36C25018B0581 0002 INFECTION CONTROL RISK ASSESSMENT.pdf

View the file

Other files

File Type Posted
36C25018C0217-000.docx DOCX document
36C25018B0581-006.pdf PDF
36C25018B0581-005.docx DOCX document
36C25018B0581-0002000.docx DOCX document
36C25018B0581-0001000.docx DOCX document
36C25018B0581-003.pdf PDF
36C25018B0581-004.pdf PDF
36C25018B0581-002.pdf PDF
36C25018B0581-001.docx DOCX document
36C25018B0581-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Construction Risk Assessment – Page 1 of 10

Combined Pre-Construction and Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

PART 1: INFECTION CONTROL RISK ASSESSMENT

Type Construction Project Activity

Type A☐

Inspection and Non-Invasive Activities.

Include, but are not limited to:

☐ Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet ☐ Painting (sanding limited to <10% of area).

☐ Wall covering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

Type B ☐

Small scale, short duration activities that create minimal dust.

Include, but are not limited to:

☐ Installation of telephone and computer cabling.

☐ Access to chase spaces using doors or hatches (not cutting).

☐ Sanding of walls for painting or wall covering (minor repairs – not sanding for drywall finishing)

Type C ☐

Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies.

Includes, but is not limited to:

☐ Sanding (>50% of surface area – drywall finishing).

☐ Cutting of walls or ceilings.

☐ Removal of floor coverings, ceiling tiles, and casework. (>50% of surface area) ☐ New wall construction.

☐ Minor duct work or electrical work above ceilings.

☐ Major cabling activities.

☐ Any activity that cannot be completed within a single work shift.

Type D ☐

Major demolition and construction projects.

Includes, but is not limited to:

☐ Activities that require consecutive work shifts.

☐ Requires heavy demolition or removal of a complete cabling system.

☐ New construction.

Pre-Construction Risk Assessment – Page 2 of 10

☐ Low Risk ☐ Medium Risk ☐ High Risk ☐ Highest Risk

☐ Office areas

☐ Out Doors

☐ Electrical or Mechanical Rooms

☐ Social Work

☐ Retail Store

☐ Stairwells

☐ Conference Rooms

☐ Hallways

☐ EMS Areas

☐ Physical and Occupational Therapy

☐ Outpatient Areas

☐ Waiting Rooms

☐ Sleep Lab

☐ Mental Health (outpatient only)

☐ Prosthetics / Orthotics

☐ Domiciliary

☐ Primary Care Clinics

☐ CBOCs

☐ Urgent Care

☐ Kitchen or Food Preparation / Dining / Canteen

☐ Echocardiography

☐ Radiology/MRI/CT

☐ Respiratory Therapy

☐ Nuclear Medicine

☐ Senior Mental Health (In Patient or Senior)

☐ Community Living Center (CLC)

☐ Clean Supply

☐ Cardiac Cath, EP Lab or Cardiology

☐ Sterile Processing Service (SPS)

☐ All inpatient medical or surgical units

☐ Care Units: PACU, MICU, SICU, TCU

☐ Spinal Cord Injury (SCI) ☐ Negative pressure isolation rooms

☐ Outpatient chemotherapy or Oncology areas

☐ Operating Rooms/Surgery Area

☐ Endoscopy

☐ Dialysis

☐ Bronchoscopy

☐ Pharmacy

☐ Clinical Laboratories ☐ Treatment /Procedure Rooms

IC Matrix Class of Precautions: Construction Project by Patient Risk Group and Construction Project Type

Patient Risk Group / Activity Type ☐ TYPE A ☐ TYPE B ☐ TYPE C ☐ TYPE D

☐ LOW Risk Group ☐ I (green) ☐ II (yellow) ☐ II (yellow) ☐ III/IV (pink)

☐ MEDIUM Risk Group ☐ I (green) ☐ II (yellow) ☐ III (pink) ☐ IV (red)

☐ HIGH Risk Group ☐ I (green) ☐ II (yellow) ☐ III/IV (pink) ☐ IV (red)

☐ HIGHEST Risk Group ☐ II (yellow) ☐ III/IV (pink) ☐ III/IV (pink) ☐ IV (red) Note: Infection Control approval is required for ALL construction or renovation activities.

Step 3: __☐Class I ☐Class II ☐Class III ☐Class IV

Notes

Class I for all work performed in Rm 1A350 and installing mixing valves.

Class II for chlorine monitoring and port work; majority will be performed in hallways or offices. Some ports will be installed above the waiting room areas for Eye Clinic and Primary Care North adjacent to the A-Side main utility chase.

Pre-Construction Risk Assessment – Page 3 of 10

+ Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES prior to beginning work.

☐Confirm construction documents indicate requirements above

CL

AS

S During construction project, the following must be performed daily: Upon completion of the phased work in any room, the following must be performed per room:

CL

AS

S I

1. Execute work by methods to minimize raising dust from construction operations.

2. For visual inspection only, dampen ceiling tile with water spray before removing. Replace a ceiling tile immediately after inspection; do not leave unattended.

Clean up ceiling tile and flooring surfaces below with HEPA filtered vacuum or damp mop.

CL

AS

S

II

As above and:

1. Provide active means to prevent dust from dispersing. Dust left on the floors, clothing and/or body is not allowed in order to prevent spreading and tracking. “Active means” are:

a. Vacuum attachments on tools with HEPA vacuum when generating dust, or

b. HEPA vacuuming immediately as the dust is generated.

c. Remove or isolate HVAC system in areas where work is being performed.

d. Water mist work surfaces to control dust while cutting.

e. Seal unused doors with duct tape.

f. Block off and seal all HVAC air vents.

g. Place +tacky mat at inside of entrance of work area and change frequently or when ineffective.

h. Wet mop and/or vacuum with +HEPA-filtered vacuum the work area before leaving the site. Brooming is not sufficient.

2. Whenever transporting outside of construction site, wipe materials, equipment and work surfaces with EPA registered, unscented +disinfectant, which has manufacturer’s labeling as a bactericide, tuberculocide, virucide, and fungicide.

3. There shall be no standing, uncovered water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.

As above and:

1. Wet mop and/or vacuum with

HEPA-filtered vacuum before leaving work area and wipe work surfaces with disinfectant.

2. Contain construction waste before transport in tightly covered containers. Tape may be used to ensure a tight cover.

3. Remove isolation of HVAC system in areas when work and area cleanup has been completed.

CL

AS

S

III

As above and:

1. Complete all critical barriers, i.e., +sheetrock, +plywood, +plastic, to seal area from non-work area or implement +control cube method before construction begins.

2. Maintain Negative / Neutral Pressure Ventilation +(NPV) at 0.01” / 0.00” Water Column (WC) within the work site utilizing NPV machine.

3. NPV monitoring devices should be visible from outside the worksite and readings shall be documented daily or more often as needed. Keep +trackin monitoring device and +tracking log at outside of entrance at the site.

4. Contain construction waste before transport in tightly covered containers. Tape covering, unless using form-fitting solid lid.

5. Seal holes, pipes, conduits, and punctures etc. appropriately during construction.

1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

2. Do not remove barriers from work area until completed project is thoroughly and inspected by COR, Safety and Infection Control.

CL

AS

S

IV

1. +Seal holes, pipes, conduits, and punctures.

2. Construct anteroom and require all personnel to pass through this room to be vacuumed using a HEPA vacuum cleaner before leaving work site OR they can wear cloth or paper coveralls that are removed each time they leave the work site.

3. All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.

As above

Pre-Construction Risk Assessment – Page 4 of 10

Identify the areas surrounding the project area, assessing potential impact.

Unit Below Unit Above East West North South enter area description enter area description enter area description enter area description enter area description enter area description

Risk Group Risk Group Risk Group Risk Group Risk Group Risk Group

Identify the impact and any precautions necessary to minimize disruptions to surrounding areas:

Identify specific site of activity, e.g., patient rooms, medication room, etc:

Identify containment measures using prior assessment. What types of barriers such as solid wall barriers?

Will barrier entry ways require doors or zipper flaps? Will HEPA filtration be required?

Note: Renovation/construction area shall be isolated from the occupied areas during construction and shall be negative with respect to surrounding areas.

Consider potential risk of water damage. Is there a risk due to compromising structural integrity (e.g., wall, ceiling, roof)?

☐ Yes ☐ No

Work hours: Can or will the work be done during non-patient-care hours?

Do plans allow for adequate number of isolation/negative airflow rooms due to those taken out of service during construction?

☐ Yes ☐ No

Do the plans allow for the required number and type of hand washing sinks due to those taken out of service during construction?

☐ Yes ☐ No

Does the infection control staff agree with the minimum number of sinks due to those taken out of service during construction for this project? (Verify against the American Institute of Architects Guidelines for types and area.)

☐ Yes

N/A

N/A

Pre-Construction Risk Assessment – Page 5 of 10

☐ No

Does the infection control staff agree with the plans relative to clean and soiled utility rooms in lieu of those taken under construction?

☐ Yes ☐ No

Discuss the following containment issues with the construction safety committee: barrier details, traffic flow, housekeeping, and debris removal (how and when).

☐ Complete

Tuberculosis Risk Assessment. A risk assessment must be conducted for the transmission of TB to the contracted construction workers based upon the construction site location, patient population, hospital layout, and the defined risk as outlined in the “CDC Guidelines for preventing the transmission of Mycobacterium Tuberculosis in Health-Care Setting, 2005.”

☐ Construction project is high risk for TB transmission. Detail safety measures. Requires contractor pre-testing.

☐ Construction project is low risk for TB transmission. No pre-contract testing required.

Who is responsible for daily cleaning inside work area?

Is terminal cleaning required at the end of each work day?

☐ Yes ☐ No

If yes, who is responsible for coordinating the terminal cleaning?

Are there any special needs required for terminal cleaning at the end of the project?

☐ Yes ☐ No

If yes, list special needs.

Confirm construction drawings show:

☐ Locations and details of construction barriers

☐ Any necessary modifications to the HVAC system needed to meet NPV requirements

☐ General location of waste dumpster(s) or bins

Pre-Construction Risk Assessment – Page 6 of 10

PART 2: PRE-CONSTRUCTION RISK ASSESSMENT

Utility Interruptions and/or impact:

During the course of the project are any of the following likely to be interrupted or impacted in any area of the facility?

Yes No ☐ ☐ Water Supply (Including shutting off any valves) ☐ ☐ Sewer Service ☐ ☐ Roof/Storm Drainage ☐ ☐ Normal Power ☐ ☐ Emergency Power ☐ ☐ Ventilation Systems ☐ ☐ Oxygen ☐ ☐ Medical Air ☐ ☐ Medical Vacuum ☐ ☐ Other Medical Gases:

☐ ☐ HVAC

☐ ☐ Sprinkler System

For any systems where interruptions are foreseen, describe the steps to be taken to mitigate the impacts:

Describe preventative measures that will be taken to insure that an unplanned interruption will not occur:

To be completed if the water supply will be interrupted or impacted in any way:

Domestic Water Outage YES NO

Will valves be shut off longer than 48 hours?

Required Actions if YES: Flush plumbing lines from closed valve to all outlets for a minimum of 10 minutes at highest temperature.

Minor Domestic Water System Modifications and Repairs YES NO Will the project modify any valves in the existing plumbing system?

Will the project modify existing plumbing lines less than or equal to 18 feet?

Required Actions if YES to either or both: New pipe, fittings, and valves required for connection may be spray-disinfected or swabbed with a minimum of 1-5 percent solution of chlorine just prior to being installed. Flush plumbing lines from closed valve to all outlets for a minimum of 10 minutes at highest temperature. After the appropriate procedures have been completed, the existing main may be returned to service prior to the completion of bacteriological testing in order to minimize disruptions to the facility.

Bacteriological testing is required to be completed per AWWA standards.

Major Domestic Water System Modifications and Installations YES NO Will the project modify install any new plumbing lines?

Will the project modify existing plumbing lines greater than 18 feet?

Required Actions if YES to either or both: Follow all AWWA requirements.

☐ Confirm construction documents show any additional work related to water safety, including but not limited to: AWWA requirements, responsibility of contractor for flushing and disinfecting, etc.

Pre-Construction Risk Assessment – Page 7 of 10

Noise and Vibration Assessment:

List any activities that will generate noise and/or vibration likely to be disruptive.

Activity:

Time & Duration:

Mitigation Strategies:

Activity:

Time & Duration:

Mitigation Strategies:

Activity:

Time & Duration:

Mitigation Strategies:

Safety Hazards:

List any hazardous materials to be used or stored within the project area:

Is the work likely to generate any noxious or unusual odors?

☐ Yes ☐ No If yes, what steps will be taken to minimize impact:

Are there any known or suspected contaminants?

☐ Asbestos ☐ Lead ☐ Mold If yes, list steps to be taken to minimize impact:

Does the planned work include any of the following?

☐ Confined space entry ☐ Excavation requiring protection ☐ Lock Out Tag Out ☐ Cranes or hoisting equipment ☐ Scaffolding ☐ Interruption of normal pedestrian or vehicular traffic ☐ Work requiring fall protection ☐ Live electrical work List steps to reduce/mitigate risk of any items checked:

Will there be hot work done on this project?

☐ Yes ☐ No If yes, a hot work permit will be required.

Will the project move, change access to, or hinder the use of an eyewash and/or shower station?

☐ Yes ☐ No If yes, describe a plan to mitigate risk.

Pre-Construction Risk Assessment – Page 8 of 10

PART 3: INTERIM LIFE SAFETY MEASURES (ILSM)

Project Evaluation Review the project/repair using the following criteria and indicate whether each item is applicable by marking the appropriate box. For any “YES” responses, coordinate with the Safety Office to review the required actions for appropriate interim life safety measures. In the Interim Life Safety Summary Sheet (PART II) at the bottom of this document, list specifically how the required interim life safety measures will be implemented for this project/repair impacting Life Safety. For the INTERIM LIFE SAFETY MEASURES Daily Inspection sheet (PART III), copy the measures from PART II into PART III, and issue PART III only to the Contractor for daily ILSM inspections.

A. EXITS YES NO

1. Does the project/repair have the potential of affecting an exit or other means of egress?

2. Will the affected exit be used by other than the contractor’s/maintenance personnel?

Required Actions: If a means of egress is obstructed, an alternate must be designated and training is required for those persons affected. Safety office will conduct/coordinate training. Means of exiting construction/repair areas must be inspected on a daily basis to prevent blockages due to debris. This needs to be documented and can be done by the contractor/shop foreman or shop designee.

B. EMERGENCY ACCESS YES NO

1. Does the project/repair have the potential to obstruct access to the emergency department?

2. Does the project/repair have the potential of obstructing access for fire department connections, hydrants, or fire lanes?

Required Actions: If an emergency access is obstructed, an alternate means of access must be designated and the Columbus Fire Department and VA Police must be notified by the Safety Office of the alternative.

C. FIRE PROTECTION YES NO

1. Does the project have the potential of impairing existing fire alarm, detection, or suppression systems?

2. Will temporary fire protection systems be required as part this project/repair?

Required Actions: If a fire protection or alarm system is to be rendered non-operational for more than 4 hours out of a 24-hour period, either a substitute system or a fire watch must be initiated. If neither of these methods can be implemented, the area must be closed down and evacuated. All of these measures must be coordinated with the Safety Office, VA Police, and the affected staff.

D. TEMPORARY PARTITIONS YES NO

1. Will construction compromise any fire or smoke partitions or barriers?

Required Actions: If construction/repair involves major breaches in fire or smoke barriers, the contractor must erect temporary walls around the construction area equal to the barrier that has been compromised.

E. ADDITIONAL FIRE FIGHTING EQUIPMENT AND TRAINING YES NO

1. Does the area affected by the project warrant placement of additional fire protection equipment?

2. Will additional firefighting training be required by affected personal?

Pre-Construction Risk Assessment – Page 9 of 10

Required Actions: If the fire load of a particular area is significantly increased over normal due to construction, additional firefighting equipment (such as fire extinguishers) will be required. If any of this additional firefighting equipment is of a different type than that already available in the affected area, training in the use of this equipment for staff or contractor personnel is required.

F. SMOKING POLICY YES NO

1. Will variance to existing medical center smoking policy be permitted?

Required Actions: If designated smoking areas are impacted or closed due to construction, temporary areas may need to be established.

G. COMBUSTIBLE LOAD LEVELS YES NO

1. Does the project involve the storage of flammable or combustible materials?

2. Does the project have the potential for creating flammable or combustible debris?

Required Actions: Surveillance of construction sites will need to be increased to prevent the accumulation of excess flammable or combustible debris. The fire load of the construction area must be kept to a minimum.

H. FIRE DRILLS YES NO

1. Does the project warrant additional fire drills within the affected areas?

Required Actions: If the life safety features of a particular area are adversely impacted by construction, then the frequency of fire drills must be increased to two per shift per quarter for healthcare/lodger occupancies. Adverse impacts would include blocked fire exits, impaired fire alarm or sprinkler systems, or major compromises in fire or smoke barriers or compartments.

I. HAZARD SURVEILLANCE YES NO

1. Does the project present additional hazards, such as excavations, construction storage or field offices, crane work, high voltage, confined spaces, scaffolding, etc., which warrant increased hazard surveillance?

Required Actions: If yes, then additional project surveillance is warranted to identify potential life safety issues.

J. OCCUPATIONAL HEALTH ISSUES YES NO

1. Do construction workers need to be restricted to dedicated corridors, elevators, or exits?

2. Is special ventilation required for the area during construction?

3. Will any disruptions of the water/plumbing system affect the purity of potable water?

4. Will the construction activities be hazardous to immune-compromised patients?

Required Actions: Any construction activities that adversely affect occupational health issues must be reviewed to minimize the effects. If negative pressurization is required for “special ventilation”, then include a daily reporting of the pressure measurement as part of the the daily ILSM log.

K. ADDITIONAL PERSONNEL TRAINING YES NO

1. Does the project have the potential of affecting structural features of the fire safety systems?

2. Does the project have the potential of affecting compartmentalization features of the fire safety systems?

3. Does the project have the potential for negatively affecting infection control procedures?

Pre-Construction Risk Assessment – Page 10 of 10

Required Actions: Affected personnel must be notified when fire safety systems or infection control procedures are compromised and trained in temporary changes in procedures to compensate for the impaired systems. Examples are the need for alternate fire exits, alarm or sprinkler systems or to evacuate behind secondary fire barriers or compartments due to fire or smoke partition compromises.

L. FACILITY-WIDE TRAINING YES NO

1. Does the project present life safety code deficiencies or construction hazards which warrant facility-wide education of personnel concerning the interim life safety measures?

2. Does the project present occupational health deficiencies which warrant facility-wide education of personnel concerning those procedures?

Required Actions: Training must be provided facility wide to educate staff, patients and visitors to any life safety system that is impaired throughout the entire building. In addition, the Columbus Fire Department and VA Police will be notified.

Part 4: APPROVALS:

Contracting Officer’s Representative (COR):

Safety:

Infection Control:

Patient Safety:

Project Section Chief:

Project Evaluation
Review the project/repair using the following criteria and indicate whether each item is applicable by marking the appropriate box. For any “YES” responses, coordinate with the Safety Office to review the required actions for appropriate interim life...
Project Number: 757-19-203
Project Description: Replace the existing domestic water pressure booster pump set in Rm 1A350. Facility-wide install a chlorine residual monitoring system and chlorine injecting ports on the domestic water loops and install thermostatic mixing valves at sinks.
A: Yes
A1: Yes
A2: Off
A3: Yes
B: Yes
B1: Yes
B2: Yes
B3: Yes
C: Yes
C1: Off
C2: Off
C3: Off
C4: Off
C5: Yes
C6: Off
C7: Off
D: Off
D1: Off
D2: Off
D3: Off
LOW: Yes
MED: Yes
HIGH: Off
HIGHEST: Off
LOW1: Yes
LOW2: Off
LOW3: Yes
LOW4: Off
LOW5: Off
LOW6: Off
LOW7: Off
LOW8: Yes
LOW9: Yes
MED1: Off
MED2: Off
MED3: Yes
MED4: Off
MED5: Off
MED6: Off
MED7: Off
MED8: Off
MED9: Off
HIGH1: Off
HIGH2: Off
HIGH3: Off
HIGH4: Off
HIGH5: Off
HIGH6: Off
HIGH7: Off
HIGH8: Off
HIGH9: Off
HIGHEST1: Off
HIGHEST2: Off
HIGHEST3: Off
HIGHEST4: Off
HIGHEST5: Off
HIGHEST6: Off
HIGHEST7: Off
HIGHEST8: Off
HIGHEST9: Off
HIGHEST10: Off
HIGHEST11: Off
HIGHEST12: Off
HIGHEST13: Off
HIGHEST14: Off
AA: Yes
BB: Yes
CC: Yes
DD: Off
LOWRISK: Yes
MEDRISK: Yes
HIGHRISK: Off
HIGHESTRISK: Off
ALOW: Yes
BLOW: Off
CLOW: Yes
DLOW: Off
AMED: Off
BMED: Yes
CMED: Off
DMED: Off
AHIGH: Off
BHIGH: Off
CHIGH: Off
DHIGH: Off
AHIGHEST: Off
BHIGHEST: Off
CHIGHEST: Off
DHIGHEST: Off
CLASS1: Yes
CLASS2: Yes
CLASS3: Off
CLASS4: Off
Construction Documents: Yes
Complete: Yes
CD1: Yes
CD2: Yes
CD3: Yes
AWWA: Yes
Asbestos: Off
Lead: Off
Mold: Off
Confined Space Entry: Off
Lock Out Tag Out: Yes
Scaffolding: Off
Fall Protection: Off
Excavation: Off
Cranes: Off
Traffic: Off
Live electrical work: Off
Project Name: Add Domestic Water Pressure Booster
Unit Below: N/A; facility-wide
Unit Above: N/A; facility-wide
East: N/A; facility-wide
West: N/A; facility-wide
North: N/A; facility-wide
South: N/A; facility-wide
Above Risk: [Low]
East Risk: [Low]
West Risk: [Low]
North Risk: [Low]
South Risk: [Low]
BelowRisk: [Low]
Specific site activity: Facility-wide; see design drawings for specifics.
Containment Measures: Welding operations shall be done utilizing local ventilation to control exposure of surrounding areas to fumes.
Work Hours: Majority of work outside of Rm 1A350 will be performed off-hours due to water loop isolation requirements. Some pump set work will be done off-hours due to whole facility water outage requirement.
Daily Cleaning: The contractor.
Coordinate Cleaning:
Special cleaning needs:
Foreseen utility interruptions: Water outages shall be performed off-hours. Power outages shall be limited to single panels for circuit tie-ins and scheduled on a case by case basis.
Unplanned utility interruptions: Water outages shall be performed off-hours.
Activity 1: Drilling of holes through floor slab and drywall for electrical conduit runs
Mitigation1: Drilling to be done off-hours.
Time1: Less than 5 minutes per hole sporadically through the project.
Activity2:
Time2:
Mitigation2:
Activity3:
Time 3:
Mitigate3:
Hazardous Materials:
Odors: Welding performed shall use local ventilation to capture fumes.
Contaminants:
Minimize surrounding area distruptions: Majority of work outside of Rm 1A350 will be performed off-hours due to water loop isolation requirements.
Water Damage: Choice2
Isolation Rooms: Choice1
Sinks: Choice1
Sinks2: Choice1
UtilityRooms: Choice1
TB: Choice2
Clean: Choice2
SpecialClean: Choice2
Water Supply: Choice1
Sewer Service: 2
Storm Drainage: 2
Normal Power: 2
Emergency Power: Choice1
Vent: 2
Oxygen: 2
Med Air: 2
Med Vac: 2
Med Gas: 2
HVAC: 2
Sprinkler: 2
Valve: 2
Valve2: Choice1
Short Pipe: Choice1
New Pipe: Choice1
Long Pipe: Choice1
Odor1: Choice1
Hot Work: Choice1
Exit1: 2
Exit2: 2
EmergencyAccess1: 2
EmergencyAccess2: 2
FireProtect1: 2
FireProtect2: 2
Temp Partition: 2
FireEquip1: 2
FireEquip2: 2
Smoking: 2
Combust1: 2
Combust2: 2
FireDrill: 2
HazardSurvey: 2
OccHealth1: 2
OccHealth2: 2
OccHealth3: 2
OccHealth4: 2
AddTrain1: 2
AddTrain2: 2
AddTrain3: 2
FacTrain1: 2
FacTrain2: 2
2017-12-29T14:37:17-0500
Phillip J Hinson 669343
2018-01-04T10:08:22-0500
Brad D Woods 680348
2018-01-04T08:11:19-0500
Kenneth R. Frigo 483115
2018-01-02T07:42:10-0500
Robin C McAdams 298340
2018-01-03T07:58:39-0500
Roger R Dunifon 193239
Negative/Neutral: [Negative]
0:
01"/0:
00": [0.01"]
Misc Risks: Utility outages shall be LO/TO'd in accordance with OSHA and VA requirements.
Eyewash Risks:
Check Box1: Off
Check Box2: Yes