This is Amendment 0005 to Request for Quote (RFQ) 36C24726Q0218 issued by the Department of Veterans Affairs, Carl Vinson VA Medical Center in Dublin, Georgia. The amendment extends the response date/time from February 19, 2026 at 4:00 PM EST to February 25, 2026 at 10:00 AM EST and represents the final extension for submission of offers.

The amendment addresses four inquiries from potential offerors regarding contract performance and requirements. The Government clarifies that: (1) there are no alternative end-of-term options available; the contractor must install equipment at the contract start and remove it upon completion with no residual value; (2) the contractor is responsible for supplies specific to their equipment (such as phantoms), while the Government provides basic consumables including linens, paper towels, blankets, and wastebaskets; (3) one full-time CT Technologist is the current staffing level expected per site, with the contractor required to supply an additional credentialed CT Technologist to provide coverage during the primary technologist's absence due to illness or leave; and (4) there is no preferred proposal format—offerors should provide only what is requested and required for evaluation. The Government also notes that future plans include an organic capability with Government-purchased equipment and contracted technologist staffing, but budgetary and programmatic barriers have delayed this transition.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

0005 01-20-2026

508-26-3-2041-0001

None

Department of Veterans Affairs

Carl Vinson VA Medical Center

1826 Veterans Blvd.

Dublin GA 31021

Department of Veterans Affairs

Carl Vinson VA Medical Center

1826 Veterans Blvd.

Dublin GA 31021

To all Offerors/Bidders

36C24726Q0218

X

X X

See CONTINUATION Page

X 1

THE PURPOSE OF THIS AMENDMENT IS TO PROVIDE RESPONSE TO RFQ INQUIRIES BY POTENTIAL OFFERORS. THE RESPONSE DATE/TIME

EXTENDED FROM 19 FEB 26 @ 1600 EST TO 25 FEB 26 @ 10AM EST. FINAL EXTENSION.

1. THE REQUESTER SUGGESTED THE GOVT EVALUATE THE FOLLOWING ALTERNATIVES:

- GUARANTEED FIVE YEAR TERM: GOVT RESPONSE: AT THIS TIME; THE INTENTION IS TO FULFILL THE FIVE (5) YEAR TERM W/OPTIONS

- GOVT PURCHASED EQUIPMENT W/CONTRACTED TECHNOLOGIST STAFFING: THIS IS THE FUTURE END STATE; BUDGETARY PROGRAMMATIC

ISSUES/BARRIERS HAVE IMPEDED AND DELAYED THIS PROCESS. HOWEVER, THE OVERAL GOAL IS TO HAVE THIS REQT BE ORGANIC

- CAPITAL BUYOUT PROTECTION IF OPTIONS NOT EXERCISED: NOT AN OPTION FOR THIS REQUIREMENT.

- HYBRID LEASE TO OWN MODEL: NOT AN OPTION AT THIS TIME.

2. WE UNDERSTAND THAT THE CONTRACTOR IS REQ'D TO REMOVE THE EQUIPMENT AT THE END OF THE POP. ARE THERE ANY ALTERNATIVE

END OF TERM OPTIONS PERMITTED (e.g., GOVT PURCHASE OF EQUIPMENT AT FAIR MKT VALUE), OR SHOULD OFFERORS ASSUME REMOVAL

JAMES E. BOLES JR.

CONTRACTING OFFICER

CONTINUATION AMENDMENT 0005

CONTINUATION OF QUESTION 1.

……..WITH NO RESIDUAL VALUE IN ALL CASES?

GOVT RESPONSE: NO, THERE IS NO ALTERNATIVE END-OF-TERM OPTION. THE

CONTRACTOR IS TO INSTALL THE EQUIPMENT AT THE BEGINNING OF THE CONTRACT

PERIOD AND REMOVE THE EQUIPMENT AT THE END OF THE CONTRACT PERIOD.

2. QUESTION: PLEASE CLARIFY THE CONTRACTOR’S RESPONSIBILITY FOR

MATERIALS AND SUPPLIES UNDER SECTION 1.3; CONSIDERING SECTION 8.5.9, WHICH

STATES THAT THE GOVERNMENT WILL PROVIDE ALL SUPPLIES, INCLUDING BASIC

CONSUMABLES AND LINENS, REQUIRED TO PERFORM CT EXAMINATIONS.

GOVT RESPONSE: SUPPLIES/MATERIALS FOR YOUR EQUIPMENT (PHANTOM, ETC).

BASIC CONSUMABLES SUCH AS LINENS, PAPER TOWELS, BLANKETS,

WASTEBASKETS, ETC., ARE PROVIDED AT THE SITE BY THE GOVERNMENT.

3. QUESTION: WE UNDERSTAND THAT THE CONTRACTOR IS RESPONSIBLE FOR

PROVIDING CT TECHNOLOGIST STAFFING UNDER THIS CONTRACT. FOR PLANNING

PURPOSES, PLEASE CONFIRM THE CURRENT CT TECHNOLOGIST STAFFING AT EACH

LOCATION, INCLUDING WHETHER COVERAGE IS TYPICALLY ONE TECHNOLOGIST PER

SITE, AND WHETHER CURRENT STAFFING LEVELS ARE CONSIDERED SUFFICIENT BY

THE GOVERNMENT FOR CURRENT OPERATIONS.

GOVT RESPONSE: ONE (1) CT TECHNOLOGIST FULLTIME FOR EACH SITE IS THE

CURRENT STAFFING LEVEL EXPECTED. THE CONTRACTOR WILL NEED TO SUPPLY

ANOTHER CREDENTIALED CT TECHNOLOGIST IN THE EVENT THE PRIMARY CT

TECHNOLOGIST IS UNABLE TO PERFORM; UNAVAILABLE (SICK/LEAVE); WE WILL STILL

HAVE COVERAGE.

4. QUESTION: IS THERE A PREFERRED PROPOSAL FORMAT?

GOVT RESPONSE: NO PREFERRED FORMAT. JUST PROVIDED WHAT IS

REQUESTED/REQUIRED FOR EVALUATION.

END OF SECTION