Amendment 0002 to Solicitation 36C24827Q0004
This is Amendment 0002 to a federal contract solicitation issued by the Department of Veterans Affairs (VA) Network Contracting Office 8 (NCO 8) in Tampa, Florida. The amendment provides answers to Request for Information (RFI) inquiries, a utility map, and wall overhead and details documentation for the project titled "BB Repair Steam Piping in Manhole Near Building 1" (Project Number 516-26-117). The quotes due date remains September 18, 2026, at 1:00 PM EST, with submissions to be sent to david.hernandez1@va.gov. The estimated project magnitude is between $5,000,000 and $10,000,000. This is a firm-fixed-price construction contract for repair and replacement of buried steam and condensate piping systems at a VA medical facility.
The scope of work includes replacing approximately 12 feet of 8-inch pipe, 17 feet of 6-inch pipe, 12 feet of 4-inch pipe, and 12 feet of 3-inch pipe inside a 10-foot-deep manhole, plus underground high-pressure steam (HPS) and pumped condensate (PC) piping to 6 feet outside the manhole or to anchor points on the north and west sides. Additional work includes manhole waterproofing, masonry retaining wall restoration, installation of temporary boilers for two buildings (B101 and B71), utility surveys via ground-penetrating radar, temporary support systems, picnic table pad removal and reinstallation, and site restoration including Bahia sod. The VA will provide fuel and DEF for generators only; the contractor is responsible for all other generator and boiler maintenance. All pipe, fittings, valves, and bolts must be American-made per VA specifications. The amendment includes 83 numbered RFI responses addressing pipe specifications, waterproofing requirements, temporary boiler requirements, staging areas, work hours, dewatering procedures, environmental considerations, and evaluation criteria clarifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wall overhead and details.pdf | ||
| Utility map.jpg | JPG image | |
| 36C24827Q0004 0001.pdf | ||
| site visit Q0004.pdf | ||
| 516-26-117 Specifications 00 01 10.pdf | ||
| PPQ -Request form.docx | DOCX document | |
| PPQ.pdf | ||
| 36C24827Q0004_1.pdf | ||
| ASBUILTS-516-26-117.pdf | ||
| 05_Drawings SECTION LP302- 516-26-117.pdf | ||
| EMR 1 page.docx | DOCX document | |
| Base Offer Price Breakdown - 1 page.xlsx | XLSX spreadsheet | |
| WD-FL20260222 DATED 5-18-26.pdf | ||
| SHOP DRAWINGS HIGH PRESSURE STEAM PUMPED ROVANCO PIPING SYSTEM.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24827Q0004
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 16
516-26-117
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy Ste 160A Tampa FL 33637
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy Tampa FL 33637
To all Offerors/Bidders
07-31-2026
X
X X
PROJECT TITLE: BB Repair Steam Piping in Manhole Near Building 1
PROJECT NUMBER: 516-26-117
This amendment provides the answers to RFIs, a utility map and Wall overhead and details pdf file quotes due date remains 09/18/2026 at 1:00PM EST, mail to david.hernandez1@va.gov
DAVID HERNANDEZ
CONTRACTING OFFICER
PROJECT TITLE: BB Repair Steam Piping in Manhole Near Building 1
PROJECT NUMBER: 516-26-117
The purpose of this amendment is:
1. Provide answers to RFIs, a utility map and a Wall overhead and details pdf file
2. Quotes due date remains: 09/18/2026 at 1:00PM EST
See attached document: Wall overhead and details.
See attached document: Utility map.
No. Question Reference Contractor
1 Do you know the total linear feet, # of pipes and pipe diameter that need replacement? Diversified
VA
Response
Inside the Manhole; Approximately 12 foot of 8”, 17 foot of 6”, 12 foot of 4” and 12 foot of 3” pipe. Outside the manhole, HPS (8” diameter to North and 6” diameter to West) and PC (4’ diameter to North and 3” diameter to West) are being replaced.
These are being replaced to 6 foot of the outside the manhole or the anchors, whichever is greater. All underground pipes to the South are not being replaced.
Page 9 of the steam distribution drawings.
2 How many buildings do they expect will require temp boilers? Diversified
VA
Response
Two, B101 and B71 which make up the community living center. The boilers are hot water heating boilers that will supply hot water to the heating hot water and domestic hot water systems.
3 Can you accommodate and or whether a boiler plant shutdown will be required for each temp connection? Diversified
VA
Response
No boiler plant shutdown is needed for any work being performed in this contract. Each temporary boiler connection will tie into the heating hot water loop in the building. The steam will be shut down in the buildings to allow for this tie in.
This can be isolated in the building where LOTO will be performed.
Can we perform a shutdown and internal and external inspection of all pipes to determine where the break is prior to starting work?
Diversified
VA
Response
No inspection of the inside of the manhole. That is why we want 100% of the pipe in the manhole replaced. There are no known leaks of the underground pipe.
5 Please identify existing waterproofing system along with specifications (thickness). Midwestern
VA
Response
It is unknown. Excavation about 24 inches down on the north side of the manhole showed no signs of any water proofing on exterior of manhole.
Are we to apply the liquid waterproofing solution to the exterior of only (3) manhole walls?
a. The 4th wall will be difficult to access.
b. The pipes are located at different elevations of the (3) walls. Do we excavate only enough to replace the pipe, therefore, we only waterproof the portion of the walls that we excavate down to. Or is it necessary to excavate all the way beyond the (wall to floor joint), to waterproof the entire depth of the walls?
c. Do we apply waterproofing to the interior walls of the manhole?
Midwestern
VA
Response
A. The retainage walls were in place before the manhole was constructed. So, the East facing wall of the manhole should be able to be accessed for water proofing.
B. There is ground water entering the manhole. Its source is unknown. The expectation is that water proofing will be installed the entire height of the walls.
C. If there is a product that can be applied to the interior of the walls that will keep out ground water the VA will listen to that option.
7 Where do we drain water from the dewatering system? Midwestern
Response
Draining will be done to the storm water system. There are at least 2 storm water inlets in the grassy area to the south of the manhole. Dewatering will be done through silt bags.
8. How do we qualify/quantify what type of repairs are to be made to the existing manhole? Midwestern
VA
Response
There are no known repairs that need to be made to the structure of the existing manhole. If majors cracks or other issues are found, then those will be addressed by another project.
9.
How many concrete dead-man blocks are there to replace?
a. Is there (1) concrete dead-man on each of the (3) sides?
b. What size are they?
Midwestern
VA
Response
The exterior pipes to the south of the manhole are not being replaced, only the link seals around them. The only exterior pipes being replaced are those to the North and West. There is a dead-man on the North and West pipes. Their size is unknown.
Not defined on the Rovanco drawing set.
10. Is there a spot on site with power for contractor to put a temporary office Conex? Midwestern
VA
Response
Yes, there is a place for an office conex. See Q83 answer, yellow boxed area. No power is available there. Contractor will need to supply own power.
11. Request a 2-week extension on the bid-due date to allow piping manufacturer time to complete their estimates. Midwestern
VA
Response Amendment 0001, extended due date to 09/18/26 at 1:00PM EST
12. Please confirm that all pipe and fittings shall be of American manufacture Midwestern
VA
Response
Yes, all pipe, fittings and valves shall be American made. Note, all bolts used on steam and condensate pipe and fittings must meet newest VA standard.
13. Parking Access area. Please provide. Midwestern
VA
Response See Q83 answer, yellow boxed area.
14. Please confirm the type of sod to be utilized for the replacement areas. Midwestern
VA
Response Bahia
15. Please confirm the GC is not responsible for irrigation repair or additions. Midwestern
VA
Response
Confirmed that GC is not responsible for damage to sprinkler heads and shallow depth small lines. There are no known control valve boxes or larger irrigation pipes in area of the manhole. 6” irrigation main is near the covered walkway to the East.
16. Please provide the required sizes for the temporary boilers to service the areas appropriately. Midwestern
VA
Response
When a shutdown happened several years ago that isolated steam to these same buildings the boilers used then were a Lattner, S165 LW (16.5 HP) for B71 and a TB-209 (27.5 HP) for B101.
17. Are there any restrictions for shutting down the roadway for material deliveries? Midwestern
VA
Response
Yes. Roadway shutdowns require a form to be filled out and a 2-week notification to the facility. DOT signage is required as well.
Even for offloading materials that will take less than 10 minutes, four things need to happen. Not during heavy traffic hours (0630 to 0900, 1500 to 1700), flaggers to direct traffic (one both ends of truck), off-loading on non-major roads, coordination with VA construction safety engineer for request to be filled out.
18. Please confirm the VA will handle all maintenance of temporary equipment for the CLC. Midwestern
VA
Response
The VA will be responsible for adding fuel and DEF (if required) to the generators only. All other Preventive maintenance and emergency maintenance for the generators and boilers are the responsibility of the GC.
19.
What the concrete design is for the dead-man, picnic table slab, and the wall section restoration. This is a Bid build not design build so who is responsible for this?
Midwestern
VA
Response
The dead-man design would be done by Rovanco. They will be replaced in kind. Picnic table slab will be replaced in kind.
Picnic table slab is 12-foot square, 4” thick 3000 psi concrete with welded wire mesh reinforcement throughout and a light broom finish. For wall section repair see answer to Q76.
20. Please provide the elevation of the water table. Is there a Geotech report for this project? Midwestern
VA
Response
The manhole is 10 foot deep. The water table is above this depth. No Geotech report has been produced.
21.
Drawing LP302 shows 3000 psi concrete for a wall. I don’t know if it’s the wall we are restoring. The few dimensions shown do not match what I saw on the walk through. Can the VA confirm any of these dimensions?
Midwestern
Response
Drawing provided for retaining wall was not correct. See attached drawing “wall overhead and detail”
22.
None of the drawings provided in the solicitation are complete.
Does the VA know how deep the wall is. The manhole appears to be 10’ deep (I had to scale it). If the wall is that deep, we will need to include a dewatering system for the wall as well as the manhole. Can the VA provide better drawings, or provide dimensions, for the wall and manhole?
Midwestern
VA
Response
Manhole is 10’ deep x 12’x12’. The provide drawings are the only ones available for the manhole. Wall is not that deep. See answer for Q76 with wall details.
23.
Please confirm whether a separate cross-section/detail sheet for the masonry retaining wall referenced in SOW Item 31 exists beyond the single LP3.02 'Hardscape Details' sheet provided, and whether a specific VA masonry specification section applies to this scope.
Section 00 01 15, List of Drawing Sheets
(LP3.02, descriptive appendix naming);
SOW Sec. Leak Repair, Item 31 (masonry restoration)
NAPC HSCC JV
VA
Response See attached drawing “wall overhead and detail”
24.
SOW Item 27 requires the contractor to perform a utility survey (ground-penetrating radar) before excavation. Can the Government provide any existing GPR or utility survey data for this area as Government-Furnished Information, or must the contractor commission a new survey at its own cost?
SOW Sec. Leak Repair, Item 27 (utility survey) NAPC HSCC JV
VA
Response New survey must be completed.
25.
Please confirm the required labeling/marking standard for the underground high-pressure condensate pipe segments that are being labeled, marked, and abandoned in place rather than replaced.
SOW Sec. Leak Repair, Item 3.d (abandoned
HPC piping)
NAPC HSCC JV
VA
Response
Pipes will be labeled by VA staff where they exit the ground and enter buildings. No need to label any underground pipe being abandoned in place.
26.
Given the proximity of the work area to occupied patient buildings (71/101) and limited on-site space, can the Government identify a specific staging/laydown area authorized for this project, including secure storage for the long-lead Rovanco pipe pending installation?
Specification 01 00 00, Sec. 1.6 Operations and
Storage Areas
NAPC HSCC JV
Response See Q83 answer, yellow boxed area.
What is the expected lead time for contractor personnel badging and any required background checks/PIV credentialing prior to mobilization, so this can be reflected in our proposed schedule?
Specification 01 00 00, Sec. 1.5 Construction
Security Requirements
NAPC HSCC JV
VA
Response
30 to 60 days is what has been advised from other COR’s who have recently done this.
28.
Please confirm the 10-calendar-day payment/performance bond submission window in Item 11 runs from the date of contract award (not Notice to Proceed) and clarify whether NTP can be issued concurrently with bond review or only after bonds are approved.
Instructions to Offerors, Item 11
(Bonds)
NAPC HSCC JV
VA
Response
The ten-calendar-day window begins on the date the award is granted. The Notice to Proceed (NTP) will be issued following the Preconstruction meeting and bonds review.
Please confirm whether the completed 'Pre-Award Contractor Safety and Environmental Record' form alone satisfies the EMR submission requirement, or whether a separate statement on the insurance carrier's letterhead confirming the current EMR must also be included.
Instructions to Offerors, Item 13;
Factor I, Item 6 (EMR)
NAPC HSCC JV
VA
Response
This solicitation require only the completion of “Pre-Award Contractor Safety and Environmental Record Form “
Specification 33 63 00 requires that daily installation reports for the direct-buried steam/condensate pipe system be reviewed, signed, and sealed by ‘the Professional Engineer responsible for the system installation.’ Please confirm whether this PE must be employed by the pre-engineered pipe manufacturer (e.g., Rovanco or an approved equal), or whether a Professional Engineer retained by the installing contractor/subcontractor satisfies this requirement
Specification 33 63 00, Steam Energy
Distribution, Sec.
3.7.H.3 (Direct-Buried System Installation — Report Certification)
NAPC HSCC JV
VA
Response PE by the pre-engineered pipe manufacturer suffices.
The Rovanco product literature included in the solicitation states that an alternate/equal direct-buried pipe manufacturer's technical data must be certified by an independent testing agency and submitted to the engineer at least 10 calendar days prior to the bid due date to be approved as an equal. Please confirm this 10-day pre-bid submission deadline and process still apply under the current solicitation schedule and confirm to whom (Contracting Officer or design engineer of record) this submittal must be directed.
Rovanco Insul-800 “Standard
Specifications” (Approved Vendors section, included in the solicitation's Rovanco shop-drawing attachment);
Specification 33 63 00, Sec. 1.5.U
(manufacturer-sealed system design)
NAPC HSCC JV
VA
Response
Due to the amount of pipe being replaced this requirement does not apply. The replacement pipe sections shall be ordered from Rovanco and a Rovanco representative shall be on site during installation to confirm proper installation.
Specification 33 63 00, Sec. 2.2.X requires a waterproof membrane between the manhole's mud slab and floor slab, continuing up the sidewalls, but the solicitation's specification table of contents does not include a Division 07 (Thermal and Moisture Protection) section specifying the membrane material, surface preparation, application method (sheet vs. liquid-applied), or warranty requirements for the existing manhole interior. Please confirm whether a waterproofing membrane specification section applies to this scope and, if so, provide it; if none applies, please specify the required membrane type and performance criteria so offerors can price this item consistently.
Specification 33 63 00, Steam Energy
Distribution, Sec. 2.2.X (Reinforced Concrete Manholes); Section 00
01 10, Table of Contents (no Division 07 section included)
NAPC HSCC JV
VA
Response
There is no way to follow specification 33 63 00 Sec 2.2.X due to this work being done on an existing manhole. No Membrane specification section will be provided for this scope. Membrane material shall be liquid applied only. It shall be a waterproofing material that can be applied over existing. Investigation (24-inch-deep excavation on north side of manhole showed no water proofing on manhole exterior surface.
33.
A sign-in sheet was used to document attendance at the 08/13/2026 site visit. Please confirm whether the Government will provide/distribute this sign-in sheet — e.g., as an attachment
Part I — General Information, Item 3
(Site Visit)
NAPC HSCC JV
to a solicitation amendment — so all attending firms have a record of which other firms and subcontractors attended.
VA
Response It was provided as an attachment, in amendment 0001
34 Can the Government identify a specific staging/laydown area authorized for this project
Specification 01 00 00, Sec. 1.6 Operations and
Storage Areas
NAPC HSCC JV
VA
Response See Q83 answer, yellow boxed area.
Please confirm all nine sheets listed in Appendix C were included in the as-built package provided.
Section 00 01 15 List of Drawing Sheets, Appendix C (as-built sheet list)
NAPC HSCC JV
VA
Response Yes, the document title” ASBUILTS-516-26-117” has 9 pages
36 Please clarify if the SSHO will need to be dedicated and full-time on site. Double Bar Const
VA
Response NO
37 Please clarify if the Project Manager will need to be full-time on site. Double Bar Const
VA
Response Yes, it needs to be fulltime
38 Please clarify if the Quality Assurance Manager is required to be full-time on site. Double Bar Const
VA
Response No
39 Please provide all available as-built drawings and existing utility drawings available. Double Bar Const
VA
Response
All as-built drawings for the manhole, steam pipe and retention wall that are available have been provided. New wall information has been provided. See Wall overhead and details and Utility Map PDFs. Snip of combined utility drawings is attached. “Utility map”. Note it is greater than 15 years old and does not show the steam lines in this area. It cannot be assumed to be accurate. GPR must be done.
40 Will the VA provide any existing GPR, utility locations, or subsurface utility engineering information? Double Bar Const
VA
Response
No, responsibility of the GC to supply new utility locate information. Only available utility drawing is attached.
41 Please provide any available geotechnical reports and groundwater information for the project area. Double Bar Const
VA
Response No available. See answer to Q20.
Please confirm that the VA is responsible for refueling generators, filing with Diesel Exhaust Fluid (DEF), and checking the oil levels for the project duration.
Double Bar Const
Response Confirmed. This is the extent of the work VA will do.
43 Please confirm that the contractor will be responsible for routine maintenance on the generators.
Double Bar Const
VA
Response
Confirmed. The contractor will be responsible for routine maintenance on the generators.
Please clarify if there is any hazardous material in old pipes, insulation, concrete, and fittings. Double Bar Const
VA
Response
Current manhole was built in 2013-time frame with new pipes and insulation. Hazardous material was longer allowed per VA spec by then.
45 Do any of the existing spaces contain asbestos or hazardous material? Double Bar Const
VA
Response
Mechanical rooms in Building 71 and 101 might contain hazardous materials. However, the connection points for the boilers do not require and material being disturbed.
LP302 hardscape sheet carries 5 separate details retaining wall, seat wall, knee wall with decorative fencing, security bollards, and the planter with no site plan, no keynotes, and no station limits tying any of them to a location. SOW Item 31 "rebuild masonry wall south of manhole." Our read is that the Retaining Wall Detail governs. Please confirm this. Even with the detail confirmed, the sheet gives us no length, no exposed height, and no top of wall elevations, so there is no defensible way to estimate the CMU, footing, or reinforcing.
Double Bar Const
VA
Response
Incorrect drawing was provided. See Wall overhead and details
PDF.
47 Please Confirm which LP302 detail governs the Retaining Wall or Knee Wall. Double Bar Const
VA
Response
Incorrect drawing was provided. See Wall overhead and details
PDF.
48 Please provide total length of wall to be rebuilt, and exposed height at each end. Double Bar Const
VA
Response
See Wall overhead and details PDF.
49 Please provide existing finish: CMU color and texture. Double Bar Const
See Wall overhead and details PDF.
Please provide reinforcing callouts, bar size, and spacing.
Assume 4,000 psi concrete, ASTM A615 Grade 60 rebar and 2,000 psi CMU.
Double Bar Const
VA
See Wall overhead and details PDF. Assumptions are correct.
51 Please provide quantities for Item 25. sidewalk repairs and picnic table pads Double Bar Const
VA
Response
Quantity of sidewalk repairs is unknown. It will be a function of what is damaged by contractor during work, moving equipment and material across them. Picnic table pad that needs to be removed is 12-foot sq, 4” 3000 psi concrete reinforced with welded wire mesh throughout and a light brush finish. Picnic table is to be removed and saved for reuse. Responsibility of GC to reinstall picnic table. It must be bolted down.
52 Please provide the depth of the foundation for the retaining wall Double Bar Const
See attached drawing “wall overhead and detail”
Scope of work says All HPS and PC piping is being replaced, then says 6 ft of manhole or anchor point, please clarify which one it is.
Double Bar Const
VA
Response
All HPS and PC pipe inside manhole is to be replaced. Also, underground pipe to the North and West to 6’ outside manhole to be replaced.
If we have a PPQ, requested for another opportunity, that is less than 12 months old, can we use it within our proposal? Or will a new PPQ need to be requested?
Double Bar Const
VA
Response IF the PPQ is less than 12 months it can be used.
55 What Size Temporary boilers will be needed? Abrams Group Construction, LLC
VA
Response
When a shutdown happened several years ago that isolated steam to these same buildings the boilers used then were a Lattner, S165 LW (16.5 HP) for B71 and a TB-209 (27.5 HP) for B101
56 How Close can we set Boilers to temporary connections, or will we need to make Taps for temporary connections? Abrams Group
Construction, LLC
VA
Response
Temporary connection points are cam lock fittings. Hoses shall run from boilers to these cam lock’s locations. It is desired that at the end of this project these cam lock hoses are left for the VA.
57 How Close can we set the generators to the boilers? (Power Cable length) Abrams Group
Construction, LLC
VA
Response
For both buildings it is about 90 feet of distance from generator location into mechanical room where boilers will be.
The solicitation says plan for 2 sets of lines into and out of the manhole, we are assuming between the building, and the manhole is one direction which of the other 2 directions would you think is leaking? Sheet 1 of 9 Drawing 7828 section AA or section BB?
Abrams Group Construction, LLC
VA
Response
Cross section AA pipes are not being touched by this project.
The pipes to the north (cross section BB) and to the West (cross section CC) are being replaced.
Please clarify how much laydown area will be available adjacent to the steam manhole to accommodate daily operations and minimize transits from laydown at rear of campus to worksite during peak patient and staff presence around the worksite.
Please identify the location for daily work stock laydown area adjacent to worksite.
CPS
Response See Q83 answer, yellow boxed area.
60 Please clarify if the steam manhole work are and fenced access routes are required to be fenced with privacy screens. CPS
VA
Response
Yes, privacy screens are desired for the area around steam manhole. Fence around laydown to the west (yellow box in drawing for Q83 answer) does not need privacy fence.
Please clarify if the cross sidewalks that run east and west on the south side of the steam manhole be closed to allow unrestricted access to the steam manhole site work site from the street? Can this access be fenced off by contractor for patient and staff safety reasons?
CPS
VA
Response See Q83 answer, yellow boxed area.
Please clarify where the nearest allowable parking adjacent to the steam manhole site is, and how many spaces will be allowed for construction vehicles given that the nature of the work will be heavy tool and equipment driven.
CPS
VA
Response See Q83 answer, yellow boxed area.
Instructions to offerors Factor 1 Technical / Management has a 5-page maximum. Please consider increasing page limit to 10 pages.
CPS
VA
Response Yes, allowed increasing page limit to 10 pages.
Instructions to offerors Factor 2 Specialized Experience has a 5-page maximum. Please consider increasing page limit to 10 pages.
CPS
VA
Response Yes, allowed increasing page limit to 10 pages.
65 Please clarify project work hours, standard work hours or WHEN hours CPS
VA
Response
This project can work during normal hours COR (or other FMS representatives) are on site, 0630 to 1700 M-F. Earlier then 0630, later than 1700 or weekends hours can be arranged with planned coordination from GC to COR. If excessively loud or dusty work must be done that work shall be coordinated to ensure it does not happen between 0800 and 0430 M-F.
Factor II defines similar scope as “a project to repair buried jacketed high pressure steam piping and or condensate system(s).” Will the Government consider projects involving high-pressure steam and/or condensate piping systems that demonstrate comparable mechanical complexity, trade coordination, outage planning, testing, and work within an active healthcare environment, but that do not specifically involve buried jacketed piping?
AMERITECH
VA
Response
Yes, projects involving those types of systems will be considered.
Factor II defines similar size as “a high pressure steam/condensate piping repair contract valued greater than $3M” and states that all submitted project experiences must meet this requirement. Does the greater-than-$3M threshold refer to the total value of the submitted construction contract/project, or
AMERITECH
must the high-pressure steam/condensate piping portion of the project itself exceed $3M?
VA
Each submitted project must be higher than $3M.
Will the Government consider a project valued below $3M when the project otherwise demonstrates highly relevant or directly comparable high-pressure steam/condensate piping scope and complexity, and if so, will the project be evaluated based on its degree of relevance notwithstanding its lower contract value?
AMERITECH
VA
Response
No, Magnitude of this project is between $5,000,000.00 and $10,000,000.00
Factor II addresses project size, scope, complexity, and performance within a healthcare environment. Will the Government consider projects that are highly relevant but do not satisfy every stated characteristic, such as a highly similar high-pressure steam/condensate piping project performed in an active healthcare environment but valued below $3M, with the degree of similarity considered as part of the Government's relevancy evaluation?
AMERITECH
VA
Response
No, Magnitude of this project is between $5,000,000.00 and $10,000,000.00
Factor II defines similar scope as repair of buried jacketed high-pressure steam piping “and or condensate system(s).” Can the Government confirm that an example project is not required to include both high-pressure steam piping and condensate piping and that a qualifying project involving either high-pressure steam piping or condensate piping may be considered
AMERITECH
VA
Response
That is confirmed. Example projects involving either high-pressure steam piping or condensate piping may be considered
May an individual completed task order, phase, or discrete scope performed under a larger IDIQ, BPA, MATOC, or similar contract be submitted as an example project under Factor II and/or Factor IV, and if so, will the Government evaluate the value and scope of the individual task order/phase or the value and scope of the overall parent contract when determining relevancy
AMERITECH
VA
Response The Government will evaluate the individual task order value.
Factor IV states that past performance examples may be the same projects submitted under Factor II or different projects and that at least two projects must involve the same or similar work described in the solicitation. Must projects submitted under Factor IV independently satisfy Factor II's Specialized Experience requirements, including the greater-than-$3-million size criterion and buried jacketed high-pressure steam/condensate piping scope, or will Factor IV projects be evaluated for relative similarity in size, scope, and complexity without being required to satisfy each Factor II threshold?
AMERITECH
VA
Response
Factor II is Specialized Experience and the evaluation criteria for experience: The information provided will be used to evaluate the relevancy and depth of each Offeror’s specialized experience.
The more recent and relevant experience, the more credit will be given.
The Government will place greater importance on projects performed as a prime contractor than as a subcontractor.
The Government will place greater importance on projects that were performed at a VA HEALTHCARE ENVIRONMENT, depending upon overall role and relevant considerations.
Factor IV is Past Performance evaluation will consider the recency and relevancy of the past performance submissions and Offerors will be assigned an overall confidence rating based on the Government’s expectation the Offeror will successfully accomplish the current requirements
The solicitation requires offerors to provide completed Past Performance surveys and/or CPARs under Factor IV; however, the provided PPQ instructions direct the reference to submit the completed questionnaire directly to the Contracting Officer. If a PPQ is submitted directly to the Contracting Officer by the reference in accordance with the PPQ instructions, will that PPQ satisfy the Factor IV submission requirement even though the completed questionnaire is not included in the offeror's proposal?
AMERITECH
VA
Response
THEY CAN BE SUBMITTED TO CONTRACTING OFFICER
OR SUBMITTED AT THE SAME TIME AS THE PROPOSAL
EITHER WAY WILL BE REVIEWED.
Two different Past Performance Questionnaire forms were provided with the solicitation package and contain different information and evaluation criteria. Which PPQ form should offerors use for this solicitation, or is the Government requiring references to complete both forms for each submitted past performance project?
AMERITECH
VA
Response
A WORD FORM AND A PDF FORM WERE PROVIDED, NO
PREFERENCE IN WHICH FORM IS COMPLETED JUST
NEED TO COMPLETE ONE FORM.
When a reference submits a completed PPQ directly to the Contracting Officer, is the offeror required to include any portion of that PPQ in its Factor IV proposal submission, such as the contractor-completed project information pages, or should the offeror simply identify the corresponding project and reference in its Factor IV narrative?
AMERITECH
VA
Response
The government is requesting one PPQ; it can be provided by offeror or reference. It is up to the contractor how to reference the PPQs in factor 4.
Factor IV requires completed Past Performance surveys.
Depending on the Government’s responses to the questions above, may offerors submit previously completed PPQs for relevant projects as part of their proposals, and may available CPARS evaluations be submitted in lieu of newly completed PPQs?
AMERITECH
VA
Response
IF PPQs ARE LESS THAN 12 MONTHS OLD AND HAVE
SIMILAR SCOPE OF WORK AND MAGNITUD THAT OUR
PROJECT YES, THEY CAN BE SUBMITTED.
Can the VA provide an exterior site plan detailing the orientation of the existing retainage wall that was in place?
a. Can the VA provide an existing irrigation drawing to prevent potential disruption?
b. The Google Earth image details a curve
Valor Construction configuration. Is this to be installed as per original design?
a. There are no known control boxes or irrigation mains around steam pit or wall. There will be shallow depth small diameter pipe and sprinkler heads. VA will be responsible for installation of shallow depth pipes and heads. Coordination with plumbing shop during build back will allow VA to install what we want before area is sodded.
b. Yes, wall is to be rebuilt per original design as it is original to the historic building. See attached drawing “wall overhead and detail” for updated wall rebuild details.
Steam Manhole
2. The SOW details approximately 6’ beyond manhole to be excavated. The area towards Bldg 1 currently has a retainage wall within the 6’ area, including an Anchor Concrete pad that will hinder excavation.
a. Due to the HPS currently dispersing in the manhole is the VA concerned of any damage to the interior structure of the manhole and will require an assessment upon Steam shutdown?
b. Will the VA request a complete replacement of the concrete structure if interior damage is sustained?
c. Is the VA to request the existing manhole covers to be replaced with new?
d. Is the Contractor to remove a portion of the retainage wall & shrubbery to access this point?
Valor Construction e.
There are no underground steam lines that enter or leave the manhole on the East side where this retainage wall is. Pipes enter and exit the manhole on the North, West and South sides.
The East side of the manhole will only be exposed to apply waterproofing.
a. No damage of the inside of the manhole is known. If some is found once steam is off that will be addressed at that time.
b. Not possible to answer at this time. Depending on too many unknown factors.
c. No, manhole lid does not need to be replaced. If lid is removed by project to replace interior piping, it must have proper sealing system installed when reinstalled.
d. No, there is thought to be enough room to fully excavate the East side of manhole to waterproof it without damaging retainage wall. Wall was in place before manhole was installed. Any shrubs removed in the area of the manhole for access and underground work will need to be replaced in-kind.
The SOW & Site visit concluded Rovanco will determine the amount of total pipe that needs to be ordered. Will exploratory excavation be required prior to Rovanco’s determination on the length of piping to replace so that contactors can factor this into our bid proposal
Valor Construction
VA
Response
Bid should be made for 6 feet of underground Rovanco pipe to be replaced for steam and condensate pipes into and out of manhole from the North and West only. One steam pipe goes into manhole from north, two team pipes leave manhole (1 to south, 1 to west). Pumped condensate comes into manhole from west (1) and south (1). High pressure condensate comes into manhole from the south (1). The high-pressure condensate return pipe that leaves the manhole to the north is being abandoned and does not need to be replaced. Its link seal does need to be replaced. All link seal pipes need to be replaced for pipes entering / leaving the manhole.
80 Can the VA provide a one-line diagram detailing the location of the Manhole sump pump panel location for reference? Valor Construction
VA
Response
The sump pump panel physical location is currently on the SE corner of the manhole. Are you asking for the power one-line diagram for the sump pump power panel. The breaker that feeds panel is known, so power can be isolated. Otherwise, power panel diagram is not available.
81 Is all Steam Shutdowns to be coordinated on a weekend schedule or during the week with VA staff present? Valor Construction
VA
Response
Shutting steam off would best be done on a weekday. The outages to connect the boilers to the two buildings of the CLC is best done on a weekday so there is support available for starting up these temporary boilers. All shutdowns need to be communicated to the facility and will need to be planned ahead of time with two weeks’ notice. Va staff will close the valves and add their LOTO lock to the valves to ensure no start-ups happen without notification. There will be one outage of steam supplied to the manhole. This will be done on a weekday as well.
Will the VA request a storm drainage cleaning as the current condensate overrun is run to the nearest Storm drain Valor Construction
VA
Response
No, storm drainage cleaning is not required by this project, unless dewatering systems silt bags fail. All storm inlets that could be impacted by excavation area need to be protected from run off.
The VA highlighted the potential for (2) Construction Staging Areas throughout the construction phase:
a. Can the VA provide a site plan detailing the location for a Connex or material storage?
b. Will the VA allow Excavation equipment to remain in the work area directly adjacent to the Manhole during the construction phasing?
Valor Construction
VA
Response
See image on next page. Pink box is where steam pit is. Yellow box is area where laydown area can be for Conex, material storage, personal vehicle parking and other storage. Va would not want entire yellow boxed area used for lay down, just what vendor needs. Yes, excavation equipment, some material, and a truck or two can be in grassy area around the manhole. Green boxed area indicates maximum area allowed for laydown in this area. There are two storm water inlets inside this green boxed area. These need to be protected during the entirety of this project from silt entering storm system. There are also trees inside these proposed laydown areas. These will be protected to their drip lines by fencing to prevent the roots being damaged.
All areas need to be fenced. 6’ tall chain link and parallel locks (one being VA provided padlock). Privacy cover is only required on green fenced area.
| PROJECT TITLE: BB Repair Steam Piping in Manhole Near Building 1 |
| PROJECT NUMBER: 516-26-117 |
| See attached document: Wall overhead and details. |