36C25020B0017-008.pdf
PDF Posted
- Solicitation number
- 36C25020B0017
About this file
This presolicitation notice provides details for an upcoming solicitation for a construction project to demolish multiple buildings at the VA Northern Indiana Health Care System in Marion, Indiana. The solicitation will be issued on or about January 31, 2020 via SAM.gov for the demolition and removal of nine buildings totaling between $500,000 to $1,000,000. The work includes asbestos/lead paint abatement, utility disconnect, removal of structures and foundations, backfilling, grading, and seeding. All items removed must be disposed of by the contractor. The project will be set aside 100% for SDVOSBs with a NAICS code of 236220. Interested parties should contact Jeff Hairston, Contract Specialist at the NCO 10 Contracting Office, for any questions via email or phone. A pre-solicitation site visit will be scheduled prior to the closing date, with details posted in the solicitation.
36C25020B0017 610-19-201 Combined Specifications.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25020B0017-0005000.docx | DOCX document | |
| 36C25020B0017-0004001.docx | DOCX document | |
| 36C25020B0017-0004000.docx | DOCX document | |
| 36C25020B0017-0003000.docx | DOCX document | |
| 36C25020B0017-0002002.xlsx | XLSX spreadsheet | |
| 36C25020B0017-0002001.pdf | ||
| 36C25020B0017-0002004.docx | DOCX document | |
| 36C25020B0017-0002003.pdf | ||
| 36C25020B0017-0002000.docx | DOCX document | |
| 36C25020B0017-0001000.docx | DOCX document | |
| 36C25020B0017-0001001.pdf | ||
| 36C25020B0017-012.txt | TXT text file | |
| 36C25020B0017-009.pdf | ||
| 36C25020B0017-010.doc | DOC document | |
| 36C25020B0017-007.docx | DOCX document | |
| 36C25020B0017-011.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Architecture | Engineering | Design Build
200 Envoy Circle, Suite 201 Louisville KY 40299 www.paradigmusa.com
SPECIFICATIONS
Bid Documents
VA Northern Indiana Healthcare System Demolish Buildings Project #610-19-201
May 15, 2018 http://www.paradigmusa.com/
Marion, IN
Demolish Buildings
610-19-201
11-01-17
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 29 Testing Laboratory Services 08-17
01 57 19 Temporary Environmental Controls 01-11
01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16
02 41 00 Demolition 08-17
02 82 13.41 Asbestos Abatement for Total Demolition Project 04-15
02 83 33.13 Lead-Based Paint Removal and Disposal 08-16
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 41 Underground Electrical Construction 01-17
26 56 00 Exterior Lighting 05-14
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
33 40 00 Storm Sewer Utilities 10-11
33 51 00 Natural-Gas Distribution 10-11
Demolish Buildings 610-19-201
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI001 COVER SHEET
CIVIL
C-001 CIVIL ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
C-002 STORMWATER POLLUTION PREVENTION PLAN
C-003 TOPOGRAPHICAL SURVEY PLAN (FOR REFERENCE ONLY)
CD401 ENLARGED SITE PLANS - EXISTING CONDITIONS, DEMOLITION, AND EROSION
CONTROL
CD402 STORMWATER POLLUTION PREVENTION PLAN
CD501 DEMOLITION AND EROSION CONTROL DETAILS AND NOTES
CD901 EXISTING SITE PHOTOS
CS100 CONTRACTOR ACCESS PLAN (FOR REFERENCE ONLY)
CS401 ENLARGED SITE PLANS - NEW WORK
CS501 SITE DETAILS
CG401 SITE GRADING PLANS – NEW WORK
CU401 ENLARGED STORM UTILITY PLANS - EXISTING CONDITIONS, DEMOLITION,
AND NEW WORK
CU402 ENLARGED SANITARY UTILITY PLANS - EXISTING CONDITIONS DEMOLITION,
AND NEW WORK
CU403 ENLARGED WATER UTILITY PLANS - EXISTING CONDITIONS, DEMOLITION,
AND NEW WORK
CU404 ENLARGED GAS UTILITY PLANS - EXISTING CONDITIONS, DEMOLITION, AND
NEW WORK
CU405 ENLARGED ELECTRICAL UTILITY PLANS - EXISTING CONDITIONS,
DEMOLITION, AND NEW WORK
LP401 ENLARGED LANDSCAPE PLAN, DETAILS, AND NOTES - EXISTING CONDITIONS
AND NEW WORK
- - - END - - -
Demolish Buildings
610-19-201
10-01-17 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 DISPOSAL AND RETENTION
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.9 RESTORATION
1.10 PHYSICAL DATA
1.11 PROFESSIONAL SURVEYING SERVICES
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 USE OF ROADWAYS
1.15 TEMPORARY TOILETS
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
1.17 TESTS
1.18 PHOTOGRAPHIC DOCUMENTATION
1.19 HISTORIC PRESERVATION
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for DEMOLISH BUILDINGS as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR.
C. Offices of Paradigm Engineers and Constructors, PLLC, as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the
Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by the COR or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, DEMOLISH BUILDINGS: Work includes general demolition, construction, alterations, roads, walks, grading, drainage, utility line modifications, necessary removal of existing structures and construction and certain other items as indicated in the drawings and specifications.
B. ITEM II: Cost adjustment for Item I LESS lead abatement and LESS total demolition of structure above ground from building B36 (structure above ground to be removed by others).
ITEM IIA: ADD work for preparation/placement of structure (from ground floor framing and above) on steel transport frames and relocating to
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 2 vacant area on VA property off limits of work (final location to be determined by COR) for transport from site by others.
C. ITEM III: Cost adjustment for Item I LESS lead abatement and LESS total demolition of structure above ground from building B38 (structure above ground to be removed by others).
ITEM IIIA: ADD work for preparation/placement of structure (from ground floor framing and above) on steel transport frames and relocating to vacant area on VA property off limits of work (final location to be determined by COR) for transport from site by others.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without written permission of the COR.
3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
D. Document Control:
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 3
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the COR upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of COR.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify COR when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies unless prior approval of designated staging of vehicles is provided in writing by
COR.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only.
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 4
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the
Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings or as determined by the COR when not shown on the drawings.
E. Workmen are subject to rules of Medical Center and Cemetery applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center and Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, Demolish Buildings
610-19-201
10-01-17
01 00 00 - 5 during construction, jointly by patients or medical personnel, and
Contractor's personnel, except as permitted by the COR.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center and Cemetery areas required to remain in operation.
3. Where access by Medical Center or Cemetery personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 6 site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to the COR and Contractor, as follows:
J. Buildings 35,36,37,38,94,95,96,149,118 and 75 will be vacated by
Government beginning immediately after date of receipt of Notice to
Proceed and turned over to Contractor.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Center or Cemetery operations will not be hindered. Contractor shall permit access to Department of Veterans
Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center or Cemetery operations will continue during the construction period.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance of landscaping and vegetation within the project scope area.
M. Utilities Services: Maintain existing utility services for Medical
Center and Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 7 where shown; or, in absence of such indication, where directed by the
COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the COR’s prior knowledge and written approval.
Refer to specification divisions 26, 27 and 28.
2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 7 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical Center or Cemetery.
Interruption time approved may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of the COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 8
O. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new or removal of existing utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
Q. Coordination of Construction with Cemetery Operations: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period:
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation and access routes through or adjacent to existing burial plots before these dates.
2. The Contractor is also required to halt noise producing equipment operations (and other noise producing work as discussed and defined at the construction Kick-off meeting) during Cemetery events/services. The COR will provide a 2-week look ahead to the
Contractor throughout the contract period with a weekly update to the Cemetery event schedule. Short-notice next-day events may occur periodically at which the COR will provide such notice of events to the Contractor no later than 2:30 pm the day prior to the short notice event occurrence.
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 9
3. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center or Cemetery.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors where discovered within the project site. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental
Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance Control Act (TSCA)
Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the
"originator" copy of the Uniform Hazardous Waste Manifest (EPA Form
8700-22), along with the Uniform Hazardous Waste Manifest
Continuation Sheet (EPA Form 8700-22A) shall be returned to the COR who will annotate the contract file and transmit the Manifest to the
Medical Center's or Cemetery's Chief.
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 10
a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261........Identification and Listing of Hazardous Waste
40 CFR 262........Standards Applicable to Generators of Hazardous
Waste
40 CFR 263........Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761........PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172........Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173........Shippers - General Requirements for Shipments and Packaging
49 CRR 173........Subpart A General
49 CFR 173........Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation
TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so (AS
MARKED DIRECTLY ON SITE), and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the
COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, Demolish Buildings
610-19-201
10-01-17
01 00 00 - 11 resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the
Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements.
Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the
Contractor's method of operations and operations planning and the
Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
- Designating areas for equipment maintenance and repair;
- Providing waste receptacles at convenient locations and provide regular collection of wastes;
- Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
- Providing adequately maintained sanitary facilities.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 12 ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.10 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. A copy of the most recent asbestos and lead paint survey report will be made available for inspection by bidders upon request to the COR at the
VA Medical Center, and shall be considered part of the contract documents.
C. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and reports; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 13
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.11 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for the project are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 14
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work is placed.
D. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to the COR.
E. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center and Cemetery property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 15 operations. These roads may be used by all who have business thereon within zone of building operations.
1.15 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by the COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
B. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by the Medical Center or Cemetery. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Contractor shall furnish all necessary temporary utility (electric, water, fuel) service required to perform the work according to the contract. The Government may make reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as agreed upon between the COR and Contractor. The amount to be paid by the Contractor for chargeable utility services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of utilities used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center or Cemetery a monthly record of the Contractor's usage of utilities as hereinafter specified.
1.17 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, Demolish Buildings
610-19-201
10-01-17
01 00 00 - 16 equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the COR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.18 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, storage and remote access to the documentation, as per these specifications.
B. Photographic documentation elements:
1. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing
200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
Demolish Buildings
610-19-201
10-01-17
01 00 00 - 17
2. Before construction, the site shall be documented. Overlapping photographic techniques shall be used to insure maximum coverage.
3. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days (“Progressions”). Exterior Progressions shall track
360 degrees around the site.
4. Miscellaneous events that occur during any Contractor site visit, or events captured by the Department of Veterans Affairs independently, shall be dated, labeled and inserted into a Section in the navigation structure entitled “Slideshows,” allowing this information to be stored in the same “place” as the formal scope.
5. Weekly Site Progressions - Photographic documentation capturing the project at different stages of construction. These progressions shall capture underground utilities, excavation, grading, backfill, landscaping and road construction throughout the duration of the project.
1.19 HISTORIC PRESERVATION
Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the COR verbally, and then with a written follow up.
- - - E N D - - -
Demolish Buildings
610-19-201
02-01-15
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposal to the COR, within
10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The COR has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal. In case of
Demolish Buildings
610-19-201
02-01-15
01 32 16.15 - 2 disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the COR; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the
Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the COR, to correct errors which affect the payment and schedule for the project.
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the COR's review; an electronic file in the previously approved CPM schedule program. The submittal shall also include a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.
Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or
Demolish Buildings
610-19-201
02-01-15
01 32 16.15 - 3 start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the COR. The contractor shall make a separate written detailed request to the COR identifying these date constraints and secure the COR’s written approval before incorporating them into the network diagram. The COR’s separate approval of the
Project Schedule shall not excuse the contractor of this requirement.
Logic events (non-work) will be permitted where necessary to reflect proper logic among work events, but must have zero duration. The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents. These changes/delays shall be entered at the first update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF
CONTRACT COMPLETION.
B. Within 30 calendar days after receipt of the complete project interim
Project Schedule and the complete final Project Schedule, the COR or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three blue line copies of the revised Project Schedule, three copies of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the COR. The revised submission will be reviewed by the COR and, if found to be as previously agreed upon, will be approved.
C. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
Demolish Buildings
610-19-201
02-01-15
01 32 16.15 - 4
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves will be used by the COR to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83 (PAYMENT
UNDER FIXED-PRICE CONSTRUCTION CONTRACTS).
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR) and VAAR 852.236 – 72 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.7 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
a. Contractor's time required for submittal…