NATIONAL FIRE CODES, THE 2018 EDITION OF THE INTERNATIONAL BUILDING CODE HAS BEEN
USED.
PROJECT SCOPE
THE PROJECT SCOPE INCLUDES RENOVATION
THE CONSTRUCTION TYPE IS DETERMINED BASED UPON THE ALLOWABLE AREA AND HEIGHT REQUIREMENTS OF CHAPTER 5 OF THE 2018 IBC. CONSTRUCTION TYPE AND MATERIALS SHALL BE PER CHAPTER 6 OF THE IBC FOR TYPE IB/TYPE II(222) CONSTRUCTION AS FOLLOWS:
OCCUPANCY TYPE: B-BUSINESS, IBC CHAPTER 3/LSC CHAPTER 38 & AMBULATORY HEALTH CARE, LSC CHAPTER 20
CONSTRUCTION TYPE: IB (IBC CHAPTER 5)
3. FIRE RESISTIVE RATINGS TYPE IB CONSTRUCTION, CHAPTER 6 IBC/NFPA 101:
STRUCTURAL FRAME: NONCOMBUSTIBLE, 2-HOUR FIRE RESISTIVE
BEARING WALLS
EXTERIOR: NONCOMBUSTIBLE, 2 -HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 2-HOUR FIRE RESISTIVE
NON-BEARING WALLS AND PARTITIONS
EXTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE-RESISTIVE
FLOOR: NONCOMBUSTIBLE, 2-HOUR FIRE RESISTIVE
ROOF: NONCOMBUSTIBLE, 1-HOUR FIRE RESISTIVE
SHAFT ENCLOSURES 2-HOUR FIRE RESISTIVE >4 STORIES (IBC 713.4, LSC 12.3.6)
SHAFT ENCLOSURES 1-HOUR FIRE RESISTIVE <4 STORIES (IBC 713.4, LSC 12.3.6)
FIREPROOFING NOTE: CONTRACTOR IS REQUIRED TO PROVIDE NEW FIREPROOFING ON NEW STEEL AND ASSEMBLIES, AND ON EXISTING CONSTRUCTION WHERE REQUIRED BY DEMOLITION AND NEW WORK TO MAINTAIN FIRE RATINGS PER THE CODE ANALYSIS GI101. PRIMARY STRUCTURAL FRAME 2 HRS, ROOF 1 HR, AND FLOOR 2
HRS.
4. STRUCTURAL DESIGN SHALL COMPLY WITH CHAPTER 16 OF THE IBC.
5. ALLOWABLE HEIGHT: UNLIMITED FT (IBC, TABLE 504.3)
6. ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLAN: 11 (IBC, TABLE 504.4)
7. ALLOWABLE AREA: BASED UPON UNLIMITED OCCUPANCY, IB CONSTRUCTION TYPE
8. OCCUPANCY SEPARATION: A ONE HOUR OCCUPANCY SEPARATION IS REQUIRED BETWEEN THE AMBULATORY HEALTH CARE OCCUPANCY (LSC CHAPTER 20) AND THE
BUSINESS SUITE OCCUPANCY (LCS CHAPTER 38). (LSC 18.1.3.4)
9. MEANS OF EGRESS
• CLEAR WIDTH OF CORRIDORS SHALL BE CLEAR 44 INCHES.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 32 INCHES
• NOT LESS THAN 2 EXITS SHALL BE PROVIDED PER FLOOR.
• ADDITION OCCUPANCY LOAD: <500 THEREFORE 2 EXITS REQUIRED (LSC 7.4.1)
• MAXIMUM TRAVEL DISTANCE, FULLY SPRINKLED: 150 FEET (LSC 20.2.6.2)
• COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET (LSC 38.2.5.3.1)
• DEAD END CORRIDORS SHALL NOT EXCEED 50 FEET. (LSC 38.2.5.2.1)
• MEANS OF EGRESS SHALL BE ILLUMINATED. (LSC 38.2.8)
• EMERGENCY LIGHTING SHALL BE PROVIDED, BUILDING OVER 3 STORIES. (LSC 38.2.9.1)
• EXIT SIGNAGE SHALL BE PROVIDED. (LSC 38.2.10)
10. PROTECTION FROM ANY AREA HAVING A DEGREE OF HAZARD GREATER THAN THAT NORMAL TO THE GENERAL OCCUPANCY OF THE BUILDING OR STRUCTURE SHALL BE PROVIDED BY PROTECTING THE AREA WITH AUTOMATIC EXTINGUISHING SYSTEMS IN ACCORDANCE WITH SECTION 9.7(3). WHERE HAZARD IS SEVERE PER LSC CHAPTER 38, SOILED HOLDING, PROTECTION IS PROVIDED WITH AN AUTOMATIC EXTINGUISHING SYSTEMS THE SPACE SHALL ALSO BE ENCLOSED WITH SMOKE
PARTITIONS IN ACCORDANCE WITH SECTION 8.4.
• 1-HOUR FIRE RESISTANCE RATING AND AUTOMATIC SPRINKLER SYSTEM IS REQUIRED FOR THE FOLLOWING: SOILED HOLDING AND HIGH HAZARD CONTENT
AREAS PER LSC 38.2.2.
11. INTERIOR FINISH
• WALLS AND CEILINGS: INTERIOR FINISH FLAME SPREAD SHALL BE LIMITED PER CHAPTER 8 OF THE NFPA 101 TO CLASS A, B AND C MATERIALS. INTERIOR WALL
AND CEILING FINISH SHALL BE CLASS A OR CLASS B IN EXITS, CORRIDORS AND LOBBIES; AND CLASS A, CLASS B, OR CLASS C IN ALL OTHER AREAS. (LSC 38.3.3)
• · CLASS A: FLAME SPREAD 0-25; SMOKE DEVELOPED 0-450.
• · CLASS B: FLAME SPREAD 26-75; SMOKE DEVELOPED 0-450.
• · CLASS C: FLAME SPREAD 76-200; SMOKE DEVELOPED 0-450
• FLOORS: INTERIOR FLOOR FINISH SHALL BE CLASS I OR CLASS II IN CORRIDORS AND EXITS.
• FABRIC DRAPERIES, CURTAINS (EXCLUDING SHOWER CURTAINS, BUT INCLUDING CUBICLE CURTAINS), AND OTHER LOOSELY HANGING FABRICS AND FILMS
SERVING AS FURNISHINGS OR DECORATIONS IN HEALTH CARE OCCUPANCIES MUST MEET THE FLAME RESISTANCE REQUIREMENTS OF NFPA 701, STANDARD
METHODS OF FIRE TESTS FOR FLAME-RESISTANT TEXTILES AND FILMS.
• UPHOLSTERED FURNITURE AND MATTRESSES. UPHOLSTERED FURNITURE AND MATTRESSES MUST ALSO MEET SPECIFIED REQUIREMENTS, BASED ON NFPA
260, NFPA 261, NFPA 266, 16 CFR 1632, ASTME E1537, AND ASTME E1590
12. EXTINGUISHMENTS REQUIREMENTS, PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED PER NFPA 10. (38.3.5)
13. DETECTION, ALARM, AND COMMUNICATIONS SYSTEMS.
• FIRE ALARM SYSTEM SHALL BE PROVIDED LSC, NFPA 70 (NEC) AND NFPA 72. (LSC 9.6.1)
• FIRE ALARM MAY BE BY MANUAL MEANS (LSC 38.4.2)(LSC 9.6.2)
• OCCUPANT NOTIFICATION SHALL BE THROUGH AUTOMATIC MEANS. (LSC 38.3.4.3)
• SMOKE DETECTION SHALL BE PROVIDED PER NFPA 72.
• EMERGENCY RESPONDER NOTIFICATION SHALL BE NOTIFIED BY ALARM AND DETECTION SYSTEM. (LSC 38.3.4.4)
14. FIRE SUPPRESSION:
SPRINKLER SYSTEM: BUILDING IS REQUIRED TO BE SPRINKLED THROUGHOUT IN ACCORDANCE WITH NFPA 13.
THE SPRINKLER SYSTEM SHALL BE HYDRAULICALLY DESIGNED IN ACCORDANCE WITH 2019 EDITION OF NFPA 13 AND THE SEVENTH EDITION OF THE DEPARTMENT OF
VETERANS AFFAIRS FIRE PROTECTION DESIGN MANUAL: MINIMUM DESIGN REQUIREMENTS:
STORAGE MECHANICAL AND ELECTRICAL ROOMS SHALL BE PROTECTED AS:
ORDINARY HAZARD OCCUPANCY, GROUP 1: 0.15 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 250 GPM
ALL OTHER AREAS SHALL BE PROTECTED AS:
LIGHT HAZARD OCCUPANCY: 0.10 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 100 GPM
ALL SPRINKLERS WITHIN THE SMOKE ZONE SHALL BE QUICK RESPONSE SPRINKLERS.
16. CONSTRUCTION BARRIERS CONSTRUCTED ALONG MEANS OF EGRESS ALONG HEALTHCARE OCCUPANCIES (LSC CHAPTER 18 AND 19) SHALL BE CONSTRUCTED AND
MAINTAINED PER NFPA 241.
PROCEDURE
0111A
STOR.
0110B
ISO EXAM
TRIAGE
RECEPTION
0103A
TRIAGE
VAULT
0103B585 SF
A
EQUIP. STORAGE
MH EXAM
M.H. TLT
EXAM / FLEX M.H.
EXAM / FLEX M.H.
0120 EXAM
SOILED
STAFF TLT
STAFF TLT
CONSULT
772 SF
A
CONSULT
CONSULT
CONSULT
VAULT
CONFERENCE RM
UC BREAK RM AND
LOCKERS
HAC
RECEIVING
DISPENSING
WINDOWS
BREAK RM
STAFF TLT
OFFICE
GENERAL WAITING
PROCEDURE ROOM
GAS - FULL
2084 SF
10022
B
EXAM SOUND
BOOTH
SECURITY OFFICE
MECHANICAL
EXIST. IT CLOSET
OFFICE
OFFICE
TEMP PHARMACY
CONSULT
AGENT CASHIER
0051A
HAC
MECH
MECH
ON-CALL
0097A
GAS - EMPTY AND
IN-USE
ON-CALL TLT /
SHOWER
0097B
VEST. / BOX BREAK
DOWN
HVAC
021E
HOUSE KEEPING
OFFICE
OFFICE
FILLING
WORK STATIONS
PHARM. STORAGE
MH EXAM
AUDIOLOGY EXAM
SHOWER
0106A
ISO / PATIENT
TOILET
NURSE MANAGER
LINEN
AUDIOLOGY CLEAN
NF AND PENDING
016 STORAGE
NURSE
0135A
NURSE / DICTATION
EXAM
EXAM
PATIENT TLT
CLEAN
EXAM
MED
0130 PROCEDURE
0110A
MAIL-OUT
B
5,512 SF
CONSULT /
DISPENSING
B
3,540 SF
URGENT CARE SUITE
FEC
FEC
FEC
FEC
FEC
FEC
FEC
FEC
FEC
PHARMACY WAITING
EXIT
EXIT
EXIT
EXIT
EXIT
EXIT
EXIT
TRAVEL DISTANCE: 198'-7"
T R
A V
E L
D
IS
T A
N C
E
'-1
0"
TRAVEL DISTANCE: 95'
TRAVEL DISTANCE: 148'-11"
10035
PHARMACY WORK
RM
ELECTRICAL
CLOSET
ELECTRICAL
CLOSET
WALK-IN ENTRANCE
MECH
CORRIDOR
C08
CORRIDOR
C05
CORRIDOR
C01
CORRIDOR
C02
CORRIDOR
C011
STORAGE
CORRIDOR
C03
EXIT PASSAGEWAY
01228
OFFICE
OFFICE
OFFICE
OFFICE
EXAM
STAFF LOUNGE/
LOCKER ROOM
OFFICE
STOR.
OFFICE
CUSTOMER SERVICE
OFFICE
OFFICE
0074A
HSK
ELEC.
OFFICE
I.T.
OFFICE
SUB WAITING
TOILET
0078A
FEMALE
ELEV.
E3
MALE
OFFICE
FEMALE
MALE
STAIR
S1
STOR.
016A
HVAC
0017E
ELEV. MACH.
0018E
ELEV.
E1
ELEV.
E2
HVAC
0020E
STAIR
S2
STOR.
PROSTHETICS
TREATMENT
WAITING
HVAC
0042E
CHIEF
EXAM SOUND
BOOTH
SECRETARY
STAIR
S5
STAIR
S3
CORRIDOR
C04
CORRIDOR
C015
STAIR
S6
TEMP VAULT
PRESCRIPTION
PICK-UP
BREAK RM
PHOTO
STOR.
EXAM SOUND
BOOTH
CORRIDOR
C06
CORRIDOR
C014
CLOSET
0111B
CORRIDOR
C010
CORRIDOR
C012
VAULT
0051B
HALL
CALL ROOM
CLOSET
0107A
MECH
0112A
OPEN OFFICE AND
AUDIOLOGY AND
TEMPORARY PHARMACY,
BUSINESS OCCUPANCY
URGENT CARE,
AMBULATORY HEALTH
CARE OCCUPANCY
PHARMACY, BUSINESS
OCCUPANCY
SHADE INDICATES AREA
NOT IN SCOPE
SHADE INDICATES AREA
NOT IN SCOPE
CROSSHATCH INDICATES AREA OF
SPRINKLER SYSTEM, SEE FIRE
PROTECTION DRAWINGS
CROSSHATCH INDICATES AREA OF
SPRINKLER SYSTEM, SEE FIRE
PROTECTION DRAWINGS
48'-8"
TEMPORARY
PHARMACY
(PHASE 1) OPEN
OFFICE AND
AUDIOLOGY
(PHASE 3)
PHARMACY
(PHASE 2)
URGENT CARE
(PHASE 4)
SHADE
INDICATES
APPROXIMATE
AREA OUT OF
SCOPE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08 - 6231
A
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
FRED VOLLMERHAUSEN
CHIEF, ENGINEERING PROJECTS
100% DESIGN SUBMISSION 03/13/2020
95% DESIGN SUBMISSION 9/13/2019
65% DESIGN SUBMISSION 12/05/2018
35% DESIGN SUBMISSION 10/12/2018
100% BID DOCUMENTS 05/20/2020
C U s e rs
\t s a n d e rs \D o c u m e n ts \1
.1
.0
V
A B
C P
H A
R U
C A ts a n d e rs g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:5
A
M
GI101
LIFE SAFETY PLAN RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
May 20, 2020 JDF JDJ
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
SCALE: 3/32" = 1'-0"GI101
2 GROUND FLOOR LIFE SAFETY PLAN
N
SCALE: 1" = 80'-0"
KEY PLAN - GROUND FLOOR
Revisions: Date:
UPUP
CONTINUOUS FIRESAFE SEALANT
TOP AND BOTTOM, & BOTH SIDES
3 1/2" SOUND ATTENUATION BATT.
5/8" TYPE X GYPSUM BOARD, BOTH
SIDES
3 5/8" METAL STUD @ 16" O.C.
WITH RUNNER CHANNELS ALONG
TOP AND BOTTOM
CONSTRUCTION
SIDE
PUBLIC
SIDE
6 MIL. FIRE RETARDANT VISQUEEN
MEMBRANE. CONTINUOUSLY
ADHERE TO THE STRUCTURAL DECK
ABOVE AND TO THE FLOOR BELOW
WITH TAPE.
UNDERSIDE OF STRUCTURAL DECK
COORDINATE WITH EXISTING
CEILING
CONTRACTOR SHALL
FINISH, INCLUDING
PAINTING, PUBLIC SIDE
OF TEMPORARY WALLS
TEMPORARY IC BARRIER WALL
CONSTRUCTION (DUST WALL)
5/8" TYPE X GYP BD
3 5/8" STEEL STUDS @ 16"
O.C.
BEAD OF CONT. SEALANT
6-MIL FIRE RETARDENT POLY
INTERIOR SIDE
CEILING
2" DEEP LEG 3 5/8" STEEL SLIP TRACK
3 5/8" STEEL STUD TRACK
6" M
IN
CONTINUOUSLY ADHERE 6-MIL. FIRE
RETARDANT POLY TO DECK WITH TAPE
CONTINUOUSLY ADHERE FIRE RETARDENT
POLY TO FLOOR WITH TAPE
EXISTING DECK
CONSTRUCTION
SIDE
OCCUPIED
SIDE
PUBLIC SIDE
1 HOUR FIRE RATED METAL DOOR ASSEMBLY
AND FRAME WITH SEALS, CARD READER,
HARDWARE AND CLOSER
NEGATIVE AIR MONITOR
HAND SANITIZER
SEAL ALL EDGES WITH TAPE
SEAL ALL EDGES WITH TAPE
REFER TO TEMPORARY BARRIER TYPE
FOR REQUIRED CONDITION TO
STRUCTURE ABOVE
VA / OSHA TEMPORARY SIGNAGE
PHASE 1
CONSTRUCTION
ACCESS. NEW
WINDOWS OPENINGS
WILL BE INSTALLED IN
PHASE 1
PHASE 1
AREA C
PHASE 1
AREA ACONSTRUCTION
BARRIER
AND ACCESS
CONSTRUCTION
BARRIER AND
ACCESS
PHASE 1
AREA B
PHASE 1 CONSTRUCTION OPENING. WINDOWS
OPENING BE INSTALLED IN PHASE 1
PHASE 1 – TEMPORARY PHARMACY SHELL SPACE SCOPE AND PORTION OF NEW
PHARMACY RENOVATION SCOPE
ESTIMATED DURATION: 18 WEEKS
PHASE 1 AREA A – TEMPORARY PHARMACY BUILD OUT AND STAFF /
EQUIPMENT MOVE TO SHELL 0G-001
• DEMOLITION AND NEW WORK IN SHELL OG-001, EXIT PASSAGEWAY, AND
EXISTING VENDING EXCEPT FOR THE AREA OF PHASE 1 AREA B. REFER
TO PHASING PLANS AND ALL CONTRACT DOCUMENTS FOR ADDITIONAL
INFORMATION.
• PROVIDE (4) NEW WINDOWS IN EXISTING EXTERIOR WALLS. WINDOW
OPENING CAN BE USED FOR CONSTRUCTION ACCESS TO EXISTING SHELL
SPACE.
• THIS IS THE CRITICAL PATH OF CONSTRUCTION FOR PHASE 1. WHEN THIS
PORTION OF WORK IS COMPLETED, THE VA WILL MOVE PHARMACY INTO
ITS TEMPORARY LOCATION.
PHASE 1 AREA B – UC BREAK RM AND ON-CALL TLT / SHOWER 0097
• DEMOLITION AND NEW WORK OF THE REMAINDER OF THE SHELL OG-001,
EXIT PASSAGEWAY, AND EXISTING VENDING. REFER TO PHASING PLANS
AND ALL CONTRACT DOCUMENTS FOR ADDITIONAL INFORMATION.
• WHEN THIS PORTION OF WORK IS COMPLETED, THE TEMPORARY
PHARMACY STAFF WILL USE THIS SPACE.
PHASE 1 AREA C – WEST SHELL SPACE
• DEMOLITION AND NEW WORK IN WEST SHELL SPACE.
• THIS AREA DOES NOT NEED TO BE COMPLETED UNTIL THE COMPLETION
OF PHASE 2 FOR PERMANENT PHARMACY LOCATION.
CONSTRUCTION PHASING SEQUENCE - PHASE 1
CONSTRUCTION PHASING GENERAL NOTES
1. GENERAL CONTRACTOR SHALL PROVIDE APPROPRIATE TEMPORARY
BARRIER THAT WILL ALLOW CONTINUING OPERATIONS OF THE FACILITY
DURING CONSTRUCTION AS DETERMINED BY COR. THE GENERAL
CONTRACTOR SHALL NOTIFY THE OWNER, AT LEAST 48 HOURS IN
ADVANCE, OF ANY ACTIVITY THAT WILL PRODUCE DISRUPTIONS TO THE
FACILITY OR OPERATIONS.
2. BASED ON THE PROXIMITY TO THE EXISTING AUDIOLOGY DEPARTMENT,
G.C. SHALL COORDINATE WITH THE OWNER CONSTRUCTION ACTIVITIES,
GENERATION OF NOISE AND / OR VIBRATION TRANSMISSION AT TIME OF
CONSTRUCTION, WHICH WILL IMPACT THE AUDIOLOGY DEPARTMENT
OPERATION. ASSUME THAT CONSTRUCTION OPERATIONS SHALL ONLY
OCCUR DURING OFF HOURS OF OPERATION (NIGHTS AND WEEKENDS)
UNLESS DETERMINED OTHERWISE.
3. THE GENERAL CONTRACTOR SHALL INCLUDE 3 WEEKS BETWEEN
COMPLETION OF EACH CONSTRUCTION PHASE FOR VA STAFF TO OCCUPY
THE COMPLETED CONSTRUCTION AREA, PRIOR TO BEGINNING WORK ON
THE SUBSEQUENT AREA OF WORK. GENERAL CONTRACTOR SHALL
SCHEDULE / COORDINATE WITH THE OWNER ALL ASPECTS OF TRANSITION
BETWEEN CONSTRUCTION PHASES.
4. THE FOLLOWING PHASES ARE INDENTED TO PROVIDE A GUIDELINE
SEQUENCE OF CONSTRUCTION. THESE SHALL INCLUDE ALL ACTIVITIES,
METHODS, CONSTRUCTION SCHEDULING AND / OR COORDINATION, WHICH
WILL ENSURE THE UNINTERRUPTED OPERATIONS IN THE FACILITY. IF
THERE IS A NEED TO VARY AND / OR REVISE THESE PHASES, THE
GENERAL CONTRACTOR SHALL INFORM BOTH THE OWNER AND THE
ARCHITECT PRIOR TO ANY VARIATION / REVISION OF THE PHASES AND
THEIR EXECUTION.
PHASE 1
PHASE 2
PHASE 3
AREA 1A - EXISTING VENDING AREA, EXIT
PASSAGEWAY, AND EAST SHELL SPACE.
AREA 1B - BREAK ROOM AND ON CALL TLT.
COMPLETE ASAP FOR TEMP. PHARM USE
PHASE 1 IS COMPLETED UPON TEMPORARY PHARMACY
AREA READY FOR OCCUPANCY
AREA 1C - WEST SHELL SPACE
PHASE 2 IS COMPLETED UPON
PERMANENT PHARMACY AREA READY
FOR OCCUPANCY
AREA 2 - EXISTING PHARMACY AREA
VA MOVES
PHARMACY TO
TEMPORARY
AREA
VA MOVES
PHARMACY TO
PERMANENT
LOCATION
PHASE 3 IS COMPLETED UPON AUDIOLOGY OFFICE
AREAS, PATIENT FUNDS, AND AGENT CASHIER READY
FOR OCCUPANCY
AREA 3A - NEW AUDIOLOGY OFFICE AREA AND
PASSAGE INTO EXISTING AUDIOLOGY
AREA 4A - EXISTING URGENT CARE
AREA 3B - NEW PATIENT FUNDS AND AGENT CASHER VA OCCUPIES
COMPLETED
SPACES
PHASE 4
PHASE 4 IS COMPLETED UPON URGENT CARE AND ALL REMAINING WORK IS READY FOR
OCCUPANCY
VA OCCUPIES
COMPLETED
SPACES
AREA 3B - NEW BOX BREAKDOWN
AND NF AND PENDING
SUB-PHASE 3C
PHASE 3C IS COMPLETED UPON BOX
BREAKDOWN, AND NF AND PENDING
READY FOR OCCUPANCY VA OCCUPIES
COMPLETED
SPACES
AREA 4B - EAST VESTIBULE
AREA 4C - ENTRY AREA TO
AUDIOLOGY WAITING, FINISH ASAP
AREA 4E - AREA OF
NEW PUBLIC
HALLWAY THROUGH
URGENT CARE,
FINISH ASAP
AREA 4D - AREA OF EXISTING
PUBLIC HALLWAY NOT BEING USED
FOR NEW HALLWAY, FINISH ASAP
AREA 4F - NEW MAIN SOUTH
VESTIBULE
AREA 4G - CORRIDOR NIGHT AND
WEEKEND WORK
INFECTION CONTROL NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 1/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH CARD
READER ACCESS. REFER TO ELEVATION 3/GI102.
PROVIDE TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION.
REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO FULL SET OF CONTRACT DOCUMENTS FOR ALL PHASING
INFORMATION.
PROJECT SHALL BE COMPLETED IN 4 PHASES AS OUTLINED IN THESE
DOCUMENTS.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR.
TEMPORARY IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS
ARE APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR ONCE
ICRA PROTOCOLS AND PLAN IS APPROVED.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CPM SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANNER UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM WEEKDAYS OR ON THE WEEKENDS.
EVERY EFFORT SHALL BE MADE TO KEEP NOISE AND VIBRATION TO A
MINIMUM.
PROVIDE A 24"X36" STICKY WALK OFF MAT AND HAND SANITIZER AT EACH
TEMPORARY DOOR LOCATION. MAT SHALL BE REPLACED OR CLEANED AS
DETERMINED BY COR.
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT TO INCLUDE SHOP VAC, MULTI-
PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE LIQUIDS
UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSE WITH
A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
INFECTION CONTROL GENERAL NOTES
PHASING LEGEND AND NOTES
# HATCH AND NUMBER INDICATE CURRENT
PHASE - SEE PHASING PLANS
TEMPORARY WALLS AND DOORS
AREA NOT IN SCOPE OF
WORK
PHASE 2
PHASE 1
AREA C
CONSTRUCTION BARRIER
AND CONSTRUCTION
ACCESS DOOR
FOR WORK ON PHASE 1C
PHASE 2 – PERMANENT PHARMACY RENOVATION
ESTIMATED DURATION: 22 WEEKS
• DEMOLITION AND NEW WORK FOR PERMANENT PHARMACY.
• THIS IS THE CRITICAL PATH OF CONSTRUCTION FOR PHASE 2. WHEN THIS
PORTION OF WORK IS COMPLETED, THE VA WILL MOVE PHARMACY INTO
ITS PERMANENT LOCATION.
CONSTRUCTION PHASING SEQUENCE - PHASE 2
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08 - 6231
A
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
FRED VOLLMERHAUSEN
CHIEF, ENGINEERING PROJECTS
100% DESIGN SUBMISSION 03/13/2020
95% DESIGN SUBMISSION 9/13/2019
65% DESIGN SUBMISSION 12/05/2018
35% DESIGN SUBMISSION 10/12/2018
100% BID DOCUMENTS 05/20/2020
C U s e rs
\t s a n d e rs \D o c u m e n ts \1
.1
.0
V
A B
C P
H A
R U
C A ts a n d e rs g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:0
A
M
GI102
CONSTRUCTION PHASES 1 & 2 /
INFECTION CONTROL PLAN
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
May 20, 2020 JDF JDJ
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
SCALE: 1 1/2" = 1'-0"GI102
1 TEMP 1 HR RATED BARRIER WALL - NFPA 241
SCALE: 1 1/2" = 1'-0"GI102
2 TEMP INFECTION CONTROL BARRIER WALL
SCALE: 1/4" = 1'-0"GI102
3 TEMP WALL CONSTRUCTION ELEVATION
N
SCALE: 1" = 20'-0"GI102
5 PHASE 1 PLAN KEY PLAN
SCALE: 12" = 1'-0"
PHASING TIMELINE LEGEND
SCALE: 1" = 20'-0"GI102
6 PHASE 2 PLAN
UPUP
UP
PHASE 3
AREA A
PHASE 3
AREA B
PHASE 3
AREA C
MODIFIED PHASE 3C
BARRIER
AND ACCESS
CONSTRUCTION BARRIER
AND ACCESS
CONSTRUCTION
BARRIER AND
ACCESS
PHASE 3 – AUDIOLOGY RENOVATION SCOPE
THE FOLLOWING DESCRIBES THE SEQUENCE OF CONSTRUCTION FOR
THE AUDIOLOGY RENOVATION WORK.
ESTIMATED DURATION: 10 WEEKS
PHASE 3 AREA A - AUDIOLOGY OFFICE AREA BUILD OUT AND STAFF
/EQUIPMENT MOVE
• DEMOLITION AND NEW WORK TO CREATE FINAL OFFICE SPACE AND TO
CREATE THE CONNECTION TO EXISTING AUDIOLOGY. RENOVATE
EXISTING SPACES AS NOTED.
• WHEN THIS IS COMPLETED, VA WILL MOVE INTO AND OCCUPY THIS AREA.
PHASE 3 AREA B - PATIENT FUNDS AND AGENT CASHER RNOVATION
• NEW RENOVATION IN PATIENT FUNDS 0024. PROVISION FOR CUTTING OF
NEW OPENINGS IN EXISTING WALL, ALONG WITH THE WORK INDICATED IN
THE PLANS.
• THIS IS THE CRITICAL PATH FOR PHASE 3. WHEN THIS AREA IS
COMPLETED, THE VA WILL OCCUPY THIS SPACE AND PHASES 3C AND 4
MAY BEGIN.
PHASE 3C – RENOVATE EXISTING PATIENT FUNDS AND AGENT CASHIER
• DEMOLITION AND NEW WORK TO RENOVATE EXISTING PATIENT FUNDS
AND AGENT CASHIER.
• THIS AREA SHOULD BE COMPLETED AS SOON AS POSSIBLE BUT DOES
NOT NEED TO BE COMPLETED PRIOR TO PHASE 4.
CONSTRUCTION PHASING SEQUENCE - PHASE 3
CONSTRUCTION PHASING GENERAL NOTES
1. GENERAL CONTRACTOR SHALL PROVIDE APPROPRIATE TEMPORARY
BARRIER THAT WILL ALLOW CONTINUING OPERATIONS OF THE FACILITY
DURING CONSTRUCTION AS DETERMINED BY COR. THE GENERAL
CONTRACTOR SHALL NOTIFY THE OWNER, AT LEAST 48 HOURS IN
ADVANCE, OF ANY ACTIVITY THAT WILL PRODUCE DISRUPTIONS TO THE
FACILITY OR OPERATIONS.
2. BASED ON THE PROXIMITY TO THE EXISTING AUDIOLOGY DEPARTMENT,
G.C. SHALL COORDINATE WITH THE OWNER CONSTRUCTION ACTIVITIES,
GENERATION OF NOISE AND / OR VIBRATION TRANSMISSION AT TIME OF
CONSTRUCTION, WHICH WILL IMPACT THE AUDIOLOGY DEPARTMENT
OPERATION. ASSUME THAT CONSTRUCTION OPERATIONS SHALL ONLY
OCCUR DURING OFF HOURS OF OPERATION (NIGHTS AND WEEKENDS)
UNLESS DETERMINED OTHERWISE.
3. THE GENERAL CONTRACTOR SHALL INCLUDE 3 WEEKS BETWEEN
COMPLETION OF EACH CONSTRUCTION PHASE FOR VA STAFF TO OCCUPY
THE COMPLETED CONSTRUCTION AREA, PRIOR TO BEGINNING WORK ON
THE SUBSEQUENT AREA OF WORK. GENERAL CONTRACTOR SHALL
SCHEDULE / COORDINATE WITH THE OWNER ALL ASPECTS OF TRANSITION
BETWEEN CONSTRUCTION PHASES.
4. THE FOLLOWING PHASES ARE INDENTED TO PROVIDE A GUIDELINE
SEQUENCE OF CONSTRUCTION. THESE SHALL INCLUDE ALL ACTIVITIES,
METHODS, CONSTRUCTION SCHEDULING AND / OR COORDINATION, WHICH
WILL ENSURE THE UNINTERRUPTED OPERATIONS IN THE FACILITY. IF
THERE IS A NEED TO VARY AND / OR REVISE THESE PHASES, THE
GENERAL CONTRACTOR SHALL INFORM BOTH THE OWNER AND THE
ARCHITECT PRIOR TO ANY VARIATION / REVISION OF THE PHASES AND
THEIR EXECUTION.
INFECTION CONTROL NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 1/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH CARD
READER ACCESS. REFER TO ELEVATION 3/GI102.
PROVIDE TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION.
REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO FULL SET OF CONTRACT DOCUMENTS FOR ALL PHASING
INFORMATION.
PROJECT SHALL BE COMPLETED IN 4 PHASES AS OUTLINED IN THESE
DOCUMENTS.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR.
TEMPORARY IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS
ARE APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR ONCE
ICRA PROTOCOLS AND PLAN IS APPROVED.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CPM SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANNER UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM WEEKDAYS OR ON THE WEEKENDS.
EVERY EFFORT SHALL BE MADE TO KEEP NOISE AND VIBRATION TO A
MINIMUM.
PROVIDE A 24"X36" STICKY WALK OFF MAT AND HAND SANITIZER AT EACH
TEMPORARY DOOR LOCATION. MAT SHALL BE REPLACED OR CLEANED AS
DETERMINED BY COR.
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT TO INCLUDE SHOP VAC, MULTI-
PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE LIQUIDS
UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSE WITH
A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
INFECTION CONTROL GENERAL NOTES
PHASING LEGEND AND NOTES
# HATCH AND NUMBER INDICATE CURRENT
PHASE - SEE PHASING PLANS
TEMPORARY WALLS AND DOORS
AREA NOT IN SCOPE OF
WORK
PHASE 1
PHASE 2
PHASE 3
AREA 1A - EXISTING VENDING AREA, EXIT
PASSAGEWAY, AND EAST SHELL SPACE.
AREA 1B - BREAK ROOM AND ON CALL TLT.
COMPLETE ASAP FOR TEMP. PHARM USE
PHASE 1 IS COMPLETED UPON TEMPORARY PHARMACY
AREA READY FOR OCCUPANCY
AREA 1C - WEST SHELL SPACE
PHASE 2 IS COMPLETED UPON
PERMANENT PHARMACY AREA READY
FOR OCCUPANCY
AREA 2 - EXISTING PHARMACY AREA
VA MOVES
PHARMACY TO
TEMPORARY
AREA
VA MOVES
PHARMACY TO
PERMANENT
LOCATION
PHASE 3 IS COMPLETED UPON AUDIOLOGY OFFICE
AREAS, PATIENT FUNDS, AND AGENT CASHIER READY
FOR OCCUPANCY
AREA 3A - NEW AUDIOLOGY OFFICE AREA AND
PASSAGE INTO EXISTING AUDIOLOGY
AREA 4A - EXISTING URGENT CARE
AREA 3B - NEW PATIENT FUNDS AND AGENT CASHER VA OCCUPIES
COMPLETED
SPACES
PHASE 4
PHASE 4 IS COMPLETED UPON URGENT CARE AND ALL REMAINING WORK IS READY FOR
OCCUPANCY
VA OCCUPIES
COMPLETED
SPACES
AREA 3B - NEW BOX BREAKDOWN
AND NF AND PENDING
SUB-PHASE 3C
PHASE 3C IS COMPLETED UPON BOX
BREAKDOWN, AND NF AND PENDING
READY FOR OCCUPANCY VA OCCUPIES
COMPLETED
SPACES
AREA 4B - EAST VESTIBULE
AREA 4C - ENTRY AREA TO
AUDIOLOGY WAITING, FINISH ASAP
AREA 4E - AREA OF
NEW PUBLIC
HALLWAY THROUGH
URGENT CARE,
FINISH ASAP
AREA 4D - AREA OF EXISTING
PUBLIC HALLWAY NOT BEING USED
FOR NEW HALLWAY, FINISH ASAP
AREA 4F - NEW MAIN SOUTH
VESTIBULE
AREA 4G - CORRIDOR NIGHT AND
WEEKEND WORK
PHASE 4 – URGENT CARE RENOVATION AND VESTIBULE RENOVATIONS AND
ADDITION
ESTIMATED DURATION: 32 WEEKS
THE FOLLOWING DESCRIBESTHE SEQUENCE OF CONSTRUCTION FOR
URGENT CARE, VESTIBULE RENOVATION AND ADDITION, AND CORRIDOR
WORK.
PHASE 4 AREA A – MAIN AREA OF URGENT CARE RENOVATION
• DEMOLITION AND NEW WORK AS REQUIRED.
• THIS WORK IS THE CRITICAL PATH. WHEN THIS WORK IS COMPLETED,
PHASE 4 CAN BE COMPLETED.
PHASE 4 AREA B - NEW CANOPY AND VESTIBULE
• CONSTRUCTION OF NEW CANOPY ADDITION VESTIBULE FOR A COVERED
EXTERIOR ACCESS TO URGENT CARE.
• THIS WORK IS CRITICAL PATH. UPON COMPLETION OF AREA B, PHASE 4
AREAS D AND E MAY BEGIN.
PHASE 4 AREA C - EAST ENTRANCE AND ENTRANCE TO AUDIOLOGY
WAITING
• DEMOLITION AND NEW WORK MAY BEGIN IN PHASE 4, BUT WILL BE
REQUIRED TO BE COMPELTED PRIOR TO AREAS D AND E.
PHASE 4 AREA D – EXISTING PUBLIC HALLWAY AREA TO BECOME URGENT
CARE SUPPORT SPACE
• DEMOLITION AND NEW WORK MAY BEGIN UPON COMPLETION OF PHASE
4 AREAS B AND C, BUT WILL NOT NEED TO BE COMPLETED UNTIL PHASE
4 IS COMPLETED.
PHASE 4 AREA E – AREA OF NEW PUBLIC HALLWAY THROUGH URGENT
CARE
• DEMOLITION AND NEW WORK MAY BEGIN UPON COMPLETION OF PHASE 4
AREAS B AND C.
• THIS AREA WILL NEED TO BE COMPLETED PRIOR TO START OF PHASE 4
AREAS F AND G.
PHASE 4 AREA F – RENOVATION OF MAIN SOUTH VESTIBULE
• DEMOLITION AND NEW WORK AS INDICATED TO CREATE NEW VESTIBULE
AND MAIN ENTRY. ENTRANCE TO THE FACILITY SHALL BE THROUGH THE
NEW EAST VESTIBULE.
• WORK MAY NOT BEGIN UNTIL PHASE 4 AREAS D AND E ARE COMPLETED.
• WORK DOES NOT NEED TO BE COMPLETE UNTIL PHASE 4 IS COMPLETED.
PHASE 4 AREA G - RENOVATION OF PUBLIC CORRIDORS
• RENOVATION WORK AS INDICATED ON NIGHTS AND WEEKENDS AS
REQUIRED TO MAINTAIN ONGOING OPERATIONS OF FACILITY.
COORDINATE WITH VA.
CONSTRUCTION PHASING SEQUENCE - PHASE 4
PROVIDE
CONSTRUCTION
PHASE 4 FENCE
PROVIDE
CONSTRUCTION
PHASE 4 FENCE
CONSTRUCTION
ENTRANCE
PHASE 4
AREA A
PHASE 4
AREA B
PHASE 4
AREA C
PHASE 4
AREA D
PHASE 4
AREA E
PHASE 4
AREA F
PHASE 4
AREA G -
CORRIDORS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08 - 6231
A
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
FRED VOLLMERHAUSEN
CHIEF, ENGINEERING PROJECTS
100% DESIGN SUBMISSION 03/13/2020
95% DESIGN SUBMISSION 9/13/2019
65% DESIGN SUBMISSION 12/05/2018
35% DESIGN SUBMISSION 10/12/2018
100% BID DOCUMENTS 05/20/2020
C U s e rs
\t s a n d e rs \D o c u m e n ts \1
.1
.0
V
A B
C P
H A
R U
C A ts a n d e rs g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:0
A
M
GI103
CONSTRUCTION PHASE 3 & 4
PLAN / INFECTION CONTROL
PLAN
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
May 20, 2020 JDF JDJ
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
SCALE: 1" = 20'-0"GI103
1 PHASE 3 PLAN - 3A
SCALE: 12" = 1'-0"
PHASING TIMELINE LEGEND
SCALE: 1" = 20'-0"GI103
2 PHASE 4 PLAN
REF.REF.
REF.
REF.
UP
UP
PROCEDURE
0111A
STOR.
0110B
ISO EXAM
TRIAGE
RECEPTION
0103A
TRIAGE
VAULT
0103B
585 SF
A
EQUIP. STORAGE
MH EXAM
M.H. TLT
EXAM / FLEX M.H.
EXAM / FLEX M.H.
0120 EXAM
SOILED
STAFF TLT
STAFF TLT
CONSULT
772 SF
A
CONSULT
CONSULT
CONSULT
VAULT
CONFERENCE RM
UC BREAK RM AND
LOCKERS
HAC
RECEIVING
DISPENSING
WINDOWS
BREAK RM
STAFF TLT
OFFICE
GENERAL WAITING
PROCEDURE ROOM
GAS - FULL
2084 SF
10022
B
EXAM SOUND
BOOTH
SECURITY OFFICE
MECHANICAL
EXIST. IT CLOSET
OFFICE
OFFICE
TEMP PHARMACY
CONSULT
AGENT CASHIER
0051A
HAC
MECH
MECH
ON-CALL
0097A
GAS - EMPTY AND
IN-USE
ON-CALL TLT /
SHOWER
0097B
VEST. / BOX BREAK
DOWN
HVAC
021E
HOUSE KEEPING
OFFICE
OFFICE
FILLING
WORK STATIONS
PHARM. STORAGE
MH EXAM
AUDIOLOGY EXAM
SHOWER
0106A
ISO / PATIENT
TOILET
NURSE MANAGER
LINEN
AUDIOLOGY CLEAN
NF AND PENDING
STORAGE
NURSE
0135A
NURSE / DICTATION
EXAM
EXAM
PATIENT TLT
0134 CLEAN
EXAM
MED
PROCEDURE
0110A
MAIL-OUT
B
5,820 SF
CONSULT /
DISPENSING
B
3,540 SF
PHARMACY SUITE
URGENT CARE SUITE
FEC
FEC
FEC
FEC
FEC
FEC
FEC
FEC
FEC
STOR.
I.T.
OFFICE
TOILET
0078A
OFFICE
STAFF LOUNGE/
LOCKER ROOM
EXAM
CORRIDOR
C04
OFFICE
CORRIDOR
C08
VESTIBULE
C09
DEDUCTIVE ALTERNATE #1: THE EAST CANOPY
RENOVATION / ADDITION. THE WORK IS INDICATED TO
BE CONSTRUCTED IN PHASE 4, SEE SHEET GI103
DEDUCTIVE ALTERNATE #2: THE URGENT CARE
RENOVATION AND MAIN CORRIDOR FINISHES. THIS
SCOPE OF WORK IS DOCUMENTED IN PHASE 4. SEE
SHEET GI103
BID DEDUCTIVE ALTERNATES
BASE BID:
ALL WORK NOTED IN THESE CONSTRUCTION DOCUMENTS INCLUDING THE BUILD
OUT OF THE EAST SHELL SPACE FOR A TEMPORARY PHARMACY, THE
RENOVATION OF THE WEST SHELL SPACE AND EXISTING PHARMACY, THE
RENOVATION OF THE TEMPORARY PHARMACY AND ASSOCIATED AREAS TO BE
OFFICES, PATIENT FUNDS, AND AGENT CASHIER, THE RENOVATION / ADDITION OF
2 VESTIBULES, THE RENOVATION OF URGENT CARE, AND THE RENOVATION OF
THE MAIN CORRIDORS IN THE PHASING INDICATED IN THESE DOCUMENTS.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08 - 6231
A
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
FRED VOLLMERHAUSEN
CHIEF, ENGINEERING PROJECTS
100% DESIGN SUBMISSION 03/13/2020
95% DESIGN SUBMISSION 9/13/2019
65% DESIGN SUBMISSION 12/05/2018
35% DESIGN SUBMISSION 10/12/2018
100% BID DOCUMENTS 05/20/2020
C U s e rs
\t s a n d e rs \D o c u m e n ts \1
.1
.0
V
A B
C P
H A
R U
C A ts a n d e rs g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:2
A
M
GI104
BID ALTERNATES RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
May 20, 2020 JDF JDJ
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
SCALE: 3/32" = 1'-0"GI104
1 ALTERNATE FLOOR PLAN
N
HAZARDOUS MATERIAL REMOVAL GENERAL NOTES
REFER TO 'LIMITED ASBESTOS AND LEAD-BASED PAINT SURVEY' PROVIDED BY
TTL ASSOCIATES MARCH 2019. ALL NOTES THIS SHEET ARE BASED ON
INFORMATION PROVIDED BY THIS SURVEY. CONTRACTOR IS RESPONSIBLE TO
REMEDIATE ALL MATERIALS CONTAINING HAZARDOUS MATERIALS AS NOTED
IN THIS REPORT.
HAZMAT REMOVAL NOTES APPLY TO ENTIRE ROOMS. CONTRACTOR SHALL
IDENTIFY ALL MATERIALS DESCRIBED BY NOTE IN EACH ROOM AND REMOVE
ACCORDING TO SAFETY STANDARDS. REFERENCE SPECIFICATION 02 82 11.
ALL HAZARDOUS MATERIALS SHALL BE REMOVED IN COMPLIANCE WITH
APPLICABLE CODES AND LAWS.
THE CONTRACTOR IS RESPONSIBLE TO VERIFY THE HAZARD(S) AND LEVEL OF
PROTECTION REQUIRED FOR ALL EMPLOYEES OR SUBCONTRACTORS TO
COMPLETE THE CONSTRUCTION WORK.
REFER TO SPECIFICATIONS AND ATTACHMENTS FOR ADDITIONAL
INFORMATION.
BASED ON THE DATE OF THE EXISTING CONSTRUCTION IT IS ASSUMED LEAD
PAINT IS WITHIN THE PROJECT AREA. CONDUCT DEMOLITION OF THE EXISTING
SPACE WITH THE ASSUMPTION OF LEAD PAINT ON EXPOSED PLASTER WALLS
AND PAINTED SURFACES. REFER TO SPECIFICATION SECTION 02 83 33.13
LEAD-BASED PAINT REMOVAL, DISPOSAL AND FOR ADDITIONAL INFORMATION.
CONTRACTOR TO SUBMIT LEAD SURFACES STABILIZATION PLAN AND
PROCEDURES PRIOR TO COMMENCING WORK. SUBMITTAL SHALL BE IN
ACCORDANCE WITH SPECIFICATIONS.
A.
B.
C.
D.
E.
F.
G.
HAZARDOUS MATERIAL REMOVAL PLAN NOTES #
REMEDIATE APPROX. 400SF BLACK WALL MASTIC.
REMOVE DOOR ASSUMED TO CONTAIN ASBESTOS.
REMEDIATE APPROX. 2 LF AIRCELL PIPE INSULATION.
REMEDIATE APPROX. 1,800 SF FLOOR TILE AND MASTIC.
REMEDIATE APPROX. 36 LAYERED PIPE INSULATION JOINTS.
REMEDIATE APPROX. 40 SF OF FLOOR TILE AND ASSOCIATED MASTIC.
H
J
L
M
M.4
N
M.1
2.1 2.2 4.2 5.4 6.3 6.4 6.8 10.2 10.7 11.7 12.913.3
13.3
14.814.9
A
B
3.8 4.9 5.3 5.7 6.5 6.9 9.9 10.6 10.8 11.311.811.9 13.2
HH
FF
JJ
GG
KK
12 3 4 5 6 7 8 9 10 11 12 13 14 15
16 C1
C2
C
DD
EE
C3
7.7 9.3
C4
C5
TEMPORARY
PHARMACY
(PHASE 1) OPEN
OFFICE AND
AUDIOLOGY
(PHASE 3)
PHARMACY
(PHASE 2)
URGENT CARE
(PHASE 4)
SHADE
INDICATES
APPROXIMATE
AREA OUT OF
SCOPE
OFFICE
STOR.
MALE
FEMALE
OFFICE
MALE
FEMALE
WAITING
C03
PHARMACY
CONTROLLED
SUBSTANCE
0015A
HVAC
0015E
SHELL
0F-001
VEST.
0F-002
STAIR
S6
EXAM
OFFICE
OFFICE
STAFF LOUNGE/
LOCKER ROOM
OFFICE
OFFICE
OFFICE
STOR.
OFFICE
CUSTOMER SERVICE
OFFICE
OFFICE
I.T.
0076 OFFICE
TOILET
SECURITY OFFICE
HSK
ELEC.
SUB WAITING
ADMISSIONS
WAITING ROOM
STAIR
S5
CORRIDOR
C01
PATIENT
INFORMATION
RECEPTION
STOR.
TRIAGE
TRIAGE
TRIAGE
0113 OFFICE
EXAM
EXAM
EXAM
TOILET
0122A
EXAM
NURSE STATION
CORRIDOR
C011
CORRIDOR
C012
RECORDS
WOMEN'S
MEN'S
CORRIDOR
C09
WAITING
SECRETARY
EXAM SOUND
BOOTH
CHIEF
HVAC
0042E
EXAM SOUND
BOOTH
EXAM SOUND
BOOTH
OFFICE
TREATMENT
PROSTHETICS
CORRIDOR
C07
STOR.
STAIR
S2
HSK
RECOVERY
CORRIDOR
C06
SHELL
0G-001
HVAC
0021E
VENDING
OFFICE
OFFICE
HOUSEKEEPING
HVAC
0020E
ELEV.
E2
ELEV. MACH.
0018E
ELEV.
E1
HVAC
0017A
PATIENT FUNDS
AGENT CASHIER
STOR.
0016A
STAIR
S1
PIPE
0014E
ELEV.
E3
TOILET
0092A
DRESSING ROOM
SOILED UTILITY
TREATMENT
TOILET
Room
EQUIP.
STAFF LOUNGE
IMMEDIATE CARE
TOILET
0103A HVAC
0050A
IT
0050E
OFFICE
CORRIDOR
C08
STAIR
S3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08 - 6231
A
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
FRED VOLLMERHAUSEN
CHIEF, ENGINEERING PROJECTS
100% DESIGN SUBMISSION 03/13/2020
95% DESIGN SUBMISSION 9/13/2019
65% DESIGN SUBMISSION 12/05/2018
35% DESIGN SUBMISSION 10/12/2018
100% BID DOCUMENTS 05/20/2020
C U s e rs
\t s a n d e rs \D o c u m e n ts \1
.1
.0
V
A B
C P
H A
R U
C A ts a n d e rs g u id o n d e s ig n .c o m
.r v t
/2
/2
:4
:2
A
M
HA101
HAZARDOUS MATERIALS
REMOVAL PLAN
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
May 20, 2020 JDF JDJ
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
SCALE: 3/32" = 1'-0"HA101
1 HAZMAT DEMO PLAN
SCALE: 1" = 80'-0"
KEY PLAN - GROUND FLOOR
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
P
V
A
V
I S
N
M
I
A
E
I D
I Q
P h a r m a c y
U r g e n t
C a r e
R e n o
D r a w i n g s C i v i l G
E N
E R
A L
N
O T
E S d w g
P
M
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020
PART. SPRINKLERED
Revisions: Date: DSMCMB
100% BID DOCUMENTS
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN
46202 317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI
48126 313.441.3000 | WWW.GHAFARI.COM
100% BID DOCUMENTS
S
T
A
T
E
O
F M
I
C
H
I
G
A
N
L I C
E
N
S
D
P
R
O
F
E
SS
I O
N
A
L
G
I
N
E
E R
GENERAL CIVIL NOTES
CI001
0 2010
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
P
V
A
V
I S
N
M
I
A
E
I D
I Q
P h a r m a c y
U r g e n t
C a r e
R e n o
D r a w i n g s C i v i l D
E M
O L I T
I O
N d w g
P
M
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020
PART. SPRINKLERED
Revisions: Date: DSMCMB
100% BID DOCUMENTS
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN
46202 317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI
48126 313.441.3000 | WWW.GHAFARI.COM
100% BID DOCUMENTS
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
DEMOLITION PLAN
CD101
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
P
V
A
V
I S
N
M
I
A
E
I D
I Q
P h a r m a c y
U r g e n t
C a r e
R e n o
D r a w i n g s C i v i l S
I T
E
P
L A
N d w g
P
M
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020
PART. SPRINKLERED
Revisions: Date: DSMCMB
100% BID DOCUMENTS
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN
46202 317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI
48126 313.441.3000 | WWW.GHAFARI.COM
100% BID DOCUMENTS
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
SITE LAYOUT PLAN
CS101
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
P
V
A
V
I S
N
M
I
A
E
I D
I Q
P h a r m a c y
U r g e n t
C a r e
R e n o
D r a w i n g s C i v i l D
E T
A I L S d w g
P
M
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020
PART. SPRINKLERED
Revisions: Date: DSMCMB
100% BID DOCUMENTS
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN
46202 317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI
48126 313.441.3000 | WWW.GHAFARI.COM
100% BID DOCUMENTS
SITE DETAILS
CS501
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
P
V
A
V
I S
N
M
I
A
E
I D
I Q
P h a r m a c y
U r g e n t
C a r e
R e n o
D r a w i n g s C i v i l G
R A
D I N
G
P
L A
N d w g
P
M
RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020
PART. SPRINKLERED
Revisions: Date: DSMCMB
100% BID DOCUMENTS
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN
46202 317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI
48126 313.441.3000 | WWW.GHAFARI.COM
100% BID DOCUMENTS
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
GRADING PLAN
CG101
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC. | 1221 N PENNSYLVANIA SUITE 200 | INDIANAPOLIS, IN 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
GHAFARI ASSOCIATES LLC. | 17101 MICHIGAN AVENUE | DEARBORN, MI 48126
313.441.3000 | WWW.GHAFARI.COM
C U s e rs
\a k e n n e d y \D o c u m e n ts \1
.1
.0
V A
U C
S v a k e n n e d y g u id o n d e s ig n .c o m
.r v t
/2
/2
:3
:3
A
M
SI001
GENERAL STRUCTURAL NOTES RENOVATE OUTPATIENT
PHARMACY & URGENT CARE
5500 Armstrong Road, Battle Creek
515-18-109
MAY 20, 2020 MAV ADK
100% BID DOCUMENTS
PART. SPRINKLERED
100% BID DOCUMENTS
GENERAL
THE STRUCTURE HAS BEEN DESIGNED FOR THE IN-SERVICE LOADS ONLY. THE METHODS, MEANS, PROCEDURES, AND SEQUENCES OF CONSTRUCTION ARE THE RESPONSIBILITY OF THE CONTRACTOR. THE STRUCTURE IS DESIGNED TO BE SELF-SUPPORTING AND STABLE AFTER THE BUILDING IS COMPLETE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO DETERMINE ERECTION PROCEDURES AND SEQUENCE TO INSURE SAFETY OF THE BUILDING AND ITS COMPONENTS DURING ERECTION. THIS INCLUDES THE ADDITION OF
NECESSARY SHORING, SHEETING, TEMPORARY BRACING, GUYS, TIEDOWNS, ETC.
THE STRUCTURAL DRAWINGS SHALL BE USED IN CONJUNCTION WITH CIVIL, ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING
DRAWINGS AND SPECIFICATIONS.
THE GENERAL NOTES ON THE DRAWINGS ARE TO BE USED IN CONJUNCTION WITH THE FULL WRITTEN MATERIAL SPECIFICATIONS (IF ANY) FOR THE PROJECT. IF A DISCREPANCY OCCURS BETWEEN THE NOTES AND THE FULL SPECIFICATIONS, THE MORE STRINGENT
REQUIREMENT SHALL APPLY.
NO PENETRATIONS THROUGH STRUCTURAL ELEMENTS, OTHER THAN THOSE SHOWN ON THE DRAWINGS, SHALL BE MADE WITHOUT
THE APPROVAL OF THE COR.
CONTRACTOR TO COORDINATE ALL EQUIPMENT, ROOF DRAINS, CHASES, AND OTHER ITEMS CONNECTED TO THE STRUCTURE BEFORE
FABRICATION BEGINS.
CONCRETE MIX DESIGN SUBMITTAL
THE CONTRACTOR SHALL SUBMIT FOR THE REVIEW OF THE COR A MIX DESIGN FOR EACH PROPOSED CLASS OF CONCRETE. EACH MIX DESIGN SHALL BE IDENTIFIED BY A MIX NUMBER OR OTHER UNIQUE IDENTIFICATION. THE CONTRACTOR SHALL NOT VARY FROM THE MIX DESIGNS NOR USE ANY CONCRETEOTHER THAN THE APPROVED MIX DESIGNS WITHOUT THE APPROVAL OF THE COR. MIX DESIGN
SUBMITTALS SHALL INCLUDE THE FOLLOWING INFORMATION:
1. MIX DESIGN NUMBER OR UNIQUE IDENTIFICATION AND INTENDED LOCATION OF PLACEMENT.
2. CEMENT TYPE, PROPORTION AND NAME OF MANUFACTURER.
3. FLY ASH PROPORTION (WHEN USED), LABORATORY ANALYSIS CERTIFICATION, AND NAME AND LOCATION OF SUPPLIER.
4. COURSE AGGREGATE PROPORTION, GRADATION REPORT, NAME AND LOCATION OF SUPPLIER.
5. FINE AGGREGATE PROPORTION, GRADATION REPORT, NAME AND LOCATION OF SUPPLIER.
6. MIXING WATER PROPORTION AND SOURCE.
7. ADMIXTURE DOSAGES, PRODUCT NAME(S) AND MANUFACTURER NAME(S).
8. FIBER REINFORCEMENT DOSAGE (WHEN USED), PRODUCT NAME AND MANUFACTURER NAME.
9. DESIGN 28-DAY COMPRESSIVE STRENGTH (F'C).
10. DESIGN SLUMP RANGE.
11. DESIGN AIR-ENTRAINMENT (FOR CONCRETE REQUIRING ENTRAINED AIR).
12. STATISTICAL ANALYSIS OF LABORATORY STRENGTH TEST DATA IN ACCORDANCE WITH "STANDARD DEVIATION"
DETERMINATION OUTLINED IN ACI 318.
SHOP DRAWING SUBMITTALS
THE CONTRACTOR SHALL PREPARE DETAILED SHOP DRAWINGS TO ENABLE HIM TO FABRICATE, ERECT AND CONSTRUCT ALL PARTS OF THE WORK IN ACCORDANCE WITH THE DRAWINGS AND SPECIFICATIONS. THESE SHOP DRAWINGS WILL BE REVIEWED FOR GENERAL COMPLIANCE WITH THE DESIGN INTENT ONLY. THE CONTRACTOR IS RESPONSIBLE FOR ALL DIMENSIONS, ACCURACY AND FIT OF WORK.
ALL SHOP DRAWINGS SHALL BE REVIEWED BY THE CONTRACTOR PRIOR TO SUBMITTAL TO THE COR. DRAWINGS SUBMITTED WITHOUT
CONTRACTOR'S REVIEW WILL BE RETURNED UNCHECKED.
SUBMIT ELECTRONIC VERSIONS OF SHOP DRAWINGS. SUBMIT SHOP DRAWINGS IN PDF FORMAT.
SUBMIT SHOP DRAWINGS FOR EACH OF THE FOLLOWING ITEMS:
1. CONCRETE REINFORCEMENT
2. CONCRETE MASONRY REINFORCEMENT
3. STRUCTURAL STEEL (INCLUDING DESIGN CALCULATIONS SEALED BY A PROFESSIONAL ENGINEER REGISTERED IN THE STATE
WHERE THE PROJECT IS CONSTRUCTED FOR ALL CONNECTIONS NOT SPECIFICALLY DETAILED ON THE DRAWINGS)
4. METAL DECKING
PRODUCT DATA SUBMITTALS
THE CONTRACTOR SHALL SUBMIT FOR APPROVAL PRODUCT DATA FOR THE SPECIFIC ITEMS LISTED BELOW. CONTRACTOR SHALL NOT
USE PRODUCTS OTHER THAN THOSE SUBMITTED WITHOUT THE APPROVAL OF THE COR.
MANUFACTURER'S TRADE NAMES AND NUMBERS USED HEREIN ARE ONLY TO IDENTIFY COLORS, FINISHES, TEXTURES, AND PATTERNS AS A BASIS OF DESIGN. PRODUCTS OF AUTHORIZED EQUAL MANUFACTURER'S EQUIVALENT TO COLORS, FINISHES, TEXTURES, AND PATTERNS OF MANUFACTURERS LISTED THAT MEET REQUIREMENTS OF TECHNICAL SPECIFICATIONS IN EVERY RESPECT MAY BE ACCEPTABLE WITH SUBMITTAL OF A COMPLETED SUBSTITUTION REQUEST CONTAINING ALL PRODUCT DATA, TESTING AND ACTUAL
SAMPLES, AND UPON…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .