This statement of work outlines requirements for a construction project to renovate restrooms at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee. The contractor shall demolish existing structures and complete all necessary general construction, demolition, electrical, mechanical, and plumbing work to renovate restrooms in multiple buildings. Bid Item I requests all work for a period of 180 calendar days, while Bid Alternates 1 and 2 reduce the scope by eliminating specific buildings and have completion periods of 140 and 120 calendar days respectively. Additional requirements include touchless door switches, updated faucets and valves, a one-year warranty on all materials and work, and compliance with security protocols to access the site.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
A. GENERAL INFORMATION
1. Title of Project: Project# 626A4-18-102 “Renovate Restrooms”
2. General Intention: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project #626A4-
18-102 Renovate Restrooms at the Alvin C. York VA Medical Center, Murfreesboro, TN 37129 as required by drawings and specifications. Building 9 is excluded from the scope of this project.
B. STATEMENT OF BID ITEM(S)
BID ITEM I, GENERAL CONSTRUCTION: Provide all labor, material, equipment, and supervision necessary to complete all work for the above-mentioned project. Work includes general construction, demolition, electrical, mechanical, and plumbing work and certain other items to renovate all restrooms.
BID ALTERNATE NO 1: Same as BID ITEM I except eliminate work in Building 116.
BID ALTERNATE NO 2: Same as BID ALTERNATE NO 1 except eliminate work in Building 4.
C. PERIOD OF PERFORMANCE
BID ITEM 1 - 180 calendar days from the issuance of the Notice to Proceed.
BID ALTERNATE NO. 1: 140 calendar days from the issuance of the Notice to Proceed
BID ALTERNATE NO 2: 120 calendar days from the issuance of the Notice to Proceed
D. ADDENDUM TO SPECS AND DRAWINGS
Replace push plate wall switches for all automatic door openers with touchless type.
Basis of Design: BEA – 4.75” square – text and logo. Model 10MS21HS1
Update drawing to reflect new required facility standard faucets and thermostatic mixing valve.
E. GENERAL REQUIREMENTS
1. All work including materials will be warranted for a period of one year.
2. Normal working hours are Monday thru Friday from 8 a.m. to 4:30 p.m.
3. Contractor may be required to work some nights and or weekends to perform this work and maintain functionality of affected areas, and to minimize disruptions to the Medical Centers operations.
Weekend and evening work shall be identified on the project schedule submitted by the contractor and approved by the VA before work begins.
4. Visits to the site by Bidders may be made only by appointment with the Medical Center Contracting Officer Engineering Officer.
5. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.