Technical Specifications - Distribution.pdf
PDF 43 MB Posted
- Attached to
- R425 Job Order Contract TVHS
- Solicitation number
- 36C24926Q0235
About this file
This is a Technical Specifications document for a Job Order Contract (JOC) covering CSI Divisions 01-46 for the VA Tennessee Valley Healthcare System, effective April 2026. The specifications establish comprehensive technical requirements across 46 construction divisions, including general requirements, concrete, masonry, metals, wood and composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, conveying systems, fire suppression, plumbing, HVAC, electrical systems, communications, electronic safety and security, earthwork, exterior improvements, utilities, transportation, and material processing equipment.
The document functions as a master specification framework establishing quality standards, testing and inspection requirements, warranty periods, contractor qualifications, and performance criteria for all work performed under the contract. Key administrative sections address general requirements including bracketed options for Owner selection, warranty coverage periods with extended manufacturer warranties handled as replacements, conflict resolution procedures between specifications and Owner's Standard Plans, and CSI Section Format compliance. Quality requirements sections mandate contractor quality-control plans, testing agency qualifications, preconstruction testing, mockup construction and approval processes, and documentation of all tests and inspections. The specifications require compliance with industry standards from organizations such as ASTM, NFPA, ACI, ASHRAE, and numerous others, with temporary facilities and controls provisions addressing field offices, storage, fire safety, moisture and mold protection, dust control, and noise mitigation during construction operations.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Job Order Contract Technical Specifications CSI Divisions 01-46 April 2026
VA Tennessee Valley Healthcare System
This Page Intentionally Left Blank
Table of Contents
VA Tennessee Valley Healthcare System JOC TOC - 1
01 General Requirements
01 00 00 00 General Requirements 01 11 13 00 Work Covered by Contract Documents 01 11 19 00 No Specification Required 01 40 00 00 Quality Requirements 01 42 00 00 References 01 50 00 00 Temporary Facilities and Controls 01 51 13 00 Temporary Electricity 01 54 23 00 Temporary Scaffolding and Platforms 01 56 39 00 Temporary Tree and Plant Protection 01 57 23 00 Temporary Storm Water Pollution Control 01 60 00 00 Product Requirements 01 74 19 00 Construction Waste Management and Disposal 01 91 13 00 General Commissioning Requirements
02 Existing Conditions
02 41 16 00 Structure Demolition 02 41 16 13 Building Demolition 02 41 19 00 Selective Demolition 02 41 19 13 Cutting and Patching 02 58 13 00 Snow Fencing 02 61 00 00 Removal and Disposal of Contaminated Soils 02 82 16 00 Engineering Control of Asbestos Containing Materials 02 82 33 00 Removal Of Friable Asbestos-Containing Materials 02 82 33 00a Removal Of Nonfriable Asbestos-Containing Materials 02 83 00 00 Lead Remediation 02 83 19 00 Lead-Based Paint Remediation 02 83 19 00a XRF Testing For Lead-Based Paint 02 83 19 00b Lead Dust Wipe, Air And Tclp Sampling And Analysis 02 84 16 00 Handling of Lighting Ballasts and Lamps Containing PCBs and Mercury 02 87 13 00 Mold Remediation 02 87 16 13 Bird Excrement Removal
03 Concrete
03 01 30 00 Maintenance of Cast-in-Place Concrete 03 10 00 00 Concrete Forming and Accessories 03 11 16 00 Architectural Concrete 03 20 00 00 Concrete Reinforcing 03 30 00 00 Cast-In-Place Concrete 03 35 43 00 Polished Concrete Finishing 03 37 13 00 Shotcrete 03 41 00 00 Precast Structural Concrete 03 51 13 00 Cementitious Wood Fiber Decks 03 53 00 00 Concrete Topping 03 54 00 00 Gypsum Cement Underlayment 03 54 16 00 Hydraulic Cement Underlayment
04 Masonry
04 01 00 00 Masonry Cleaning 04 01 20 51 Brick Masonry Repair 04 01 20 91 Brick Masonry Repointing 04 20 00 00 Unit Masonry 04 20 00 00a Masonry Veneer 04 22 00 00 Concrete Unit Masonry 04 23 00 00 Glass Unit Masonry 04 42 00 00 Exterior Stone Cladding
TOC - 2 VA Tennessee Valley Healthcare System JOC
04 72 00 00 Cast Stone Masonry
05 Metals
05 01 70 51 Decorative Metal Cleaning 05 01 70 61 Decorative Metal Repair 05 01 70 63 Decorative Metal Refinishing 05 12 00 00 Structural Steel Framing 05 21 00 00 Steel Joist Framing 05 31 00 00 Steel Decking 05 40 00 00 Cold-Formed Metal Framing 05 44 00 00 Cold-Formed Metal Trusses 05 50 00 00 Metal Fabrications 05 51 13 00 Metal Pan Stairs 05 51 19 00 Metal Grating Stairs 05 52 13 00 Pipe And Tube Railings 05 53 00 00 Expanded Metal Gratings 05 53 13 00 Bar Gratings 05 53 16 00 Plank Gratings 05 58 00 00 Heating_Cooling Unit Covers 05 58 13 00 Column Covers 05 70 00 00 Decorative Metal 05 71 00 00 Decorative Metal Stairs 05 71 13 00 Fabricated Metal Spiral Stairs 05 73 00 00 Decorative Metal Railings 05 73 00 00a Glazed Decorative Metal Railings 05 75 00 00 Decorative Formed Metal
06 Wood, Plastics, and Composites
06 10 00 00 Rough Carpentry 06 13 00 00 Heavy Timber Construction 06 15 00 00 Wood Roof Decking 06 15 00 00a Wood Patio Decking 06 16 00 00 Sheathing 06 17 53 00 Shop-Fabricated Wood Trusses 06 18 00 00 Glued-Laminated Construction 06 20 23 00 Interior Finish Carpentry 06 41 00 00 Architectural Wood Casework 06 41 13 00 Residential Cabinets 06 42 16 00 Flush Wood Paneling 06 42 19 00 Plastic-Laminate-Faced Wood Paneling 06 44 00 00 Ornamental Woodwork 06 74 13 00 Fiberglass Reinforced Gratings
07 Thermal And Moisture Protection
07 01 50 19 Preparation for Reroofing 07 11 13 00 Bituminous Dampproofing 07 13 53 00 Elastomeric Sheet Waterproofing 07 14 13 00 Hot Fluid-Applied Rubberized Asphalt Waterproofing 07 14 16 00 Cold Fluid-Applied Waterproofing 07 16 13 00 Polymer Modified Cement Waterproofing 07 16 16 00 Crystalline Waterproofing 07 16 19 00 Metal Oxide Waterproofing 07 17 00 00 Bentonite Waterproofing 07 18 00 00 Traffic Coatings 07 19 00 00 Water Repellents 07 21 00 00 Thermal Insulation 07 21 19 00 Foamed-In-Place Insulation
VA Tennessee Valley Healthcare System JOC TOC - 3
07 24 13 00 Polymer-Based Exterior Insulation And Finish System (EIFS) 07 25 00 00 Weather Barriers 07 26 00 00 Vapor Retarders 07 31 13 00 Asphalt Shingles 07 31 16 00 Metal Shingles 07 31 26 00 Slate Shingles 07 31 29 00 Wood Shingles And Shakes 07 32 13 00 Clay Roof Tiles 07 32 16 00 Concrete Roof Tiles 07 41 13 00 Formed Metal Roof Panels 07 41 13 00a Standing-Seam Metal Roof Panels 07 41 13 00b Batten-Seam Metal Roof Panels 07 41 16 00 Insulated Metal Roof Panels 07 42 13 19 Insulated Metal Wall Panels 07 42 13 23 Composite Wall Panels 07 42 93 00 Soffit Panels 07 46 16 00 Aluminum Siding 07 46 19 00 Steel Siding 07 46 33 00 Plastic Siding 07 46 46 00 Fiber-Cement Siding 07 51 13 00 Built-Up Asphalt Roofing 07 52 13 00 Atactic-Polypropylene (APP) Modified Bituminous Membrane Roofing 07 52 16 00 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing 07 53 16 00 Chlorosulfonate-Polyethylene (CSPE) Roofing 07 53 23 00 Ethylene-Propylene-Diene-Monomer (EPDM) Roofing 07 54 19 00 Polyvinyl-Chloride (PVC) Roofing 07 54 23 00 Thermoplastic-Polyolefin (TPO) Roofing 07 55 52 13 Atactic-Polypropylene (APP) Modified Bituminous Protected Membrane Roofing 07 55 52 16 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Protected Membrane Roofing 07 57 00 00 Coated Foamed Roofing 07 61 00 00 Sheet Metal Roofing 07 62 00 00 Sheet Metal Flashing And Trim 07 71 00 00 Roof Specialties 07 72 00 00 Roof Accessories 07 72 53 00 Snow Guards 07 81 00 00 Applied Fire Protection 07 81 23 00 Intumescent Fire Protection 07 84 13 00 Penetration Firestopping 07 84 43 00 Joint Firestopping 07 91 00 00 Preformed Joint Seals 07 92 00 00 Joint Sealants 07 92 19 00 Acoustical Joint Sealants 07 95 13 00 Parking Deck Expansion Joint Cover Assemblies 07 95 13 13 Interior Expansion Joint Cover Assemblies 07 95 13 16 Exterior Expansion Joint Cover Assemblies
08 Openings
08 01 52 61 Wood Window Repairs 08 11 13 00 Hollow Metal Doors and Frames 08 11 73 00 Sliding Metal Fire Doors 08 12 13 00 Hollow Metal Frames 08 14 16 00 Flush Wood Doors 08 18 16 00 Sliding Aluminum-Framed Glass Doors 08 18 16 00a Multipanel Sliding Aluminum-Framed Glass Doors 08 18 16 00b Sliding Wood-Framed Glass Doors 08 18 16 00c Multipanel Sliding Wood-Framed Glass Doors 08 31 13 00 Access Doors And Frames 08 33 13 00 Coiling Counter Doors 08 33 23 00 Overhead Coiling Doors 08 33 26 00 Overhead Coiling Grilles 08 33 43 00 Overhead Coiling Smoke Curtains 08 34 73 13 Metal Sound Control Door Assemblies 08 34 73 16 Wood Sound Control Door Assemblies 08 35 13 00 Folding Doors 08 35 13 13 Multipanel Folding Aluminum-Framed Glass Doors 08 36 13 00 Sectional Doors 08 38 00 00 Traffic Doors
TOC - 4 VA Tennessee Valley Healthcare System JOC
08 42 13 00 Aluminum-Framed Entrances 08 42 26 00 All-Glass Entrances 08 42 29 23 Sliding Automatic Entrances 08 42 29 33 Swinging Automatic Entrances 08 42 29 33a Revolving Door Entrances 08 43 13 00 Aluminum-Framed Storefronts 08 44 13 00 Glazed Aluminum Curtain Walls 08 45 23 00 Fiberglass-Sandwich-Panel Assemblies 08 51 13 00 Aluminum Windows 08 51 13 00a Aluminum Replacement Windows 08 51 19 00 Stainless Steel Windows 08 51 69 00 Metal Storm Windows 08 52 00 00 Wood Windows 08 53 13 00 Vinyl Windows 08 54 00 00 Composite Windows 08 54 13 00 Fiberglass Windows 08 62 00 00 Unit Skylights 08 63 00 00 Metal-Framed Skylights 08 71 00 00 Door Hardware 08 71 13 00 Power Door Operators 08 80 00 00 Glazing 08 83 00 00 Mirrors 08 84 00 00 Plastic Glazing 08 88 53 00 Security Glazing 08 91 16 00 Operable Wall Louvers 08 91 19 00 Fixed Louvers 08 95 16 00 Wall Vents
09 Finishes
09 01 20 00 Gypsum Board Renovation 09 01 20 91 Plaster Restoration 09 01 90 52 Maintenance Repainting 09 05 61 13 Moisture Vapor Emission Control 09 22 16 00 Non-Structural Metal Framing 09 23 00 00 Gypsum Plastering 09 24 00 00 Cement Plastering 09 29 00 00 Gypsum Board 09 30 13 00 Ceramic Tiling 09 51 13 00 Acoustical Panel Ceilings 09 51 23 00 Acoustical Tile Ceilings 09 51 33 00 Acoustical Metal Pan Ceilings 09 54 00 00 Stretched-Fabric Ceiling Systems 09 54 00 00a Fabric-Wrapped Ceiling Panels 09 54 23 00 Linear Metal Ceilings 09 63 13 00 Brick Flooring 09 64 00 00 Wood Flooring 09 64 66 00 Wood Athletic Flooring 09 65 13 00 Resilient Base and Accessories 09 65 16 00 Resilient Sheet Flooring 09 65 19 00 Resilient Tile Flooring 09 65 43 00 Linoleum Flooring 09 65 66 00 Resilient Athletic Flooring 09 66 13 00 Portland Cement Terrazzo Flooring 09 66 23 00 Resinous Matrix Terrazzo Flooring 09 67 23 00 Resinous Flooring 09 68 13 00 Tile Carpeting 09 68 16 00 Sheet Carpeting 09 69 00 00 Access Flooring 09 72 00 00 Wall Coverings 09 91 13 00 Exterior Painting 09 91 23 00 Interior Painting 09 93 00 00 Staining and Transparent Finishing 09 96 00 00 High-Performance Coatings 09 96 53 00 Elastomeric Coatings 09 97 26 00 Cementitious Coatings
VA Tennessee Valley Healthcare System JOC TOC - 5
10 Specialties
10 11 00 00 Visual Display Units 10 12 00 00 Display Cases 10 13 00 00 Directories 10 14 16 00 Plaques 10 14 19 00 Dimensional Letter Signage 10 14 23 00 Panel Signage 10 14 23 00a Room-Identification Panel Signage 10 14 23 00b Post And Panel_Pylon Signage 10 14 23 00c Modular Signage 10 14 23 00d Painted Signage 10 21 13 13 Metal Toilet Compartments 10 21 13 14 Stainless Steel Toilet Compartments 10 21 13 16 Plastic-Laminate-Clad Toilet Compartments 10 21 13 19 Plastic Toilet Compartments 10 21 13 43 Phenolic-Core Pedestal-Mounted Privacy Toilet Compartments 10 21 16 17 Phenolic-Core Shower and Dressing Compartments 10 21 23 00 Cubicle Curtains and Track 10 22 00 00 Folding Panel Partitions 10 22 00 00a All-Glass Partitions 10 22 13 00 Wire Mesh Partitions 10 22 19 00 Demountable Partitions 10 22 33 00 Accordion Folding Partitions 10 26 00 00 Wall and Door Protection 10 28 00 00 Toilet, Bath, and Laundry Accessories 10 28 13 63 Detention Toilet Accessories 10 28 19 00 Tub and Shower Enclosures 10 44 13 00 Fire Protection Cabinets 10 44 16 00 Fire Extinguishers 10 45 00 00 Photoluminescent Egress Path Markings 10 51 13 00 Metal Lockers 10 55 00 00 USPS-Delivery Postal Specialties 10 55 00 00a Private-Delivery Postal Specialties 10 56 13 00 Metal Storage Shelving 10 73 13 00 Awnings 10 75 16 00 Ground-Set Flagpoles 10 75 23 00 Wall-Mounted Flagpoles
11 Equipment
11 11 36 00 Vehicle Charging Equipment 11 12 00 00 Parking Control Equipment 11 13 13 00 Loading Dock Bumpers 11 13 16 00 Loading Dock Seals and Shelters 11 13 19 00 Stationary Loading Dock Equipment 11 13 23 00 Portable Dock Equipment 11 30 13 00 Residential Appliances 11 40 00 00 Foodservice Equipment 11 52 13 00 Projection Screens 11 52 13 00a Rear Projection Screens 11 53 13 00 Laboratory Fume Hoods 11 61 23 00 Folding And Portable Stages 11 61 43 00 Stage Curtains 11 66 23 00 Gymnasium Equipment 11 66 53 00 Gymnasium Dividers 11 68 00 00 Play Field Equipment and Structures 11 73 00 00 Patient Care Equipment 11 82 26 00 Facility Waste Compactors 11 97 26 00 Detention Gun Lockers 11 98 12 00 Detention Doors And Frames 11 98 14 00 Detention Door Hardware 11 98 21 00 Detention Windows
TOC - 6 VA Tennessee Valley Healthcare System JOC
12 Furnishings
12 21 13 00 Horizontal Louver Blinds 12 21 16 00 Vertical Louver Blinds 12 22 00 00 Curtains and Drapes 12 24 13 00 Roller Window Shades 12 30 00 00 Manufactured Wood-Veneer-Faced Casework 12 30 00 00a Manufactured Plastic-Laminate-Clad Casework 12 36 23 13 Plastic-Laminate-Clad Countertops 12 36 53 00 Metal Countertops 12 48 13 00 Entrance Floor Mats and Frames 12 55 00 00 Detention Furniture 12 61 00 00 Fixed Audience Seating 12 66 00 00 Telescoping Stands
13 Special Construction
13 34 19 00 Metal Building Systems 13 34 23 16 Fabricated Control Booths 13 46 13 00 Lightning Protection for Structures 13 47 13 00 Cathodic Protection 13 49 00 00 Radiation Protection
14 Conveying Equipment
14 21 00 00 Electric Traction Elevators 14 21 13 00 Electric Traction Freight Elevators 14 21 23 00 Machine Room-Less Electric Traction Passenger Elevators 14 24 00 00 Hydraulic Elevators 14 24 13 00 Hydraulic Freight Elevators 14 26 00 00 Limited-Use_Limited-Application Elevators 14 30 00 00 Escalators 14 32 00 00 Moving Walks 14 41 19 00 Stairway Chairlifts 14 42 00 00 Wheelchair Lifts 14 91 82 00 Trash Chutes
21 Fire Suppression
21 05 00 00 Common Work Results for Fire Suppression 21 05 23 00 General-Duty Valves for Water-Based Fire-Suppression Piping 21 05 29 00 Hangers and Supports for Fire-Suppression Piping and Equipment 21 05 33 00 Heat Tracing for Fire-Suppression Piping 21 05 48 00 Vibration And Seismic Controls For Fire-Suppression Piping And Equipment 21 05 48 13 Vibration Controls for Fire-Suppression Piping and Equipment 21 05 53 00 Identification for Fire-Suppression Piping and Equipment 21 07 00 00 Fire-Suppression Systems Insulation 21 08 00 00 Commissioning Of Fire Suppression 21 10 00 00 Water-Based Fire-Suppression Systems 21 13 39 00 Foam-Water Systems 21 21 00 00 High-Pressure, Carbon-Dioxide Fire-Extinguishing Systems 21 21 00 00a Low-Pressure, Carbon-Dioxide Fire-Extinguishing Systems 21 22 00 00 Clean-Agent Fire-Extinguishing Systems 21 31 13 00 Electric-Drive, Centrifugal Fire Pumps 21 31 16 00 Diesel-Drive, Centrifugal Fire Pumps 21 34 13 00 Pressure-Maintenance Pumps
VA Tennessee Valley Healthcare System JOC TOC - 7
22 Plumbing
22 05 00 00 Common Work Results for Plumbing 22 05 23 00 General-Duty Valves for Plumbing Piping 22 05 29 00 Hangers and Supports for Plumbing Piping and Equipment 22 05 33 00 Heat Tracing for Plumbing Piping 22 05 48 00 Vibration And Seismic Controls For Plumbing Piping And Equipment 22 05 48 13 Vibration Controls for Plumbing Piping and Equipment 22 05 53 00 Identification for Plumbing Piping and Equipment 22 07 16 00 Plumbing Equipment Insulation 22 07 19 00 Plumbing Piping Insulation 22 08 00 00 Commissioning Of Plumbing 22 11 16 00 Domestic Water Piping 22 11 19 00 Domestic Water Piping Specialties 22 11 23 13 Domestic-Water Packaged Booster Pumps 22 11 23 23 Inline, Domestic-Water Pumps 22 12 19 00 Facility Ground-Mounted, Potable-Water Storage Tanks 22 12 23 00 Facility Indoor Potable-Water Storage Tanks 22 13 00 00 Facility Gray-Water Storage Tanks 22 13 16 00 Sanitary Waste And Vent Piping 22 13 19 00 Sanitary Waste Piping Specialties 22 13 19 13 Sanitary Drains 22 13 23 00 Sanitary Waste Interceptors 22 13 29 00 Sanitary Sewerage Pumps 22 14 00 00 Facility Storm-Water Retention Tanks 22 14 13 00 Storm Drainage Piping 22 14 29 00 Sump Pumps 22 15 13 00 General-Service Compressed-Air Piping 22 15 19 00 General-Service Packaged Air Compressors and Receivers 22 31 00 00 Domestic Water Softeners 22 32 00 00 Domestic Water Filtration Equipment 22 33 00 00 Electric Domestic-Water Heaters 22 34 00 00 Fuel-Fired, Domestic-Water Heaters 22 35 00 00 Domestic-Water Heat Exchangers 22 41 00 00 Residential Plumbing Fixtures 22 42 00 00 Commercial Plumbing Fixtures 22 43 00 00 Healthcare Plumbing Fixtures 22 45 00 00 Emergency Plumbing Fixtures 22 46 00 00 Security Plumbing Fixtures 22 47 00 00 Drinking Fountains And Water Coolers 22 63 13 00 Gas Piping For Laboratory And Healthcare Facilities 22 66 00 00 Chemical-Waste Systems for Laboratory and Healthcare Facilities 22 67 00 00 Processed Water Equipment for Laboratory and Healthcare Facilities 22 67 13 00 Processed Water Piping for Laboratory and Healthcare Facilities
23 Heating, Ventilating, and Air-Conditioning (HVAC)
23 01 30 51 Existing HVAC Air Distribution System Cleaning 23 05 00 00 Common Work Results for HVAC 23 05 00 00a Coatings for HVAC 23 05 23 00 General-Duty Valves for HVAC Piping 23 05 29 00 Hangers and Supports for HVAC Piping and Equipment 23 05 33 00 Heat Tracing for HVAC Piping 23 05 48 00 Vibration and Seismic Controls for HVAC 23 05 48 00a Vibration Instruments 23 05 48 13 Vibration Controls for HVAC 23 05 53 00 Identification for HVAC Piping and Equipment 23 05 66 00 AntiMicrobial Ultraviolet Lamp Systems for HVAC 23 07 13 00 Duct Insulation 23 07 16 00 HVAC Equipment Insulation 23 07 19 00 HVAC Piping Insulation 23 08 00 00 Commissioning Of HVAC 23 09 00 00 Speed Instruments 23 09 23 00 Direct Digital Control (DDC) System for HVAC
TOC - 8 VA Tennessee Valley Healthcare System JOC
23 09 23 00a Leak Detection Instruments 23 09 23 00b Position Instruments 23 09 23 00c Sequence of Operations for HVAC DDC 23 09 23 11 Control Valves 23 09 23 12 Control Dampers 23 09 23 13 Energy Meters 23 09 23 14 Flow Instruments 23 09 23 16 Gas Instruments 23 09 23 19 Moisture Instruments 23 09 23 21 Motion Instruments 23 09 23 23 Pressure Instruments 23 09 23 27 Temperature Instruments 23 11 23 00 Facility Natural-Gas Piping 23 11 26 00 Facility Liquefied-Petroleum Gas Piping 23 12 13 00 Facility Fuel-Oil Pumps 23 13 13 00 Facility Underground Fuel-Oil Storage Tanks 23 13 23 00 Facility Aboveground Fuel-Oil Storage Tanks 23 21 13 00 Hydronic Piping 23 21 16 00 Hydronic Piping Specialties 23 21 23 00 Hydronic Pumps 23 22 00 00 Steam And Condensate Piping 23 22 00 00a Underground Steam and Condensate Heating Piping 23 22 16 00 Steam and Condensate Heating Piping Specialties 23 22 23 00 Steam Condensate Pumps 23 23 00 00 Refrigerant Piping 23 25 00 00 HVAC Water Treatment 23 25 00 00a Water Treatment for Open-Loop Hydronic Systems 23 25 00 00b Water Treatment for Steam System Feedwater 23 25 00 00c Water Treatment for Humidification Steam System Feedwater 23 25 00 00d HVAC Makeup-Water Filtration Equipment 23 25 13 00 Water Treatment for Closed-Loop Hydronic Systems 23 31 13 00 Metal Ducts 23 31 16 00 Nonmetal Ducts 23 31 16 23 Fabric Air-Distribution Devices 23 33 00 00 Air Duct Accessories 23 34 00 00 HVAC Fans 23 34 33 00 Commercial Air Curtains 23 34 39 00 High-Volume, Low-Speed Fans 23 35 00 00 Listed Kitchen Ventilation System Exhaust Ducts 23 36 00 00 Air Terminal Units 23 37 13 13 Air Diffusers 23 37 13 13a Registers and Grilles 23 37 13 43 Security Registers and Grilles 23 37 23 00 HVAC Gravity Ventilators 23 38 13 00 Commercial-Kitchen Hoods 23 41 00 00 Particulate Air Filtration 23 41 33 00 High-Efficiency Particulate Air Filtration 23 42 00 00 Gas-Phase Air Filtration 23 43 00 00 Electronic Air Cleaners 23 51 13 00 Draft Control Fans 23 51 13 00a Gas Vents 23 51 13 00b Insulated Sectional Chimneys 23 51 13 16 Vent Dampers 23 51 16 00 Fabricated Breechings and Accessories 23 52 13 00 Electric Boilers 23 52 16 00 Condensing Boilers 23 52 23 00 Cast-Iron Boilers 23 52 33 00 Water-Tube Boilers 23 52 39 00 Fire-Tube Boilers 23 53 13 00 Boiler Feedwater Pumps 23 53 16 00 Deaerators 23 54 13 00 Electric-Resistance Furnaces 23 54 16 13 Gas-Fired Furnaces 23 54 16 16 Oil-Fired Furnaces 23 55 23 13 Low-Intensity, Gas-Fired, Radiant Heaters 23 55 33 13 Oil-Fired Unit Heaters 23 55 33 16 Gas-Fired Unit Heaters 23 57 00 00 Heat Exchangers for HVAC 23 62 00 00 Packaged Compressor and Condenser Units 23 63 13 00 Air-Cooled Refrigerant Condensers
VA Tennessee Valley Healthcare System JOC TOC - 9
23 64 13 00 Direct-Fired Absorption Water Chillers 23 64 13 16 Indirect-Fired Absorption Water Chillers 23 64 16 00 Centrifugal Water Chillers 23 64 23 13 Air-Cooled, Scroll Water Chillers 23 64 23 16 Water-Cooled, Scroll Water Chillers 23 64 26 13 Air-Cooled, Rotary-Screw Water Chillers 23 64 26 16 Water-Cooled, Rotary-Screw Water Chillers 23 65 13 16 Closed-Circuit, Forced-Draft Cooling Towers 23 65 14 13 Open-Circuit, Induced-Draft, Counterflow Cooling Towers 23 65 14 14 Open-Circuit, Induced-Draft, Crossflow Cooling Towers 23 65 14 16 Closed-Circuit, Induced-Draft, Counterflow Cooling Towers 23 72 13 00 Heat Wheel Air-To-Air Energy Recovery Units 23 72 16 00 Heat Pipe Air-to-Air Energy Recovery Units 23 73 00 00 Indoor, Indirect, Gas-Fired Heating and Ventilating Units 23 73 00 00a Indoor, Direct-Fired Heating and Ventilating Units 23 73 13 00 Indoor, Basic Air-Handling Units 23 73 13 00a Indoor, Semi-Custom Air-Handling Units 23 74 16 13 Packaged, Large-Capacity, Rooftop Air-Conditioning Units 23 74 23 00 Packaged, Indirect-Fired, Outdoor, Heating-Only Makeup-Air Units 23 74 23 13 Packaged, Direct-Fired, Outdoor, Heating-Only Makeup-Air Units 23 81 00 00 Variable-Refrigerant-Flow HVAC Systems 23 81 13 11 Packaged Terminal Air-Conditioners, Through-Wall Units 23 81 13 13 Packaged Terminal Air-Conditioners, Outdoor, Wall-Mounted Units 23 81 23 00 Small Capacity Computer-Room Air-Conditioners Floor-Mounted Units 23 81 23 00a Computer-Room Air-Conditioners, Console Units 23 81 23 00b Computer-Room, Rack-Cooling Equipment 23 81 23 12 Large Capacity (7 Tons (25 kW) and Larger), Computer-Room Air-Conditioners, Floor-Mounted Units 23 81 23 13 Computer-Room Air-Conditioners, Ceiling-Mounted Units 23 81 26 00 Split-System Air-Conditioners 23 81 46 00 Water-Source Unitary Heat Pumps 23 81 46 00a Water-To-Air Heat Pumps 23 82 00 00 Chilled Beams 23 82 16 11 Hydronic Air Coils 23 82 16 12 Steam Air Coils 23 82 16 13 Refrigerant Air Coils 23 82 16 14 Electric-Resistance Air Coils 23 82 19 00 Fan Coil Units 23 82 29 00 Radiators 23 82 33 00 Convectors 23 82 36 00 Finned-Tube Radiation Heaters 23 82 39 13 Cabinet Unit Heaters 23 82 39 16 Propeller Unit Heaters 23 82 39 19 Wall and Ceiling Unit Heaters 23 83 13 00 Radiant-Heating Electric Cables 23 84 13 16 Wetted-Element Humidifiers 23 84 13 23 Direct-Steam-Injection Humidifiers 23 84 13 29 Self-Contained Steam Humidifiers 23 84 16 16 Indoor, Mechanical Dehumidification Units
26 Electrical
26 01 00 00 Supplemental Requirements for Electrical 26 05 00 00 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 26 05 13 00 Medium-Voltage Cables 26 05 19 00 Low-Voltage Electrical Power Conductors and Cables 26 05 23 00 Control-Voltage Electrical Power Cables 26 05 26 00 Grounding and Bonding for Electrical Systems 26 05 29 00 Hangers And Supports For Electrical Systems 26 05 33 13 Conduits for Electrical Systems 26 05 33 16 Boxes and Covers for Electrical Systems 26 05 33 23 Surface Raceways for Electrical Systems 26 05 36 00 Cable Trays for Electrical Systems 26 05 39 00 Underfloor Raceways For Electrical Systems 26 05 43 00 Underground Ducts and Utility Structures 26 05 46 00 Poles for Electrical Systems 26 05 53 00 Identification for Electrical Systems 26 08 00 00 Commissioning Of Electrical Systems 26 09 00 00 Addressable Luminaire Lighting Controls
TOC - 10 VA Tennessee Valley Healthcare System JOC
26 09 00 00a Relay-Based Lighting Controls 26 09 23 00 Electrical Power Monitoring 26 09 23 00a Lighting Control Devices 26 11 16 00 Secondary Unit Substations with Switchboard Secondary 26 11 16 00a Secondary Unit Substations with Motor Control Center Secondary 26 11 16 11 Secondary Unit Substations with Switchgear Secondary 26 12 13 00 Liquid-Filled, Medium-Voltage Transformers 26 12 16 00 Dry-Type, Medium-Voltage Transformers 26 12 19 00 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 26 12 19 00a Low-Voltage Switchgear 26 13 29 00 Medium-Voltage Compartmentalized Switchgear 26 21 16 00 Paralleling Low-Voltage Switchgear 26 22 13 00 Low-Voltage Distribution Transformers 26 24 13 00 Switchboards 26 24 16 00 Panelboards 26 24 16 00a Electronically Operated Circuit-Breaker Panelboards 26 24 19 00 Motor-Control Centers 26 25 00 00 Low-Voltage Enclosed Bus Assemblies 26 27 13 00 Electricity Metering 26 27 16 00 Electrical Cabinets and Enclosures 26 27 19 00 Multi-Outlet Assemblies 26 27 26 00 Wiring Devices 26 27 26 00a Receptacles with Arc-Fault and Ground-Fault Protective Devices 26 27 26 00b Locking Receptacles 26 27 33 00 Power Distribution Units 26 28 13 00 Fuses 26 28 16 00 Enclosed Switches And Circuit Breakers 26 29 13 00 Manual and Magnetic Motor Controllers 26 29 13 00a Soft-Start Motor Controllers 26 29 23 00 Variable-Frequency Motor Controllers 26 31 00 00 Photovoltaic Collectors 26 32 13 13 Diesel-Engine-Driven Generator Sets 26 32 13 19 Bi-Fuel-Engine-Driven Generator Sets 26 33 43 00 Battery Chargers 26 33 53 00 Static Uninterruptible Power Supply 26 35 33 00 Power Factor Correction Equipment 26 36 00 00 Transfer Switches 26 43 13 00 Surge Protective Devices for Low-Voltage Electrical Power Circuits 26 50 00 00 Lighting 26 55 61 00 Theatrical Lighting 26 55 68 00 Athletic Field Lighting
27 Communications
27 11 00 00 Communications Equipment Room Fittings 27 13 13 00 Communications Copper Backbone Cabling 27 13 23 00 Communications Optical Fiber Backbone Cabling 27 15 13 00 Communications Copper Horizontal Cabling 27 15 23 00 Communications Optical Fiber Horizontal Cabling 27 15 33 00 Communications Coaxial Horizontal Cabling 27 41 33 00 Master Antenna Television System 27 51 00 00 Public Address Systems 27 51 23 20 Commercial Intercommunications and Program Systems 27 52 23 00 Nurse Call Code Blue Systems 27 53 13 00 Clock Systems
28 Electronic Safety and Security
28 10 00 00 Access Control 28 10 00 00a Access Control Software and Database Management 28 10 00 00b Access Control System Hardware 28 15 00 00 Integrated Access Control Hardware Devices 28 15 00 00a Access Control Credentials
VA Tennessee Valley Healthcare System JOC TOC - 11
28 15 00 00b Electrified Locking Devices and Accessories 28 15 00 00c Egress Management Devices 28 15 00 00d Telephone Entry Systems 28 15 00 00e Intercom Entry Systems 28 15 00 00f Electronic Key Management Systems 28 15 00 00g Access Control Electronic Turnstiles and Mobility Systems 28 15 11 00 Integrated Credential Readers and Entry Management 28 20 00 00 Video Surveillance 28 40 00 00 Emergency Responder Communications Enhancement System ERCES 28 46 00 00 Fire Detection and Alarm 28 47 00 00 Mass Notification
31 Earthwork
31 10 00 00 Site Clearing 31 20 00 00 Earth Moving 31 23 19 00 Dewatering 31 24 13 00 Levee Closure 31 31 16 00 Termite Control 31 32 19 16 Pond and Reservoir Liners 31 50 00 00 Excavation Support and Protection 31 62 13 00 Concrete Piles 31 62 16 00 Steel Piles 31 62 19 00 Timber Piles 31 62 23 00 Composite Piles
32 Exterior Improvements
32 12 16 00 Asphalt Paving 32 13 13 00 Concrete Paving 32 13 16 00 Decorative Concrete Paving 32 13 73 00 Concrete Paving Joint Sealants 32 14 00 00 Unit Paving 32 14 16 00 Vitrified Brick Pavement Replacement 32 17 13 00 Parking Bumpers 32 17 16 00 Manufactured Traffic-Calming Devices 32 17 23 00 Pavement Markings 32 17 26 00 Tactile Warning Surfacing 32 18 16 13 Playground Protective Surfacing 32 31 13 00 Chain Link Fences And Gates 32 31 16 00 Welded Wire Fences and Gates 32 31 19 00 Decorative Metal Fences and Gates 32 32 23 00 Segmental Retaining Walls 32 33 00 00 Site Furnishings 32 84 00 00 Planting Irrigation 32 91 13 00 Soil Preparation 32 92 00 00 Turf and Grasses 32 93 00 00 Plants 32 96 00 00 Transplanting
33 Utilities
33 01 30 41 Cleaning of Sewers 33 05 00 00 Common Work Results For Utilities 33 11 13 00 Potable Water Supply Wells 33 14 00 00 Site Water Distribution Piping 33 31 00 00 Site Sanitary Sewerage Piping 33 32 00 00 Site Packaged Sewage Pumping Stations 33 42 00 00 Stormwater Conveyance 33 44 36 00 Oil Water Separator 33 46 00 00 Subdrainage
TOC - 12 VA Tennessee Valley Healthcare System JOC
33 71 00 00 Overhead Medium-Voltage Wiring
34 Transportation
34 01 23 33 Welded Track Rails 34 01 23 33a Thermite Welded Track Rail 34 01 23 33b Direct Fixation Track 34 01 23 33c Resilient Track Cross Ties 34 01 23 33d Traction Power 34 01 23 33e Roadway Crossing Control Equipment 34 11 00 00 Rail Tracks 34 11 26 00 Ballasted Track Rail 34 11 33 13 Concrete Track Cross Ties 34 11 33 16 Timber Track Cross Ties 34 11 36 13 Direct Fixation Fasteners 34 11 93 00 Track Appurtenances and Accessories 34 71 13 00 Active Vehicle Barriers 34 71 13 26 Vehicle Guide Rails
35 Waterway and Marine Construction
35 22 26 00 Sluice Gates 35 24 00 00 Dredging 35 51 13 00 Floating Piers 35 51 13 23 Stone Groins 35 51 13 23a Stop Logs
41 Material Processing and Handling Equipment
41 22 23 00 Hoists 41 22 23 00a Specialty Hoists 41 22 23 00b Monorails With Electric Powered Hoists 41 22 23 00c Monorails With Manual Hoist
46 Water And Wastewater Equipment
46 82 83 00 Sewage Treatment Plant Electrical Controls And Instrumentation 46 86 29 00 Water Treatment Plant Electrical Controls And Instrumentation
01 - General Requirements
2026 General Requirements VA Tennessee Valley Healthcare System JOC 01 00 00 00 - 1
SECTION 01 00 00 00 - GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 BRACKETED OPTIONS
A. Within these Technical Specifications there are bracketed options. For example [6ft] [12ft] [24ft] or <Insert…>. The final selection will be made by the Owner and set forth in the Detailed Scope of Work.
1.2 WARRANTY
A. Within these Technical Specifications there are warranty periods listed. The warranty periods listed cover both material and labor for that period. If a manufacture will warranty a material for a longer period than what is listed, the material is covered as a replacement by the manufacture for the extra period.
The labor to replace will be at the installation price for the contractor.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 00 00 00
General Requirements 2026 01 00 00 00 - 2 VA Tennessee Valley Healthcare System JOC
THIS PAGE INTENTIONALLY LEFT BLANK
VA Tennessee Valley Healthcare System JOC 01 10 00 00 to 01 11 00 00 - 1
Task Specification Specification Description 01 10 00 00 01 00 00 00 General Requirements 01 11 00 00 01 00 00 00 General Requirements
01 10 00 00 to 01 11 00 00 - 2 VA Tennessee Valley Healthcare System JOC
2026 Work Covered by Contract Documents VA Tennessee Valley Healthcare System JOC 01 11 13 00 - 1
SECTION 01 11 13 00 - WORK COVERED BY CONTRACT DOCUMENTS
1.1 GENERAL
A. If any conflicts arise in the Specifications; the Owner’s Standard Plans and Specifications supersede the Gordian Technical Specifications. Specification conflicts shall be resolved as directed by the Owner.
B. Contractor is to provide a competent person to ensure operations are completed per plans, specifications, local laws and regulations which pertain.
C. Specification Format
1. The specification format shall be based on the Construction Specifications Institute (CSI) Section
Format.
1.2 PRODUCTS - (Not Used)
1.3 EXECUTION - (Not Used)
END OF SECTION 01 11 13 00
Work Covered by Contract Documents 2026 01 11 13 00 - 2 VA Tennessee Valley Healthcare System JOC
VA Tennessee Valley Healthcare System JOC 01 11 13 00 - 1
01 11 13 00 01 00 00 00 General Requirements
01 11 13 00 - 2 VA Tennessee Valley Healthcare System JOC
2026 No Specification Required VA Tennessee Valley Healthcare System JOC 01 11 19 00 - 1
SECTION 01 11 19 00 - NO SPECIFICATION REQUIRED
1.1 GENERAL
A. A separate specification is not required for this item. The description given in the line item of the Construction Task Catalog completely defines the item.
1.2 PRODUCTS - (Not Used)
1.3 EXECUTION - (Not Used)
END OF SECTION 01 11 19 00
No Specification Required 2026 01 11 19 00 - 2 VA Tennessee Valley Healthcare System JOC
VA Tennessee Valley Healthcare System JOC 01 11 19 00 to 01 35 33 00 - 1
01 11 19 00 01 00 00 00 General Requirements 01 20 00 00 01 00 00 00 General Requirements 01 22 00 00 01 00 00 00 General Requirements 01 22 00 00 01 11 19 00 No Specification Required 01 22 16 00 01 00 00 00 General Requirements 01 22 16 00 01 11 19 00 No Specification Required 01 22 20 00 01 00 00 00 General Requirements 01 22 20 00 01 11 19 00 No Specification Required 01 22 23 00 01 00 00 00 General Requirements 01 22 23 00 01 11 19 00 No Specification Required 01 30 00 00 01 00 00 00 General Requirements 01 35 00 00 01 00 00 00 General Requirements 01 35 29 00 01 00 00 00 General Requirements 01 35 33 00 01 00 00 00 General Requirements
01 11 19 00 to 01 35 33 00 - 2 VA Tennessee Valley Healthcare System JOC
2026 Quality Requirements VA Tennessee Valley Healthcare System JOC 01 40 00 00 - 1
SECTION 01 40 00 00 - QUALITY REQUIREMENTS
1.1 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-assurance and quality-control services required by Architect, Owner,[ Commissioning Authority,][ Construction Manager,] or authorities having jurisdiction are not limited by provisions of this Section.
C. Related Requirements:
1. Section 012100 "Allowances" for testing and inspection allowances.
1.2 DEFINITIONS
A. Experienced: When used with an entity or individual, "experienced," unless otherwise further described, means having successfully completed a minimum of [five] previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
B. Field Quality-Control Tests and Inspections: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, subcontractor, or sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations.
1. Use of trade-specific terminology in referring to a Work result does not require that certain construction activities specified apply exclusively to specific trade(s).
D. Mockups: Physical assemblies of portions of the Work constructed to establish the standard by which the Work will be judged. Mockups are not Samples.
1. Mockups are used for one or more of the following:
a. Verify selections made under Sample submittals.
b. Demonstrate aesthetic effects.
c. Demonstrate the qualities of products and workmanship.
Quality Requirements 2026 01 40 00 00 - 2 VA Tennessee Valley Healthcare System JOC
d. Demonstrate successful installation of interfaces between components and systems.
e. Perform preconstruction testing to determine system performance.
2. Product Mockups: Mockups that may include multiple products, materials, or systems specified in a single Section.
3. In-Place Mockups: Mockups constructed on-site in their actual final location as part of permanent construction.
E. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria.
Unless otherwise indicated, copies of reports of tests or inspections performed for other than the Project do not meet this definition.
F. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) in accordance with 29 CFR 1910.7, by a testing agency accredited in accordance with NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.
G. Source Quality-Control Tests and Inspections: Tests and inspections that are performed at the source (e.g., plant, mill, factory, or shop).
H. Testing Agency: An entity engaged to perform specific tests, inspections, or both. The term "testing laboratory" has the same meaning as the term "testing agency."
I. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work, to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
J. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work, to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality-control services do not include contract administration activities performed by Architect[ or Construction Manager].
1.3 DELEGATED DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.
B. Delegated Design Services Statement: Submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.
1.4 CONFLICTING REQUIREMENTS
A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements is specified and the standards or requirements establish different or conflicting
VA Tennessee Valley Healthcare System JOC 01 40 00 00 - 3 requirements for minimum quantities or quality levels, inform the Architect regarding the conflict and obtain clarification prior to proceeding with the Work. Refer conflicting requirements that are different, but apparently equal, to Architect for clarification before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements.
Refer uncertainties to Architect for a decision before proceeding.
1.5 ACTION SUBMITTALS
A. Mockup Shop Drawings:
1. Include plans, sections, elevations, and details, indicating materials and size of mockup construction.
2. Indicate manufacturer and model number of individual components.
3. Provide axonometric drawings for conditions difficult to illustrate in two dimensions.
1.6 INFORMATIONAL SUBMITTALS
A. Contractor's Quality-Control Plan: For quality-assurance and quality-control activities and responsibilities.
B. Qualification Data: For Contractor's quality-control personnel.
C. Contractor's Statement of Responsibility: When required by authorities having jurisdiction, submit copy of written statement of responsibility submitted to authorities having jurisdiction before starting work on the following systems:
1. Seismic-force-resisting system, designated seismic system, or component listed in the Statement of Special Inspections.
2. Primary wind-force-resisting system or a wind-resisting component listed in the Statement of Special Inspections.
D. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
E. Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1. Specification Section number and title.
2. Entity responsible for performing tests and inspections.
3. Description of test and inspection.
4. Identification of applicable standards.
5. Identification of test and inspection methods.
6. Number of tests and inspections required.
7. Time schedule or time span for tests and inspections.
8. Requirements for obtaining samples.
9. Unique characteristics of each quality-control service.
F. Reports: Prepare and submit certified written reports and documents as specified.
G. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, 01 40 00 00 - 4 VA Tennessee Valley Healthcare System JOC certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
1.7 CONTRACTOR'S QUALITY-CONTROL PLAN
A. Quality-Control Plan, General: Submit quality-control plan within [10] days of [Notice of Award][Notice to Proceed], and not less than [five] days prior to preconstruction conference. Submit in format acceptable to Architect. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality-assurance and quality-control responsibilities and to coordinate Owner's quality-assurance and quality-control activities. Coordinate with Contractor's Construction Schedule.
B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality-assurance and quality-control procedures similar in nature and extent to those required for Project.
1. Project quality-control manager [may also serve as Project superintendent][does not have other Project responsibilities].
C. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review.
D. Testing and Inspection: In quality-control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following:
1. Contractor-performed tests and inspections, including subcontractor-performed tests and inspections. Include required tests and inspections and Contractor-elected tests and inspections.
Distinguish source quality-control tests and inspections from field quality-control tests and inspections.
2. Special inspections required by authorities having jurisdiction and indicated on the Statement of Special Inspections.
3. Owner-performed tests and inspections indicated in the Contract Documents[, including tests and inspections indicated to be performed by Commissioning Authority].
E. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified.
Indicate types of corrective actions to be required to bring the Work into compliance with standards of workmanship established by Contract requirements and approved mockups.
F. Monitoring and Documentation: Maintain testing and inspection reports, including log of approved and rejected results. Include Work Architect has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming Work into compliance with requirements. Comply with requirements of authorities having jurisdiction.
1.8 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections.
Include the following:
1. Date of issue.
VA Tennessee Valley Healthcare System JOC 01 40 00 00 - 5
2. Project title and number.
3. Name, address, telephone number, and email address of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample-taking and testing and inspection.
11. Comments or professional opinion on whether tested or inspected Work complies with the
Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of technical representative making report.
2. Statement on condition of substrates and their acceptability for installation of product.
3. Statement that products at Project site comply with requirements.
4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
5. Results of operational and other tests and a statement of whether observed performance complies with requirements.
6. Statement of whether conditions, products, and installation will affect warranty.
7. Other required items indicated in individual Specification Sections.
C. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of factory-authorized service representative making report.
2. Statement that equipment complies with requirements.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
4. Statement of whether conditions, products, and installation will affect warranty.
5. Other required items indicated in individual Specification Sections.
1.9 QUALITY ASSURANCE
A. Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements.
C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
01 40 00 00 - 6 VA Tennessee Valley Healthcare System JOC
D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that is similar in material, design, and extent to those indicated for this Project.
F. Specialists: Certain Specification Sections require that specific construction activities be performed by entities who are recognized experts in those operations. Specialists will satisfy qualification requirements indicated and engage in the activities indicated.
1. Requirements of authorities having jurisdiction supersede requirements for specialists.
G. Testing and Inspecting Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspection indicated, as documented in accordance with ASTM E329, and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.
H. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect, demonstrate, repair, and perform service on installations of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
J. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:
1. Contractor's Responsibilities:
a. Provide test specimens representative of proposed products and construction.
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Provide sizes and configurations of test assemblies, mockups, and laboratory mockups to adequately demonstrate capability of products to comply with performance requirements.
d. Build site-assembled test assemblies and mockups, using installers who will perform same tasks for Project.
e. When testing is complete, remove test specimens and test assemblies[, and mockups];
do not reuse products on Project.
2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to Architect[ and Commissioning Authority][, through Construction Manager], with copy to…