This document contains a price cost schedule and details for a federal contract opportunity to renovate restrooms at a VA medical center. The price cost schedule includes three bid items and alternates for the general construction project to renovate restrooms in various buildings. Bid Item I is for all work included in the project with a period of performance of 180 days from notice to proceed. Alternate 1 excludes work in Building 116 and reduces the period of performance to 140 days. Alternate 2 excludes work in Building 4 and further reduces the period of performance to 120 days.

The related federal contract opportunity is solicitation number 36C24922B0004 to renovate restrooms at the Alvin C. York VA Medical Center for a project magnitude between $500,000 and $1,000,000. The opportunity is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1.00 JB __________________ __________________

Title of Project: Project# 626A4-18-102 “Renovate Restrooms”

General Intention: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project #626A4-18-102 Renovate Restrooms at the Alvin C. York VA Medical Center, Murfreesboro, TN 37129 as required by drawings and specifications.

BID ITEM I, GENERAL CONSTRUCTION: Provide all labor, material, equipment, and supervision necessary to complete all work for the above-mentioned project. Work includes general construction, demolition, electrical, mechanical, and plumbing work and certain other items to renovate all restrooms.

Period of Performance is 180 calendar days from the issuance of the Notice to Proceed (NTP).

BID ALTERNATE NO 1: Same as BID ITEM I except eliminate work in Building 116.

Period of Performance is 140 calendar days from the issuance of the

BID ALTERNATE NO 2: Same as BID ALTERNATE NO 1 except eliminate work in Building 4.

Period of Performance is 120 calendar days from the issuance of the

GRAND TOTAL __________________

A.3 PRICE/COST SCHEDULE