This document is a Scope of Work (SOW) for Project #516-23-604, focused on installing temporary shoring in the crawl and basement space of Building 1. The infrastructure project is specifically for structural repairs in critical areas, with construction documents signed and sealed by an engineer of record. The project requires the construction contractor to complete temporary shoring during construction and arrange for special inspections by a Florida PE Certified Special Inspector. The total project completion time is 90 calendar days from the receipt of the Notice to Proceed.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope Of Work/SYNOPSIS:

a. Project # and Title: 516-23-604, Install Temp Shoring in Crawl Space at Building 1

b. Description of project: This project is an infrastructure project specifically for the structural discipline. This project is for the structural repairs of critical areas in the crawl and basement space of Building 1. Construction documents signed and sealed by an engineer of record for the repairs to the critical area are provided as part of the scope. The repairs, temporary shoring during construction, and special inspections (from a Florida PE Certified Special Inspector) are required for this project as part of the construction contractor's responsibilities.

c. Completion time: 90 calendar days from receipt of Notice to Proceed.