Y1DA | 521-24-102 | Renovate Wards 2K and 2B for Optometry/Ophthalmology Clinical Use
Solicitation number
36C24726R0134
Issued by

About this file

This document is a Consolidated Requests for Information (RFI) and Addendum #1 for a federal construction project to renovate Wards 2K and 2B at a VA Medical Center (Project 521-24-102, Solicitation 36C24726R0134). The project is a negotiated best-value Request for Proposals with a 365-calendar-day performance period beginning November 1, 2026, and concluding November 1, 2027. The contract includes phased construction work requiring coordination with the VA and multiple divisions covering structural, mechanical, electrical, and low-voltage systems (Divisions 26, 27, and 28).

Key requirements include: mechanical work with new HVAC equipment and ductwork; electrical systems including new panelboards, seismic bracing for non-structural elements, and VFD-rated cabling; telecommunications infrastructure with CAT6A cabling, fiber-optic backbone runs, and wireless access points; fire alarm integration with existing Edwards systems; security systems including access control, CCTV cameras, and duress buttons; nurse call system expansion; public address system extension; and coordinated infection control (ICRA Level IV) containment during phased demolition and construction. The VA will provide certain equipment including televisions, BAS/DDC system access (Johnson Controls), and some VA-furnished clinical equipment designated as "VV" (VA-furnished and VA-installed), while contractor-furnished items are designated "CC" and VA-furnished contractor-installed items as "VC." Critical coordination points include work hour restrictions (8:00 AM–4:30 PM weekdays for normal work, with after-hours restrictions for occupied adjacent spaces), elevator usage requiring VA approval, asbestos abatement per drawings ASB-01 (dated 05/15/2026), and compliance with NFPA Type II (222) fire-resistance ratings. The proposal due date is November 12, 2026, at 1:00 PM Eastern Standard Time. The wage determination is General Decision AL20260087 from May 18, 2026, and the general-construction limitation on subcontracting applies under NAICS 236220.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Consolidated Requests for Information

Renovate Wards 2K and 2B | Project 521-24-102 | Solicitation 36C24726R0134

ADDENDUM #1

AE Fim responses in Green

VA Engineering Responses in Blue

VA Contracts responses in Red

CPS, Inc.

1. Please clarify if the roof within the proposed work area is still under warranty. If so please provide roof warranty company and point of contact.

Roof within proposed area is not under warranty.

2. During the site visit, contractors were not permitted to take photographs of the existing conditions. To assist with preparing an accurate and complete bid, please provide photographs of the common areas and typical exam rooms included in the scope of work.

No.

3. If the contractor is responsible for furnishing televisions, please provide the required quantity, screen sizes, manufacturer or approved specifications, and any requirements for healthcare-grade or commercial-grade displays..

VA Will provide all Televisions once work is complete.

4. Will the VA furnish any materials, such as Cat6A cable, fiber-optic cable, keystone jacks, faceplates, patch panels, patch cords, connectors, and related termination hardware, or is the contractor responsible for furnishing all materials required for a complete and operational installation?

AE REPLY: Contractor to provide (furnish and install) all required materials per the drawings. If questions arise due to ongoing separate EHRM project and current contract VA to provide direction.

BIC and YES Electric LLC

1. Work hours. The Statement of Work §5 states 8:00 AM–4:30 PM Monday–Friday.

GI002 (Construction Period Staging of Work) sets an 8:00 AM–6:00 PM shift and places the following after hours (6:00 PM–6:00 AM weekdays, 8:00 AM–5:00 PM weekends): all work in adjacent occupied spaces, all work requiring system shutdowns, all concrete or metal-deck coring/cutting/drilling, powder- actuated fasteners, and all impact noise. E001 note 11 restricts any task that exposes active bus, including removing the cover of any panelboard, to 11:00 PM–5:00 AM with three weeks' notice and Medical Center Director approval. Please confirm which governs, and specifically whether (i) adding or removing breakers in an existing energized panelboard, (ii) all concrete coring and anchor drilling, and (iii) Phase I work adjacent to the occupied 2B clinic must be performed after hours.

AE REPLY: Statement of Work prevails, but also VA needs to clarify their preference on i, ii, iii.

2. Outage notice and energized-work approval. Notice periods differ: 7 days (01 00 00 1.6.L.2), 15 days for "major" interruptions (1.6.L.4), 14 days (SOW; 27 05 11 3.1.C.2.a), two weeks (E001 notes 17 and 18), three weeks with Medical Center Director approval (E001 note 11). Please state a single notice period for (a) branch-circuit outages confined to the construction area, (b) outages affecting occupied areas or any Life Safety/Critical/Equipment-branch panel, and (c) energized-work permits, and confirm whether Director approval applies to every panel-cover removal or only to energized work as defined by NFPA 70E.

AE REPLY: Approval needed for energized work.

3. Phasing of Room 2206 distribution and Mechanical Room 2228. New panels L22C- A/B, C22C-A/B and PPHT1A in Room 2206 and AHU-101 in Room 2228 serve both wings, and 2B remains an operating clinic through Phase I (GI102 note E; EPD102 note D). Please confirm that Room 2206, Room 2228/AHU-101 and the feeders from G208 and 3301 are constructed and energized in Phase I, and identify what existing or temporary power and HVAC keeps 2B in service until Phase II.

AE REPLY: See electrical phasing plan EPP001 added as part of Addendum #1

4. Elevator, hoisting and laydown. 01 00 00 1.19.A prohibits use of existing elevators and requires an outside hoist; 1.19.B permits "Elevator No. 5 ... between the hours of ______" (blank). Please confirm (a) whether an elevator is available to the contractor and its hours, (b) the designated material and debris route to 2K/2B, (c) whether an exterior hoist is required, and (d) the location of any on-site laydown/storage.

AE REPLY: Drawings note contractor to coordinate any elevator usage with VA prior work. VA to advise if use of elevator/s will be allowed and to specify which elevator will be allowed to be used by the contractor.

5. Sheets stamped "REVIEW ONLY – NOT FOR CONSTRUCTION" and asbestos quantities. Sheets ASB-01, S000–S300, P001–P602 and M001–M702 in Attachment 9 carry that notation; ASB-01 is dated 03/16/2026 and its key plan reads "BLDG 1 PHASING TO BE DETERMINED"; every ACM quantity in 02 82 11 1.1.B is blank.

Please confirm these sheets are contract documents for bidding and construction (or issue construction versions), fill in the 02 82 11 quantities or confirm ACM is limited to window glazing and exterior-wall brick waterproofing as keyed on ASB-01, and confirm the abatement contractor opens the new louver, duct and conduit penetrations in the exterior wall before other trades work there.

AE REPLY: See Addendum #1 specification update referencing ACM quantities to be obtained from the drawing ASB-01. ASB-01 ISUUE FOR BID is dated 05/15/2026, not 03/16/2026. The latter is 95% CD. ACM quantities should be obtained directly from the drawings (ASB-01).

6. Period of performance. The solicitation states 365 calendar days from NTP; the PCRA and ICRA permits (Attachments 10 and 11) show 11/01/2026–11/01/2028. Please confirm 365 days and that the permits will be re-dated.

Confirm 365 day per period, then dates will be reissued. I.E. 365 days 01 Nov 2026 – 01 Nov 2027, then the same period for 2028.

7. Coring, anchoring and shear-wall penetrations. GI003 note 26 requires X-ray before any coring (GI001 note 20 and E001 say "scan"); S000 C.18 prohibits openings or sleeves in slabs or walls not shown on the structural drawings without Structural Engineer approval; the special-inspection table requires continuous inspection of post-installed anchors by an owner-employed agency; MV102.x limits shear-wall penetrations to above door openings. Please confirm (a) GPR scanning is acceptable in lieu of X-ray,

(b) whether each conduit sleeve through an existing shear wall or floor slab requires SE approval and the expected turnaround, and (c) that the Government employs and pays the special-inspection agency.

AE REPLY: GPR is acceptable to be used in lieu of XRAY.

8. Seismic delegated design. S000 lists Seismic Design Category D with Ip = 1.5; 13 05 41 requires delegated design with stamped calculations for mechanical and electrical components, including suspended cables. Please confirm 13 05 41 applies to EMT raceway, cable tray, panelboards and suspended luminaires under Divisions 26/27/28, and whether a single delegated engineer retained by the prime may cover all trades.

AE REPLY: Per Specification 13 05 41 listed parameters, all non-structural building elements are required to receive seismic bracing by a certified professional, including items under Division 26/27/28. If contractor utilizes a single delegated engineer is considered “means and methods” from the standpoint of the AE.

9. Submittal and review durations. 01 33 23 1.10.D states 15 business days for submittal review and 10 for RFIs; 01 32 16.15 1.7.A.3 states not less than 20 work days. Division 27 submittals route to TVE-005OP3B/OIT (27 05 11 1.6.C; 27 51 16 and 27 52 23 1.8.A) and Division 28 to the four-stage 35/65/90/100 design-package review (28 13 00 1.4.E).

Please confirm the governing review period, whether early procurement submittals for switchgear, panelboards and lighting will be reviewed ahead of the full CPM approval, and the expected review duration for the Division 27/28 technical packages within the 365-day period.

AE REPLY: Standard VA review period is 15 days for submittals and 10 days for RFIs. VA to confirm if any deviation from this will be applied to this contract.

10. Proposal due time. SF1442 block 13a reads "1:00 pm EDT 11/12/2026"; daylight time ends 11/01/2026. Please confirm 1:00 PM Eastern Standard Time

- Proposal due date is confirmed as Nov. 12th, 2026, 1:00 pm Eastern Standard Time.

11. Critical-branch source for panel C22C-A. ED500 shows C22C-A fed from a 200 A breaker in switchboard FCGC (400 A) through a 150 A enclosed circuit breaker. E500 shows FCGC as 600 A frame/300 A with a 100 A breaker shared with C2GC/C21C/C23C/C24C through a tap, and an ECB labeled 100 A drawn as existing with keynote 1 ("change label to read 'feed from 100A breaker'"). Please confirm (a) the existing FCGC breaker rating and whether a new breaker is required, (b) whether the ECB is existing-to-be-relabeled or new, and (c) whether feeder 100NG is pulled in the existing riser conduit (as keynote 4 states for 200NG) or in new 1-1/4" conduit.

AE REPLY: See revised ED500 and E500 added as part of Addendum #1. Existing label shown below.

Contractor to field verify breaker at FCGC and provide new label to reflect correct breaker rating at FCGC. Keynote 4 is for normal power source.

12. Sheet EP101A and the PPHT1A feeder route. E400 detail 2 reads "TO PANEL PPHT1A SEE SHEET EP101A FOR CONTINUATION"; EP101A is not in the issued set or the G002 index. Feeder 225NG runs from ELEC 3301 (third floor, west end) to Room 2206 with no route or floor-penetration location shown. Please issue EP101A or confirm the intended route and penetration location. Related: MD201 keynote 1 demolishes a third-floor exhaust fan "including power" (Rooms 3211/3216) and no electrical sheet covers that floor; please identify its source panel and circuit.

AE REPLY: EP101A is incorrect. It should say EP102A. Please see revised EP102A for new conduit route.tt

13. Panel PPHT1A schedule, fault current and spare capacity. PPHT1A (480Y/277 V, 225 A, Room 2206) appears only on E500 with eleven breakers, of which only EF-102 and AHU-101 are named; no schedule, AIC rating or enclosure type is given. E500 shows no load calculation or available fault current for FLGC, FCGC or PPHT1, while E500 note A and 26 05 73 1.7 require the contractor to "provide new circuit breakers as required by the results of the study." Please issue the PPHT1A schedule and AIC, provide the available fault current and existing demand at FLGC, FCGC and PPHT1 (or confirm the A/E has verified spare capacity for the added loads), and confirm that breakers added to existing switchboards as a result of the 26 05 73 study, beyond those shown on E500, would be handled by change order.

AE REPLY: Please see revised E500 for fault current levels and AIC for new panel PPHT1A PPHT1A is a new panel with connected load as shown. Please provide spares and spaces as shown. 26 05 73 study for new breakers installed as part of this project scope and not for outside the scope area.

14. Panel LS22C branch designation, night-light and exit circuits. E601 labels EX.LS22C "CRITICAL BRANCH" while E500 diagram 5 feeds it from Life Safety switchboard LS2G, and EL102A notes E/F call it the Life Safety panel. EL102A note E assigns night lights to

LS22C circuit 1; E601 shows circuit 1 as an existing load ("EX.FA PNL RESEARCH"), exit signs on 2 and night lights on 3. The plans tag 18 egress fixtures "NL" but E600 has no NL type, and the 105 VA on circuit 2 implies 26 exit signs against 24 drawn. Please confirm the branch designation (it governs device color and labeling), confirm night lights on circuit 3 and exit signs on circuit 2, state the luminaire type for NL fixtures, and confirm the exit-sign quantity and faces.

AE REPLY: This life is existing life safety, and this is how VA has identified it. This panel consists of many spares. Please field adjust circuiting and provide updated panel directory.

15. Existing 2B panels and loads outside the project. EPD102 shows existing panels L22B, C22B, PPLS, LS22B and E22B in ELEC/TR 2302 with no riser, schedule or scope, while all new 2B circuits run to Room 2206. ED500 note A names C22C-A/B circuits 16, 18 and 20 as existing loads; E601 shows 18 and 20 as SPARE and adds "EX.HVAC RM 2714A" on 6/8. Please (a) confirm demolished 2B circuits are removed back to the 2302 panels and those panels relabeled per E001 demolition note 3.C, (b) confirm no new loads connect to them, and (c) issue the existing panel directories for L22C-A/B, C22C-A/B, E22C and LS22C identifying every circuit that serves areas outside the project and must be maintained with temporary power during the panel replacement.

AE REPLY: All panels inside room 2302 are existing to remain in place. Note A on ED500 is about the panels located in room 2206. Please see EPP001 added as part of Addendum #1, which is showing temporary panel scope.

16. Branch-circuit homerun make-up and conductor sizing. E002 defines the homerun as "4#10 + 1#12 G in 3/4" conduit" (shared neutral); E001 note 21 requires a separate neutral per circuit and no more than three circuits per homerun; the E001 distance table sizes 20 A circuits #8 at 175–300 ft and #6 in 1" at 300–450 ft. All 49 Zone 2 homeruns on EP102B terminate in Room 2206 at roughly 200–340 ft. 26 05 19 2.1.C.3 requires #10 and smaller solid; E001 note 21 requires #12 and larger stranded. Please confirm

(a) a dedicated neutral per circuit, (b) the E001 distance table governs conductor and conduit size, and (c) solid or stranded for #10 and #12.

AE REPLY: Please see revised E001 and E002.

17. Panelboard bonding in Room 2206. E500 note B (#6 in 3/4" conduit), EP102A keynote 3 (#4 to a new ground busbar; #4/0 between busbars per keynote 2) and 26 05 26 3.5.I (#10 minimum in rigid metal conduit) each describe the normal-to-essential panelboard bonding. Please confirm conductor size and raceway type, whether E500 note B is satisfied by the keynote 3 busbar bonds, and the location of the building-steel connection (exothermic per 26 05 26 2.4.B.2).

AE REPLY: Please provide #4 in ¾" connection from ground busbar to the first panel and #10 in ¾" for panel-to-panel ground bus connection.

18. AHU-101 and EF-102 wiring and starter/VFD responsibility. AHU-101 is scheduled with factory-installed unit-mounted VFDs (M602 note 8) and a single-point 110 MCA connection; EH102 note D requires VFD-rated cable "from panel to equipment." M602 note 4 calls for a remote combination starter for EF-102 furnished by Division 23; EP101 note D has the electrical contractor install and wire it; the 23 09 23 responsibility table says starters are installed by 23 and VFDs installed by 26. Please confirm whether feeder 130G requires VFD-rated cable, which division installs the EF-102 starter and where it mounts, and that no field-installed VFD exists under Division 26.

AE REPLY: Yes, 130G is VFD rated cable. Please refer electrical drawings for EF- 102 stater location. We believe it is efficient when EC install starter and line voltage conduits. However, coordinate with GC for mechanical and electrical sub scope.

19. Equipment requiring 120 V circuits that appear on no electrical sheet. (a) Bottle-filling station P-604 (P701; PS102B kn 7); (b) five hardwired sensor faucets P-418 with transformers (PS102B ×3, PS102K ×2); (c) the AHU-101 access-section marine lights and receptacle single-point connection required by 23 73 00; (d) the CHW flow meter (M201 kn 14). Please confirm the electrical contractor provides these circuits and identify source panels, or confirm they are not required.

AE REPLY: Yes, an electrical contractor provides these circuits. Please share one circuit for all faucet and connect to circuit 41 at panel L22C-A utilize 2#12, & 1#12 gnd in ¾" C.

Please provide GFCI outlet at bottle filling station and provide dedicated circuit for bottle filling station from panel L22C-A circuit 40, utilize 2#12, & 1#12 gnd in ¾" C.

Please share one circuit for marine light and receptacle and connect to panel L22C-B circuit 38, utilize 2#12, & 1#12 gnd in ¾" C.

Please connect flow meter to panel L22C-B circuit 40, utilize 2#12, & 1#12 gnd in ¾" C.

Please coordinate with equipment shop drawings and provide necessary power supply and field install at accessible locations.

20. Electrified door hardware. TS102.1/TS102.2 show card reader, electric strike, door contact and request-to-exit at doors 284A/B, 2201A/B, 2225, 2224, 2207 (existing) and two cross-corridor pairs, but AE601 assigns these doors non-electrified sets (HW-4K, HW-3E, HW-1L, HW-13, or none), and 08 71 00 3.5 says to disregard sets not shown on the drawings. Conversely, doors 2229 (HW-SH-4) and 273C (HW-SH-10A) carry AC/EL/REX/DPS sets referencing Section 08 17 10, which is not in the specifications, and set SH-3C (door 2213) is "NOT USED." Set 8D (door 270A) and the HW-13 family call for 120 VAC "by Division 26" with no circuit on EP102A/B. 28 13 00 2.15.G requires fail-safe 24 VDC locks; 08 71 00 2.12 requires fail-secure strikes at rated doors (284A/B are 90-minute). Please issue a schedule of electrified openings identifying, for each door, the locking device, power transfer, DPS, REX, power supply location, source circuit, fail-safe/fail-secure, and the division that furnishes and installs each item; define or delete sets SH-10A, SH-3C and SH-4; and state the number and location of fire-alarm release relays to the access control panel required by 28 31 00 3.2.A.5.

AE REPLY: Door hardware updated at door schedule on AE601 and spec section 08 71 00 updated, with 08 17 10 specification added. See Addendum #1.

Room ELEC EXIST 2207 is existing and door and hardware are to remain (see plans), and for Room 2224 OPH TECH hardware set is shown in door schedule at AE601 as 1L, which is correct.

Hardware HW-SH-3C is used on the corridor closet door, room STORAGE 2213, also shown in specification. HW-3C is NOT USED.

21. Laser room 2806. AQ602 schedules three ophthalmic lasers (U0012, U0013, U0014) in OPH Imaging 2806. No laser-in-use warning light, illuminated sign, door interlock or emergency stop appears on EP102B, EL102B, AW101 or the T sheets. Please confirm whether ANSI Z136.3 provisions are required and which trade furnishes and powers them.

AE REPLY: Please provide a "LASER IN USE" warning sign and interlock with the door. No EPO is required. Provide line voltage power from panel L22C-A circuit 42.

Provide 2#12 & 1#12 gnd in ¾"C.

22. Exam chairs and acuity systems. AQ601/AQ602 list M4915/M4915.1 exam chairs

(20) with the acquisition column blank and M5562 visual acuity systems (20, VV) with no tagged outlet; the only dedicated exam-room circuits are the U0022/U0023 stand circuits. Please confirm who furnishes the chairs, whether a floor outlet or dedicated circuit is required at the chair, and whether the acuity system requires a dedicated outlet and data drop.

AE REPLY: Dedicated outlet for U0022 covers the chair and its associated equipment.

23. GFCI receptacles, exterior SPDs and Room 2206 working space. EP102A note C requires a GFCI receptacle within 6 ft of every sink; the plans show five against roughly 26 rooms with sinks per AQ601/AQ602. E701 detail 6 requires individual SPDs on exterior-load circuits (EF-102 and the roof receptacle). Seven panelboards, two tap/ECB points and a new ground busbar are shown in the existing 155 sf ELEC/MECH room 2206. Please confirm the GFCI count (or that GFCI breakers are acceptable), confirm the two exterior-circuit SPDs, and confirm the 2206 panel arrangement meets NEC

110.26 or issue an enlarged plan.

AE REPLY: Please provide GFCI receptacles per note C on EP102A. Coordinate with plumbing and equipment drawings for total count.

Provide SPD for two exterior circuits.

Working space is shown on EP102A with dashed lines. Electrical room 2206 enlarge plan has been added as part of addendum #1.

24. Exam-room dimming range. E600 catalog numbers for F1–F3 carry no driver designation (note 5 says numbers are "intentionally incomplete"); 26 51 00 does not specify a minimum dimming level; the 26 09 23 riser confirms 0–10 V. For exam, imaging, dilation and optic-shop luminaires, please state the required minimum dimming level (1% or 10%).

AE REPLY: Please provide dimming level to 1%.

25. Lighting-control system power and BAS integration. E602 feeds the nLight system controller from Normal-branch panel L22C-A circuit 39; 26 09 23 2.12.B requires an equipment-emergency circuit. 26 09 23 2.12.A.2 requires BACnet IP communication with the 23 09 23 BAS, and 23 09 23 lists lighting on/off and scene control at the ECC, yet no network drop or point list is shown. Please confirm the controller circuit, identify the network and data outlet serving the controller, and the trade responsible for BACnet point mapping.

AE REPLY: Currently station BAS does not have a lighting control set up.

Designed lighting controller is BACnet/IP compatible, for VA to integrate with BAS in future.

26. Former Research Office 2817. ELD102 demolishes luminaires in the former Research Office 2817 footprint; GI101.2 shows that area as existing Business Occupancy (HR Admin Storage / Engineering / Environmental Management) outside the work boundary; EL102B shows no replacement luminaires there. Please confirm whether those luminaires remain, or are to be demolished and replaced (type, quantity, circuit).

AE REPLY: ELD102, EL102B, and GI102.2 are showing coordination and shows no demo and new work.

27. Lighting clarifications. (a) Occupancy time-out: 26 09 23 3.1.D says 15 minutes, E600 narrative says 20; (b) 26 51 00 2.9.F.1 requires cast/stamped stencil-face exit panels while E600 EX1 is an edge-lit Lithonia EDG; (c) 26 51 00 1.4.A.1.j requires the discontinued DOE Lighting Facts label; (d) E700 note 3 cites Section 10 05 41 (seismic is 13 05 41); (e) EL102A note I "UL934" should read UL 924; (f) nLight bus cable is CAT5e per the 26 09 23 riser and CAT-6 per EL102A note G. Please confirm each.

AE REPLY: Provide CAT6 cables.

28. Existing system manufacturer and panel location. 28 31 00 1.1.A identifies the existing system as Edwards (EST 278 pull stations, SIGA-CT1 modules); general note E on FAD101, FA101 and FA601 requires a technician qualified on a "Notifier network fire alarm system." Keynote 1 references a panel "located in G114"; 1.1.D says "security office"; 1.1.E says "first floor, fire alarm control room." Please confirm the manufacturer and model of the control unit and network the new devices connect to, and the room and floor of that panel.

AE REPLY: VA to confirm manufacturer and model listed in specification 28 31 00 1.1A is accurate and confirm location of panel.

VA Response: Panel is located in G114.

29. Device quantities and strobe candela. The FA101 plan shows 32 ceiling speaker/strobes, 6 wall strobes and 6 door holders; the FA101 legend lists 21, 4 and 4;

FA601 shows 32 and 6 and no door holders. FA101 note G calls for 15 cd in toilet rooms and 75 cd elsewhere (consistent with 28 31 00 2.7.C.1); FAD101 and FA601 note G say all strobes are 15 cd. Please confirm the plan quantities govern and 75 cd outside toilet rooms.

AE REPLY: Contractors shall refer to contract documents to perform counts and utilize worst case or highest quantity indicated where conflicts are identified.

Contractors shall follow instructions provided in the specifications where conflicts are identified with drawings.

30. Speaker circuit capacity and the BPS. FA601 connects all 32 speaker/strobes to an "existing speaker circuit" and the wall strobes to a BPS on a dedicated 120 V circuit, with no BPS location, trigger module, or panel circuit shown (none on E601/E602). 28 31 00 2.6.C/E require 50% spare amplifier and circuit capacity. Please identify the existing amplifier and speaker circuit, its present load and spare wattage, whether a new amplifier and speaker circuit from the FACU are required, and the BPS location, trigger and feed.

AE REPLY: Provide new voice evacuation amplifier equipment, additional notification appliance circuit (NAC) panel, and listed booster power supply equipment as required to accommodate the new fire alarm speaker/strobe appliances and strobe appliances indicated on the drawings.

Provide a separate listed 24 VDC power supply, as required, for the new door holders. Provide compatible fire alarm control/interface modules to initiate door holder release.

The Contractor shall coordinate with the existing VA fire alarm system service provider and verify the existing Edwards fire alarm control panel configuration and compatibility with all proposed equipment. Connect and integrate the new amplifier, NAC equipment, booster power supplies, and associated interface modules with the existing EST3 fire alarm system located in room G114.

The Contractor shall provide all necessary modules, wiring, programming, power supplies, batteries, and accessories required for a complete, operational, and code-compliant system. GC's certified fire alarm contractor to provide updated battery calculations, voltage-drop calculations, and revised fire alarm shop drawings for VA review and approval prior to installation.

All new equipment shall be listed, compatible with the existing Edwards system.

Please provide dedicated circuits to amplifier, NAC panel, BPS and door holder power supply from life safety panel LS22C. Provide 20A/1P circuit breaker at ckt.

9, 10, 11, and 12. Provide 2#12, & 1#12 Gnd, in ¾" conduit for each panel. Locate all panels inside room 2207.

31. Door holders. Six holders are drawn, four are listed, none appear on the riser, and AE601 assigns no hardware set containing a magnetic holder (sets HW-1J/4H/6B are unused). Please confirm quantity, new or existing, furnishing section (08 71 00 or 28 31 00), and the power/release path (24 VDC from the FACU per 2.11.A.2 or 120 V with a relay).

AE REPLY: Door holders are 4, two at 270 A, 284A, 284B; see door schedule notes on Addendum #1.

32. Smoke dampers, duct detectors and AHU shutdown. M702 closes supply and return smoke dampers on duct-detector alarm and the 23 09 23 table assigns smoke-damper low-voltage wiring and line power to 28 31 00, but 23 31 00 2.6 reads "SMOKE DAMPERS (NOT USED)" and none are drawn. M103 shows two duct detectors at AHU- 101; M702 lists only DSD-1. Please confirm whether any smoke or fire/smoke dampers are in scope (quantity, location, wiring section), confirm two addressable duct detectors with remote test stations, and confirm the shutdown is one control-module relay to the AHU-101 safety circuit with status only to the BAS.

AE REPLY: Smoke dampers are not indicated within the project documents and are not required as part of the current design scope. Accordingly, no smoke dampers or associated wiring are required.

Two duct-mounted smoke detectors (DSD) are required for AHU-101, as indicated on drawing M103. NFPA 90A requires smoke detection within the supply ductwork, while the IMC requires smoke detection within the return ductwork for an air-handling system of this configuration and capacity. Accordingly, both detectors shall be provided to maintain compliance with the applicable code requirements.

Both detectors shall be addressable and provided with remote test stations in accordance with the project specifications.

Upon activation of either duct smoke detector, a smoke detection signal shall be transmitted to the BAS, which shall initiate shutdown of AHU-101 through the designated safety circuit interface. The fire alarm control panel shall annunciate the associated alarm condition, and AHU shutdown status shall be monitored through the BAS.

Drawing M702 identifies DSD-1 within the control sequence; however, the same shutdown sequence shall apply to both duct smoke detectors indicated on M103.

33. Five-year service, training and software. 28 31 00 1.6 requires five years of inspection, testing, maintenance, normal call-back and 40 hours/year overtime call-back by the manufacturer's authorized representative; 3.5 requires 46 instructor hours of training; 2.13.E requires programming software and licenses;

2.13 requires spare parts and a storage cabinet; 3.4 requires a 30-day burn-in.

Please confirm these apply in full to this modification of an existing system that the VA already maintains, or state which are waived.

34. Existing devices and the occupied 2B wing. FAD101 shows no existing fire alarm devices; 28 31 00 1.2.B and 3.1.D require removal of all unused existing equipment and conduit; FA601 ends the new loop "to existing devices." Please provide the existing device count and circuit assignments within 2K/2B (or confirm the contractor field-surveys), confirm devices in occupied 2B and downstream devices on shared circuits remain in service throughout Phase I, and confirm the existing record drawings and panel database will be provided.

AE REPLY: Currently existing total FA devices count in 2K and 2B area are 4 smoke detectors, and 20 strobes. Yes, during phase 1, devices in 2B area to service, the contractor to field verify shared circuit information.

35. Fire alarm wiring method. FA notes A/H and E001 require all fire alarm circuits in conduit painted red; 28 05 13 2.10.C.3 lists red- stripe fire-alarm-rated MC cable and 2.10.B.1 lists circuit-integrity (2-hour) cable. Please confirm (a) all new fire alarm circuits, including drops above accessible ceilings, are in red top-coated or painted conduit and MC is not permitted, and (b) whether CI cable is required on any circuit.

AE REPLY: All fire alarm system wiring shall be installed in dedicated raceways, separate from raceways serving other electrical, communications, and low-voltage systems. All fire alarm raceways shall be red in color. Fire alarm conductors shall be copper, UL-listed for their intended fire alarm application, and installed in accordance with NEC Article 760, NFPA 72, and the VA Fire Protection Design Manual. MC cable shall not be used for fire alarm system wiring.

36. Backbone fiber. TD102 keynote 1 and T103 keynotes 1/7 require the existing B-side backbone fiber from MCR 3431 to TR2 2718 and TR2 3718 to be removed and re-pulled under this contract, "actual location per final EHRM construction"; T411 labels those rooms "ONGOING EHRM PROPOSED"; 27 10 00 2.3.D requires a minimum of 24 multimode and 12 single-mode strands per path, fusion spliced. No strand count, length or pathway type is given. Please confirm the strand count and construction of the existing fiber, route length and pathway (conduit, innerduct or tray), that MCR 3431, TR2 2718 and TR2 3718 will exist and be accepted under the EHRM contract before this contract's NTP, that the new fiber is contractor-furnished and contractor-spliced at both ends, and the outage windows OI&T will permit.

AE REPLY: See revised spec 27 13 23i for fiber type and detail 1/T411 for counts.

Pathway type specified but must be field verified per existing conditions (per final EHRM construction) as noted on sheet T102. AE does not specify the length. See floor plans and slab elevations in 1/T411 for Contractor's materials take-offs. Refer to specifications (01 00 00, 26 05 11, and 27 05 11) for outages.

37. Division 27/28 raceway and pathway method. 27 05 33 3.1.D requires rigid steel or IMC in furred/suspended ceilings and walls; the 27 05 33 table and 27 51 16 2.4.B.2.b / 27 52 23 3.4.G.1.b require complete, separate conduit for PA and nurse call unless the COR grants a partitioned-tray exception in writing; T513 requires all access-control cabling in dedicated 1" conduit and T001 requires 1" conduit for CCTV lines, while 28 13 00 3.5.D permits plenum cable above accessible ceilings and in stud walls and 28 05 00 1.1.B says the specification prevails. The drawings show 1-1/2" EMT outlet stubs to unpartitioned wire-basket tray (T513; T102.3). Please confirm (a) EMT with compression fittings is acceptable for all Division 27/28 raceway, (b) unpartitioned basket tray is acceptable for Category 6A, (c) whether PA and nurse-call cabling may run plenum-rated in partitioned tray (and issue the COR exception with the bid documents if so), and

(d) the governing pathway for PACS, duress and camera cabling within the ceiling and from the project area to TR2 2718.

AE REPLY: Raceway and pathway method exceptions per specifications. Division 27 fitting types per spec section 27 05 33 – 2.1.C.2.b.(1)&(2). Division 28 fittings per spec section 28 05 28.33 - 2.4.B.3.

38. Outlet stub size. T513 details 1, 4, 5 and 6 call for 1-1/2" EMT from every outlet box to the tray; T001 shows 1" for CCTV and 3/4" for intercom/nurse call; 27 05 33 3.1.C.1 sizes by 40% fill. Please confirm the stub size for P1/P2/TV outlets, WAP boxes, PA back boxes, nurse-call stations and camera boxes.

AE REPLY: Conduit stub sizes per details in sheet T513. All other conduit sizes per specifications.

39. Wireless access points. T001 note 11 states all existing WAPs "shall remain in place"; TD102.1/TD102.2 note B says WAPs are to be removed, stored at a VA site and the cable pulled back to source. Demo sheets tag up to 38 WAPs; the new plans show

19. Please state the in-scope WAP count, whether the contractor or VA OI&T removes, stores and reinstalls them, whether any relocate, and whether VA furnishes replacement WAPs or brackets.

AE REPLY: Wireless Access Points shall be new. See revised General Telecom Note #11. AE does not provide counts. Contractor shall base material takeoff from drawing floor plans. Unless it states for VA to remove, it is the Contractor's SOW to remove the WAPs. Coordinate storage with VA OI&T. New Work Wireless Access Points are shown for Contractor to provide new cabling and "biscuit".

WAP installation per VA.

40. Public address scope. T512 detail 3 taps 39 new 70 V speakers onto an existing amplifier in Room 3435; TD102/T103 place the existing amplifier at MCR 3431. 27 51 16 requires an OEM-authorized dealer, two remote stations minimum, continuous supervision, 50% spare capacity, TVE-witnessed intermediate and acceptance tests, and eight 8-hour preventive-maintenance visits over two years. Please identify the amplifier manufacturer, model, room and spare wattage; confirm capacity for 39 speakers plus 50%; and confirm whether the remote stations, supervision, UPS, witnessed tests and two-year maintenance visits apply to this extension.

VA Reply: Due to the age of the building, a single brand of record is not isolated within the Birmingham VA facility. Coordination will be required between the COR, Contractor, and responsible VA parties to implement new equipment.

Contractor/subcontractor to coordinate best amplifier manufacture via coordination with COR and VA Electronics. Current system does not have capacity for 39 additional speakers within the 2K2B wing. Booster amplifier will likely need installed. The existing hospital PA system has exceeded its practical service life and is being sustained through temporary repairs. Failed speakers may still provide signal continuity to operational speakers, so removing seemingly unused equipment could interrupt service. System tracing and documentation are needed before any components are disconnected or removed.

41. Nurse call. T102.1/T102.2 show four pull-cord stations (toilets 2226, 2227, 2208, 2810), four corridor dome lights and a new head- end cabinet in TR2 2718 (keynote 3) compatible with the existing Ascom Telligence system, annunciating at the master in Room 3313. 27 52 23 adds two remote annunciation points (2.1.J), software on three owner computers, an HL7 interface, 104 hours of training (4.3), and head-end power from the Critical branch with the instruction to "consult with COR ... prior to bidding" if not shown (3.4.A.9); no circuit for TR2 2718 appears on any electrical sheet. Please confirm the device scope, state which of the 27 52 23 items apply, and identify the panel and circuits serving the nurse-call cabinet and UPS.

AE REPLY: Wire 2#12, 1#12G in 3/4"C to new (1) 20A/1P circuit breaker of the type and AIC rating to match existing panel L22C-B ckt #45. Utilize existing bussed space for installation of new circuit breaker. Provide typewritten directory to reflect changes.

42. Distributed antenna system. Nine existing DAS antennas (head-end "existing T- Mobile equipment") are to be protected, temporarily supported and reinstalled within 2 ft, with non-working antennas or cabling replaced at the contractor's expense (TD102.x note C; T102.x note A); 27 05 11 3.6.H.2 requires post-construction RF measurements;

the referenced Section 27 53 19 is not included. Please identify the DAS owner and maintaining vendor, confirm whether the contractor or the carrier's vendor detaches and reinstalls the antennas, confirm VA will furnish a pre-construction RF baseline, and state who performs the 3.6.H.2 measurements.

VA Reply: Due to the age of the building, a single brand of record is not isolated within the Birmingham VA facility. Coordination will be required between the COR, Contractor, and responsible VA parties to implement new equipment. Orange Cat 5 Cable leads to telemetry equipment and must be re-installed within 24 inches of current location.

43. TR2 2718, IT 2217 and head-end power. TD102 keynote 3 requires a new TBB from IT 2217 to TR2 2718 "immediately for minimal downtime" with no route or length; 27 05 26 2.1 says "utilize existing" busbars. TD102.x note A removes existing cabling back to source, and T411 states 413 of 432 ports in TR2 2718 are in use. The nurse-call cabinet, access control panel and power supplies, new CCTV NVR, PoE switch (if any) and the two VA switches all land in TR2 2718 (Bridge), and 28 05 00 1.14.A requires their 120 V emergency circuits to be shown on the Division 26 drawings; none are, and TR2 2718 is outside the EP102A/B limits. Please state the TBB route and length, confirm whether existing horizontal cables serving 2K/2B are removed from the TR2 2718 panels and whether those positions are reused or new 48-port panels installed, and identify the emergency-branch panel and circuits serving each head-end device in TR2 2718, including the automatic door operators at 270A/270B/273C/284C.

AE REPLY: See drawings updated for new telecommunications bonding backbone. Provide new patch panels per Construction Documents. See RFI #41 for nurse call head-end unit branch circuit. Horizontal cabling to be removed back to source per Construction Documents. Access control power supplies shall be wired with 2#12, 1#12G in 3/4"C to new (1) 20A/1P circuit breaker of the type and AIC rating to match existing panel L22C-A ckt #46. Utilize existing bussed space for installation of new circuit breaker. Provide typewritten directory to reflect changes.

44. Telecommunications clarifications. (a) CATV: T512 detail 2 shows the entrance protector and amplifier "BY VA" at ELEC/TR 2301; please confirm the number and location of new splitters, the RG-11 route, and that all televisions and mounts are VA-furnished (AQ601 lists two against eight outlets). (b) Sleeves: T511 detail 4 note 2 leaves the sleeve quantity to "ENGINEER TO PROVIDE"; please schedule the rated-wall crossings and 4" pathway devices. (c) Port count: T411 states approximately 258 ports; the plans total about 314 Category 6A runs (130 two-port, 8 single, 8 TV, 19 WAP × 2); please confirm and issue the port map required by 27 10 00 3.1.A.5. (d) Mechanical Room 2228 is hatched "not in scope" on TS102.2 but carries DDC and WAP drops on T102.2; please confirm it is in the telecommunications scope.

AE REPLY: (a) CATV riser is typical. Riser is existing. (b) See revised drawing T102.2. Number of coaxial outlets as shown on plans. See revised detail T511. See revised sheet T102.3 for sleeve sizes and quantities. (c) port map provided. See updated schedules. (d) Mechanical Room 2228 is in scope of work.

45. Existing PACS/VMS manufacturers, integrator and NVR. T411 detail 2 and T512 detail 5 show a new CCTV NVR in TR2 2718 "compatible with existing campus system";

no VMS manufacturer, retention or license count is stated. T513 names Lenel for the access control panel; 28 26 00 refers to an "apC"; 28 13 00 1.3.E, 28 23 00 1.4.F and 28 26 00 1.3.F require an authorized regional representative of the existing manufacturers with three same-system references and a service facility within 60 miles; 28 05 00 3.6.B requires offsite programming on the contractor's own licensed copy of the Owner's current SMS version; T512 note B refers to the "VA security vendor." Please identify the manufacturers and versions of the existing PACS and VMS, confirm the NVR is new and contractor- furnished with its retention and license requirements, state whether the station has a current security integrator that bidders may or must use, and state the PIV-compatible card reader model the station has standardized on (28 13 00 2.10).

AE REPLY: Coordinate manufacturer and license with VA OI&T. Please clarify what is an "apC". Existing PACS is manufacturer Altronix.

46. Security device counts. The plans show 46 duress buttons (23 on TS102.1, 26–27 on TS102.2, three shared at Reception 2201), 10 labeled cameras plus three unlabeled camera symbols (RCC281R, Waiting 2200, Stair 11 corridor door), an undefined "X / CR" tag at the Stair 11 door, and no alarm-input boards on the T513 riser. Please confirm the duress and camera counts, confirm each duress button is an individually supervised input (28 26 00 3.1.D), state where duress alarms annunciate and whether a second location is required (2.2.G), and identify the "X / CR" device.

AE REPLY: "X" indicates "existing to remain" device. Per sheet TD102.2 Keynote #1, extend any existing access controls to new panel location. "Unlabeled" cameras shall be at 90°. Provide alarm input boards compatible with access controls system. Duress alarm annunciation shall be at Police Room. Secondary alarm shall be at Boiler Plant.

47. Existing 2B access control panel, network ports and GFE. TD102.2 keynote 1 demolishes an existing access control panel and extends its "existing to remain circuits" to the new panel; 28 05 13 3.9 bars reuse of existing wiring unless shown. 28 23 00 2.10 lists a switch, router and FIPS 140-2 encryptor as system components and 3.1.A/3.2.C refer to Government-furnished equipment without a list; T411 sizes the two VA switches for data. Please state how many doors and devices outside 2K/2B are served by the demolished panel and whether their cabling may be reused, confirm the new ACP replaces it and that the existing head-end has licensed capacity for the added readers and inputs, state whether cameras connect to VA OIT switch ports or a contractor-furnished PoE switch, whether the encryptor is required, and provide the GFE list.

AE REPLY: Rewire existing PACS to new control panel. Coordinate with VA OI&T for switch specifications. Contractor to field verify any existing PACS circuits that remain after demolition work. Cabling may be reused if impedance test conforms to the cable standard. Coordinate with VA OI&T for license requirements. Confirm with VA OI&T they furnish the POE camera switch.

48. Security acceptance process. Per 28 05 00 3.7.B.3, is a Pre-Delivery Test required?

Please also confirm the VA office that reviews and accepts the PACS/VASS submittals and tests, and that the four-stage design-package review (28 13 00 1.4.E) and one-year maintenance period (28 13 00 1.8) apply to this extension.

AE REPLY: Conform to specifications.

49. (a) CSG-101 on M602 is circuited as "HUM-101" on L22C-B 23; (b) RO-1 lists MFS 15 on a 20/1 breaker; (c) the AHU-101 UV panel lists 15 MOCP on a 20/1; (d) E602 L22C-B lists "#U0023 RM 2802" on circuits 27 and 30 and omits 2820; (e) 01 35 26 states 48 hours (1.17.O) and 24 hours (1.25) for hot-work permits; (f) 01 32 16.01 is written for the A/E and 01 32 16.15 leaves the activity count blank. Please confirm or correct each. Louis Aller III, Licensed electrical contractor

VA Reply: Hot work permits are provided 24 hours in advance.

50. The solicitation calls for the commissioning to be under the GC, section 01 91 00 “ General Commissioning Requirements” calls for the commissioning to be under the VA.

Which is correct?

VA will coordinate 3rd party commissioning.

51. Can SSHO have combined duties with the superintendent, or will it need to be a standalone position?

No, both positions can not be combined. It must be separate roles.

AACON General Contractors

1. Will onsite parking be provided for the prime contractor, superintendent, SSHO, QCM and subcontractors? Please confirm the number and location of available spaces or permits, any fees, and whether remote parking or shuttle arrangements are required.

No. The Contractor must determine parking locations if required near the job site.

2. Will the VA provide space for a temporary field office, safety/QC records, worker break or changing area, and limited storage? Are temporary power, water, restrooms and electrical connections for ICRA equipment available to the contractor?

No, nothing outside of the work space. If the contractor chooses to use a portion of the 2K2B work space as an onsite office, that is within their scope.

3. May one qualified, full-time onsite employee serve as both the superintendent and QCM/CQC System Manager, provided all required QC duties and inspections are performed, or must these positions be staffed separately?

No, these must be staffed separately.

4. Although Section 01 35 26 calls for a dedicated SSHO with no other duties, would the VA allow an approved double- or triple-hatted superintendent, SSHO and QCM? If not, please confirm the SSHO must be separately staffed during every construction shift.

No, these must be staffed separately.

5. Please confirm the required SSHO and alternate credentials and years of experience, as the specifications cite differing thresholds. Also clarify minimum QCM experience and when the Construction Quality Management certificate must be held.

VA Reply: Min 1 year experience for each. CQM Certificate must be held.

6. Please provide the intended sequence, turnover dates and occupancy requirements for Ward 2K, waiting/check-in and Ward 2B. Will the VA vacate each phase before work begins, and who is responsible for patient/staff relocations and temporary swing spaces?

AE REPLY: During design phase services, phasing was not finalizing due to VA pending information. AE proposed mechanical room to be used as a temporary space during the phased construction, VA requested time to confirm. VA mentioned that the Optic Shop was considered in internal VA Phasing meeting to serve the function of temporary space. VA to revisit and advise on further direction. Intended sequence is shown on Phasing Plan GI102. Turnover dates will depend on contractor’s means and methods. Occupancy requirements are shown on Life Safety plan GI101.2 Business Occupancy separated via 2 hr rated construction from the rest of the hospital. VA is to provide 2K ward unoccupied by staff and furniture for contractor to demolish as shown on drawings. Staff relocation furniture is by the VA, however, if existing Mechanical room 2206 is used as swing space(to be confirmed by the VA) contractor will have to prepare the swing space by demolishing existing unused equipment and providing temporary power/data lighting.

7. Are there additional restricted work periods, blackout dates, noise or vibration limits, patient-care events or access limitations that bidders should account for? Please identify approved times for coring, demolition and system tie-ins.

Confirmed. All work in adjacent occupied spaces and requiring shutdowns will have to be after hours, to include nights and weekends with a three week notice to prepare.

Coordination will be completed via the COR. Work stoppage may be implemented if noise levels are to high during normal working hours.

8. Will the contractor be provided access to the first-, third-floor, roof, mechanical, electrical and telecommunications areas shown in the drawings outside Wards 2K and 2B? Please identify any occupied-area restrictions, escort requirements or after-hours access limitations.

Yes, however there may be some occupied area restrictions that will need coordinated with the COR. Some spaces may require VA Staff escort. After hours access is possible but will need coordinated with COR.

9. For Level IV ICRA containment, where may the contractor exhaust HEPA-filtered negative air during each phase? Please identify approved outdoor discharge points and routes, and confirm whether the ICRA Appendix A alternative can be used if exterior exhaust is impractical.

AE REPLY:AE considers this means and methods of the contractor. Contractor to follow infection control drawings and specifications and to utilize Appendix A, as necessary.

VA Engineering Concurs.

10. Will the VA provide approved phase-specific ICRA barrier, anteroom and decontamination layouts, or must the contractor design them? Please confirm negative-pressure monitoring, documentation and inspection responsibilities.

AE REPLY: See sheets GC401, GC402, GC501 for infection control details.

Contractor to provide what is shown on the drawings and specifications pertaining infection control.

11. Please provide the existing asbestos and hazardous-material survey, laboratory results, marked locations and estimated quantities for all affected areas, including concealed spaces. How will previously unidentified hazardous materials be handled after award?

AE REPLY: See Addendum #1, attachments to 02 82 11 specifications.

12. Who is responsible for independent asbestos air monitoring, industrial hygienist services, clearance sampling, reporting and retesting - the VA or the contractor? Please confirm the required sequence of abatement and follow-on demolition.

AE REPLY: AE is responsible for preparing and coordinating the drawings and specifications. Contractor is responsible for the execution of the contract per the drawings and specifications.

13. Please confirm the applicable NFPA Type II construction subtype and fire-resistance ratings (II(222), II(111) or II(000)). Is fireproofing work limited to repair of disturbed material, or is new fireproofing required? Please provide locations, quantities and existing material information.

AE REPLY: NFPA Type II (222) confirmed. All work performed under this contract that disturbs existing fireproofing calls for repair and…