Amendment 0001 Attachment - RFI Log - Questions and Answers - 36C24826Q0393.pdf

PDF 232 KB Posted

Attached to
Z1LZ--FY26: STATION (PROJ: N/A) BB Repaint all curbs crosswalks and roadway markings
Solicitation number
36C24826Q0393
Issued by

About this file

This is an RFI Log documenting questions and responses for a VA Station facility improvement project involving the repainting of all curbs, crosswalks, and roadway markings. The RFI log covers eleven question-and-answer entries received between March 12-18, 2026, addressing project scope, scheduling, and operational requirements.

Key project details include: a 90-calendar-day performance period from Notice to Proceed (not subject to extension per the VA); seven distinct work phases covering various parking areas and roadways across the facility; surface preparation is not required, though work carries a one-year warranty; and payment is made upon work completion and invoice approval by the Contracting Officer Representative (COR). The work must be executed during nights, weekends, and off-peak hours to maintain continuous emergency vehicle access and minimize disruption to the 24/7 healthcare campus operations. Contractors must provide their own power source for additional lighting beyond existing facility lighting and may use only one designated staging area (Lot 23) for material and equipment storage. Scheduling submissions with approximate dates require at least three days' advance notice to stakeholders. The project incorporates seven phases: Main Entrance and ER Parking (Phase 1), Cancer Center Parking Lot (Phase 2), CLC and Building 10 Parking Lots (Phase 3), Buildings 4, 16, and 12 Parking Area including MRI (Phase 4), Perimeter roads, Roundabout, and designated lots (Phase 5), Employee Parking (Phase 6), and Building back sides and dock areas (Phase 7), with detailed phase mapping provided in Amendment 0001 Attachment—Site Layout.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI LOG

FY26: STATION (PROJ: N/A) BB Repaint all curbs crosswalks and roadway markings

03/13/2026

RFI

Number

Question VA Response

Reference Sheet, Section of Detail

Dated Received

1Q: Will payments be made after the completion of every phase of the striping?

03/12/2026

1R: VA Response: Vendors can be paid as work is completed and invoices are approved by the COR.

03/16/2026

2Q: During the site visit, it was said the repainting of the wheel stop curbs are part of the SOW. Please confirm as it is not stated on the statement of work.

2R: VA Response: It is stated clearly on the SOW Part D. Section D of

SOW

03/16/2026

3Q: Please provide a map identifying all phases of work associated with the Combined Synopsis/Solicitation. It was said during the site visit we weren’t to do any work within the parking lot near the construction of the fisher house.

3R: VA Response: COR will provide, and no work required on the construction area, see SOW for specified Phases.

Phase 1: Main Entrance Parking level and next to ER Parking.

Phase 2: Cancer Center Parking Lot Phase 3: CLC and Bldg 10 Parking Lots Phase 4: Bldg. 4, 16 and 12 Parking Area (MRI included) Phase 5: Perimeter roads, Roundabout, Ramp and parking areas Lot 12, 23, 17, 10, 21, 22, 11 Phase 6: Employee’s Parking areas Phase 7: Back sides of buildings, Lot 14, Dock 6, 11, 9 areas

See “Amendment 0001 Attachment - Site Layout”.

Section C of

SOW.

Amendment Attachment - Site Layout

03/18/2026

4Q: The SOW says to simply provide 1 paint coat, will any surface preparation be required?

4R: VA Response: Not required, however, the warranty of work is for 1 year.

03/16/2026

5Q: Will the VA be opened to allowing any day time work to complete any repainting related to the project?

5R: VA Response: Work shall be nights, weekends, and off-peak hours as required to minimize disruption.

Maintain continuous emergency vehicle access at all times.

Section E of

SOW

03/16/2026

6Q: How much lead time is required to notify onsite VA contacts to ensure access to an area or to have a non-critical area closed/coned off?

6R: VA Response: Scheduling must be submitted with approximate dates, at least 3 days notification time for stakeholders knowledge and coordination.

03/16/2026

7Q: Given the 90-day project window, we require certain areas to be vacated and free of all vehicles to complete the specified phases on schedule. Will we have the VA's full cooperation in ensuring these areas are cleared?

7R: VA Response: This project has been structured to support a fully operational, 24/7 healthcare campus, with an emphasis on patient safety, emergency access, and minimal disruption to daily medical operations. To maintain VA operations, Work shall be nights, weekends, and off-peak hours as required to minimize disruption. Maintain continuous emergency vehicle access at all times. Coordinate daily work limits and access routes with VA Facilities and the COR. Install and maintain temporary barricades, cones, signage, and flagging as required. Phase work to keep parking and circulation operational wherever possible. Restore work zones to a safe, usable condition at the end of each shift.

See section B, E and F of

SOW.

03/16/2026

8Q: A large portion of this work must be completed at night. Will we have continuous access to onsite electrical supplies, or will we need to provide our own power source?

8R: VA Response: VA property is well lit at nighttime, if additional light is needed, contractors must provide their own power source.

03/16/2026

9Q: Would it be possible to revise the project completion timeframe to 150 calendar days instead of 90 calendar days from the Notice to Proceed?

9R: VA Response: The period of performance for this project is 90 days and not planned to be increased at this time.

03/16/2026

10Q: Since the work will be performed throughout various areas of the site, will multiple staging areas be designated for material and equipment storage?

10R: VA Response: No. Just one area will be given if required by lot 23.

03/16/2026

11Q: Can you provide a map describing the breakdown of the 7 phases?

11R: VA Response: See response 3R.

See “Amendment 0001 Attachment - Site Layout”.

Amendment Attachment - Site LayoutA

03/18/2026